RESOLUTION OF CONSTRUCTION DISPUTES ARISING FROM MAJOR
INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES – CASE STUDY
OF GHANA
Joseph Mante
PhD
September
2014
RESOLUTION OF CONSTRUCTION DISPUTES ARISING FROM MAJOR
INFRASTRUCTURE PROJECTS IN DEVELOPING COUNTRIES – CASE STUDY
OF GHANA
JOSEPH MANTE, LLB (Hons), LL.M, BL
A thesis submitted in partial fulfilment of the
requirements of the University of Wolverhampton
for the degree of Doctor of Philosophy
September, 2014
This work or any part thereof has not previously been presented in any form to the University
or to any other body whether for the purposes of assessment, publication or for any other
purpose (unless otherwise indicated). Save for any express acknowledgments, references
and/or bibliographies cited in the work, I confirm that the intellectual content of the work is
the result of my own efforts and no other person.
The right of Joseph Mante to be identified as author of this work is asserted in accordance
with ss.77 and 78 of the Copyright, Designs and Patents Act 1988. At this date copyright is
owned by the author.
Signature :
Date
: 10 September 2014
Abstract
ABSTRACT
This study undertook a critical examination of developing countries’ experiences of
infrastructure-related construction dispute resolution using Ghana as a case study. It
investigated the dispute resolution processes and procedures which parties to infrastructure
construction disputes employed to address such disputes. To gain a better understanding of
the dispute resolution processes, the study also assessed the legal framework for procurement
and contract formation and other contextual issues which influenced parties’ dispute
resolution choices. Consequently, strategies for efficient and effective dispute resolution were
developed. The main rationale for the study was the need for effective and efficient dispute
resolution processes in the context of infrastructure projects in developing countries. The
literature indicated that disputes often occurred on such projects in developing countries that
were resolved at great cost mainly by arbitral tribunals in the developed world. However,
there was limited information on the extent to which other dispute resolution mechanisms
were utilised prior to resort to international arbitration.
The study adopted a qualitative research approach informed by the interpretivist
philosophical paradigm. Data was collected from fifty-six interviewees from the State as the
Employer and foreign contractors through semi-structured interviews and documents and
analysed using qualitative data analysis procedures associated with grounded theory research
such as coding, constant comparison, memoing and diagramming, and doctrinal legal
analysis. It was found that engineer’s determination, negotiation and international arbitration
were the most used dispute resolution mechanisms. Others such as mediation were rarely
used. The dispute resolution processes were characterised by high cost, low satisfaction with
outcomes and negative effect on relationships. It was also found that the extant dispute
resolution processes were the product of the nature of the parties, the context in which they
operated and their responses to the context. Factors such as lack of coordination among the
Employer’s sub-units, human resource constraints and political interference had varying
negative impacts on dispute occurrence, dispute resolution system design and the dispute
resolution processes.
To deal with these challenges and achieve efficient and effective dispute resolution
processes, four sets of remedial strategies (condensed into a model called the Dispute
Resolution Efficiency Cycle (DREC)) were proposed. The study has provided empirical
evidence which has addressed some of the gaps identified in the literature on issues such as
absence of information on pre-international arbitration dispute processes. The study has also
highlighted the impact of context and dispute system design on dispute resolution.
Contributions to practice included diagnosing challenges with the extant dispute resolution
processes and proposing possible remedial strategies.
Keywords: Construction, Developing countries, Dispute resolution processes, Dispute
Resolution Efficiency Cycle, Infrastructure development, Procurement
i
Table of Content
TABLE OF CONTENT
ABSTRACT … ...................................................................................................................... i
TABLE OF CONTENT ........................................................................................................... ii
LIST OF ABBREVIATIONS ...................................................................................................x
LIST OF AUTHORITIES ...................................................................................................... xii
LIST OF FIGURES.................................................................................................................xv
LIST OF TABLES ................................................................................................................ xvi
ACKNOWLEDGMENT ...................................................................................................... xvii
DEDICATION ...................................................................................................................... xix
CHAPTER ONE - GENERAL INTRODUCTION .................................................................2
1.1.
Introduction ......................................................................................................2
1.2.
Background of Study ........................................................................................2
1.3.
Aim and Objectives ..........................................................................................7
1.4.
Research Methodology .....................................................................................8
1.5.
Research Justification .....................................................................................12
1.6.
Summary of Findings, Conclusions and Recommendations ..........................13
1.6.1.
Extant Dispute Resolution Processes .............................................................13
1.6.2.
Factors Accounting for the Extant Dispute Resolution Processes .................14
1.6.3.
Remedial Strategies ........................................................................................16
1.6.4.
Implications of findings for other Developing Countries ...............................19
1.7.
Scope and Limitation ......................................................................................19
1.8.
Contribution to Knowledge ............................................................................21
1.9.
Structure of the Thesis ....................................................................................22
CHAPTER TWO-INFRASTRUCTURE DEVELOPMENT: CURRENT STATE
AND TRENDS IN DEVELOPING COUNTRIES ........................................26
2.1.
Introduction ....................................................................................................26
2.2.
Nature and Characteristics of Infrastructure Projects .....................................27
2.3.
Infrastructure Projects in Developing Countries –Current trends ..................28
2.4.
Infrastructure Development in Ghana – Current State and Trends ................30
2.5.
Funding Infrastructure Development .............................................................31
2.6.
Infrastructure Development and Economic Development .............................33
2.7.
Summary.........................................................................................................35
ii
Table of Content
CHAPTER THREE - PROCUREMENT OF MAJOR INFRASTRUCTURE
PROJECTS IN GHANA ................................................................................37
3.1.
Introduction ....................................................................................................37
3.2.
Procurement- Definition .................................................................................37
3.3.
Procurement Methods .....................................................................................38
3.3.1.
The Traditional methods.................................................................................39
3.3.3.
The Management-orientated Methods ............................................................40
3.3.4.
The Collaborative Procurement Methods ......................................................41
3.4.
Procurement of Infrastructure projects in Ghana –Pre-Act663 ......................41
3.5.
Procurement of Infrastructure – Post Act663 .................................................43
3.6.
Other rules on Infrastructure Procurement .....................................................44
3.7.
Procurement Practice ......................................................................................45
3.8.
Summary........................................................................................................45
CHAPTER FOUR - RESOLVING INFRASTRUCTURE-RELATED
CONSTRUCTION DISPUTES......................................................................47
4.1.
Introduction ....................................................................................................47
4.2.
Definition and Scope ......................................................................................48
4.2.1.
Claims .............................................................................................................48
4.2.2.
Dispute ............................................................................................................49
4.2.3.
Overview of Causes of Construction Disputes ...............................................52
4.3.
Major Construction Dispute Resolution - Options in Developed Countries ..57
4.3.1.
Dispute Avoidance and Management .............................................................58
4.3.2.
Negotiation .....................................................................................................60
4.3.3.
Mediation and Conciliation ............................................................................61
4.3.4.
Early Neutral Evaluation ...............................................................................64
4.3.5.
Dispute Boards ...............................................................................................64
4.3.6.
Expert Determination .....................................................................................67
4.3.7.
Adjudication ...................................................................................................69
4.3.8.
Arbitration ......................................................................................................70
4.4.
Developing Countries and Construction Dispute Resolution .........................71
4.4.1.
Generic Problems with ICA............................................................................73
4.4.2.
Peculiar Concerns with ICA ...........................................................................75
4.4.3.
Resolving Major construction Disputes in Ghana .........................................75
iii
Table of Content
4.5.
Knowledge Gaps ............................................................................................76
4.6.
Summary.........................................................................................................77
CHAPTER FIVE - RESEARCH METHODOLOGY ............................................................79
5.1.
Introduction ....................................................................................................79
5.2.
Epistemological Position ................................................................................79
5.2.1.
Positivism .......................................................................................................80
5.2.2.
Interpretivism .................................................................................................81
5.3.
Research Approaches .....................................................................................81
5.4.
Choice and Rationale for Epistemological Position and Research Approach 83
5.5.
Research Methodologies ................................................................................85
5.6.
Research Methods ..........................................................................................87
5.6.1.
Data Collection Methods ................................................................................87
5.6.2.
Data Analysis..................................................................................................90
5.7.
Research Design .............................................................................................93
5.7.1.
Case Design ....................................................................................................94
5.7.1.1.
Case Selection and Justification .....................................................................95
5.7.1.2.
Individuals and Groups relevant to the Study ................................................97
5.7.1.3.
Sampling Techniques for the Selection of Participants ..................................98
5.7.2.
Negotiating Access: Vertical/ Top-down and Horizontal Access Strategies..98
5.7.3.
Data Collection ............................................................................................100
5.7.3.1.
Semi-structured Interviews ...........................................................................100
5.7.3.2.
Pilot Study ....................................................................................................102
5.7.3.3.
Documents ....................................................................................................103
5.7.4.
Sample Size ...................................................................................................104
5.7.5.
Data Analysis................................................................................................105
5.8.
Research Evaluation: Trustworthiness .........................................................106
5.9.
Summary.......................................................................................................106
CHAPTER SIX - DATA ANALYSIS .................................................................................109
6.1.
Introduction ..................................................................................................109
6.2.
Background of Interviewees .........................................................................109
6.3.
General Overview of the Data Analysis Strategy.........................................112
6.4.
Preparing the Data for Analysis ...................................................................113
6.5.
Coding ..........................................................................................................114
iv
Table of Content
6.5.1.
Open Coding .................................................................................................115
6.5.2.
Development of Categories ..........................................................................117
6.5.3.
Integration (Clustering Categories around the Core theme) .......................121
6.6.
Memo Writing ..............................................................................................127
6.6.1.
Code Memos .................................................................................................127
6.6.2.
Methodological and Theoretical Memos ......................................................127
6.7.
Generation of Diagrams and Models ............................................................128
6.8.
Legal Analysis ..............................................................................................130
6.9.
Summary.......................................................................................................131
CHAPTER SEVEN – RESULTS OF DATA ANALYSIS ..................................................134
7.1.
Introduction ..................................................................................................134
7.2.
Features and Context of Parties to Infrastructure-related Construction
Disputes ........................................................................................................135
7.2.1.
The Employer................................................................................................135
7.2.1.1.
The Office of the President ...........................................................................137
7.2.1.2.
Government Ministries and Implementing Agencies ....................................138
7.2.1.3.
Multiple functions and Operational Inefficiencies .......................................141
7.2.2.
Relevant Contextual Issues ...........................................................................147
7.2.2.1.
Human Resource Concerns and Lack of Specialisation...............................147
7.2.2.2.
Political Interference and Corruption ..........................................................149
7.2.2.3.
Fear of Blacklist ...........................................................................................151
7.2.2.4.
Funding Major Infrastructure Projects ........................................................153
7.2.3.
Foreign Consultants and Contractors ..........................................................156
7.3.
Procurement ..................................................................................................158
7.3.1.
Procurement Rules and Methods in use .......................................................159
7.3.2.
The Contract Formation and Review Process ..............................................161
7.3.2.1.
Nominated Conditions of Contract ...............................................................161
7.3.2.2.
Dispute Clauses ............................................................................................163
7.3.2.3.
Special Conditions: Negotiating Dispute Clauses .......................................165
7.3.2.4.
Impact of Public law requirements on Construction Contract Formation ..166
7.3.3.
Legal Institutions ..........................................................................................169
7.3.4.
Use of Alternative Dispute Resolution .........................................................171
7.3.5.
Claim Events and Dispute Causes ................................................................171
v
Table of Content
7.3.6.
Settling Claims..............................................................................................174
7.4.
Construction Disputes Resolution - Mechanisms and Procedure in Use .....176
7.4.1.
DRMs Regularly used ...................................................................................176
7.4.1.1.
The Engineer’s Determination .....................................................................176
7.4.1.2.
Negotiations ..................................................................................................177
7.4.1.3.
International Commercial Arbitration .........................................................180
7.4.1.3.1.
Selection and use of ICA by parties ..............................................................180
7.4.1.3.2.
Cost and ICA ................................................................................................181
7.4.1.3.3.
Delays ...........................................................................................................182
7.4.1.3.4.
Perception of Bias versus Playing Victims ...................................................183
7.4.1.3.5.
Other Perceptions about ICA .......................................................................184
7.4.2.
DRMs Rarely used ......................................................................................184
7.4.2.1.
Dispute Adjudication Boards .......................................................................185
7.4.2.2.
Expert Determination/Independent Experts .................................................186
7.4.2.3.
Conciliation and Mediation ..........................................................................186
7.4.3.
DRMs not agreed by Parties but in use .......................................................188
7.4.4.
Procedure for Dispute Resolution ...............................................................190
7.5.
Barriers to the Use of Alternative Dispute Resolution Mechanisms ............192
7.5.1.
Employer-related barriers ............................................................................192
7.5.2.
Contractor-related factors............................................................................195
7.5.3.
Generic Barriers ...........................................................................................195
7.6.
Summary.......................................................................................................197
CHAPTER EIGHT - DISCUSSIONS: IMPLICATIONS OF RESULTS AND
REMEDIAL STRATEGIES ........................................................................201
8.1.
Introduction ..................................................................................................201
8.2.
Evaluation of the extant dispute resolution processes ..................................201
8.2.1.
Availability of multiple DRM options ...........................................................203
8.2.2.
Freedom to move back and forth between Mechanisms ...............................205
8.2.3.
Substantial involvement of Parties in the design of dispute system .............205
8.2.4.
Voluntary participation, confidential process and involvement of third
party neutrals................................................................................................205
8.2.5.
Transparency and accountability .................................................................206
8.2.6.
Education and training .................................................................................206
vi
Table of Content
8.2.7.
Transaction Cost ..........................................................................................207
8.2.8.
Satisfaction with Outcome and Party relationships .....................................207
8.3.
Factors Accounting for the Extant Dispute Resolution Processes ...............208
8.3.1.
Foreign Contractors and the dispute resolution processes ..........................209
8.3.2.
Influence of funding requirements on Dispute System design ......................209
8.3.3.
The Employer as a Monolith ........................................................................212
8.3.3.1.
Implications for the Occurrence of Disputes................................................213
8.3.3.2.
Dispute Prevention ......................................................................................215
8.3.3.3.
Implications for Dispute Resolution System Design ....................................216
8.3.3.4.
Implications for Dispute Resolution Practice ..............................................219
8.3.3.4.1.
Lack of Inter-organisational Cooperation and Coordination ......................220
8.3.3.4.2.
Impact of Human Resource Constraints on current Dispute resolution
processes.......................................................................................................222
8.3.3.4.3.
Impact of Threat of Blacklist and Political Interference on Dispute
Resolution .....................................................................................................224
8.3.3.4.4.
Impact of the Legal System on Infrastructure-related Construction
Dispute Resolution........................................................................................225
8.4.
Summary of Key Features of the Extant Dispute Resolution Processes ......226
8.5.
Remedial Strategies ......................................................................................227
8.5.1.
Paying Attention to Structures and Context .................................................228
8.5.2.
The Contract Formation Stage – Designing the Dispute Resolution
Structure .......................................................................................................232
8.5.3.
Dispute Avoidance and Resolution ...............................................................233
8.5.4.
Post-Dispute resolution - Evaluation of Outcome........................................235
8.5.5.
The Dispute Resolution Efficiency Cycle .....................................................236
8.5.6.
Contribution of Foreign contractors and Funding Organisations...............238
8.6
Summary.......................................................................................................238
CHAPTER NINE - VALIDATION .....................................................................................241
9.1.
Introduction ..................................................................................................241
9.2.
Validation in Qualitative Research ...............................................................241
9.3.
Procedures for Validation .............................................................................243
9.3.1
Triangulation ................................................................................................244
9.3.2
Reflexivity .....................................................................................................244
vii
Table of Content
9.3.3
Peer Review ..................................................................................................245
9.3.4
Respondent validation ..................................................................................245
9.4.
Validation in this study.................................................................................246
9.5.
Feedback from Interviewees........................................................................247
9.5.1.
Background of Interviewees .........................................................................247
9.5.2.
Results of Analysis ........................................................................................249
9.6.
Transferability ..............................................................................................251
9.7.
Dependability and Confirmability ................................................................252
9.8.
Research Impact ...........................................................................................253
9.9.
Summary.......................................................................................................254
CHAPTER TEN - FINDINGS, CONCLUSIONS AND RECOMMENDATIONS ............257
10.1.
Introduction ..................................................................................................257
10.2.
Research Overview .......................................................................................257
10.2.1.
Objective One ...............................................................................................258
10.2.2.
Objectives two to six .....................................................................................259
10.3.
Findings ........................................................................................................260
10.3.1.
The Extant Dispute Resolution Processes ....................................................260
10.3.2.
Factors Accounting for the Extant Dispute Resolution Processes ...............261
10.3.2.1.
The Complex Employer ................................................................................261
10.3.2.2.
Foreign Contractors .....................................................................................263
10.3.2.3.
The Legal Framework for Procurement and Dispute System Design ..........263
10.3.2.4.
The Legal Framework for Infrastructure-related Dispute Resolution .........265
10.3.2.5.
Factors inhibiting use of Alternative Dispute Resolution Mechanisms .......266
10.3.3.
Remedial Strategies ......................................................................................266
10.3.3.1.
Addressing structural and contextual issues ................................................266
10.3.3.2.
Paying attention to Dispute Resolution System Design ...............................267
10.3.3.3.
Dispute Avoidance and Resolution ...............................................................267
10.3.3.4.
Post dispute resolution –Evaluation of Outcome .........................................268
10.4.
Contribution to Knowledge ..........................................................................269
10.4.1
Contribution to the Field of Dispute Resolution ..........................................269
10.4.2
Contribution to Practice ...............................................................................271
10.5.
Implications of the Research Findings .........................................................271
10.6.
Limitations of Findings ................................................................................273
viii
Table of Content
10.6.1
Geographical Limitation ..............................................................................273
10.6.2
Methodological Limitations..........................................................................274
10.6.3
Subject-Matter Limitation ............................................................................274
10.7.
Self-Reflection ..............................................................................................275
10.8.
Recommendations for further Research .......................................................277
10.9.
Summary.......................................................................................................278
REFERENCES .....................................................................................................................280
APPENDICES ......................................................................................................................293
Appendix A - Interview Guide .............................................................................................293
Appendix A1 - Updated Interview Guide after pilot ............................................................297
Appendix B - A sample Request Letter to Institutions affiliated with the Employer ..........300
Appendix B1 - Request Letters addressed to Interviewees with Institutions affiliated
to the Employer ............................................................................................303
Appendix B2- A sample Request Letter to Foreign Contractors and adjunct
organisations .................................................................................................306
Appendix C –List of Codes ..................................................................................................312
Appendix D – Themes, Categories, Sub-categories and Codes ...........................................328
Appendix E- List of Interviewees and their Code Names ....................................................352
Appendix F - Sample Code Memo .......................................................................................355
Appendix G - Line-by-line coding an impractical tedium for this work ..............................359
Appendix G 1- A Return to Line-by-line coding inevitable in certain circumstances .........361
Appendix H – Request for Feedback on Findings (Interviewees) .......................................362
ix
List of Abbreviations
LIST OF ABBREVIATIONS
AALCO
Asian-African Legal Consultative Organization
ADR
Alternative Dispute Resolution
ADRM
Alternative Dispute Resolution Mechanism
AESC
Architectural Engineering Services Corporation
A-Gs
Attorney-General’s Department
AICD
Africa Infrastructure Country Diagnostics
AsDB
Asian Development Bank
AfDB
African Development Bank
CIDA
Canadian International Development Agency
CPAR
Country Procurement Assessment Report
DAB
Dispute Adjudication Board
DANIDA
Danish International Development Agency
DB
Dispute Board
DFID
United Kingdom Department for International Development
DRBF
Dispute Resolution Board Foundation
DRM
Dispute Resolution Mechanism
DRMs
Dispute Resolution Mechanisms
EBRD
European Bank for Reconstruction and Development
ECG
Electricity Company of Ghana
EIF
European Investment Fund
FDI
Foreign Direct Investment
FIDIC
International Federation of Consulting Engineers
GHACMA
Ghana Association of Certified Mediators and Arbitrators
GhIS
Ghana Institution of Surveyors
GNCC
Ghana National Construction Corporation
GNI
Gross National Income
GOG
Government of Ghana
GRIDco
Ghana Grid Company
GWCL
Ghana Water Company Limited
GWSC
Ghana Water and Sewerage Corporation
IBRD
International Bank for Reconstruction and Development
x
List of Abbreviations
ICA
International Commercial Arbitration
ICC
International Chamber of Commerce
ICSID
International Centre for Settlement of Investment Disputes
IDB
Inter-American Development Bank
IIC
Inter-American Investment Corporation
JICA
Japan International Cooperation Agency
LCIA
London Court of International Arbitration
MDAs
Ministries, Departments and Agencies
MDBs
Multilateral Development Banks
MDFIs
Multilateral development finance institutions
MIF
Multilateral Investment Funds
MOFEP
Ministry of Finance and Economic Planning
ODA
Official Development Assistance
OECD
Organization for Economic Cooperation and Development
OHADA
Organization for the Harmonization of Corporate Law in Africa
PPI
Private Participation in Infrastructure
PPIAF
Public-Private Infrastructure Advisory Facility
PWD
Public Works Department
SALC
South African Law Commission
SHC
State Housing Company
SIDA
Swedish International Development Authority
TCC
Technology and Construction Court
UNCITRAL
United Nations Commission on International Trade Law
UNCTAD
United Nations Conference on Trade and Development
USAID
United States Agency for International Development
VfM
Value for Money
VRA
Volta River Authority
xi
List of Authorities
LIST OF AUTHORITIES
Cases
1.
Ackerman v Ackerman [2011] EWHC 3428 (Ch) …………………………68
2.
ADC Affiliate Limited and ADC & ADMC Management Limited v.
The Rep. of Hungary (ICSID Case Number ARB/03/16) ………………….74
3.
A-G v Faroe Atlantic Company Limited (the Faroe Atlantic Case)
[2005-2006] SCGLR 27 ......................................................................... passim
4.
A-G v. Balkan Energy (Ghana) Limited & Ors (the Balkan Energy
Case) [2012] 2 SCGLR 998 ................................................................... passim
5.
Amec Civil Engineering Ltd v Secretary of State for Transport (the
Amec Case)([2004] EWHC 2339 (TCC) ...................................................50,51
6.
Beck Peppiatt Ltd v. Norwest Holst Construction Ltd. [2003] EWHC
822 ..................................................................................................................50
7.
Bernhard Schulte GmbH & Co KG v Nile Holdings Ltd [2004] 2 Lloyd's
Rep.52…………………………………………………………………… .... 68
8.
Bovis Lend Lease Ltd v Trustees of the London Clinic [2009] EWHC 64
(TCC)………………………………………………………………………. 51
9.
Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC)… ............................51
10.
City Basements Ltd v Nordic Construction UK Ltd QBD (TCC) 14
April 2014 (Unreported)…. ............................................................................51
11.
City & Country Waste Ltd. v Accra Metropolitan Assembly
(the
CCWL Case) [2007-2008] 1 SCGLR 409………… ....................................168
12..
Collins (Contractors) Limited v. Baltic Quay Management (1994) Limited
[2005] BLR 63………………………………………….………………….. 51
13.
Construction Pioneers Baugesellschaft Anstalt (CP) v. Government of
Ghana(Case No. 12078/DB/EC)……………. .............................................170
14.
Ellerine Brothers (Pty) Limited and Another v. Klinger [1982] W.L.R.
1375 ................................................................................................................50
15.
Fastrack Contractors Limited v. Morrison Construction Limited [2000]
BLR168 ..........................................................................................................50
16.
Fili Shipping Co Ltd and others v Premium Nafta Products Ltd and
others [2007] UKHL40………………………………………….. ................70
xii
List of Authorities
17.
Gibson (Banbridge) Limited v Fermanagh District Council [2013]
NIQB 16… ................................................................................................….51
18.
Halifax Life Ltd v Equitable Life Assurance Society [2007] 2 All E.R.
(Comm)……………………………………………………………………...68
19.
Halki Shipping Corporation v. Sopex Oils Limited [ 1998]2 All ER 23
( CA) ...............................................................................................................50
20.
Halki Shipping Corporation v. Sopex Oils Limited [1997] 3 All ER 833
(Q.B) ...............................................................................................................50
21.
Hayter v Nelson and Home Insurance Company [1990] 2 Lloyd’s Rep.
265 ..................................................................................................................53
22.
Lesotho Highlands Development Authority (Respondents) v. Impregilo
SpA and Others [2005] UKHL 43 ..................................................................73
23.
Macro & Others v. Thompson & Others (No.3) [1997] 2BCLC 36……. ......67
24.
Martin Amidu v A-G & 2 Ors. (The Waterville Case) Suit Number
J1/15/2012, judgment of 14 June 2013........................................................168
25.
Pey Casado v. Chile (ICSID Case Number ARB/98/2).. ...............................74
26.
Plama Consortium v. Bulgaria (ICSID Case Number ARB /03/24) .............74
27.
RJT Consulting Engineers Ltd v. DM Engineering (Northern Ireland) Ltd.
[2002] 1 WLR 2344…....................................................................................69
28.
RWE NPower Plc v Alstom Power Ltd [2010] C.I.L.L. 2835)… ...................51
29.
Sterling (t/a M&S Contracts) v Westminster Properties Scotland
Ltd [2007] B.L.R. 537… ................................................................................51
30.
Thames Valley Power Ltd v Total Gas & Power Ltd [2005] [2006]
1Lloyd's Rep. 441 (QBD) (Comm)……………………………………... .....68
31.
Tradax International v. Cerrahogullari TAS [1981]3 All ER 344 .................51
32.
Veba Oil Supply & Trading Ltd v Petrotrade Inc (The Robin) [2002]
1 All E.R. 703……..…………………………………………………………68
33.
Waguih Elie George Siag and Clorinda Vecchi v. The Arab
Republic of Egypt (ICSID Case Number ARB/05/15) ...................................74
Statutes
1.
Alternaternative Dispute Resolution Act, 2010 (Act 798)… ..................76,170
xiii
List of Authorities
2.
Architectural Engineering Services Corporation Act, 1973 (NRCD 193) .....42
3.
Bui Power Authority Act, 2007 (Act 740) ...................................................139
4.
Civil Service Act, 1993 (PNDCL 327)….....................................................138
5.
Companies Act, 1963 (Act 179) … .......................................................156,157
6.
Courts Act, 1993 (Act 459) ..........................................................................170
7.
Ghana Highway Authority Act, 1997(Act 540) ...........................................139
8.
Ghana Investment Promotion Centre Act, 2013 (Act 865)… ......................227
9.
Ghana Water and Sewerage Corporation Act, 1965 (Act 310) ......................42
10.
Housing Grant, Construction and Regeneration Act 1996 ........................49,69
11.
Incorporated Private Partnership Act, 1962 (Act 152) .................................157
12.
Local Democracy, Economic Development and Construction Act,2009 .......69
13.
New South Wales Building and Construction Industry Security of
14.
Payment Act, 1999 .........................................................................................69
15.
Public Procurement Act, 2003 (Act 663) ............................................... passim
12.
State Proceedings Act, 1998(Act 555) .........................................................159
13.
State Property and Contracts Act, 1960 (C.A.6) ..........................................138
14.
Statutory Corporations (Conversion to Companies) Act, 1993 (Act 461) .....42
15.
Statutory Corporations Act, 1964 (Act 232) ..................................................42
16.
Volta River Development Act, 1961 (Act 46) ..............................................139
Rules
High Court (Civil Procedure) Rules,2004 (C.I. 47) .....................................170
International Instruments
1.
Convention on the Recognition and Enforcement of Foreign Arbitral
Awards, 1958 (the New York Convention)……………………………….....71
2.
United Nations Commission on International Trade Law Model Law on
International Commercial Arbitration, 1985 (as amended in 2006) ..............71
xiv
List of Figures
LIST OF FIGURES
1.1
Overview of the Research Process…………………………………………....11
2.1
Total private investment commitments to infrastructure projects
in developing countries, by region, 1990–2008………………………………30
5.1
The Research Process Disc…………………………………………………….80
5.2
Case Description……………………………………………………………….95
5.3
Number of Interviews per week……………………………………………...102
6.1
Interviews by Participants……………………………………………………111
6.2
Professional Background of Participants…………………………………….111
6.3
Coding Hierarchy…………………………………………………………….115
6.4
Link between ‘Institutional Structures’ and child nodes…………………….119
6.5
The theme ‘Features and Context of Parties to the dispute resolution
processes’ associated categories and some linked codes…………………….120
6.6
The theme ‘Features and Context of Parties to the dispute resolution
processes’ associated categories and some linked codes……………………124
6.7
The theme ‘Remedial Strategies’ and its categories ………………………...125
6.8
The five themes generated through the process of Clustering……………….125
6.9
Contract Review Process-Embedded in the procurement process…………...130
7.1
The Organogram of GHA…………………………………………………….141
7.2
Visual representation of interactions between sub-units
of the Employer prior to contract execution…………………………………145
7.3
Factors influencing the selection of Dispute Resolution mechanisms ……...166
7.4
Dispute Resolution Mechanism in use……………………………………….189
7.5
Dispute Resolution Procedure………………………………………………..191
7.6
Dispute Resolution Route…………………………………………………….192
7.7
Employer-related barriers…………………………………………………….195
8.1
The Dispute Resolution Efficiency Cycle (DREC)…………………………..238
9.1
Participants in the validation by Participants………………. ……………….248
9.2
Professional Background of Participants……………………………………..248
xv
List of Tables
LIST OF TABLES
2.1
Distribution of Findings on impact of infrastructure on productivity
and growth……………………………………………………………………33
4.1
List of studies on construction disputes………………………………………53
4.2
Reasons affecting the selection of dispute resolution mechanisms…………..58
6.1
Participating Ministries, Departments and Agencies with number of
interviewees in brackets………………………………………………...109,110
6.2
Codes on question regarding claim events…………………………………..117
6.3
The Category ‘claim events’ and its child nodes……………………………118
6.4
List of
Categories……………………………………………………………………120
6.5
Research Objectives and the corresponding themes and categories
addressing them……………………………………………………………...126
7.1
Codes on Factors considered during contract review by the A-Gs………….143
7.2
Ghana-Budgetary Allocation for the Energy Sector………………………...153
7.3
Ghana –Budgetary Allocations for the Road Sector………………………...154
7.4
Ghana –Budgetary Allocations for the Water Resource, Works and
Housing Sectors……………………………………………………………..154
7.5
Claim Events and Dispute Causes…………………………………………..172
8.1
Recommendations on Front-end Preparations for Dispute Resolution……..229
8.2
Summary of the Four Sets of Remedial Strategies………………………….235
9.1
Lincoln and Guba’s (1985) criteria for qualitative validation compared
with Quantitative Approaches………………………………………………242
9.2
Practical Steps towards ensuring Quality of the Research ………………….253
xvi
Acknowledgment
ACKNOWLEDGMENT
My foremost thanks go to the Most High God who gave me the desire, wisdom and
strength to undertake this study. With you, all things are possible!
My sincerest gratitude goes to my Director of Studies and mentor, Professor Issaka
Ndekugri whose inspiration and keen interest in the field of construction law and dispute
resolution gave birth to this study in the first place. Prof, thank you for the unwavering
support, guidance and direction you have provided throughout this process. Your deep
insights, amazing commitment and firm belief in high academic standards have left indelible
marks on my thought processes. I am also grateful to Dr Nii Ankrah and Dr Felix Hammond,
members of the supervisory team, for their immense contribution. Nii, I owe my improved
appreciation of the value of packaging to you!
I thank the University of Wolverhampton for providing the resources which made this
study possible. I also thank Professor Cousins for her encouragement throughout the study. To
the Dean of the Faculty of Law, University of Ghana thanks for your support. I am
particularly indebted to Mr. K.K.K. Ampofo, the Vice-Dean of the Faculty for his
encouragement, constant support and advice throughout this study. To you, Madam Justina
Tete-Donkor, your support is deeply appreciated.
To all the interviewees, too numerous to mention individually, who made time to share
their perspectives on the subject of investigation, I deeply appreciate your contribution to this
work. My thanks also go to all the esteemed individuals at the Attorney-General’s
Department, the Ministry of Finance and Economic Planning, the Ministries of Roads and
Highways, Energy and Water, Works and Housing for their unparalleled assistance during
data collection. Similarly, my heartfelt appreciation goes to all the personnel at Ghana
Highways Authority, Ghana Water Company Limited, the Volta River Authority, Electricity
xvii
Acknowledgment
Company of Ghana and the Public Procurement Authority who made time to assist in the data
collection process.
To my friends, Dorothy Dede Wetseh, Esther Lamptey, Victoria and the crew at High
Court two, Accra, thanks for your amazing contribution. To Christina Corquaye and Aasiya
Nettey who assisted me with the transcription and Nana Ntenah, I appreciate your sacrifices
for me.
To my Mother, Beatrice and siblings, Felicia, Rose, Mercy, William and Emmanuel, this
achievement is only possible because you have supported and prayed with me throughout my
life. Your constant inquiries about progress of work and encouragement did it! To the body of
Christ both at home and at Wolverhampton, thank you for your spiritual support. To the
Baffour-Awuahs, Solomon, Dingayo, Stan, Emmanuel, Nami, Tulika, Dominic and all other
colleagues, we have travelled together on this journey. Your support is much appreciated!
Finally, to my loving and supportive wife, Genevieve Juliet Mante and my children, Charis
and Joel, thank you for your understanding, love and support. Gene, I will always remember
your profound sacrifice for me and the children during this study.
xviii
Dedication
DEDICATION
This thesis is dedicated to my Heavenly Father. In Him I live, and move and have my being!
And to my earthly Parents, Mathew and Beatrice
xix
General Introduction
CHAPTER ONE
1
General Introduction
CHAPTER ONE - GENERAL INTRODUCTION
1.1.
Introduction
This study was about how construction disputes arising out of major infrastructure
projects in developing countries were resolved. A brief background to the study is provided
leading to the identification of gaps in the relevant dispute resolution literature. The chapter
then provides an outline of the research aim and objectives, the methodology employed and
justification for the study. A summary of the findings, the scope and limitations of the
research and the structure of the thesis are also presented.
1.2.
Background of Study
Like oxygen to the body is infrastructure development to economic development. It is not
the only thing needed for sustainability, growth and development, but it is, without doubt,
indispensable. This is more so for developing countries (Giang and Sui Pheng, 2011;
Moavenzadeh, 1978). The International Bank for Reconstruction and Development and other
Multilateral Development Banks (MDBs) have identified infrastructure development (roads,
water treatment, plants, power generation/transmission plants and irrigation projects) as
essential part of any effective strategy for alleviating poverty in the developing world (World
Bank, 1994; Briceno-Garmendia et al., 2004).
As a consequence of their importance and the huge investment required, infrastructure
projects have historically been the preserve of States (World Bank, 1994; UNCTAD, 2008;
Briceno-Garmendia et al., 2004). As of 1994, developing countries were investing about two
hundred billion United States dollars ($200 billion), amounting to about four per cent (4%) of
their national output and a fifth of their total investment into infrastructure development
(Kessides, 1993; World Bank, 1994). UNCTAD (2008) maintains that States will need to
spend between seven per cent (7%) and nine per cent (9%) of their gross domestic product
(GDP) on infrastructure if the huge infrastructure gap is to be bridged. The efforts of States in
2
General Introduction
the provision of infrastructure have been complemented by the private sector (World Bank,
1994; UNCTAD, 2008). The last two decades have seen increased public-private participation
in infrastructure development. Between 1990 and 2001, about 2500 infrastructure projects in
developing countries attracted investment commitments of more than $755 billion from the
private sector (Harris, 2003; Kirkpatrick et al., 2006). According to the World Bank
sponsored Private Participation in Infrastructure Advisory Facility (PPIAF), these investment
commitments increased to about US$ 843.3 billion between 2001 and 2008 (World Bank and
PPIAF, 2010). Both State and private sector participation in infrastructure has been bolstered
by increasing number of studies indicating a strong relationship between infrastructure
development and economic development (see section 2.6). The literature on the current state
of infrastructure development, the role of the MDBs, and the impact of infrastructure on
economic development is reviewed in chapter two.
At the heart of the expansion of infrastructure in developing countries is the procurement
process. As a result of the huge capital outlay required, many infrastructure projects are
awarded to foreign construction companies with capacity to execute these projects (Chan and
Suen, 2005). In Africa, for instance, many American, European and Asian construction
companies have been involved in infrastructure project construction for decades. A table
compiled from Engineering News Record by Chen et al. (2007) spanning the period 20012005 reveals that American contractors had 15.42% market share of construction projects on
the African continent in 2005. Whilst British firms had 5.04% of the share of the market,
European contracting firms collectively had 49.33% of the construction market share. In
recent years, many Chinese construction companies have joined the competition for
construction projects on the African continent and controlled 21.36% of the market as of 2005
(Chen et al., 2007). The story in Ghana was not different. The main parties involved in the
procurement of major infrastructure projects were the State and its agencies, and foreign
3
General Introduction
contractors. The literature on procurement of infrastructure projects in Ghana is reviewed
under chapter three.
By virtue of the very nature of infrastructure projects (see section 2.2) and the peculiarities
of the construction industry (section 4.2.3), disputes do occur during and after the process
(Hibberd and Newman, 1999; Gaitskell, 2006; Hinchey, 2012). Many infrastructure-related
construction disputes which occur in the developing world, including Ghana, were
international in nature as they involved foreign contractors and were resolved at great cost to
the parties. Dispute resolution on international projects is by nature very expensive. The
literature on dispute resolution in developing countries points to international commercial
arbitration
(ICA)
Ehrenhaft,1977;
as
the
preferred
McLaughlin,1979
dispute
resolution
;Herrmann,1983;
mechanism
Hoellering,1986;
(Sanders,1973;
Perloff,1992;
Paulsson,1996; Asouzu,2001; Tackaberry and Marriott,2003; Blackaby et al., 2009).
Developing countries have had to embrace the option of international arbitration for
reasons associated with investment (Sempasa, 1992; Asouzu, 2001). In the specific case of
major infrastructure-related construction dispute resolution, ICA has been adopted for reasons
including obtaining funding for projects. Procurement rules of foreign sponsors invariably
demanded the incorporation of ICA into transactions they sponsored. Virtually all standard
form contracts governing major construction transactions in developing countries, notably
those published by the International Federation of Consulting Engineers (FIDIC), contain
provisions on ICA. It is stated that the dominance of the use of ICA has created a de facto
universality of it as the normal method of dispute settlement and parties often choose it
without much thought as to its appropriateness (Capper and Bunch, 1998). Other reasons why
arbitration is preferred as the dispute resolution mechanism of choice have been examined
under section 4.3 and 4.3.8.
4
General Introduction
However, the literature also revealed that developing countries have issues with ICA.
These included challenge to their sovereignty, legitimacy of the system of international
arbitration and fear of frivolous and vexatious claims against States by disenchanted entities
(Asouzu, 2001). Additionally, there were issues of cost, delays and consequent disruption of
works and perceived bias (Asouzu, 2001; UNCTAD, 2010). For instance, regarding cost, the
perception was that disputes arising out of major infrastructure projects were often resolved at
great cost to developing countries. The United Nations Conference on Trade and
Development (UNCTAD) report on investor-State dispute prevention confirmed cost of
arbitration was increasing (UNCTAD, 2010). For many developing countries, this was a cause
for concern. Often, out of their meagre resources, these countries bore the cost of resorting to
ICA. This entailed payment of registration fees, administrative expenses, counsel fees and
arbitrator’s fees and expenses. Other financial liabilities included expenses relating to
witnesses, court, travel, accommodation and feeding for local representatives and lawyers
pursuing or defending claims on arbitration (Asouzu, 2001). Another concern was delay
occasioned by resort to ICA (UNCTAD, 2010). Major Construction projects are expensive
long term undertakings. Unresolved disputes can threaten timely completion of projects and
add to cost (Miller and Lessard, 2000).
Apart from the multiplicity of sources of disquiet raised about ICA, three other conclusions
emerged from the literature. Firstly, construction disputes were treated like any other dispute
involving the State and a foreign entity such as trade and investment disputes (Asante, 1998;
Asouzu, 2001). Construction contracts and resultant disputes have their technical peculiarities.
Capper and Bunch (1998) name the multiplicity of parties, site specificity, lack of clear and
fixed specification by an employer and the sheer variety and volume of evidentiary material
as some of the distinctive features of the construction contract. Another of the peculiar
features is the complicated payment system which often fosters disputes. Again, construction
5
General Introduction
disputes (invariably relating to cost, time and or defects) are often technical and require the
services of technical specialists (Capper and Bunch, 1998). It is therefore not surprising that
in many developed countries such as the United Kingdom, there are specific courts devoted to
the handling of construction disputes.
Secondly, the existing literature on the subject of dispute resolution in developing
countries did not provide adequate information on how construction disputes arising out of
major construction projects involving the State and foreign contractors were resolved. Both
the World Bank Procurement Guidelines and the International Federation of Consulting
Engineers (FIDIC) Conditions of Contract acknowledge the need for other resolution
mechanisms apart from international arbitration for construction disputes. However, there was
dearth of literature dealing specifically with infrastructure-related construction dispute
resolution mechanisms in use in developing countries, particularly those in Africa. Very little
information existed on dispute avoidance, management and resolution generally. The issue of
lack of empirical information was acknowledged by Fenn et al. (1998) in their report on the
techniques and procedure for the management of construction disputes. They indicated that
discourse on construction disputes, even in the developed world, has mainly been theoretical.
The lack of empirical information, they acknowledged, was an international problem.
However, the national practices collected in the said report also contained information mainly
from developed countries.
Thirdly, there was a knowledge gap in respect of what transpired immediately a dispute
arose and when formal ICA processes commenced. The FIDIC Conditions of Contract often
advocated the use of the Engineer’s determination (see the Red book, 1987), Dispute Boards,
amicable settlement and ICA. No empirical evidence was found on the workings of the FIDIC
recommended resolution mechanisms and the challenges associated with them. What parties
did in the course of the period for amicable settlement was generally unknown. Further, the
6
General Introduction
materials reviewed did not consider the viability and the role that alternative dispute
resolution mechanisms (ADRMs) other than arbitration could play in resolving such disputes
and the factors impeding their use. Again the literature did not examine the issues of
efficiency and effectiveness of the mechanisms in use and how the front-end processes
affected the resolution processes. The literature relating to construction disputes arising out of
major projects and trends on the use of various resolution mechanisms are discussed further
under chapter four.
On the basis of the gaps identified in the existing literature and the problems identified,
two key questions arose. The first question was how did parties to major infrastructure
projects in developing countries resolve construction disputes which arose out of such
projects? Flowing from this key question, other issues including the following emerged: (i)
the features of the organisational structure of the main parties involved in major infrastructure
procurement and the context within which they operated; (ii) the legal framework for the
procurement of infrastructure projects and dispute resolution; and (iii) mechanisms and
procedures by which parties resolve construction disputes which arose out of major projects.
The second key question was what strategies could assist parties in their bid to resolve
construction disputes effectively and efficiently. An offshoot of this question was what the
barriers or peculiar obstacles preventing efficient and effective resolution of construction
disputes were and how they could be remedied?
1.3.
Aim and Objectives
On the basis of the questions which emerged from the literature review, this study aimed at
a critical examination of developing countries’ experiences of infrastructure-related
construction dispute resolution with the view to develop strategies for efficient and effective
resolution. To achieve the above aim, six objectives were set and pursued namely:
7
General Introduction
1. a critical review of the literature on the state and trends of infrastructure development
in developing countries, the processes relating to major project acquisitions and how
construction disputes arising out of such transactions were resolved;
2. identification and examination of features and context of the key parties involved in
construction and civil engineering contracts relating to major infrastructure projects;
3. an investigation into aspects of the legal framework for infrastructure procurement
relating to dispute resolution such as the contract formation process;
4. examination of the legal framework for resolving disputes arising out of major
projects including the processes involved from the emergence of a dispute to its final
determination;
5. identification of challenges to the existing modes of resolution including barriers to
the use of methods other than litigation and international commercial arbitration;
6. development of an explanatory framework and remedial strategies for the extant
construction dispute resolution processes.
1.4.
Research Methodology
The study adopted a qualitative research approach informed by the interpretivist
philosophical paradigm. The choice of philosophical paradigm was based on reasons outlined
in section 5.4. The enquiry aimed at securing an in-depth understanding of the process of
dispute resolution through the views of participants in the major infrastructure sector.
Disputes and their resolution are integral parts of the life of individuals. Thus, their views and
experiences were relevant to understanding the process (Denzin and Lincoln, 2005; Marshall
and Rossman, 2006; Creswell, 2007; Creswell, 2009). The study used case study as a strategy
of inquiry for reasons such as the nature of the research objectives, the contemporary nature
of the object of inquiry and the need for an in-depth investigation into its heterogeneous
properties in a holistic manner (see section 5.5 and 5.7).
8
General Introduction
Ghana was selected as a holistic and typical case (in the context of developing countries)
with data collected from the State and its agencies (as the employer) and contractors (see
section 5.7.1). The selection of Ghana as a typical case was based on the assumptions that
States are the main clients to infrastructure development in most developing countries (see
section 2.3), most infrastructure construction projects are executed by foreign contractors
(7.2.3) and there is heavy reliance on external funding for such projects (see section 2.5).
Other assumptions include the prevalence of disputes and similarities in approaches to dispute
resolution in developing countries. Further, Ghana was selected as a typical case on the basis
of prospects of in-depth investigations into the phenomenon studied due to the accessibility
and hospitability of the case and convenience (see Stake, 1995; Yin, 2009).
In all, fifty-six interviewees participated in the research. Forty-five participants were
drawn from five government ministries, eight implementing agencies and one independent
institution of State. The participants were mainly employees of the State in senior
management positions. They had diverse backgrounds in law, engineering and quantity
surveying and were sampled based on their knowledge and experiences with past and ongoing major infrastructure projects, especially those which had or were still experiencing
disputes. Additionally, eleven participants from private construction and allied organisations
were also selected based on previous dispute resolution experiences on major projects
involving the State. Details of the background of the participants are reported in chapter six
(see section 6.2).
Data were collected through two main sources, interviews and documents. This was in
line with qualitative sources of data discussed by Denzin and Lincoln (2005), Creswell
(2007), Gubrium and Holstein (2002) and other treatises on qualitative data. Three types of
documentary data were collected. These were archival records, internal documents of relevant
organisations and institutions, and documents of a legal nature such as legislations and
9
General Introduction
judicial decisions (see section 5.7.3.3). Additionally, semi-structured interviews were
conducted with participants. Themes covered by the interviews included background of
interviewees and their organisations, the extent of their involvement in the procurement of
major infrastructure projects and matters relating to disputes and how they were resolved. The
themes were based on the research objectives. Semi-structured interviews were used because
of the opportunities they offered for further exploration of interesting concepts and
verification of ideas from previous interviews (see Gubrium and Holstein, 2002; Denscombe,
2007).
Borrowing from qualitative data analysis procedures associated with grounded theory
research, this study employed procedures such as coding, constant comparison, memoing and
diagramming (hereafter referred to collectively as grounded theory principles) as tools for
data analysis. Doctrinal legal analysis was used to examine documents which were of a legal
nature. Generally, the approach to data analysis was inductive. Data were broken down to
smaller chunks and labelled as codes under the process of open coding. A total of six hundred
and twenty-one codes were generated out of which thirty-eight sub-categories and twentythree categories were developed. Subsequently, the categories and sub-categories were further
integrated into five themes which addressed the objectives two to six of the study. The five
themes are ‘Features and Context of Parties to Dispute Resolution’, ‘Procurement’, Dispute
Resolution Processes’, ‘Consequences of the Extant Dispute Resolution Processes’ and
‘Remedial strategies’. The process of data analysis was accompanied by memo writing and
diagraming. Memos were used to explore codes and categories, to record thoughts about
methodology and to capture the emerging story from the data analysis. Diagrams were also
used to illustrate emerging linkages between ideas explored through the memos. Details of the
data analysis procedures are reported in chapter six. The study adopted Lincoln and Guba’s
10
General Introduction
(1985) criteria of trustworthiness and authenticity to establish the credibility of the research
findings (see chapter 9). Below is an overview of the research process.
Review of relevant literature
Problem Statement
Research Questions
(derived from review of the literature)
Aim and Objectives
Qualitative Research Approach
(Interpretivism)
Data Analysis
Data – Source
A holistic case study
Semi- structured Interviews (56
interviews from Employers and
Contractors)
Documents(Archival
records,contemporary documents on
internal procedures of institutions,
documents of a legal nature, e.g.
legislations, judicial decisions etc.)
Ghana
Grounded Theory
principles
Doctrinal Legal
Analysis
Theoretical Work
(Further literature
review)
Results of Data Analysis /
Meeting Research Objectives
(Emergence of explanatory framework &
remedial strategies)
Validation
Writing up Research findings
Figure 1:1: Overview of the Research Process
11
General Introduction
1.5.
Research Justification
The growing emphasis on infrastructure development in developing countries has
translated into the procurement of major projects. With increased construction activities,
disputes have become inevitable (see section 4.2.3). Effective dispute resolution is crucial to
project success. Unfortunately, the literature indicated that such disputes were often resolved
largely in international fora leading to cost and delays (Asouzu, 2001). There have been
sustained concerns about the effect of infrastructure-related dispute resolution on State
resources in Ghana in recent times (see Daily Graphic, 2013). This has culminated in the
conduct of parliamentary inquiries into how some disputes between the State and some
foreign entities were resolved (Parliament of Ghana, 2012).
As a further response, the
Government appointed a Commissioner to investigate the extent of the liability of the State
(Daily Graphic, 2012).
However, as important as this subject is, little was known about pre-ICA dispute resolution
approaches. There were no known studies exploring dispute avoidance, management and
alternative resolution strategies in the specific case of Ghana. There was no known empirical
study on how parties to major infrastructure projects resolved construction disputes arising
out of such projects. The absence of research into construction dispute resolution in Ghana, as
was the case with many developing countries, meant parties involved in major construction
disputes were deprived of standards by which their current dispute resolution practices could
be appraised. The lack of industry-specific policies, structures and expertise for construction
dispute resolution could also be attributed partly to the absence of research clarifying issues in
the field and suggesting possible solutions. This study has contributed to efforts to fill this
knowledge gap in the context of the developing world. It has provided information that will
help the different constituencies involved in major infrastructure projects better appreciate the
dynamics of the resolution processes within the industry. It is expected that such an
12
General Introduction
understanding will influence dispute resolution choices of parties to projects and improve
outcomes.
In terms of contribution to policy, there were no clear industry-specific policy and
guidelines on how construction disputes involving the State and foreign contractors should be
dealt with in Ghana. Consequently, negotiation of contracts and construction dispute
resolution were dealt with on ad hoc basis. This research has made contribution to policy by
drawing the attention of governments in the developing world to the utility of such a process.
A policy on dispute resolution will enhance transparency in the dispute resolution processes.
For foreign contractors, international arbitration may not necessarily be the most costeffective and useful means of resolving disputes. Considering and encouraging the use of
intermediary dispute resolution mechanisms may eventually lead to reduction in cost and
delays and the preservation of business relationships.
1.6.
Summary of Findings, Conclusions and Recommendations
The findings of the study have been divided into three main components namely, the
extant dispute resolution processes, factors accounting for it and remedial strategies. The first
component describes the findings on current construction dispute resolution practices as they
relate to major infrastructure projects in Ghana. The second part identifies factors that account
for the extant dispute resolution processes. The third component examines recommendations
for improvement. A summary of the findings are presented below.
1.6.1. Extant Dispute Resolution Processes
The phrase ‘extant dispute resolution processes’, as used in this work, refers to the
existing infrastructure-related construction dispute resolution practices particularly those
relating to parties’ choices of dispute resolution mechanisms or methods and how they are
utilised. The study found that Engineer’s determination; negotiation and international
arbitration were the regularly utilised dispute resolution mechanisms (DRMs) (see section
13
General Introduction
7.4.1). This finding partly confirms the position of the existing literature that ICA remains the
preferred mechanisms for dispute resolution (Asouzu, 2001). Other mechanisms such as
Dispute Adjudication Boards (DAB), Expert determination, Mediation and Conciliation were
rarely used (see section 7.4.2). Further, there was evidence of the use of informal mechanisms
such as intervention by government officials in dispute resolution (see section 7.4.3). The
study pointed to high dispute resolution transaction cost (in terms of money and time
expended), low satisfaction with international arbitration outcomes and negative effect of
international arbitration on relationships between parties (see sections 7.4.1.3.2 to 7.4.1.3.5)
as features of the extant dispute resolution processes.
Informal dispute resolution mechanisms such as resort to political officeholders lacked
transparency and accountability. Parties relied extensively on negotiations due to lack of
regular education and training of professionals in other dispute mechanisms. There was no
national policy on infrastructure-related construction dispute resolution. Construction and
engineering disputes were treated like any other, despite their peculiar features. Further, there
was no written policy or guidelines on the use of ADR by the Employer on disputes arising
out of major projects. To address the challenges with the extant dispute resolution processes
there was a need to identify the factors which had shaped it. These factors are summarised
below.
1.6.2. Factors Accounting for the Extant Dispute Resolution Processes
The data analysis disclosed that the existing dispute resolution processes was the product
of the nature of the parties involved in major infrastructure procurement, the context in which
they operated and their activities, which were essentially, their responses to the context. The
two main parties, namely, the Employer (the State and its agencies) and foreign contractors
possessed distinct features which had enormous bearing on the workings of the dispute
resolution processes. The State as an Employer is considered as a single unit. This
14
General Introduction
consideration failed to take into account the multiple structures which came together to
constitute the entity called the State. The study found that the Employer was made up of
multiple organisations (sub-units). Each of these sub-units played a unique role in the
performance of the contractual duties of the Employer. As a result, every step taken by the
Employer towards the fulfilment of its obligations required cooperation among the sub-units
and coordination of their activities. These translated into lengthy consultations and approvals.
Consequently, the Employer’s performances under construction contracts naturally suffered
delays.
The problems associated with the workings of the Employer were exacerbated by other
contextual issues such as internal turf wars, human resource constraints, political interference
and the fear of being blacklisted. These weaknesses affected the Employer’s ability to prepare
adequately for projects, avoid disputes, negotiate an efficient dispute resolution system and
resolve disputes effectively.
By virtue of their nature as foreign entities, foreign contractors preferred dispute
resolution mechanisms which were neutral, fair and could deliver binding outcomes capable
of enforcement not only in the Employer’s jurisdiction but also worldwide. International
arbitration satisfied these criteria and thus remained the preferred dispute resolution
mechanism for foreign contractors. Detailed examination of the structure, functions and other
features of the Employer and foreign contractors which impacted the dispute resolution
processes can be found in chapter seven.
The framework for procurement, particularly the process by which parties designed the
dispute resolution system for future use had enormous influence on how they eventually
resolved disputes which arose from projects. It was found that parties to major construction
transactions had limited influence over the selection of dispute resolution mechanisms and
procedures. Funding agencies nominated Conditions of Contract which contained dispute
15
General Introduction
clauses. Parties’ negotiations on future dispute resolution took place within the parameters of
the dispute clauses in nominated Conditions of Contract. Very little was done by the parties,
especially the Employer, to adjust the standard dispute clauses to suit their needs or address
existing problems with dispute resolution. Procurement strategy was determined mainly by
funding requirements. There was little awareness of the potential positive impact that the
procurement process can have on dispute resolution (see section 7.3.1). Detailed analysis of
the procurement process as it related to contract formation and the dispute resolution system
design in particular is presented in section 7.3.
On the basis of the finding that intermediary dispute resolution mechanisms were rarely
used (see section 1.6.1), the study sought to identify factors which inhibited the use of such
mechanisms. The factors identified were categorised into three, namely employer-related,
contractor-related and generic barriers. The employer-related barriers included lack of
institutional cooperation, poor record keeping and fear of failure to meet expectations. Other
examples of employer-related barriers were the fear of being blacklisted entertained by
contractors, lack of stance on alternatives to ICA, public suspicion and lack of specialisation.
An example of contractor-related barriers was fear of victimisation. The generic barriers to
the use of intermediary dispute resolution mechanisms identified included lack of adequate
knowledge of alternatives to international arbitration, the adversarial culture and negative
perceptions of ADR. Detailed examination of the barriers to the use of ADR is presented in
chapter seven (see section 7.5).
1.6.3. Remedial Strategies
Based on the features of the extant dispute resolution processes, the factors accounting for
them and the consideration of the relevant literature, four sets of remedial strategies were
recommended. These are as follows: (i) addressing structural and contextual problems; (ii)
paying attention to dispute resolution system design; (iii) focusing on dispute avoidance and
16
General Introduction
resolution; and (iv) institutionalising post-dispute resolution evaluation of processes and
outcome. Regarding structural preparations, it is submitted that parties to major infrastructure
contracts, particularly the Employer, need to take specific steps to prepare the context within
which procurement takes place and to put in place adequate structures to ensure that they can
effectively deal with disputes which subsequently emerge.
Ten structural and contextual preparations are recommended based on the data analysis.
These include the formulation of specific policies on dispute avoidance and resolution with
overriding objectives for infrastructure-related construction dispute resolution, developing
standards and guidelines for the use of less known and utilised dispute resolution mechanisms
and streamlining institutional roles in the resolution of disputes. Further information on the
other recommendations under this set of remedial strategies is reported under section 8.5.1.
The second set of remedial strategies focused on dispute system design. For the Employer,
five specific strategies are recommended for adoption and utilisation during contract
negotiations, particularly the aspect on dispute clauses. Firstly, negotiations on dispute clauses
must focus on establishing a dispute resolution framework or structure capable of achieving
the overriding dispute resolution objectives of the Employer. Secondly, lessons from previous
dispute resolution experiences must inform new negotiations on dispute clauses. Thirdly,
negotiations on dispute clauses need to incorporate new terms on specific possible
intermediary resolution mechanisms which parties will utilise during the period of amicable
settlement. The fourth recommendation is that personnel involved in contract negotiations at
the Ministries, Departments and Agencies (MDAs) of the Employer must receive regular
training. Finally, to help the Attorney-General’s Department (A-Gs) to efficiently perform its
legal obligation of contract review, the Employer need to consider setting up a unit within the
A-Gs to specifically perform this role. Additional information on this set of recommendations
is presented under section 8.5.2.
17
General Introduction
The third set of remedial strategies focuses on enhancing dispute avoidance and reduction
and effective resolution. Strategies which can be employed to realise the goal of
institutionalising and enhancing dispute avoidance and reduction include the following: (i)
developing a policy on dispute prevention and reduction; (ii) using standing neutrals such as
Dispute Review Boards; (iii) employing collaborative procurement methods which encourage
parties to focus on reducing disputes;(iv) effective project management; and (v) training staffs
responsible for projects to be aware of and comply with the Employer’s policy on avoidance.
In relation to the actual dispute resolution processes, three strategies are recommended.
Firstly, it is suggested that the MDAs’ capacity to effectively perform their existing roles of
dispute resolution should be strengthened through regular training in the use of ADR
mechanisms. Effective dispute handling at the MDAs will limit the number of disputes which
eventually reach the A-Gs. At the A-Gs, it is recommended that a unit be established to be
solely responsible for infrastructure-related dispute resolution referred to the A-Gs by the
MDAs. Secondly, the Employer must focus on the use of intermediary dispute mechanisms in
appropriate cases. The decision to use a particular dispute resolution mechanism must be
made in accordance with the proposed guidelines on the use of ADR. Finally, active costcutting measures must be implemented during international arbitration proceedings through
the enforcement of agreements on cost sharing and the use of rules of evidence which aim at
cost reduction. Further details of this set of remedial strategies are presented under section
8.5.3.
The final set of remedial strategies aim at institutionalizing post-dispute resolution
evaluation of processes and outcome. It is expected that lessons learnt from such process will
be fed back into the system to improve subsequent infrastructure-related dispute resolution
processes. The four sets of remedial strategies have been integrated into a theoretical model
called the Dispute Resolution Efficiency Cycle which demonstrates how parties involved in
18
General Introduction
infrastructure procurement can, through regular improvements, resolve disputes more
effectively (see Figure 8.1). Further information on the proposed model is presented under
section 8.5.5.
1.6.4. Implications of findings for other Developing Countries
The findings have implications for other developing countries. As demonstrated by the
literature, ICA remains the dominant resolution mechanism for infrastructure-related
construction disputes in many developing countries especially those in Africa (Asouzu, 2001;
Cotran and Amissah, 1996). This study shows that creating an effective dispute resolution
system in developing countries will require more than the dominant use of ICA. A holistic
approach to dispute resolution as captured by the Dispute Resolution Efficiency Cycle is what
is recommended (see section 8.5.5). However, it is noted that the issues to be addressed under
each component of the Cycle may differ from country to country.
1.7.
Scope and Limitation
This section describes the scope of the study in terms of the kind of disputes, parties,
projects and geographical location it relates to.
The study primarily focused on how
construction-related disputes arising out of major infrastructure projects were resolved.
Dispute resolution, the core concept under examination relates to all aspects of life. Indeed,
the process of major infrastructure procurement in developing countries is often fraught with
various kinds of disputes relating to issues such as labour, land, ownership, compensation
claims and resettlement. The study concentrated on construction disputes. The work did not
extend to the other types of disputes mentioned. However, the core principles and findings of
the study are likely to be useful to the resolution of other disputes as well.
Further, the investigation focused on main parties to major infrastructure procurement in
developing countries, the State/Government and its agencies as the Employer and foreign
contractors. It is acknowledged that, disputes may and do erupt between parties other than the
19
General Introduction
main parties to an infrastructure-related construction contract with different ramifications.
There are instances where such disputes may erupt between a foreign design firm and a
construction firm, a foreign major contractor and a domestic sub-contractor, two foreign
design firms or two foreign construction firms. There is also a possibility of multi-party
disputes involving three or more parties (see Draetta, 2011). The focus of this research,
however, was on construction disputes between the State as an Employer and foreign
contractors.
Additionally, the study focused on specific types of projects described as major
infrastructure projects (see chapter two). In the context of this study, major infrastructure
projects are public projects involving the Employer and foreign contractors. Though a
contractor may be incorporated in a particular developing country, it does not necessarily
mean that transactions it conducts with the government of that particular country or its
agencies are to be considered as domestic in all situations. Using Ghana as an example, so
long as the place of central management and control of the contractor is situated outside the
jurisdiction of Ghana and the transaction has a significant foreign element, such a project will
be considered as involving foreign participation and thus, come under the scope of this work
(see A-G v. Balkan Energy (Ghana) Limited & Ors (the Balkan Energy Case) [2012] 2
SCGLR 998). Examples of major infrastructure projects which remained the focus of this
study included the construction of roads, water supply systems, dams and thermal plants.
In terms of the geographical location of interest, the study relates to developing countries
generally with Ghana as a case study (see section 5.7.1.1). Notwithstanding the choice of
Ghana, the findings of the research may be useful to developing countries many of which
share infrastructure procurement characteristics similar to those pertaining to the Ghana (see
Flyvbjerg, 2006). Admittedly, country-specific differences may warrant further work to be
done in order to make the findings specifically applicable to the situations of individual
20
General Introduction
developing countries (see section 9.6). Methodologically, it is appreciated that the primary
goal of a case study is to focus on the case in issue. However, the use of grounded theory
principles enabled the issues at stake to be examined conceptually. Consequently, the
relevance of the resulting concepts goes beyond Ghana to other developing countries.
1.8.
Contribution to Knowledge
Contribution that this study has made to knowledge can be viewed from two perspectives
namely substantive contribution to the field of dispute resolution (see section 10.4.1) and
practice (see section 10.4.2). On the first perspective, the study has contributed to the body of
knowledge on the field of dispute resolution as it pertains to the resolution of infrastructurerelated construction disputes arising from projects in developing countries. The study has
provided descriptive data on the existing dispute resolution processes. It has also furnished
insights into what transpired between parties to disputes prior to resort to international
arbitration. Again, the study has highlighted the need for attention to be focused not only on
the back-end dispute resolution processes but also the front-end where the dispute system is
designed. Other contributions to knowledge are examined under section 10.4.1. In relation to
practice, the study has identified the main features and difficulties with the extant resolution
practice. It has also recommended remedial strategies to deal with the problems identified (see
section 10.4.2).
Regarding dissemination of the research outcome, an aspect of this study on the concept of
arbitrability in the context of Ghana’s arbitration law has been published in the International
Arbitration Law Review, a refereed journal of international repute (Mante and Ndekugri,
2012). Two other draft articles on the interplay between contract and public law and the
implications of the nature of the Employer as a complex entity for problem-solving on
projects are currently under review towards publication. Additionally, two papers presented at
the RICS Construction and Property Conference (COBRA) and the Association of
21
General Introduction
Researchers in Construction Management Conference (ARCOM) respectively have also been
published as part of the conference proceedings (Mante et al., 2011; Mante et al., 2012).
1.9.
Structure of the Thesis
The thesis is organised into ten chapters. Chapter one provides an overview of the entire
research. Chapter two examines the current state and trends in infrastructure development in
developing countries. It presents an overview of the literature on nature and characteristics of
infrastructure, its importance to economic development and the trends in developing
countries, Africa and Ghana. Chapter three reviews the literature on infrastructure
procurement methods and infrastructure procurement practice in Ghana. The chapter points
out the limitations of the existing literature.
In chapter four, a review of studies on how infrastructure-related construction disputes are
resolved is presented. The chapter begins with an examination of the concepts of claim and
dispute. An overview of sources and types of construction disputes is then provided. The
literature on construction dispute avoidance and resolution mechanisms available in
developed countries such as arbitration, mediation, adjudication and dispute boards are also
reviewed. The chapter then examines studies on construction dispute resolution in developing
countries. It ends with an identification of the knowledge gaps.
In chapter five, the research methodology for the study is set out. The first part of the
chapter (sections 5.2-5.6) discusses the literature on research methodology with a focus on
choices for the study. This part identifies and provides rationale for the epistemological
position of the study. It also examines the methodologies and methods available to both
quantitative and qualitative researchers. The second part of the chapter (sections 5.7-5.9)
discusses the research design. Issues addressed under this part include case design, data
collection and data analysis. This is followed by a brief examination of the research
evaluation criteria.
22
General Introduction
The procedure for data analysis is reported in chapter six. The chapter begins with a
presentation of information on the background of the participants for the research. This is
followed by a general overview of the data analysis. Detailed information on the coding
process, memo writing and the generation of diagrams and models are then reported. Finally
information on doctrinal legal analysis is presented. The data analysis culminated in the
development of five themes which addressed the objectives of the research.
The outcomes of the data analysis are reported in chapter seven. The chapter is divided into
three sections. The first section reports the outcome of the data analysis on the theme
‘Features and Context of Parties to Dispute Resolution’. Findings relating to the nature of the
State as an Employer, the workings of its sub-units and the context within which they worked
are presented under this section. Similarly, results of the analysis on the nature of foreign
contractors and how this affected the dispute resolution processes is also reported under this
section.
The second section of chapter seven reports the results of the data analysis as summed up
under the theme ‘Procurement’. Issues addressed included the legal framework for
procurement and construction dispute resolution, procurement methods for infrastructure and
the impact of procurement on dispute resolution. Results of the analysis on contract
formation, Conditions of Contract and dispute clauses are also presented under this section.
Essentially, the dispute mechanisms usually agreed in the Conditions of Contract were the
same as those regularly used. This finding underscored the importance of the procurement
process to the dispute resolution processes.
Results of the data analysis on the nature and features of the extant infrastructure-related
dispute resolution processes (embodied in the theme ‘the dispute resolution processes’) are
reported in chapter seven. Also reported in this chapter are the results on barriers to the use of
ADRs, particularly the intermediary mechanisms.
23
General Introduction
Chapter eight is the discussion chapter. The extant dispute resolution processes are
evaluated on the basis of the relevant literature. Following the evaluation, implications of
factors identified as accounting for the current state of the dispute resolution processes are
examined. The chapter concludes with a discussion of the remedial strategies leading to the
formulation of a new model called Dispute Resolution Efficiency Cycle (DREC). Chapter nine
reports on how the research was validated. Finally, chapter ten provides a brief overview of
the research process, an outline of how the research objectives were met, summary of the
research findings and contributions of the study has made to knowledge and practice. The
chapter ends with limitations of the findings and recommendations for further research.
24
Chapter 2- Infrastructure Development: Current state and trends
CHAPTER TWO
25
Chapter 2- Infrastructure Development: Current state and trends
CHAPTER TWO-INFRASTRUCTURE DEVELOPMENT: CURRENT STATE
AND TRENDS IN DEVELOPING COUNTRIES
2.1.
Introduction
In this chapter, a review of the literature relating to the state and trends of infrastructure
development in developing countries is presented as a necessary background to the study. As
part of the review process, searches were conducted in key infrastructure databases such as
the World Bank’s website on infrastructure development, the World Bank/ PPIAF Library and
the Stanford University-Global Project Portal. Multi-disciplinary databases such as Google
scholar, Science direct and Scopus (currently operated by Elsevier) were also interrogated.
Key words and phrases such as ‘infrastructure’, ‘infrastructure development’, ‘infrastructure
funding’, ‘infrastructure development in developing countries’, ‘multilateral development
banks and infrastructure development’ and ‘infrastructure development and economic
development’ were used in the searches. The above keywords were selected on the basis of
their potential to lead to literature on current state and trends on infrastructure development in
developing countries. Information obtained from materials collected through internet and
library searches formed the basis of this chapter.
The chapter highlights the growing emphasis on infrastructure development by
developing countries and multilateral development institutions and the reasons for it.
According to the literature, the current emphasis on infrastructure is largely attributable to
increased research indicating a positive correlation between infrastructure and economic
development. This has culminated in increased investments in infrastructure projects in
developing countries. The literature on the current state of infrastructure development, the
role of the MDBs, and the impact of infrastructure on economic development is discussed. In
this study, ‘developing countries’ include all lower and middle income economies (World
Bank, 2011a).
26
Chapter 2- Infrastructure Development: Current state and trends
2.2.
Nature and Characteristics of Infrastructure Projects
Infrastructure has been defined as comprising the physical facilities, institutions and
organizational structures, or the social and economic foundations, for the operation of a
society (UNCTAD, 2008). The World Bank (1994) also defines infrastructure, in physical and
economic terms, as public utilities (power, telecommunications, piped water supply,
sanitation and sewerage, solid waste collection and disposal, and piped gas), public works
(roads and major dam and canal works for irrigation and drainage) and transport facilities
(urban and inter-urban railways, urban transport, ports and waterways, and airports).
However, the World Bank’s definition is steeped in the historical view of infrastructure as
‘public utilities’ and/or ‘public works’. This characteristic of infrastructure is not allencompassing as there are many infrastructure projects today which do not fit the ‘public’ tag.
However, one can agree with the World Bank (1994) on the examples of infrastructure
projects cited. The United Nations Conference on Trade and Development’s (UNCTAD)
report on infrastructure and Trans-national Corporations (UNCTAD, 2008) provide a similar
list of examples of infrastructure but provide a caveat that the category is changing with the
advent of information communication technology (ICT) (see also Prud’homme,2004;
Kessides, 1993). In Ghana, infrastructure has been defined to include immovable capital such
as,
roads,
power
plants,
water
delivery
systems,
sewerage
treatment
plants,
telecommunication and transport facilities (MOFEP, 1997).
Physical infrastructure projects share some common characteristics. UNCTAD (2008)
identifies five of them. Firstly, they are capital-intensive. They are challenging undertakings
involving huge financial outlay. Secondly, they often involve physical networks of strategic
importance. Often lumpy, they are long-lasting and space-specific (Prud’homme, 2004).They
are also major determinants of the competitiveness of an economy. Good infrastructure can
play a major role in the decision of an investor to set up in a particular economy. Fourthly, in
27
Chapter 2- Infrastructure Development: Current state and trends
many societies, services associated with infrastructure are thorny social and political issues
and thus subject to public interventions. Finally, infrastructure projects are relevant to
economic development and global integration.
Odams and Higgins (1996) identify five additional characteristics of major infrastructure
projects. Firstly, there is often an external funder who plays an active role in determining the
project structure. Secondly, the client is often the State or a State-owned entity. Further, there
is a foreign element in the form of an investor or a contractor. Additionally, the contractor
often plays a more active role in what is traditionally the role of the client. Finally, the
contractor tends to assume much more significant risks. Cheung and Yiu (2007) adds that
these projects are often laden with complexities which make them dispute-prone. These types
of projects and associated construction disputes were the subject-matter of this study.
2.3.
Infrastructure Projects in Developing Countries –Current trends
Provision of infrastructure has historically been the responsibility of States (World Bank,
1994;Briceno-Garmendia et al., 2004 ; UNCTAD, 2008). State involvement in infrastructure
development was justified on various grounds; public interest, contribution to growth and
development and the fear of creating private monopolies among others (Annez, 2006).
Infrastructure projects were the responsibility of governments (Kessides, 2004; Estache and
Fay, 2007). This is still the case for many countries and national resources are committed to
infrastructure development annually.
For some developing countries however, huge budget deficits have made it impossible to
cater adequately for infrastructure projects from internal resources. World Bank and
UNCTAD figures revealed that as of 1994, developing countries were investing about
US$200 billion, amounting to about four per cent (4%) of their national output in
infrastructure development (Kessides, 1993; World Bank, 1994; UNCTAD,2008). Calderon
and Serven (2010) discussing the current infrastructure gap in Latin America, attributed it to
28
Chapter 2- Infrastructure Development: Current state and trends
the lag in public spending in the late 1980s and the 1990s by governments in the region. On
the average, Latin American countries were spending about two to three per cent (2% - 3%) of
their GDP on infrastructure, though about three to six per cent (3% - 6%) spending was
required to make the needed difference (Fay and Morrison, 2007). Part of the economic
successes achieved by East Asia in the last quarter of a century has been attributed to
continued public spending on infrastructure in the 1990s (ADB et al., 2005). Data from the
World Bank’s Private Participation in Infrastructure (PPI) for 2005 revealed that Cambodia,
the Philippines and Indonesia spent between zero and four per cent (0-4%) of their GDP on
infrastructure, whilst China, Thailand and Vietnam spent more than seven per cent (7%)
(ADB et al., 2005).
Africa’s infrastructure needs remain enormous. The Africa Infrastructure Country
Diagnostics (AICD), a project aimed at collecting comprehensive data on Africa
infrastructure and providing an integrated analysis of the data, indicates that Africa lags well
behind other regions of the world in terms of provision of infrastructure (Foster and BriceñoGarmendia, 2010). Power generation and paved roads are some of the infrastructure
provisions in respect of which the gap is particularly wide. It was observed that the total
power generated by the forty-eight (48) countries in Sub-Saharan Africa with a population of
800 million was equal to the power generation capacity of Spain, with forty-five (45) million
people (Foster and Briceño-Garmendia, 2010). It is reported that Africa will need to invest
about US$93 billion (15% of the region’s GDP) a year, in infrastructure if it is to make up for
the infrastructure deficit (Foster and Briceño-Garmendia, 2010). UNCTAD (2008) maintained
that developing countries will need to spend between seven per cent (7%) and nine per cent
(9%) of their national output on infrastructure if the huge infrastructure gap is to be bridged.
In spite of the increases in private participation in infrastructure procurement in developing
29
Chapter 2- Infrastructure Development: Current state and trends
countries over the last two decades (see Figure 2.1 below), States still remain key clients of
infrastructure projects.
1990-2000
Middle
East and
North
Africa
3%
Latin
America
and the
Caribbea
n
51%
South
Asia
5%
2001-2008
SubSaharan
Africa
3%
East Asia
and
Pacific
28%
South
Asia
17%
Middle
East and
North
Africa
6%
Europe
and
Central
Asia
10%
SubSaharan
Africa
9%
Latin
America
and the
Caribbe
an
28%
East
Asia and
Pacific
17%
Europe
and
Central
Asia
23%
Figure 2.1: Total investment commitments to infrastructure projects with private
participation in developing countries, by region, 1990–2008. (Source: World Bank and
PPIAF, PPI Project Database)
2.4.
Infrastructure Development in Ghana – Current State and Trends
The bulk of infrastructure development activities are in the roads and transport, housing,
water, education and energy sectors of the economy (MOFEP, 1997;Government of Ghana,
2008 ; Government of Ghana, 2010a). Infrastructure development in the road sector cover the
construction, rehabilitation and maintenance of trunk roads, urban road networks and feeder
roads linking remote production hubs to markets in towns and cities across the country. The
transport sector infrastructure projects cover expansion and maintenance of rail tracks,
airports, water and seaports (MOFEP, 1997). Major infrastructure construction activities in
the energy sector cover the generation, transmission and distribution of power.
As part of the AICD research, substantial data on the state of Ghana’s infrastructure
development covering principally the period 2001 and 2006 (and in some cases the period up
to 2009) were collected and same has been synthesised into a report and a policy research
30
Chapter 2- Infrastructure Development: Current state and trends
paper on Ghana’s infrastructure (Foster and Pushak, 2011). The infrastructure outlook of
Ghana presented in this section is largely based on this report. In sum, the report observed that
Ghana’s infrastructure is in a relatively better position when compared with other low-income
countries in the region. Nevertheless, Ghana’s infrastructure contributed a little over one per
cent (1%) to the country’s GDP growth which averaged 5.6% during the last decade; a further
boost in infrastructure development has the potential to raise the contribution of infrastructure
to GDP to 2.7% (Foster and Pushak, 2011).
2.5.
Funding Infrastructure Development
Many developing countries rely on external resources to fund projects. These resources are
mobilized through multilateral and bilateral arrangements. Bilateral institutions such as the
United States Agency for International Development (USAID), Canadian International
Development Agency (CIDA), Japan International Cooperation Agency (JICA), the Swedish
International Development Authority(SIDA),
and the United Kingdom Department for
International Development (DFID) have been instrumental in supporting states to improve
their infrastructure (DFID, 2011). The emerging role of some developing economies
particularly China and India as capital exporting States has also been acknowledged by
UNCTAD in its 2010 World Investment Report.
Regarding multilateral assistance, contributions of developed States in the form of Official
Development Assistance (ODA) has been a major source of capital for infrastructure
development in developing countries ( Jepma, 1991; Clark, 1992). Much of ODA assistance is
disbursed through multilateral development institutions and banks, notably the World Bank
and the four regional banks namely, the African Development Bank (AfDB), the Asian
Development Bank (AsDB), the Inter-American Development Bank (IDB), and the European
Bank for Reconstruction and Development (EBRD) (Nelson, 2010). There are also
multilateral development finance institutions (MDFIs) such as the European Investment Fund
31
Chapter 2- Infrastructure Development: Current state and trends
(EIF), the Multilateral Investment Funds (MIF), and Inter- American Investment Corporation
(IIC) also performing similar functions.
The main role of the MDBs has been to offer financial products in the form of loans, grants
and technical assistance to developing countries in line with lending conditions. The lending
facilities provided by the MDBs are in the nature of policy-based loans usually tagged to
agreements on policy reforms and investment project loans typically granted for large
infrastructure projects (Nelson, 2010). In sum, States remain largely responsible for
infrastructure procurement. Internal resources are supplemented by external funds namely
official development assistance, private participation in infrastructure (PPI) and non-OECD
funds from countries such as Brazil, China and India.
Information on Ghana’s infrastructure funding can be tracked through the annual national
budgets of Ghana and various World Bank studies notably, the AICD reports. Sources of
infrastructure funding can be broadly categorized into domestic and foreign sources
(Government of Ghana, 2010b,para 17). The foreign sources can further be categorized into
ODA, non-OECD and PPI sources. In terms of sectoral coverage, funding for ICT and power
projects are mainly from domestic and non-OECD sources, whilst the country rely
substantially on ODA for road and water capital investments (Foster and Briceño-Garmendia,
2010).
Ghana’s current annual infrastructure spending amounts to $1.2 billion equivalent of
eleven per cent (11%) of its 2006 GDP (Foster and Pushak, 2011). This expenditure is
sourced from four main sources; ODA represents thirty-five per cent (35%), public
investment constitutes twenty-eight per cent (28%), private investment, twenty-four per cent
(24%) and the remaining percentage spending from non-OECD sources. With the rising
involvement of China and other non-OECD members in infrastructure provision in Ghana,
their percentage contribution is likely to rise (Foster et al., 2009).
32
Chapter 2- Infrastructure Development: Current state and trends
2.6.
Infrastructure Development and Economic Development
The question of impact of infrastructure on economic development has engaged the
attention of many authors (Estache, 2004). Research on Latin America (Andrés et al., 2008;
Calderón and Servén, 2010b), Sub-Saharan Africa (Calderón and Servén, 2010a; PEI,
February, 2011; Ncube, 2010; Foster and Briceño-Garmendia, 2010) and East Asia (ADB et
al., 2005) have all shown positive linkages between infrastructure development and economic
growth and productivity. These reports have also indicated regression in growth where there
have been cuts in infrastructure development. Briceño-Garmendia et al. (2004) reproduced
and analysed the findings of a study conducted by de La Fuente and Estache (2004) to
illustrate the impact of infrastructure development on growth (Table 2.1 below).
Table 2.1: Distribution of Findings on impact of infrastructure on productivity and
growth (Source: de la Fuente and Estache, 2004 in Briceño-Garmendia et al. 2004).
Area Studied
Number
Studies
Multiple countries
of
Percentage
showing positive
effect
Percentage showing
no significant effect
Percentage showing
a negative effect
30
40
50
10
United States
41
41
54
5
Spain
19
74
26
0
Developing Countries
12
100
0
0
Total/Average
102
53
42
5
Although the study showed varied impact of infrastructure development on economic growth
and productivity in other countries, the verdict on developing countries was unequivocally
positive.
Since the pioneering work of Aschauer (1989) on the subject, many authors have
acknowledged that infrastructure development is crucial to economic development (Canning
and Pedroni, 1999; Kessides, 1993; Kirkpatrick et al., 2006; Harris, 2003; Briceno-Garmendia
et al., 2004; World Bank, 1994; UNCTAD, 2008; Calderón and Serven, 2010; Sanchez
33
Chapter 2- Infrastructure Development: Current state and trends
Robles, 1998; Giang and Sui Pheng, 2011). For instance, Briceno-Garmendia et al. (2004)
indicate that reliable and affordable infrastructure can reduce poverty and thus help achieve
the Millennium Development Goals. Other authors have independently corroborated this
through empirical research conducted on Sub-Saharan Africa (Agenor et al., 2005). Again,
Sanchez- Robles (1998) found a positive impact on economic growth after a study of road
length and electricity generating capacity (see also Canning and Pedroni, 1999).
A study which examined the impact of investment in telecommunication infrastructure in
Nigeria on economic growth found a positive correlation (Osotimehin et al., 2010). Giang
and Sui Pheng (2011) argue that infrastructure has the potential to raise the productivity of
other factors of production. After an assessment of empirical data from sub-Saharan Africa
and comparative data from over 100 countries, Calderón et al.(2008) found that infrastructure
development impacts economic growth and equity. Authors like Estache and Vagliasindi
(2007) and Foster (2011) have submitted that deficit in power generation have limited growth
in Ghana. At the continental level, it has been argued that lack of adequate infrastructure in
Sub-Saharan Africa is holding back GDP growth by 2.2% (PEI, February,2011; Foster and
Briceño-Garmendia, 2010).
The general consensus in the burgeoning literature on the subject is that there is a
correlation between infrastructure and economic development (Estache and Fay, 2007). It is
predicted that under the right conditions, infrastructure development can play a major role in
productivity and thereby help reduce poverty (Calderón and Servén, 2010b; Andrés et al.,
2008). It is therefore not surprising that both States and MDBs focusing on development such
as the International Bank for Reconstruction and Development (IBRD) and the various
regional development banks have placed a lot of premium on infrastructure development
across the globe (World Bank, 1994; Briceno-Garmendia et al., 2004; World Bank, 2008).
34
Chapter 2- Infrastructure Development: Current state and trends
2.7.
Summary
The past two decades have witnessed phenomenal increase in infrastructure development
globally and particularly in developing countries. These developments have been undertaking
principally by States who have been responsible for infrastructure development historically.
Apart from the obviously inadequate internally generated resources, development assistance
in the form of OECD-ODA, non-OECD funds and private sector-sourced funds have
increased the capacity of developing countries to carry out infrastructure developments.
Available evidence suggest that increased clarity of research on the impact of infrastructure
development on economic development and poverty reduction has acted as a catalyst for the
growing investment in infrastructure (World Bank, 2008). The next chapter examines the
literature on public procurement of infrastructure in Ghana.
35
Chapter 3- Infrastructure Procurement
CHAPTER THREE
36
Chapter 3- Infrastructure Procurement
CHAPTER THREE - PROCUREMENT OF MAJOR INFRASTRUCTURE
PROJECTS IN GHANA
3.1.
Introduction
Realising a country’s goals on infrastructure development necessarily entails the
procurement of infrastructure projects. As a follow-on to the review on the trends of
infrastructure development, this chapter examines the literature on infrastructure procurement
generally and the process in Ghana in particular. The review entailed interrogation of
databases on procurement such as the World Bank’s database on Country Procurement
Assessments, the United Nations Commission on International Trade Law’s (UNCTAD)
portal on procurement and infrastructure and the website of the Public Procurement Research
Group at the University of Nottingham.
Databases of the Government of Ghana, its
ministries, departments and agencies (MDAs) such as the Public Procurement Authority were
also explored. Key words and phrases searched included ‘public procurement’, ‘infrastructure
procurement’, ‘public procurement practice in developing countries’ and ‘procurement and
dispute resolution’. This review was necessary because it furnished the context within which
infrastructure-related construction disputes occurred.
Issues covered in this chapter included general information on construction and
engineering procurement methods, principles governing public procurement and infrastructure
procurement practice in Ghana. The review found that infrastructure procurement in Ghana
suffered from several deficiencies. These included delays associated with contract formation,
preparation of technical specifications and drawings, evaluation, approvals and payments.
These had a snowballing effect on performance and dispute occurrence.
3.2.
Procurement- Definition
The concept of procurement, in the context of construction, is broad and covers virtually
the entire process of acquisition; procurement planning, the process of contractor selection,
negotiation of contract terms, contract formation and contract administration (Bower, 2003;
37
Chapter 3- Infrastructure Procurement
Arrowsmith,2005; Arrowsmith, 2010). Based on the CIB W92 definition of procurement as
the framework through which construction is brought about, acquired or obtained, Akintoye
et al.(2003) have opined that procurement entails the acquisition of land, design, construction,
commissioning and management of a project. Contract strategy and formation are at the core
of the process. Love et al. (1998) identifies procurement as an organisational system that
identifies relationships and assigns responsibilities among key players in the construction
process. This definition, like the others, presents the contract formation process as integral to
procurement. Throughout this thesis, contract formation and all issues relating to the
construction contract are treated under procurement. Over the years, many procurement
methods have evolved to guide both clients and contractors of major infrastructure projects.
Masterman (2002) attributes the proliferation of procurement methods to factors such as client
dissatisfaction, project complexity and escalating project cost.
3.3.
Procurement Methods
Various authors have provided their respective classifications of the available procurement
methods. Masterman (2002) identifies three categories of building procurement systems
namely the separated and cooperative procurement systems, the integrated procurement
systems and the management-orientated procurement systems (see also Turner, 1990; Frank,
1998; Morledge et al, 2006). Each system has its variants. Negotiated contracts, two-stage
tendering, continuity contracts, serial contracts and the cost-reimbursable contracts are
variants under the separated and cooperative procurement category (traditional methods).
Variants of the integrated system (Design and Build) include package deals, design and
construct and turnkey. The main methods under the management-orientated systems are
management contracting, design and manage and construction management.
Bower (2003) categorizes the procurement for civil engineering projects into traditional,
direct labour, management contracting, design and build, framework agreements, partnering
38
Chapter 3- Infrastructure Procurement
and alliances and their respective variants. Payment mechanisms such as fixed price,
admeasurements, cost-reimbursable and target cost can also be the basis for classifying
procurement strategies (Bower, 2003; Turner, 1990; Morledge et al., 2006). Two observations
can be made from the classifications above. Firstly, whilst most of the classifications outlined
above relates to buildings, they are equally applicable to other construction and engineering
works as well (Bower, 2003). Secondly, regardless of the terminology used, four categories of
procurement methods can be identified. They are the traditional methods, the integrated
methods, the management–orientated methods and the collaborative procurement methods. In
this study, partnering is examined under the collaborative methods. Each of the methods is
examined briefly.
3.3.1. The Traditional methods
The traditional procurement methods are the most pervasive of all the procurement
methods available (Franks, 1998). With this method, the client, after an initial deliberation on
project concept and feasibility, appoints consultants to produce detailed complete designs of
the project. On the basis of the designs, tender documents, including bill of quantities, are
prepared. The project is then submitted to competitive tendering at which stage contractors
are required to bid on a lump sum basis. The client enters into a contract with the successful
bidder who then undertakes the construction work under the supervision of the design
consultants (Masterman, 2002).
Advantages of this method include the following: (a) assurance of competition; (b) fairness
and minimised tender cost due to the availability of bills of quantities; and (c) potential to
achieve low project cost, quality and functionality (Turner, 1990; Franks, 1998; Masterman,
2002; Morledge et al., 2006). Disadvantages of these methods include the following: (a)
excessive cost overruns as incomplete designs; (b) fragmentation; (c) excessive variations; (d)
39
Chapter 3- Infrastructure Procurement
disruption of work; and (e) increased completion time (Latham, 1994; Franks, 1998; National
Audit Office, 2001; Morledge et al., 2006).
3.3.2. Integrated Methods
Design and Build (DB) has been described as a fast track method as design and
construction can take place simultaneously (Morledge et al., 2006). Under this method, a
single contractor takes sole responsibility for the custom-made design and construction of the
project for a fixed lump sum (Griffith et al., 2003). The client prepares an initial brief. It then
employs a design consultant to prepare a preliminary design and other tender documents. On
the basis of these, bids are obtained from selected number of contractors under a single or
two-stage tendering process. The bids are evaluated on the basis of price, specification and
design and the suitable bid selected to undertake both detail design and construction of the
project (Masterman, 2001). DB is noted for its use in the execution of complex infrastructure
projects where time is of the essence.
Advantages of DB include improve buildability, speed and improved communication. The
challenge with this system, however, is the client’s inability to prepare a comprehensive brief
to forestall subsequent variations (Ndekugri and Turner, 1994). Other demerits include
difficulty in valuing variations due to the absence of bills of quantities and expensive
variation (Masterman, 2002; Morledge et al., 2005).
3.3.3. The Management-orientated Methods
Management contracting, construction management and design and manage are the main
variants of the management-oriented procurement methods. The common feature of these
methods is the emphasis on management for a fee (Franks, 1998). Under management
contracting, the client appoints a construction-based firm in addition to the design team at the
initial stages. The work of this firm is to manage the entire construction process at a fee.
Works are carried out by package contractors who are directly employed by the management
40
Chapter 3- Infrastructure Procurement
contractor. The latter is reimbursed by the client. Unlike management contracting, the entity
employed by the client to manage the construction process under construction management is
not contractually involved with the package contractors who undertake the works. The
process of selection of the management contractor focuses on expertise, experience and the
management fee.
Whilst price uncertainty, increased costs and greater project risks for the client remain the
key disadvantages, the management-centred approaches are flexible and are able to
accommodate delays and variations in the cost and scope of uncommitted work (Masterman,
2002; Morledge et al., 2006).
3.3.4. The Collaborative Procurement Methods
Morledge et al. (2005) identify, as a key feature of all the variants of this procurement
method, the transformation of the relationship between client and the project team
(traditionally seen as customer/supplier relationship) into a ‘shared risk/shared reward’ team,
putting their efforts together to ensure the success of a project ( see also Latham, 1994; Egan,
1998; Egan, 2002). Methods here include alliancing and Private Finance Initiatives (PFI)/
Public-Private Partnerships (PPP).
PPP methods entail private entities teaming up with
government to provide major infrastructure projects. The private entity may be involved in the
initiation, planning, design, financing, construction, maintenance, ownership and operation of
a major infrastructure project (Akintoye et al., 2003).
3.4.
Procurement of Infrastructure projects in Ghana –Pre-Act663
The Public Procurement Act, 2003 (Act 663) is the governing law on public procurements
public procurement in Ghana. During the pre-independence era, procurement was the function
of the colonial administration performed by Crown agents and the Public Works Department
(PWD). The former was responsible for the procurement of goods and the latter, works. After
independence from British rule in 1957, a number of MDAs were established in the 1960s and
41
Chapter 3- Infrastructure Procurement
entrusted with responsibilities including carrying out infrastructure projects and providing
consultancy for such acquisitions. These included Ghana National Construction Corporation
(GNCC), the Electricity Corporation of Ghana (see the Statutory Corporations Act, 1964 (Act
232)), the Ghana Water and Sewerage Corporation (GWSC) (see the GWSC Act, 1965 (Act
310)) and the Architectural Engineering Services Corporation (AESC). Section 2 of Act 310,
for instance, gave the GWSC mandate, inter alia, to make engineering survey plans and
construct and operate works relating to water and sewerage. Again, the objects of AESC
under section 3 of the Architectural Engineering Services Corporation Act, 1973 (NRCD 193)
included carrying out technical studies in planning, design and supervision of infrastructural
works. Central, Regional and District Tender Boards were set up to advice on the
procurement of works.
By the mid-1990s, the public entities set up as conduits for procurement had become
overwhelmed by the growing demands from the MDAs and had become inefficient (World
Bank, 2003b). In 1993, the Statutory Corporations (Conversion to Companies) Act, 1993 (Act
461) was enacted to enable existing corporations to be converted into companies. The AESC,
ECG and GWLC were all transformed into limited liability companies. Public entities were
no longer obliged to use State institutions to carry out works on their behalf. State entities
increasingly relied on private consultants and contractors to execute projects.
The literature points to the traditional method of procurement with design split from
construction both in time and space, as the dominant procurement method used during the
Pre-Act 663 era (Anvuur et al., 2006; Kheni, 2008). The World Bank (2003b) identified
selective tendering and sole sourcing as the most widely used tendering methods prior to the
enactment of Act 663. The two methods were used in about two-thirds of all projects within
the public sector. The other tendering method used was competitive tendering. Tender Boards
set up in the 1960s and subsequently regulated under the District Tender Board Regulations,
42
Chapter 3- Infrastructure Procurement
1995 (L.I. 1606) continued to perform their roles until the coming into force of the Public
Procurement Act, 2003 (Act 663).
Procurements, during the pre-Act 663 period, were plagued with several deficiencies
(World Bank, 2003b). These included lack of a comprehensive legal framework with clear
procedures on procurement, weak capacity of procurement staff and unclear institutional and
organisational framework for procurement. There were delays in contract closure, preparation
of technical specifications and drawings, evaluation, approvals and payments (World Bank,
2003). These had a snowballing effect on contract delivery, performance and disputes.
3.5.
Procurement of Infrastructure – Post Act663
For the first time in Ghana, a new unified law on procurement was enacted in 2003. Act
663 had nine parts which covered issues such as the establishment of a procurement authority
and structures (see Part one and two), general rules on procurement (Part three), methods of
procurement (Part four) and tendering procedures (Part five). There are separate rules on
engaging services of consultants (Part six). The law applies to all procurement of goods,
works and services financed in whole or in part from public funds, loans obtained or
guaranteed by the State and foreign aid, and activities incidental thereto such as description of
requirements, invitation of sources, preparation, selection, award of contract and contract
administration.
Under Act 663, competitive tendering (national and international) is the main method for
contractor selection except in cases where a justification exist for the use of other tendering
methods such as two-staged tendering, restricted tendering and sole-sourcing. Conditions and
procedures for the use of these tendering methods are outlined in the Act. For externally
funded projects where the funding agencies’ procurement guideline is used, contractors were
selected mainly by international competitive tendering. All procurement entities were required
to use the appropriate tender documents as provided in the Fourth Schedule to the Act.
43
Chapter 3- Infrastructure Procurement
Section 50 requires that these documents shall be used with minimum modifications to be
introduced through the Contract data sheet and the Special Conditions of Contract. No
changes were to be made in the standard tender documents. Bids were to be opened at the
time and place stipulated in the invitation documents and in the presence of all bidders. Bid
evaluation criteria were to be predetermined as per the invitation documents and were to be
objective and quantifiable.
Evaluation was not to be based solely on the lowest tender price but also other weighted
criteria provided in the bid document. In arriving at the lowest evaluated tender, the
committee had to consider the tender price in the light of any margin of preference applied,
the cost of operating or maintaining the works, the functional characteristics of the works,
payment or guarantee terms and national security. Section 59 of the Act additionally required
that the effect of the acceptance of the tender on the national economy be considered in terms
of the balance of payment position and foreign exchange reserves of the country, counter
trade arrangements offered by suppliers and contractors, extent of local content, and the
overall economic development potential offered by tenders.
3.6.
Other rules on Infrastructure Procurement
The issue of choice of procurement method for major projects in Ghana was, in most cases,
tied to donor funding requirements. As a result, there existed two streams of procurement
rules namely those under Act 663 and those contained in agreements with donors or creditors.
There were two instances where the provisions of Act 663 did not apply. Firstly, the Minister
of State responsible for a particular procurement could decide that it was in the national
interest to use a different procedure. Secondly, an applicable loan agreement, guarantee
contract or foreign agreement could provide different procedure for the utilisation of such
funds. Thus, the established practice of using World Bank and other donor procurement
guidelines for donor funded projects in Ghana continued alongside the provisions of Act 663.
44
Chapter 3- Infrastructure Procurement
3.7.
Procurement Practice
The existing literature points to the continuation of the dominance of the traditional
method in practice (Anvuur et al., 2006). However, there was evidence of the use of design
and build and Engineer, Procure and Construct (EPC) (Ameyaw, 2011; Hensengerth, 2011).
Again, there were indications that variants of public private partnership (PPP) have been
employed in the water sector (Fuest and Haffner, 2007). The challenge with the literature
available is the lack of details on how these procurement methods were utilised in practice.
Challenges associated with procurement of works in Ghana during the period before Act
663 was passed are well documented (World Bank, 2003b; Westring, 1997; Anvuur et al.,
2006; Eyiah and Cook, 2003). A study conducted after Act 663 came into force revealed very
low compliance levels and a continuation of old practices and challenges (Osei-Tutu and
Sarfo Mensah, 2008). Deficiencies associated with the process of infrastructure procurement
often resulted in avoidable claims and disputes (World, 2003). However, there is very little
information from the literature on how such claims and disputes were resolved.
3.8.
Summary
At the heart of infrastructure development is procurement. Procurement methods used in
building and civil engineering works include the traditional, integrated, management-centred
and collaborative methods. In Ghana, the traditional procurement method was dominant in
infrastructure projects delivery. There was also information on the use of other methods such
as design and build, EPC and PPP. Again, where donor funds were involved, procurement
guidelines of funders were used. There were several deficiencies with the extant procurement
process and these resulted in claims and disputes. However, the literature provides limited
information about the mode of resolution.
45
Chapter 4- Resolving Infrastructure-related construction disputes
CHAPTER FOUR
46
Chapter 4- Resolving Infrastructure-related construction disputes
CHAPTER FOUR - RESOLVING INFRASTRUCTURE-RELATED
CONSTRUCTION DISPUTES
4.1.
Introduction
This chapter surveys the literature on the resolution of infrastructure-related construction
disputes. The review entailed the exploration of databases on construction, engineering, law
and dispute resolution such as the American Society of Civil Engineers’ (ASCE) library,
Construction Information Service and Westlaw. Other databases interrogated included Lexis
library, Hein online and multi-disciplinary databases such as Google Scholar, Business source
complete, Emerald Insight, Elsevier (Scopus), Swetswise and Taylor and Francis online. Key
phrases such as ‘dispute resolution’, ‘construction dispute resolution’, ‘causes of construction
disputes’, ‘alternative dispute resolution in construction’, ‘construction dispute resolution in
developing countries’ were searched across databases. Periodically, specific searches were ran
on issues such as dispute avoidance, dispute management and dispute resolution mechanisms
such as arbitration, mediation and Dispute Adjudication Boards. This chapter is the outcome
of a review of the literature obtained through the internet and library searches.
The chapter presents a general overview of construction dispute resolution practice in both
developed and developing countries. The literature indicated that disputes were a global
phenomenon. However, differences existed on how they were resolved in developed and
developing countries. In developed countries, there is a growing trend of resolving them by
less costly Alternative Dispute Resolution Methods (ADR). On the other hand, the literature
on developing countries, particularly those in Africa, showed that international commercial
arbitration (ICA) was the dominant mechanism for resolving infrastructure-related
construction disputes. There were gaps in the literature on pre-ICA resolution processes and
the viability of ADR mechanisms. The chapter commences with a discussion of some
introductory conceptual issues relating to claims and disputes. Then there is a brief
47
Chapter 4- Resolving Infrastructure-related construction disputes
exploration of causes of construction disputes and the extant approaches to dispute resolution
both in developed and developing countries. Finally gaps in the literature are presented.
4.2.
Definition and Scope
Conflicts, disputes, differences and claims are terms used frequently by the literature on
construction disputes. In a sense, these terms are related. In the case of conflicts and disputes,
they are sometimes improperly used interchangeably (Fenn et al., 1997). The use of these
terms, without the necessary clarification as to their meaning and scope can create confusion
in the mind of readers. A discussion of these terms and how they relate to each other in the
context of this research is therefore important.
4.2.1. Claims
A claim has been defined as an assertion of a right (Powell-Smith and Stephenson, 1999).
This may be assertion to money, property or a remedy/relief (Semple et al., 1994; PowellSmith and Stephenson, 1999). Claim is thus simply an assertion of an entitlement. In the
context of construction, the term is used in reference to a request by a contractor not only for
an additional money due under a construction contract (money claims) but also for an
application for extension of time (Powell-Smith and Stephenson, 1999; Chappell et al., 2001).
Ndekugri and Rycroft (2009) provide four legal bases for claims under a construction
contract. Firstly, a contractor may make a claim expressly authorised under a contract under
which a particular work is being executed. Such claims often for loss and expense are referred
to as contractual claims or loss and expense claims. Secondly, a claim may be based on a
breach of contract or breach of a legal duty resulting in a foreseeable damage. These
categories of claim are referred to as common law claims since they have their basis in the
common law (Chappell et al., 2001; Powell-Smith and Stephenson, 1999). When successful, a
party who makes a claim under these common law categories is entitled to unliquidated
damages. Thirdly, a party may also assert a claim for restitution, typically quantum meruit.
48
Chapter 4- Resolving Infrastructure-related construction disputes
Finally, some construction law texts include another set of claims often referred to as ex
gratia claims. Ndekugri and Rycroft (2009) rightly refer to this category of claims as ‘moral’
or ‘sympathy’ claims. It is doubtful if demands under this category can legally be referred to
as ‘claims’ at all. The very concept of claim is based on the existence of a right. Where no
right exists, there cannot be a claim properly so-called.
Most construction claims, whether contractual or common law based, revolve around
issues relating to cost, time and the correction of defects. A contractor’s claim may revolve
around increased cost (loss and expense) and time in respect of excess works, unforeseen
works, works shortfalls, subsequent works or any other additional works resulting from a
variation(Sims and Bunch, 2003)and extension of time resulting from delays. The Employer’s
claims, on the other hand, may commonly relate to delay in completion of works, failure to
complete works and correcting defects (Hobeck et al., 2008; Ndekugri and Rycroft, 2009).
4.2.2. Dispute
A claim is distinguishable from a dispute. Hibberd and Newman (1999) have argued that a
claim is what it is; an assertion of a right under a contract and does not become a dispute until
it is rejected. To Hibberd and Newman (1999), a dispute exists when there is a genuine
difference of opinion over how a contractual term or condition should be interpreted or
implemented. Disputes are therefore disagreements or differences which manifest themselves
in ‘distinct, justiciable issues’ (Brown and Marriott, 1999, p. 2). In law, a dispute may be held
to exist under different situations depending on the subject-matter. It is not uncommon for
legislation relating to a specific area of law to delineate what will constitute a dispute in a
given situation. Under section 108 of the English Housing Grant, Construction and
Regeneration Act 1996, the existence of a dispute is a pre-condition for reference to
adjudication. The Act, like s.82 (1) of the Arbitration Act, 1996, defines a dispute as including
a difference.
49
Chapter 4- Resolving Infrastructure-related construction disputes
There are several judicial pronouncements on what constitutes a dispute in the context of
construction dispute arbitration and adjudication under English law. A number of these
judicial decisions have been discussed by Ndekugri and Russell (2006) and Ndekugri and
Rycroft (2009). A synopsis of the current position of the law on the definition of disputes can
be found in Amec Civil Engineering Ltd v Secretary of State for Transport (the Amec Case)
([2004] EWHC 2339 (TCC)). In this case, the Court presided over by Jackson J. outlined
seven propositions which may be useful in determining whether a dispute exist for the
purposes of adjudication/arbitration after considering earlier judicial pronouncements on the
issue (see the Amec Case, para 68). Firstly, the word ‘dispute’ must bear its normal meaning
in ordinary usage (see also Halki Shipping Corporation v. Sopex Oils Limited [1997] 3 All ER
833(Q.B); Halki Shipping Corporation v. Sopex Oils Limited [1998]2 All ER 23(CA); and
Beck Peppiatt Ltd v. Norwest Holst Construction Ltd.[2003] EWHC 822).Secondly, although
the earlier decisions have not laid out a hard-edged rule for determining whether or not a
dispute existed, they provided helpful guidance on the matter. Thirdly, mere assertion of right
does not amount to a dispute. A dispute arises only after it emerges that a claim is not
admitted (see also Ellerine Brothers (Pty) Limited and Another v. Klinger [1982] W.L.R.
1375; Fastrack Contractors Limited v. Morrison Construction Limited [2000] BLR168, para
28; Tradax International v. Cerrahogullari TAS [1981]3 All ER 344).
The fourth proposition outlined in the Amec Case is that the circumstances under which it
may emerge that a claim is not admitted are wide-ranging. The Court provided four examples
of such situations: (i) a claim may be expressly rejected; (ii) there may be discussions between
the parties from which an inference may be drawn that a claim is not admitted; (iii) the
respondent may prevaricate thus given rise to an inference that a claim is not admitted; and
(iv) the respondent may remain silent thereby given rise to the inference that the claim is not
admitted. The fifth proposition is an expansion of one of the examples under proposition four
50
Chapter 4- Resolving Infrastructure-related construction disputes
namely, silence. Not every silence after a claim will amount to non-admission. Much
depended on the circumstances of each case. In some cases (e.g. where the claim is well
known) a short period of silence may suffice to give rise to inference of denial. Where the
claim is addressed to a third party/ agent of the respondent who has a legal duty to consider
the claim and provide a response, a longer period of time may be required before silence may
be deemed to amount to no admission.
The sixth proposition deals with situations where a deadline for responding to claim is
provided. Even though the reasons for the imposition of the deadline may be taken into
account by the Court, the key consideration in such cases remains whether the time allocated
for a response is reasonable. Finally, a claim must be clear enough for it to establish a duty in
the recipient to respond. If the claim as presented by the claimant is so ill-defined that the
respondent cannot sensibly respond to it, neither silence by the respondent nor even an
express denial is likely to give rise to a dispute for the purposes of arbitration or adjudication
(see the Amec Case, para 68, 7th proposition).
In both Collins (Contractors) Limited v. Baltic Quay Management (1994) Limited [2005]
BLR 63and Amec Civil Engineering Ltd v Secretary of State for Transport [2005] BLR 227
AC, the Court of Appeal endorsed the propositions set out by Jackson J. Nearly a decade on,
the principles outlined in the Amec Case remain the position of the law and have been applied
in a number of cases to determine whether or not disputes existed for purposes of adjudication
(see Sterling (t/a M&S Contracts) v Westminster Properties Scotland Ltd [2007] B.L.R.
537;Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC);Bovis Lend Lease Ltd v Trustees
of the London Clinic [2009] EWHC 64 (TCC); RWE NPower Plc v Alstom Power Ltd [2010]
C.I.L.L. 2835). For instance, in two recent decisions in Gibson (Banbridge) Limited v
Fermanagh District Council [2013] NIQB 16 and City Basements Ltd v Nordic Construction
UK Ltd QBD (TCC) 14 April 2014 (Unreported), the Courts, applying the principles outlined
51
Chapter 4- Resolving Infrastructure-related construction disputes
in the Amec Case, held that failure to admit or deny a claim for payment within a reasonable
time gave rise to inference of non-admission and consequently, the existence of disputes.
It has also been held in the context of arbitration that the fact that a claim is indisputable
does not mean that there is no dispute. In Hayter v Nelson and Home Insurance Company
[1990] 2 Lloyd’s Rep. 265, Saville J. was of the view that so long as what was regarded as
‘indisputable’ could not be resolved or determined immediately, a dispute existed regardless
of the fact that the issue could be determined one way or the other at an opportune time
without any argument. In sum, a dispute may emerge where a claim is rejected expressly or
impliedly by the respondent.
The decisions of the English Courts on the definition of disputes are logically worthy of a
wider application even if only as guides (Hibberd and Newman,1999).In any case,
establishing the existence of a dispute as a prerequisite for referring an issue to adjudication or
arbitration is not a feature of English construction law only. Under Clause 20 of the FIDIC
1999 and Clause 67 of FIDIC 1987, a party seeking to utilise the dispute resolution
mechanisms available is required to establish the existence of a dispute (Seppala, 2005).
4.2.3. Overview of Causes of Construction Disputes
By virtue of the very nature of the construction industry whether domestic or international,
disputes have been said to be inevitable. Reasons for this inevitability have been discussed in
the literature (Hibberd and Newman, 1999;Seppala, 2009; Gerber and Rogers, 2000). For
instance, Newey (1992) points to the size of the industry, the number of individuals and
corporate entities involved, the public authorities involved in regulating the industry, the sites
where work is done and the length of a project cycle as some of the rationales for this state of
affairs. In his foreword to ‘The ICE Arbitration Practice’ (Hawker et al., 1986) Lord
Donaldson noted,
It may be that as a Judge, I have a distorted view of some aspects of life, but I cannot
imagine a civil engineering contract, particularly one of any size, which did not give
52
Chapter 4- Resolving Infrastructure-related construction disputes
rise to some disputes. This is not to the discredit of either party to the contract. It is
simply the nature of the beast. What is to their discredit is if they fail to resolve those
disputes as quickly, economically and sensibly as possible.
Considerable research has been carried out on the subject of causes of disputes over the
past three decades. As shown by the synopsis below (see Table 4.1), studies on the subject
have taken place in different countries across the world, thereby providing an indication that
the issue of dispute is not localised. Diekmann and Nelson (1985), one of the earliest works
found that disputes are predominantly the product of design errors and discretionary and
mandatory changes. Since then, other studies have explored and identified several other
factors contributing to the occurrence of disputes (see Table 4.1). For instance, Hewitt (1991)
found that change of scope; change conditions, delay, disruption, acceleration and termination
are factors which engender disputes. Conlin et al. (1996) identified payment and budget,
performance, delay and time, negligence, quality and administration as factors giving rise to
disputes.
Kumaraswamy (1997) on the situation in Hong Kong attempted not only to identify causes
but to distinguish root causes from proximate or immediate causes. Unfair risk allocation,
industry culture, contract issues and unrealistic objectives in relation to cost, time and quality
were some of the common root causes of construction claims. The proximate causes included
inadequate
site
investigation,
inaccurate
design
information,
incomplete
contract
documentation, inadequate design documentation, errors in estimates and changes by client
during the course of project execution.
Table 4.1: List of studies on construction disputes (Adapted from Fenn et al., 1997;
Fenn, 2002; Love et al., 2010)
Authors
Diekmann
Nelson, 1985
Setting
and
Type of Study
USA
Factors contributing to Claims/Disputes
Design errors
Empirical
Watts and Scrivener,
1993
Australia
Empirical
Love et al, 2009
Australia
Empirical
Discretionary and mandatory changes
Variations
Negligence
Delays
Latent conditions (pathogens) of task, practice and
circumstance
53
Chapter 4- Resolving Infrastructure-related construction disputes
Authors
Setting
Type of Study
Factors contributing to Claims/Disputes
Adversarialism
Contractual complexity and risk allocation
Diekmann et al.,
1994; Diekmann and
Girard, 1995
USA
Empirical
Semple et al., 1994
Canada
Empirical
Bristow
and
Vasilopoulos, 1995
Canada
Empirical
Conlin et al., 1996
UK
Empirical
Ogunlana
1996
Thailand
Empirical
Sykes, 1996
UK
Commentary
Kumaraswamy, 1997
Hong
Kong
Empirical
Hong
Kong
Empirical
Egypt
Empirical
Fenn, 2007
UK
Empirical
Hanna, 2007
USA
Commentary
USA
Empirical
Malaysia
Literature
et
al.,
Cheung and Yiu,
2006
Bassioni et al., 2007
Mitropoulos
Howell, 2001
Jaffar et al., 2011
and
Contract Indexicality
Project uncertainty
Process problems
People issues
Project uncertainty
Acceleration
Restricted access
Weather/cold
Increase in scope
Unrealistic expectations by parties
Ambiguous contract documents
Poor communications between project participants
Lack of team spirit
Failure of participants to deal promptly with changes
and
Payment and budget
Performance
Delay and time
Negligence
Quality
Administration
Supply problems
Problems caused by clients and consultants
Problems of contractor incompetence/inadequacies
The nature of construction contracts (insufficient
clarity, ambiguity and internal contradictions creating
misunderstandings)
Unpredictable future events/ unforeseen circumstances
Inaccurate design information
Inadequate design information
Slow client response to decision
Poor communication
Unrealistic time targets
Listed 33 construction and behavior-related causes of
disputes eg. variation, site possession issues, error in
documentation etc.
Variations caused by clients and consultants
Problems with design/drawings /specifications
Delays in approving shop drawings, instructions and
slow decision making
Construction and chemical processing contracts
compared for impact on disputes
Poor quality of design drawings
Increased use of disclaimer clauses
Shortened construction duration
Increased shift of risks
Uncertainty
Contractual problems
Opportunistic behaviour
Behavioural problems
Contractual problems
Technical problems
54
Chapter 4- Resolving Infrastructure-related construction disputes
Authors
Setting
Type of Study
Factors contributing to Claims/Disputes
Love et al., 2011
Australia
Empirical
Ilter, 2012
Turkey
Empirical
Rosenfeld, 2014
Israel
Empirical
Hewitt ,1991
UK
Theoretical
Rhys-Jones, 1994
UK
Empirical
Love et al., 2010
Australia
Empirical
Heath et al. (1994)
UK
Empirical
Bounded rationality
Opportunism
Variations
Late instructions from the employer
Inadequate specifications
Unclear contractual terms
Adversarialism
Unclear scope definition
Poor communication
Lack of familiarity with local conditions
Technical inadequacy of the contractor
Fifteen root causes of cost overrun – first three of which
are premature tender documents, changes in owners'
requirements or definitions and use of the traditional
procurement method
Change of scope
Change conditions
Delay
Disruption
Acceleration
Termination
Poor management
Adversarial culture
Poor communications
Inadequate design
Economic environment
Unrealistic tendering
Influence of lawyers
Unrealistic client expectations
Inadequate contract drafting
Poor workmanship
Nature of the task being performed (e.g. failure to
detect and correct errors)
People’s deliberate practices (e.g. failure to oblige by
contractual requirements)
Contract terms
Payments
Variations
Extensions of time
Nomination
Re-nomination
Availability of information
Diekmann et al.(1994) and Diekmann and Girard (1995) studied data from 159 projects
and categorized the project features which were predisposed to disputes into people issues
(organisations, relationships, roles, responsibilities and expectations), process issues (related
to how the project is procured) and project issues (project characteristics).The research was
based on the hypothesis that some disputes could be predicted and thus be avoided. On the
55
Chapter 4- Resolving Infrastructure-related construction disputes
basis of the project features identified, they developed the dispute potential index (DPI), a
dispute predictor. Mitropoulos and Howell (2001) identified the uncertainty surrounding
construction projects, contractual problems and opportunistic behaviour as contributory
factors to disputes. For Love et al.(2010), a combination of pathogens (latent conditions
acting as stimuli for dispute occurrence) such as tasks, practices, circumstances and
organisations and active failures from people involved in projects such as slips, lapses and
procedural violations are the real underlying conditions for disputes.
It appears nearly all aspects of the construction process have been named as likely sources
of claims or disputes (see e.g. Killian, 2003; Fryer et al., 2004). Most studies offer some kind
of classification for dispute causes. Consequently, there are as many classifications as there
are different studies. This situation may be as a result of the terminological muddle associated
with the undefined use of terms such as ‘claims’, ‘disputes’, ‘conflicts’, ‘causes’, and
‘sources’ and the lack of framework (see Fenn et al., 2002; Fenn,2007). Examination of the
studies on disputes also raises the question of why all the studies? If the aim is to provide a
framework which will help deal with disputes by way of predicting them, then only few
studies have their focus on such venture (Diekmann et al., 1994; Diekmann and Girard, 1995;
Mitropoulos and Howell, 2001; Love et al., 2010b; Love et al., 2010a; Ilter, 2012). Yet, it has
been argued that dispute prediction must be at the heart of every avoidance strategy (Fenn,
2007).
Nevertheless, factors underscoring the project owner’s contribution to disputes such as
changes in owners’ requirement, poor definition of scope of work, variations, delays and
payment issues cut across most of the findings on factors leading to disputes (see Table 4.1).
Apart from direct contribution as outlined above, poor quality documents and poor
performance by consultants can also be laid at the owner’s door since it is ultimately
responsible for all such arrangements.
56
Chapter 4- Resolving Infrastructure-related construction disputes
In relation to international construction transactions, Seppala (2009) has argued that
dispute causes are fundamentally similar to those in the domestic setting. Beyond the general,
the oft-cited reasons for the occurrence of disputes include the involvement of different
parties and professionals with distinct interest and cultural backgrounds, multiple linked
contracts, complexity of projects, the involvement of State parties and third party funders as
well as political and economic concerns (Schwartz, 1995; Bockstiegel, 1999; Chan et al,2006;
Draetta, 2011; Fellows and Liu, 2008). Dispute causes on infrastructure projects are pervasive
in developing countries due to lack of adequate knowledge of construction law, bureaucracy
and lack of institutional structures to ensure compliance with contracts (World Bank, 2003;
Anvuur et al., 2006; Chan et al., 2006).
4.3.
Major Construction Dispute Resolution - Options in Developed Countries
Traditionally, the construction industry resolved disputes arising from projects through
litigation and arbitration. Whitfield (1994), reports that 250 writs relating to construction
disputes were issued in the UK in 1960. He asserts that this number increased five-fold by
1990. This assertion is confirmed by Mix (1996-97) who reports that absolute litigiousness
characterized the construction industry of the United States in the 1980s. All these have
changed considerably in the course of the past two decades with more attention turned to the
use of alternative dispute resolution (Gaitskell, 2005).
From the literature on the subject, alternative dispute resolution mechanisms are
increasingly being used in the construction industry both domestically and at the international
level in addition to litigation and arbitration (Schwartz, 1995; Seppala, 2005; Draetta, 2011).
Reasons accounting for the proliferation of dispute resolution mechanisms in the construction
industry include concerns about cost, delays and rigid procedural requirements (Hobeck et al.,
2008. See also Table 4.2 below). In addition to providing a rationale for the use of ADR, the
57
Chapter 4- Resolving Infrastructure-related construction disputes
reasons outlined in Table 4.2 also constitute attributes of ADR mechanisms and serve as
benchmark for selecting, measuring and prioritising them.
Table 4.2: Reasons affecting the selection of dispute resolution mechanisms
Selected Literature
Attributes
1 Cheung, 1999
2
3
4
5
Nature of decision(whether binding or not), Economy
(cost), Confidentiality, Control over proceedings, Creative
remedies, Enforceability, Fairness, Flexibility, Privacy,
Speed, Width of remedy and Preservation of relationships.
Gaitskell, 2006
Contractual procedure dispute resolution, confidentiality,
working relationships, speed, Statutory limitation, Cost
and Complexity
Hobeck et al. , 2008
Predictability, flexibility, swiftness, effectiveness and
robustness.
Ndekugri and Rycroft, Cost, Simplicity of Procedure, Expertise, Advocacy,
2009 (in the context of Expedition,
Convenience,
Courtesy,
Privacy,
arbitration
and Confidentiality, Future business relations, Powers of the
litigation)
third party Neutral, Summary relief, Finality and national
sovereignty
Blake et al., 2011
Cost, Speed of settlement, Control of process, Choice of
forum, consideration of wide range of issues in the course
of process, Wide range of potential outcomes, Client
satisfaction, Process flexibility, Possible reduction of risk
of win/lose, Expert knowledge required, Confidentiality,
Court order required, judicial precedent needed, Future
relationships, Chance of success, enforcement etc.
Generally, the various resolution mechanisms are often categorised on the basis of factors
such as party control, outcomes (whether binding or non-binding), involvement of an
independent third party and decision-making (Blake et al., 2011). The literature on
construction dispute resolution tends to categorise the mechanisms in terms of their ultimate
goals namely dispute prevention, management and resolution (Fenn et al., 1997; Cheung,
1999; Morgan, 2008; Hinchey, 2012).
4.3.1. Dispute Avoidance and Management
Dispute avoidance approaches focus on the initial stages of a project and aim at ensuring
that the parties start right so as to reduce or prevent the occurrence of disputes (Vorster, 1993;
Yates and Duran, 2006). The literature identifies a broad range of dispute avoidance
58
Chapter 4- Resolving Infrastructure-related construction disputes
techniques most of which fall under one or the other of the following four areas. These are the
use of standing neutrals, procurement and relational contracting, effective project
management, and planning and general preparation. On the first set of techniques, Gerber
(2000) identifies three main standing neutrals (Dispute Avoidance Procedures (DAPs)) for
purposes of dispute avoidance. These are the Dispute Resolution Adviser (DRA) (Project
Neutral or Dispute Resolution Expert (DRE)) (see also Cheung and Yeung,1998), Dispute
Adjudication Boards and Dispute Review Boards (see also Harmon, 2003; Yates and Duran,
2006 and Ng et al., 2007).
The second set of avoidance techniques uses procurement and related processes to manage
relationships so as to avoid or reduce disputes. Examples of this set of techniques are
partnering, alliancing and related integrated project delivery systems and equitable risk
allocation (Cowan, 1991; Construction Industry Institute, 1991; Crowley and Karim, 1995;
C.I.B, 1997; Critchlow, 1998; Stehbens et al., 1999; Bresnen and Marshall, 2000; Harmon,
2003; Doug, 2006; Hanna, 2007; Ross, 2009; Kratzsch, 2010; Le Nguyen, 2011; Hinchey,
2012). These methods focus on maintaining good relationships and healthy communication
links among project teams and engender a cultural shift. It is envisaged that such change in
project environment will encourage parties to resolve their differences more easily and thus
avoid disputes.
The third set of avoidance techniques is management-related. The focus of these
techniques is on ensuring effective documentation, cost and schedule control, quality
management and constructability (Fenn et al., 1997; Yates and Duran, 2006; Ng et al., 2007).
Morgan (2008) recommends about thirteen such avoidance techniques. These include
preparing staff for projects, being abreast with the terms of the contract and ensuring
compliance, identifying potential dispute area, effective communication and disclosure of
information. The final set of avoidance techniques entails activities relating to general
59
Chapter 4- Resolving Infrastructure-related construction disputes
planning and preparation for projects (Mitropoulos and Howell, 2001). The effectiveness of
these avoidance strategies can be greatly boosted if dispute causes can be sufficiently
predicted at the inception of projects (Diekmann et al., 1994; Fenn, 2007).
Some of the techniques listed under avoidance are also used for dispute management.
These include the use of standing neutrals and negotiations. The idea underpinning dispute
management is to ensure that festering disputes are nipped in the bud and not allowed to
escalate. The current approach to dispute avoidance and management is summed up in the
two-pronged approach to dispute avoidance by the Dispute Prevention and Resolution Task
Force of the Construction Industry Institute (CII) which require parties to ‘start right’ and
‘stay right’(Vorster, 1993; Diekmann and Girard, 1995; Yates and Duran, 2006).
The avoidance and management techniques are often implemented alongside the resolution
mechanisms. Mediation, adjudication, expert determination, dispute review boards and early
neutral evaluation are common among construction industry users in the United Kingdom, the
United States, Australia, Singapore and Hong Kong (Hibberd and Newman, 1999; Gaitskell,
2005; Gaitskell, 2006; Rana, 2009). These options are dominant both in minor and major
construction projects (Levin, 1998; Harmon, 2003). Some of the main dispute resolution
mechanisms commonly used in the construction industry are briefly examined.
4.3.2. Negotiation
This is an informal process where parties to a dispute either by themselves or through their
representatives discuss some or all their issues with a view to resolve them on agreed terms
(Blake et al., 2011). Whilst the role of negotiations in dispute resolution is endorsed by many
authors, others are unconvinced that negotiation qualifies as an ADR process (Brown and
Marriott, 2011). To Brown and Marriott (1999), there is no ADR unless the process of
resolving a dispute involves an intervention by a third party neutral and a structured process
framework. The general view of the construction literature appears to disagree with the
60
Chapter 4- Resolving Infrastructure-related construction disputes
argument excluding negotiation from the list ADR options (Fenn et al., 1997; Cheung, 1999).
There are no formal rules or procedure for this resolution option. However, over the years,
strategies and tactics have emerged which parties may adopt in terms of approach. These
include competitive, cooperative or collaborative tactics (Menkel-Meadow et al., 2005; Blake
et al., 2011).
The strengths of this process lie in its flexibility, the opportunity it offers to parties to
fashion out their own terms of settlement at a very low cost, and the privacy and
confidentiality it offers. Its consensual nature remains its strength and a weakness at the same
time. Parties can engage in negotiation at any time during the life span of a dispute even if
other resolution mechanisms are being used. However, because it thrives on consent, a party
ready to negotiate cannot compel another who is unwilling to participate. For the construction
industry where the culture of claims exist, many disagreements between a claimant and a
client or its representative over such claims are resolved through negotiations (Love et al.,
2010b). In terms of speed, efficiency and cost reduction, much depends on the preparation of
the parties involved (Blake et al., 2011). Where parties are unprepared or the issues involved
are complex technical or legal, the outcome may be less successful.
4.3.3. Mediation and Conciliation
Where parties are unable to resolve their differences by negotiations or they envisage that
this may not be possible, they may seek the assistance of a third party neutral to help them
arrive at settlement. Mediation is one of many third party procedures available. In mediation,
the parties own both the processes leading to a decision and the outcome itself. The mediator,
who is required to be independent, neutral and impartial, is expected to help the parties
through what is often a private and confidential process aim at finding a mutually acceptable
solution without making a finding of his own or expressing a bias (Gaitskell, 2006; Uff,
2009). The mediator’s role, among others, is to create an opportunity and the environment for
61
Chapter 4- Resolving Infrastructure-related construction disputes
parties to meet and discuss their dispute. The mediator plays this role by ensuring that the
parties put their cases across, learn each other’s positions, explore their real needs and focus
on the issues at stake (Brown and Marriott, 1999; Stitt, 2004). The mediator’s authority is
from the parties who appoint him. He has no power to decide the dispute.
As a facilitated negotiation, mediation is informal and come in different shades. It may be
facilitative, evaluative or transformative in style (Brown and Marriott, 1999; Stitt, 2004;
Brooker, 2007). In facilitative mediation, the mediator’s role goes no further than creating the
environment conducive for the parties to seek their own solutions. This is achieved by helping
the parties to focus on the issues at stake rather than extraneous issues which might have crept
into the dispute.
Evaluative mediation on the other hand goes further with the mediator’s role including
assessing parties’ positions based on merits (that is, their rights and likely chances of success
in a court of law) (Stitt, 2004). On the basis of such evaluations, the mediator may give an
indication as to which party’s case is stronger and suggest a solution which the parties may
then consider. Such mediator positions remain suggestions only and are not binding on the
parties. In this respect, evaluative mediation is akin to other evaluative processes like minitrial and early neutral evaluation.
There is considerable disagreement in the literature on the relationship between mediation
and conciliation (Hibberd and Newman, 1999). Some authors opine that the words
‘conciliation’ and ‘mediation’ are used interchangeably (Brown and Marriott, 1999) and
attempts at distinguishing them amounts to ‘nit-picking and is ‘only of academic interest’
(Hibberd and Newman, 1999, p.59). Gaitskell (2006) asserts that evaluative mediation is often
referred to as conciliation in the United Kingdom. On the other hand, a report by UNCTAD in
2010 on ADR and investor-State disputes identified three main distinctions between
conciliation and mediation namely degree of control, focus and degree of formality. Whilst
62
Chapter 4- Resolving Infrastructure-related construction disputes
conciliation is more formal, evaluative in nature and focuses less on relationship-building, the
reverse is the case for mediation (UNCTAD, 2010b). Transformative mediation places more
emphasis on process rather than outcome and is more interested in behavioural change in
future dealings (Brown and Marriott, 2011).
Mediation and conciliation have numerous strengths and weaknesses. Some of the
accusations against the use of mediation include lack of compulsion, reliance on a party’s
voluntary participation and issues with enforcement of outcomes. Other factors which are
often publicised as weaknesses of mediation include the perception that the one advocating
for mediation has a weak case, fear that mediation will delay the commencement of litigation
(with the associated danger of having the action declared statute barred) or arbitration and the
concern that a party may reveal their strong points to an opponent (Blake et al., 2011).
Notwithstanding the outlined concerns with mediation, many private and public
institutions in the developed world are increasingly turning to mediation as preferred means
of resolving construction disputes (Hibberd and Newman, 1999; Harmon, 2003; Blake et al.,
2011; Gaitskell,2005; Blake et al.,2011). Many standard form contracts for major construction
works, particularly those which advocate for relationship-based procurement strategies, such
as partnering, contain provisions on mediation as part of a tiered dispute resolution strategy.
Examples of such forms are JCT Framework Agreement, JCT Constructing Excellence
Contracts, 2006 & 2011, NEC ECC Edition 3 (Partnering Option X 12), ACA Standard Form
of Contract for Project Partnering PPC2000 and SPC 2000 Perform 21 Public Sector
Partnering Contract, 2005 (Clamp et al., 2007). Flexibility of process, savings in cost and time
and the empowerment of parties with ownership and control over the resolution process are
some of the advantages associated with the use of mediation (Blake et al., 2011). The process
offers parties in an on-going relationship a less acrimonious way to deal with their disputes
63
Chapter 4- Resolving Infrastructure-related construction disputes
and help them maintain, and in some cases, strengthen their existing commercial relationships
(Fuller, 1971).
4.3.4. Early Neutral Evaluation
Like mediation, early neutral evaluation (ENE) is a non-binding third party neutral process.
In many respects, this process shares common features with evaluative mediation (Blake et
al., 2011). ENE involves a process where parties request a neutral to evaluate various issues
involved in a dispute on the basis of the law to ascertain the merits of the parties’ cases as a
preliminary step towards using other resolution processes (Gaitskell, 2006). It is a private and
confidential process. Who carries out the evaluation, the extent of the evaluation and the
timing of the evaluation depends on the parties. As a consensual non-binding process, it
suffers from similar weaknesses as mediation. Its strength lies in the information or the
assessment which is made available to parties prior to or in the course of the use of other
dispute resolution processes.
4.3.5. Dispute Boards
A Dispute Board (DB), another resolution mechanism involving the use of neutrals, may
consist of one or three independent, experienced experts who are jointly appointed by the
parties to a construction or engineering project at the onset of a project and prior to the
emergence of disputes (Harmon, 2009). The panel remains in existence throughout the life
span of a project. Its main task is to deal with disputes as they occur or indeed nip incipient
disputes in the bud before they bloom into obdurate disputes (Thompson and Vorster, 2000).
To perform its role effectively, the panel must have a good knowledge of the project and its
progression. Thus, the DB has access to project documents and pays regular visits to project
sites where representatives of the parties are met and discussions about progress of work and
any pending issues are undertaken (Gerber and Rogers, 2000; Harmon, 2003; McMillan and
Rubin, 2005).When a dispute arises that the parties are unable to resolve through negotiations,
64
Chapter 4- Resolving Infrastructure-related construction disputes
such a dispute is passed on to the DB. After following informal procedures often agreed with
the parties, the issues in contention will be examined and a decision reached. The type of
decision that is arrived at depends on the variant of DB which is used (Matyas et al., 1996;
Ndekugri et al., 2013).
The two main types of DB are Dispute Review Board (DRB) and Dispute Adjudication
Board (DAB). After hearing the parties’ positions on issues in contention and examining the
available evidence, both physical and documentary, a DRB will issue a non-binding decision
referred to as a recommendation (McMillan and Rubin, 2005). The parties may accept or
reject some or all the recommendations. The decision of the DAB is however binding unless a
settlement is reached, a notice of dissatisfaction is served or the issue is decided by arbitration
or litigation as per the contract between the parties (Gerber and Rogers, 2000; Harmon, 2003).
Ndekugri et al. (2013) cautions that parties need to look at substance and not form to
determine whether a particular arrangement is a DAB or DRB as the form may be deceptive.
As compared to the DRB, the DAB format is more structured and formal with strict timelines
on the service of notice and particulars of dispute and timeframe for decision-making.
DRB originated from the United States of America. There is some unanimity in the
literature that DRB in its current form was first used during the construction of the
Eisenhower Tunnel (Second bore) in Colorado, United States in 1975, even though its
emergence can be traced to an earlier time (Hibberd and Newman, 1999). Since 1975, DRB
has been used on major civil engineering and construction projects in the United States,
Canada, Australia, South Africa, Denmark, Ethiopia, Italy, Uganda, India, China and many
other countries (Gerber and Rogers, 2000; DRBF, 2012). Since its inception in 1996, the
Dispute Resolution Board Foundation, an entity dedicated to the promotion of DRB, has kept
a database of projects on which DRB has been used. The data set date back to 1975. As of
2006, DRB had been used on one thousand, four hundred and thirty-four projects (recorded)
65
Chapter 4- Resolving Infrastructure-related construction disputes
across the globe, with total project value of $ 97.637 billion. The individual project values
range between $ 1 million and $ 14.7 billion. Some of the notable projects which have used
the DRB include the Channel Tunnel and the Lesotho Highlands Water Projects. The DRBF
report indicates a high success rate in dealing with disputes with DRB. Out of a total of one
thousand, eight hundred and sixty recorded disputes which have been heard by DRBs, one
thousand, seven hundred and eighteen were settled. Only fifty-three disputes were settled by
other dispute resolution methods. Whilst this database may have limitations in terms of its
capacity to cover all projects using DRB around the world, it is indicative of the extent of use.
Dispute Adjudication Boards, on the other hand, owe their widespread use mainly to the
sponsorship of two key institutions involved in major infrastructure procurement and delivery
in most parts of the world; the World Bank and the Fédération Internationale Des IngénieursConseils (FIDIC) (Chapman, 2006;Ndekugri et al., 2013). The World Bank which had been
involved in the construction of the El Cajon Hydroelectric Project in Honduras between 1980
and 1986 had experienced the effectiveness of the DRB concept and saw its variant, the DAB,
as a suitable replacement for the long-standing quasi-judicial role of the Engineer or the
Architect as the arbiter of disputes arising in the course of projects (Chapman, 2006; Ndekugri
et al., 2013). Whilst the existence of an on-the-job arbiter on construction projects has been
viewed as crucial and useful, Ndekugri et al. (2007) state that the individual who played this
role (the Engineer or Architect) had been the subject-matter of discontent for several decades
due to his lack of neutrality and affiliation with the client. The Bank’s recommendation of
DABs as a dispute resolution alternative to the independent engineer for construction projects
financed by it became a mandatory requirement for all bank-funded major construction
projects in 1994.
In response to the Bank’s decision, FIDIC initiated various changes which culminated in
the replacement of the Engineer/Architect as the on-the-job arbiter of the first instance with
66
Chapter 4- Resolving Infrastructure-related construction disputes
the DAB. With the adoption of the 1999 FIDIC Red book and subsequent versions (e.g. the
Multilateral Development Bank Harmonised Edition, 2010) by the World Bank for its
projects, DAB has now become an entrenched part of the dispute resolution strategy under
many project contracts particularly in developing countries. Cost of retaining three experts
over the life span of a project remains the key challenge to the use of DRB or DABs.
4.3.6. Expert Determination
Expert determination is one of the third party processes by which parties involved in a
dispute may have their dispute resolved with finality. The parties may agree at the time of the
formation of the contract or at the occurrence of a dispute to appoint a third party with
expertise in the subject area to which the disputed matter belong to make a final or interim
determination of disputes. The powers and the activities of the expert are defined by the
parties. They determine the scope of the dispute the expert is to settle and the procedure, but
the expert thereafter will have the right to add to the procedure unless expressly prohibited
from doing so.
Unlike arbitration, expert determination is not a judicial process and is thus not subject to
the strict rules of natural justice, though the expert is required to act fairly and impartially
(Gaitskell, 2006; Blake et al., 2011). In Macro & Others v. Thompson & Others (No.3)
[1997] 2BCLC 36 it was held that apparent partiality will not be sufficient to set aside the
decision of an expert. Proven bias, however, will be sufficient. Another fact that distinguishes
expert determination from arbitration is its flexibility. Apart from the limitation on the expert
to make a decision within the boundaries of his instructions as given by the parties, he has the
liberty to employ his own skills and expertise to determine the dispute at hand (Gaitskell,
2006). He is bound neither by the submissions of the parties nor the evidence presented to
him. His approach to the resolution process may be inquisitorial in nature. He may determine
the matter according to his own opinion formed on the basis of his own investigations
67
Chapter 4- Resolving Infrastructure-related construction disputes
(Dundas, 2008). Currently, the law regulating expert determination in the United Kingdom is
the common law.
The issue of what kind of dispute can be referred to an expert does not suffer any of the
confusion associated with arbitrability for example. Every matter which the parties have
power to resolve by themselves can be the subject of expert determination (Dundas, 2008). It
has been indicated that it is most useful where the subject matter of the dispute is highly
technical (Blake et al., 2011). The mechanism has been used to resolve disputes in computing
(Blunt and Osborne, 2011), insurance (Halifax Life Ltd v Equitable Life Assurance Society
[2007] 2 All E.R. (Comm)), shipping (Bernhard Schulte GmbH & Co KG v Nile Holdings Ltd
[2004] 2 Lloyd's Rep. 352), engineering and construction and energy (Gaitskell, 2006;
Dundas, 2008).
There is a burgeoning jurisprudence on the mechanism under English law addressing
questions such as: (i) the appropriateness of expert determination for all disputes; (ii) whether
a stay can be granted for parties to resort to an expert; (iii) whether or not an expert is obliged
to give reasons for his/her decisions; and (iv) under what circumstances the decision of an
expert may be set aside (see Thames Valley Power Ltd v Total Gas & Power Ltd [2005]
EWHC 2208 (Comm); Bernhard Schulte GmbH & Co KG v Nile Holdings Ltd [2004] EWHC
977 (Comm)). Only fraud or manifest error including material deviation from the instructions
of the parties can result in the setting aside of the decision of the expert (Veba Oil Supply &
Trading Ltd v Petrotrade Inc (The Robin) [2002] 1 All E.R. 703; see also Dundas, 2008). The
authorities also distinguish between a mistake by an expert and a departure from instructions;
whilst the former will have no effect on the binding nature of the expert’s decision, the latter
does (Ackerman v Ackerman [2011] EWHC 3428 (Ch).
In the context of international transactions, it has been argued that issues of enforcement
may render expert decisions less attractive as compared to an award (Gaitskell, 2006). The
68
Chapter 4- Resolving Infrastructure-related construction disputes
way out is to incorporate into the agreement stipulating the use of expert determination that
the decision will be interim and subject to a final reference to arbitration for enforcement
(Gaitskell, 2006).
4.3.7. Adjudication
In the present context, the term adjudication is used as a term of art. It refers to an
essentially interim dispute resolution mechanism which allows a third party neutral, called the
adjudicator, to determine construction disputes submitted to him under the terms of a contract
or a statute. The outcome is binding until a final decision is made on the dispute by a court or
an arbitral tribunal. There are essentially two kinds of adjudications; contractual and statutory.
In countries such as the United Kingdom, Singapore, New Zealand and Australia, statutes
have been enacted to regulate the process of adjudication. In other countries such as South
Africa and Ghana adjudication is based on contract. Tackaberry (2009) observe that the
defining moment for adjudication in England was marked by the Latham recommendations
which eventually culminated in the enactment of the Housing Grants, Construction and
Regeneration Act, 1996 (HGCR) as amended by the Local Democracy, Economic
Development and Construction Act,2009 (LDEDC). The core essence of statutory
adjudication in most of the jurisdictions where it exists is to ensure payment security. No
statute reflects this intention better than the New South Wales Building and Construction
Industry Security of Payment Act, 1999. It is worth mentioning that beyond this core goal,
some of the statutes on adjudication such as the HGCR and the New Zealand legislation do
not limit the kinds of disputes which can be submitted to adjudication to only monetary
claims.
Adjudicators are required to act fairly and swiftly. The basic idea of the process is ‘pay
now, argue later’ (see RJT Consulting Engineers Ltd v. DM Engineering (Northern Ireland)
Ltd. [2002] 1 WLR 2344; Blake et al., 2011). Speed is assured through strict time-lines
69
Chapter 4- Resolving Infrastructure-related construction disputes
allowing for extension under certain circumstances. As an interim mechanism manned by
persons who often lack enforcement powers, the courts remain the ultimate avenue for
enforcement where decisions rendered by adjudicators are not complied with promptly. The
ambit of contractual adjudication is determined by the parties. They may decide on whom to
appoint as an adjudicator, what issues to refer to an adjudicator, timeframe for the adjudicator
and the extent to which parties may be bound by the decision of the adjudicator.
4.3.8. Arbitration
Arbitration is one of (if not) the commonest dispute resolution mechanisms among parties
involved in the construction industry. Like all the other dispute resolution mechanisms
discussed above, arbitration is based on an agreement between parties to refer a dispute or a
difference to a third party neutral, an arbitrator, who is clothed with authority by virtue of his
instructions to make a binding award (Tackaberry and Marriott, 2003). In Fili Shipping Co
Ltd and others v Premium Nafta Products Ltd and others [2007] UKHL 40, para 6, Lord
Hoffmann outlined the fundamental principles or purposes of arbitration as: (i) existence of a
relationship between parties; (ii) an agreement to submit future disputes to a chosen tribunal
based on factors such as privacy, neutrality and expertise; (iii) selection of a seat for the
resolution process based on the availability of legal services and the ‘unobtrusive efficiency of
its supervisory law’;(iv) the need for quick and efficient determination of disputes; and (v)
avoidance of delay and partiality of national courts in the case of international transactions.
Another feature of arbitration is the delivery of binding outcomes which may be enforced in
many parts of the world.
Arbitration may be domestic or international (see section 4.4.1). At the national level, most
countries have enacted legislations which regulate the practice of arbitration by providing
default rules for situations where parties fail to agree. On the international stage, arbitration
has benefitted from near universal patronage due to treatise such as the Convention on the
70
Chapter 4- Resolving Infrastructure-related construction disputes
Recognition and Enforcement of Foreign Arbitral Awards, 1958 and the promotion efforts by
organisations such as the United Nations Commission on International Trade Law
(UNCITRAL). Generally, key points of arbitration will include the existence and scope of the
arbitration agreement, the seat of arbitration, appointment of arbitrators and jurisdictional
issues (Redfern, 2004). The arbitration proceedings and issues concerning the arbitral award
and enforcement are also among the core elements of this popular dispute resolution
processes.
4.4.
Developing Countries and Construction Dispute Resolution
Disputes arising from transactions within a State fall within the jurisdiction of the national
courts (Mante et al., 2011). However, the involvement of foreign participants in international
transactions within developing countries has changed the dynamics of this principle. National
courts have lost their appeal as the preferred choice for settling disputes arising from such
transactions due to perceived bias against foreign parties, over-crowded national courts, lack
of confidentiality and issues with enforcement of foreign judgments (Leahy and Pierce, 198586; Perloff, 1992; McLaughlin, 1979).The need for fair and final decisions, jurisdictional
neutrality, privacy, confidentiality and party autonomy has led to the choice of ICA as the
preferred mechanism for dispute resolution in international transactions including
infrastructure procurement (Cotran and Amissah, 1996; Asouzu, 2001;Tackaberry and
Marriott, 2003; Redfern, 2004; Blackaby et al., 2009).
The growth of ICA in developing countries can be examined from two perspectives, legal
and institutional developments. In respect of legal developments, two international
instruments have been crucial. These are the Convention on the Recognition and Enforcement
of Foreign Arbitral Awards, 1958 (the New York Convention) and the UNCITRAL Model
Law on International Commercial Arbitration, 1985 (as amended in 2006) (the Model Law).
The main objective of the New York Convention is to commit States to give effect to
71
Chapter 4- Resolving Infrastructure-related construction disputes
agreements to arbitrate and to enforce within their territories foreign arbitral awards which
satisfy certain agreed criteria for validity and legitimacy (the New York Convention, Article
III). Currently, 149 countries are parties to this treaty. Even in Latin America, a region noted
for its support of the Calvo doctrine (which insisted on non-intervention and absolute equality
of foreigners with nationals in dealings by States with foreign nationals), it is reported that all
countries within the region have signed on to the New York Convention as of 2003 (Bernal,
2009). The UNCITRAL Model Law, on its part, aims at eliminating the inadequacies of
national laws and disparities between them. To this end it sets out a special procedural regime
for ICA. Currently, over 70 States, many of them developing nations, have adopted national
arbitration legislations based on the Model law.
Beyond the global efforts, there have been regional efforts to develop international
arbitration. For example, the Organization for the Harmonization of Business Law in Africa
(OHADA) set up by treaty in 1993 with sixteen mainly francophone West and Central
African member States, aims at harmonizing business laws among members. As part of its
activities it has adopted a uniform Arbitration Act, set up a court, and developed its own
arbitration procedures (Dickerson, 2005).
Regarding institutional developments, international arbitral institutions in Europe have
traditionally served as venues for ICA involving many developing countries and foreign
entities. Examples of such institutions are the International Court of Arbitration of the
International Chamber of Commerce (ICC), the London Court of International Arbitration
(LCIA), and the International Centre for Settlement of Investment Disputes (ICSID).
Recently, other arbitral institutions have been set up in Hong Kong, Singapore, China, Dubai,
Cairo and Nigeria. The Asian-African Legal Consultative Organisation (AALCO) has been
instrumental in the effort to ‘regionalise’ arbitration centres (Sempasa, 1992; Asouzu, 2001;
Asouzu, 2006). AALCO’s efforts led to the setting up of regional centres in Cairo and
72
Chapter 4- Resolving Infrastructure-related construction disputes
Nigeria. The rationale was to bring ICA closer to countries in Asia and Africa (Asouzu,
2001).
Generally, little exists by way of literature on infrastructure-related construction dispute
resolution in developing countries, particularly those in Africa. The limited literature
identified so far has revealed that ICA remains the dominant resolution mechanism in all
commercial transactions (Tiewul and Tsegah, 1975; Sempasa, 1992; Cotran and
Amissah.,1996; Asouzu, 2001). Virtually all standard form contracts governing construction
transactions in developing countries (notably the FIDIC suite of contracts) contain provisions
on ICA (Tackaberry and Marriott, 2003). The literature on dispute resolution in Africa
primarily focus on problems posed by ICA to developing countries (Yelpaala,
2006;Asante,1993; Asouzu,2001; Sempasa, 1992).
These problems are divided into the
generic and peculiar.
4.4.1. Generic Problems with ICA
Key issues under the generic category of problems with ICA are cost and delays (Asouzu,
2001). Regarding cost, infrastructure-related construction disputes are often resolved at great
cost to developing countries. A good example is the case of Lesotho Highlands Development
Authority (Respondents) v. Impregilo SpA and Others [2005] UKHL 43. In 1991 (after a sixty
year preparatory period), the Lesotho Highlands Development Authority engaged a
consortium of seven companies from the United Kingdom, South Africa, Italy, Germany and
France to construct the Katse Dam. Disputes arising from this project over reimbursement of
cost and adjustment to rates ended up in the English Supreme Court after the engineer’s
determination and international arbitration. What is worrying is that Lesotho, a small
landlocked developing country with serious human development challenges had to bear the
cost of the arbitration and protracted litigation outside its jurisdiction.
73
Chapter 4- Resolving Infrastructure-related construction disputes
In a study on investor-State arbitrations, UNCTAD found that the cost of arbitration
generally has increased drastically (UNCTAD, 2010a). Whilst legal fees constitute about 60%
of expenses, arbitrators’ fees, administration fees of arbitral centres, expenses of witnesses
and experts also constituted substantial cost. Referring to previous UNCTAD reports
(UNCTAD 2005b, 2006a, 2008a and 2009) the 2010 report cited four cases to support the
conclusion on cost of arbitration. In Plama Consortium v. Bulgaria (ICSID Case Number
ARB /03/24), the legal cost for the claimant amounted to US$4.6 million whilst that of the
respondent amounted to US$ 13.2 million. The claimant’s legal cost in Pey Casado v. Chile
(ICSID Case Number ARB/98/2) relating to the jurisdictional and merit phases of the
arbitration amounted to US$ 11million, whilst that of the respondent amounted to US$ 4.3
million. In ADC Affiliate Limited and ADC & ADMC Management Limited v. The Republic
of Hungary (ICSID Case Number ARB/03/16) the respondent country had to pay US$7.6
million in legal cost. Finally, in Waguih Elie George Siag and Clorinda Vecchi v. The Arab
Republic of Egypt (ICSID Case Number ARB/05/15), the respondent was obliged to pay an
amount of $6 million as legal costs, expert and other expenses.
These examples relating to investment are not far-fetched as international investment
agreements often define investment to include, ‘claims to money and claims under a contract
having a financial value’ (UNCTAD, 2011, p.9). Thus, the issue of the rising cost of ICA is a
common attribute of both investment and construction disputes.
Regarding delays, ICA was reputed for its swiftness (Ehrenhaft, 1977). However, this
feature of ICA has been questioned as cases take more time to resolve (UNCTAD, 2010a).
Indeed, ICA has been described as a highly complex commercial litigation (Oh, 1981).
Though this description was provided some thirty years ago, it remains true. Nearly all the
procedural complexities associated with a court proceeding can be found in most arbitral
hearings involving huge projects. The consequences of these are delays. The impact of delays
74
Chapter 4- Resolving Infrastructure-related construction disputes
on project delivery and increased project cost is hackneyed, and particularly severe on
developing countries.
4.4.2. Peculiar Concerns with ICA
The second category of concerns with ICA relate to those peculiar to developing countries.
Asouzu (2001) draws attention to some factors in the current international regime for dispute
resolution which are causing serious disaffections in the developing world. He observed that
there is a perception of bias against African States involved in international dispute resolution
processes. Factors fuelling the perception of bias identified by Asouzu (2001) include absence
of African arbitrators on arbitration panels in the West, the choice of American and European
venues or arbitration centres over equally well established ones in Africa and the longstanding arguments of lack of judicial infrastructure, qualified personnel and fair hearing.
Asouzu’s recommendations focused on regionalizing arbitral centres and awareness
creation, but are dismissive of development of alternatives such as mediation, dispute boards
and other ADR mechanisms. On the absence of African arbitrators on international arbitration
panels, most Arbitration Rules permit parties to nominate an arbitrator, whether the
requirement is for one or three arbitrators. Most developing countries end up selecting
arbitrators from the developed world due to lack of local experts (Asouzu, 2006).
4.4.3. Resolving Major construction Disputes in Ghana
The process of infrastructure-related construction dispute resolution in Ghana is largely
unexplored. Some work has been done in the area of investment dispute resolution (see
Tiewul, 1974; Asante, 1993; Asante, 1996). These works have focused on issues such as
dispute resolution options and enforcement of arbitral awards. Asante (1998), for instance, has
argued in respect of choice of dispute resolution mechanisms where foreign investment is
involved as follows:
A foreign investor may insist on the reference of disputes arising from the joint
venture to international arbitration. This may be an aspect of the investor's overriding
75
Chapter 4- Resolving Infrastructure-related construction disputes
concern to insulate the joint venture from the local judicial process as an insurance of
fair adjudication. In this regard, it should be pointed out that most developing
countries involved in negotiating international business transactions recognise the
virtual inevitability of international commercial arbitration. Indeed, the acceptance of
international arbitration has become an invariable ingredient of the liberalization
package which developing countries provide as a sine qua none of their strategies to
attract foreign investment, technology, international finance and foreign trade (Asante,
1998,p.71).
As to whether a similar rationale applies to construction dispute resolution is unclear. What is
clear however is that arbitration has long been considered a useful mechanism in the
resolution of private disputes of international character. As early as 1961, Ghana had enacted
arbitration law which acknowledged foreign awards and catered for their treatment under
Ghanaian law. This law has been replaced by the Alternative Dispute Resolution Act, 2010
(Act 798). Commentaries on dispute resolution from authors such as Torgbor (2011) provide
a generic reflection on Act798 with no specific treatment of the issue in the context of
infrastructure-related construction disputes in Ghana. Sarkodie’s (2011) exposition on Act
798 examines the Act and its possible impact on international construction arbitration. He
argues that the only alternative to international arbitration is litigation in the domestic courts.
What is clear from the commentary, however, is that it is based on provisions of Act 798 and
not evidence from practice. Anecdotal evidence points to the existence of disputes between
the Employer and foreign contractors, most of which have been determined or are currently
pending before international arbitral bodies. There is a need for an exploration of practice to
help fill the gaps in the literature.
4.5.
Knowledge Gaps
At least four gaps in the literature have emerged from this review. Firstly, the existing
literature relating to resolution of disputes between the State and foreign entities focuses on
investment. Even so, the attention of the existing literature is generally on ICA (Cotran and
Amissah, 1996). In spite of growing activity in infrastructure procurement, there is no
empirical study on how infrastructure-related construction disputes are being resolved.
76
Chapter 4- Resolving Infrastructure-related construction disputes
Secondly, the literature does not consider the impact of the peculiar features of the
construction sector, parties involved, procurement strategies and the general context in which
major construction transactions take place on disputes and their resolution. These issues
remain unexplored.
Thirdly, there is little information, if at all, on pre-ICA efforts at resolution of construction
disputes by parties or third party neutrals. Whilst one may look at the dispute clauses in the
various conditions of contract for answers, these do not reflect practice. Further, the materials
so far reviewed do not consider the viability and the role that alternative dispute resolution
mechanisms, such as mediation currently play or can play in the resolution of such disputes.
On the basis of the gaps identified in the literature and questions which they raised, the aim
and objectives of the research were identified (see section 1.3). Chapter five identifies and
examines the appropriate research methodology for the study.
4.6.
Summary
In this chapter, the literature on infrastructure-related construction dispute resolution in
developed and developing countries has been examined. Increasingly, many developed
countries are resorting to ADR mechanisms to resolve infrastructure-related disputes.
However, trends in developing countries show a continuing emphasis on the use of ICA. The
literature demonstrates that many developing countries have issues with the use of ICA. These
include concerns with costs and delays. But, limited information exists on how infrastructurerelated construction disputes are resolved. Again, in spite of the apparent dissatisfaction with
the extant dispute resolution system, there is no study examining the viability of ADR
mechanisms or factors inhibiting their use. The next chapter identifies the appropriate
research methodology for the study.
77
Chapter 5- Research Methodology
CHAPTER FIVE
78
Chapter 5- Research Methodology
CHAPTER FIVE - RESEARCH METHODOLOGY
5.1.
Introduction
This chapter provides an overview of the research methodology. The study employed a
qualitative research approach using case study as the strategy of enquiry. It relied on semistructured interviews and documents as data sources. Borrowing from data analysis
procedures and principles associated with grounded theory research, this study employed
techniques such as coding, constant comparison, memoing and diagramming (hereafter
referred to as grounded theory principles) as tools for data analysis. Data which were of a
legal nature were analysed using doctrinal legal analysis. The qualitative data analysis
software, NVivo was employed as an aid to data organisation, coding, theme generation,
memoing and other aspects of the data analysis. Lincoln and Guba’s (1985) criteria of
trustworthiness was used to establish the credibility of the research findings. The chapter is
divided into two parts. The first part (sections 5.2-5.6.2) examines the literature on research
methodology with a focus on methodological choices for this study. It begins with a brief but
critical outline of epistemological positions and research approaches. The second part (section
5.7) presents the research design. Details on strategies for data collection and analysis are
provided. Finally, the evaluation criteria for the research are outlined.
5.2.
Epistemological Position
The research process entails the use of techniques and procedures called methods (Crotty,
1998). These methods often sit within a framework, called methodology, which is anchored in
epistemological and ontological positions (Crotty, 1998; Schwandt, 2007; Bryman, 2008).
There are many epistemological positions, research methodologies and methods (see Figure
5a). Examination of each of these concepts is beyond the scope of this work. In this section,
the focus shall be on the epistemological position for this study, namely interpretivism. To
illuminate the rationale for the selection of this epistemological standpoint, interpretivism is
79
Chapter 5- Research Methodology
discussed alongside positivism, the philosophical perspective to which it emerged as a
counter-perspective.
Philosophical Worldview
In
Co ter
ns pre
tr ti
uc vi
ti v s m
is /
m
Research Approaches
pe
rim
en
t
Ex
tive R
es
y
graph
Mo
del
s
nnair
e
Phe
n
Docu
Research
Methods
(Data Analysis)
Grounded Theory
Content Analysis
Thematic Analysis
Legal Analysis
Statistical Analysis
om
eno
l
ments
t
pan ion
tici
Par servat
b
O
iews
Interv
n
rvatio
Ob se
tive
stu
itiv
i sm
ogy
arch
Rese
Ques
tio
Pos
t-po
s
Research Methods
(Data Collection)
ative
Quali
ta
Sur
vey
s
Ethno
rxis
t
study
tit
Quan
earch
Case
Ma
Positivism
Strategies of Enquiry/
Research Methodologies
Realism
s
die
ra
Nar
Groun
d
ed th
eory
atism
Pragm
Mixed Methods Research
ories
al The
Critic
Figure 5.1: The Research Process Disc (Source: developed from Crotty, 1998; Denzin
and Lincoln, 2005; Saunders et al., 2007; Bryman, 2008 and Creswell, 2009).
5.2.1. Positivism
All research methodologies have an explicit or implicit theory of knowledge generation,
that is to say, an epistemological position (Crotty, 1998; Bryman, 2008). Thus the positivist
tradition roots its theory of knowledge in the natural sciences where reality is held to be
relatively straightforward to access from observation and from a researcher stance of
neutrality (Crotty, 1998; Neuman, 2003; Mottier, 2005; Bryman, 2008; Denzin and Lincoln,
2008). To the positivists, true knowledge is that which can be confirmed by the senses. They
contend that there is a reality (an absolute truth of knowledge) out there to be studied and
understood through observation, experiments and other scientific methods (Denzin and
Lincoln, 2008). Neuman (2003) summed up the positivist researcher’s approach to inquiry in
the following words:
A positivist approach implies that a researcher begins with a general cause-effect
relationship that he or she logically derives from possible causal law in general theory.
80
Chapter 5- Research Methodology
He or she logically links the abstract ideas of the relationship to precise measurement
of the social world. The researcher remains detached, neutral and objective as he or
she measures aspects of social life, examines evidence, and replicates the research of
others. These processes lead to an empirical test of and confirmation for the laws of
social life as outlined in a theory.
Positivism is often associated with quantitative research (Bryman, 2008).
5.2.2. Interpretivism
Aware of the difficulties of humans objectively studying humans, there was a shift in
social science away from positivism towards a post-positivist stance that strives for
objectivity but accepts the difficulty of achieving this fully. This shift marked a turn towards
an acknowledgement that interpretation plays a key part in both data gathering and analysis.
Indeed much qualitative research has come to be framed as interpretivist though it is
important to see this paradigm as a very broad umbrella, containing diverse philosophical
approaches.
Neuman (2003) defines interpretivism as relating to the study of socially meaningful
human actions through direct detailed observation of people in their natural settings in order
to arrive at understandings and interpretations of how people create and maintain their social
worlds. Interpretivists hold the view that subjects of social science research (humans) are
different to those of natural science and therefore require a different research approach that
reflects their distinctiveness as against the natural order (Bryman, 2008). The goal of social
research, for the interpretivist, therefore is to develop an understanding of social life and to
discover how people construct meanings (Neuman, 2003). The task of the researcher is to
uncover the processes and effects of such construction. His approach is inductive and aim at
theory building rather than theory testing.
5.3.
Research Approaches
As indicated in Figure 5a (above), there are different research approaches. The main
approaches namely, qualitative and quantitative research, have developed as separate
independent spheres of social research (Flick et al., 2004). In suitable cases, these two
81
Chapter 5- Research Methodology
separate streams are combined to form a third sphere or research orientation called the mixed
methods (Creswell, 2009). Some writers prefer to see these designs as existing on a
continuum (Bryman, 2008). Admittedly, however, there are key philosophical differences
between them.
The quantitative research approach is associated with the positivist philosophy of research.
It focuses on the measurement and analysis of causal relationships between variables within a
value-free research framework.
Bryman (2008) isolates three key characteristics of
quantitative research. Firstly, it adopts a deductive approach to research where emphasis is
placed on theory testing and not theory formulation. On this point, Creswell (2009) adds that
the aim of theory testing is accomplished by the researcher specifying narrow hypotheses and
collecting data to refute or support it. Secondly, it incorporates the norms of positivism and
natural science. Thirdly, it sees social reality as an external, objective reality. One of the
known advantages of the quantitative method is its ability to measure the responses of large
number of people to a limited set of questions, thereby facilitating comparison and statistical
aggregation of data which result in generalizable findings (Patton, 2002).
The very
advantages of quantitative research enumerated above become its limitations once the object
of study changes into a human being. As Black (1999, p.7) remarked, ‘human beings are
notoriously uncooperative subjects’, and are difficult to subject to the controls associated with
the positivists/quantitative approaches to research. To fully appreciate human interaction, a
more subjective rather than the objective approach to research need to be considered.
The qualitative research paradigm traces its roots to anthropology, ethnography and
American sociology (Kirk & Miller, 1986; Denzin& Lincoln, 2005; Platt, 1996; Vidich
&Lyman, 2003) and has been increasingly used in social and behavioural research. The focus
of qualitative research is to explore and understand what individuals or groups make of social
phenomena or interactions in the context of the real world (Creswell, 2009). Qualitative
82
Chapter 5- Research Methodology
researchers appreciate that individuals develop subjective meanings of their experiences, and
seek to explore these varied and complex situation (Denzin & Lincoln, 2005). Rossman and
Rallis (2003) identify five key features of qualitative research namely: (a) it is naturalistic; (b)
it relies on various methods which respect the humanity of the participants; (c) it is contextbased; (d) it is emergent rather than pre-figured; and (e) fundamentally interpretive. Whiles
quantitative research relies on deductive reasoning and focuses on theory verification,
qualitative research inductively develop theories or patterns of meanings out of data collected
from participants (Creswell, 2009). The qualitative researcher, unlike his quantitative
colleagues, is not an objective outsider completely detached from the study using unbiased
approaches (Rossman and Rallis, 2003).
The mixed method approach occupies the centre of the research design continuum
employing methodologies from both quantitative and qualitative studies depending on
suitability. Mixed method researchers see the boundary erected between qualitative and
quantitative research by virtue of allegiance to and influences from philosophical worldviews
as artificial and unhelpful (Bryman, 2008; Creswell, 2009). Combining the best of both
worlds is therefore the focus of the mixed method approach.
5.4.
Choice and Rationale for Epistemological Position and Research Approach
This study adopted an interpretivist philosophical stance and employed the qualitative
research approach because these perspectives provided the best opportunity for the
achievement of research objectives two to six (see section 1.3) namely:
1)
identification and examination of features and context of the key parties involved in
construction and civil engineering contracts relating to major infrastructure projects;
2)
an investigation into aspects of the legal framework for infrastructure procurement
relating to dispute resolution such as the contract formation process;
83
Chapter 5- Research Methodology
3)
examination of the legal framework for resolving disputes arising out of major
projects including the processes involved from the emergence of a dispute to its final
determination;
4)
identification of challenges to the existing modes of resolution including barriers to
the use of methods other than litigation and international commercial arbitration; and
5)
development of an explanatory framework and remedial strategies for the extant
construction dispute resolution processes.
To achieve the aim and objectives of the study, in-depth information about parties, the
settings within which they operated and the processes by which they resolved their disputes
was needed. The qualitative approach was thus the most suitable for this kind of research
(Denzin and Lincoln, 2005; Marshall and Rossman, 2006; Creswell, 2007; Creswell, 2009).
There were two other reasons accounting for the choice of an interpretivist perspective and
a qualitative approach over other paradigms for this study. Firstly, to understand the
complexities of the processes of dispute resolution among parties to major infrastructure
projects, interpretivists’ assumptions were to be preferred to positivists’ postulations. This
was because views of participants in major infrastructure procurement were crucial to the
understanding of how parties resolved construction disputes and why the industry preferred
one dispute resolution mechanism to another. Positivism, on the other hand, assumes that
social phenomena are objective and external to the individuals who make up the society or a
social group (Hammersley, 1993). This research was based on the assumption that dispute
resolution was an integral part of the life of individuals. Their views were therefore relevant
to our understanding of the process.
Secondly, there was lack of prior empirical research into the issues of interest namely the
resolution of infrastructure-related construction disputes in developing countries. Thus, the
study sought to explore this little understood issue. Hence, the inductive approach was
84
Chapter 5- Research Methodology
preferred to the deductive approach. Further, most of the major treatises on research design
pointed to a qualitative research approach being the most appropriate for research with these
types of features (see for example Berger and Luckmann, 1967; Hammersley, 1993; Guba
and Lincoln, 1994; Denzin and Lincoln, 2005; Bryman, 2008; Creswell, 2009).
5.5.
Research Methodologies
A methodology is a set of explicit rules and procedures for research on the basis of which
knowledge claims are evaluated (Chava and David, 2000). The different research approaches
are associated with different methodologies. For instance, quantitative researchers often
employ methodologies such as experiments and surveys. The survey methodology (with its
emphasis on the description of general trends based on numeric values) and experiment (with
its focus on the testing of impacts of an intervention on an outcome) are predominantly suited
to the positivist philosophy and the quantitative approach to research. Qualitative researchers
also have at their disposal wide array of research methodologies (Denscombe, 2007). Using
research methods as a basis of classification, Wolcott (1992) identifies over twenty different
methodologies. Tesch (1990), on the other hand, identifies about twenty-seven different
qualitative research types. Examples of qualitative methodologies include ethnography,
phenomenology, grounded theory, the biographical method, narrative research and case study.
Ethnography, as a methodology, involve direct observation and participation of a
researcher in small cultural settings with the aim to provide a detailed description of the
culture from the perspective of insiders (Neuman and Kreuger, 2003; Bryman, 2008).
Phenomenology, as a research methodology focuses on understanding the ‘lived experience’
of participants regarding a phenomenon through an in-depth and extensive engagement with
participants (Denscombe, 2007; Creswell, 2009). Schwandt (2007) identifies narrative
research and biographical method as a generic term for a number of methodologies that aim at
the generation, analysis and presentation of data of an individual’s life history, life story, and
85
Chapter 5- Research Methodology
personal experiences. Variants of this methodology include biography, autobiography, life
history and oral history (Creswell, 2007). Data, under this method, is often collected through
interviews, personal letters diaries and journals (Bryman, 2008). Grounded theory is a
research methodology developed by Glaser and Strauss (1967) which aims at the discovery
and generation of theory from systematically obtained interview, documentary and
observation data (Glaser and Strauss, 1967).
Case study is a methodology used to conduct in-depth investigations into a contemporary
phenomenon in its natural or real-life context (Yin, 2009). It focuses on one or a few instances
of a phenomenon in its natural context and provide in-depth account of relationships and
processes occurring in that particular instance (Denscombe, 2007). As Stake (1995, pp.xv)
puts it, case study ‘is the study of the particularity and complexity of a single case, coming to
understand its activity within important circumstances’. Denscombe (2007, p.54) identifies
six key features of case study as a methodology. Firstly, it emphasises depth rather than
breadth of study. Secondly, case study underscores the particular rather than the general.
Thirdly, the methodology highlights relationships and processes rather than outcomes and end
products. Further, it takes a holistic view of the phenomenon rather than concentrate on
isolated factors. Again, it focuses on natural settings rather than artificial ones. Finally, case
study utilises multiple sources of data collection and analysis rather than using just one
research method. Although case study may provide bases for comparison of cases, its primary
focus is to generate deep and rich understanding of a phenomenon.
Yin (2009) argues that in making a choice between case study and other social science
methodologies, consideration should be given to factors such as the research questions and
objectives of the study. If the enquiry is about some contemporary phenomenon, over which
the researcher has little or no control and in-depth study is envisaged, then case study will be
a good choice of strategy. The features of case study make it a suitable methodology for the
86
Chapter 5- Research Methodology
inductive study envisaged in this work. Yin (2009) also identifies two types of case study
designs; the single-case and the multiple-case study designs. The single-case design may be
holistic (constituting a single unit of analysis) or embedded (with multiple sub-units of
analysis). An example of the former will be a study of a single organisation as an entity. If the
study focuses on the organisation as a unit and various departments of the organisation as subunits, such a study will be an example of the latter. The multiple-case design may also be
holistic (with every case constituting a single unit of analysis) or embedded (with every case
entailing sub-units of analysis).
Delineating the boundaries (both spatial and temporal) of a case is an important
consideration in case study. Denscombe (2007, p.56) provides that a case needs to be fairly
self-contained, with distinct boundaries. The boundaries of a case may be defined in terms of
its physical borders or geographical context, individuals or groups relevant to the study of the
case, the period the study covers and the activities of interest (Miles and Huberman, 1994).
Research methodologies serve as links between the philosophical worldview underpinning
a study and the methods for the collection and analysis of data (Schwandt, 2007). Thus a
choice of methodology determines the research methods, that is, the means by which data are
collected and analysed.
5.6.
Research Methods
For purpose of clarity, the research methods for data collection and analysis are examined
separately.
5.6.1. Data Collection Methods
The quantitative research approach, with its associated methodologies such as experiments
and survey, usually employ data collection methods such as self-administered questionnaires,
internet-based questionnaires, reviewing of existing statistical data, interviews and structured
observations (Black, 1999; Fink, 2002; Creswell, 2009). There are varied sources of data
87
Chapter 5- Research Methodology
common to most qualitative research methodologies. Creswell (2007) mentions four of these
sources namely observations, documents, interviews and audio-visual materials. To this list,
Yin (2009) adds physical artefacts. Two of the sources predominantly used across all
qualitative methods namely interviews and documents are examined further.
Interviews provide the qualitative researcher the opportunity to obtain, through exchanges,
in-depth, nuanced and diverse meanings of a phenomenon from the interviewee’s experience.
In their treatise on interview research, Gubrium and Holstein (2002) identify five different
forms of interview. These include survey, qualitative and, in-depth interviewing. The others
are life story and focus group interviewing. Not all these types of interviews are suitable for
qualitative research. For instance, survey interviewing (which relies principally on sampling,
standardised questions and interviewer’s neutrality and objectivity) is usually useful in
quantitative studies.
Qualitative interviewing, on the other hand is more interpretivist in its approach. Its
emphasis is on understanding the meaning of the interviewee’s experiences regarding the
phenomenon under study (Gubrium and Holstein, 2002). It is open-ended in nature and
focuses on the variety of meanings that emerge from conversation between the interviewer
and the interviewee. The interviews may be in-depth (Gubrium and Holstein, 2002) , focused
(Yin, 2009) or semi-structured (Kvale, 1996).
Techniques for semi-structured or open-ended interviewing vary. Patton (1990) identifies
three different approaches or techniques. These are the informal conversational interview, the
general interview guide approach and the standardised open-ended interview. These
approaches do not only differ in terms of the preparation required but also in terms of
conceptualisation and instrumentation (Patton, 1990, p.280). In the case of conversational
interviews, questions are generated as the interaction between the interviewer and the
interviewee progresses. There are no pre-determined questions. The second interview
88
Chapter 5- Research Methodology
technique described by Patton (1990) is the standardised open-ended questions. With this
approach, carefully worded set of questions pre-arranged in a particular order is administered
to all interviewees in the same way. The advantage of this approach is that variation in
questions asked is minimised.
The third interview technique is the general interview guide approach. Patton (1990, p.280)
described this interview approach as entailing the following features:(i) outlining a set of
issues to be explored prior to the interview;(ii) issues in the outline need not be dealt with in
any particular order;(iii) actual wording of questions used to elicit responses about the issues
need not be pre-determined; (iv) interview guide simply serve as a basic checklist to ensure
that all relevant topics are covered; (v) the interviewer adapts both the wording and the
sequencing of questions to specific interviewees in the context of the actual interview. The
advantage of this interviewing technique is that it allows interviewers to cover relevant topics
whilst at the same time offering the flexibility to probe and ask follow-on questions in relation
to specific topics.
Documents, as an important source of data in qualitative research, may take several forms
such as policy documents, published laws, parliamentary proceedings and law reports. These
may be categorised into different classes depending on their nature and where they were
retrieved. For instance, some documents may be of a legal nature such as statutes, regulations
and case law. Others may be archival records, such as past project reports. Yet still, other
documents may be contemporary internal documents of organisations such as memoranda and
internal procedures. Creswell (2009) provides three advantages that documents possess.
Firstly, they carry the language and words of the authors thoughtfully assembled. Secondly,
they are unobtrusive source of information capable of being accessed and reviewed at any
time. Finally, they save the researcher time for transcription. Though useful as data source,
documents may sometimes be inherently biased. They may be prepared for specific events
89
Chapter 5- Research Methodology
and may not carry a complete picture of the phenomenon they address (Yin, 2009). There is
also the challenge of accessibility of relevant documents due to confidentiality (Creswell,
2009).
5.6.2. Data Analysis
Distinct approaches to data analysis are employed by quantitative and qualitative
researchers. Quantitative researchers rely heavily on statistical analysis using both descriptive
and inferential statistical tests and tools. Quantitative data analysis, apart from its emphasis on
breadth, aims at testing pre-determined hypotheses leading to a confirmation or a falsification
and modification of theory. Data is thus, organised around pre-determined hypothesis.
In contrast, qualitative data analysis essentially involves taking the data apart,
understanding the components and how they relate to each other (Stake, 1995). Miles and
Huberman (1994, p56) summed up the idea of qualitative data analysis in the following
words: ‘to review a set of field notes, transcribed or synthesised, and to dissect them
meaningfully, while keeping the relations between the parts intact, is the stuff of analysis’.
Creswell (2009, pp.184-190) argues that regardless of the type of qualitative methodology
employed, a common process to qualitative data analysis involving six steps is discernible,
though the steps may not necessarily be linear. These are as follows: (a) organisation and
preparation of data for analysis (including transcribing interview data, typing field notes,
scanning documents and other visual images) ; (b) reading through the data over and over
again to get the general sense of the data; (c) coding (segregating data into chunks); (d) using
the coding process to identify categories or themes and also to generate description; (e)
contextualising and finding linkages between the themes to identify how they fit together in
the narrative; and (f) interpretation-making meaning of the data.
Qualitative data analysis methods commonly employed by researchers using different
qualitative research methodologies include thematic analysis and qualitative content analysis.
90
Chapter 5- Research Methodology
Bryman (2008, p.529) describe qualitative content analysis as entailing ‘searching-out of the
underlying themes in the materials being analysed.’ In this sense, this method of data analysis
can be distinguished from quantitative content analysis which places emphasis on word
frequency count (Morgan, 1993; Stemler, 2001). Hsieh and Shannon (2005, p.1278) also
define qualitative content analysis as ‘a research method for the subjective interpretation of
the content of text data through the systematic classification process of coding and identifying
themes or patterns’. The authors identify three approaches to qualitative content analysis
namely conventional, directed and summative content analysis. With the conventional
approach, categories of codes are derived from the text itself. The directed approach however
relies on the theory undergirding the study for coding categories which are predetermined.
The summative approach relies on counting and comparisons. Of the three approaches, the
conventional approach suits the naturalistic research framework as it emphasises on the
emergent nature of codes and categories.
The emphasis on the identification and development of themes rather than frequencies per
se in qualitative content analysis means this data analysis method is similar to thematic
analysis. In this regard, Bryman (2008) argues that thematic analysis is common to many
other qualitative data analysis techniques such as narrative analysis, critical discourse
analysis, and the use of grounded theory principles. To advance Bryman’s (2008) argument
even further, a closer examination of the qualitative data analysis methods discussed above
shows that generally, they all share common techniques and approaches to data analysis.
Nevertheless, Creswell (2009, p.184) acknowledges that in addition to the common
qualitative data analysis methods there are specific data analysis procedures which are
primarily associated with particular methodologies. For instance, Yin (2009) recommends
five analytical techniques for case study analysis namely pattern-matching (comparing an
empirically-based pattern with a predicted one with the aim of developing theoretically
91
Chapter 5- Research Methodology
significant explanation for the outcome), explanation building, time-series analysis, logic
models and cross-case synthesis. Ethnographers employ thick description and theme
development whilst phenomenologists focus on generating meaning from data.
Grounded theorists also have elaborate and systematic principles and tools for data
analysis. These include coding, constant comparison, questioning, diagramming and
memoing. Grounded theorists employ different types of coding. Glaser (1978) and Glaser and
Holton (2004) identify three data coding phases namely open/substantive, selective and
theoretical coding. Substantive coding refers to the process of conceptualizing data in the
empirical state (Glaser and Holton, 2004). This is an intensive line-by-line coding which
generates concepts closely related to the data. Theoretical coding refers to a ‘second-order’
coding which determines how the substantive codes may relate to each other (Glaser and
Holton, 2004). Strauss and Corbin (1990, 1998) maintain an elaborate three-phased coding
system namely open, axial and selective coding. Open coding is the researcher’s first
analytical engagement with the data which results in breaking down of data into chunks.
Incidents, events/actions and interactions are compared with others for both similarities and
differences. Conceptual labels are then assigned. Further, the dimensions and properties of
these conceptual labels are explored.
In axial coding, a connection is made between categories and their sub-categories and the
ensuing relationships are tested with data through the ‘coding paradigm’ of conditions, actions
/interactions and consequences (Strauss and Corbin, 1998, p.128). The ‘coding paradigm’ is
described by Strauss and Corbin (1998) as a process which helps in systematic analysis of the
data so as to enhance integration between structure and process. The element of the paradigm
called ‘conditions’ focuses on aspects of the data dealing with situations or circumstances in
which a phenomenon under investigation is embedded. The ‘actions/interactions’ component
of the coding paradigm is about the ‘strategic or routine responses made by individuals or
92
Chapter 5- Research Methodology
groups to issues, problems, happenings, or events that arise under those conditions’ (Strauss
and Corbin, 1998, p.128). Consequences are simply outcomes of the actions and interactions.
Thus, the idea behind axial coding is to re-assemble the data broken up during open coding in
a more meaningful and logical way. With selective coding, all other categories are
reconnected to a core category.
Constant comparison refers to that part of the analytical process where different pieces of
data are compared for differences and similarities. Glaser and Holton (2004) identify three
types of comparisons namely (a) incident to incident; (b) concepts to more incidents; and (c)
concept to concepts. The aim of the first type is to generate concepts. The second type aims at
achieving theoretical elaboration. Concept-to-concept comparison aims at integrating
concepts into hypotheses which eventually culminate in the development of a theory. Corbin
and Strauss (2008) refer to two types of comparisons namely incident to incident and
theoretical comparison. The latter is a comparison at the level of properties and dimensions
and helps the researcher to think in terms of abstracts.
As coding proceeds, thoughts, ideas, analysis and notes are captured in memos. Memoing
is the means by which outcomes of the analysis at every stage of the process are recorded,
tracked and developed as more information is introduced and data is coded and explored
(Glaser and Strauss, 1967). Consequently, memo writing is required to commence at the onset
of analysis (Corbin and Strauss, 2008) and may cover issues such as ideas developed during
the coding process, concept development and elaboration, identification of categories and the
relationship between them and integrating the emerging story from the process. Diagramming
is also employed to generate visual representations to aid the process of data analysis.
5.7.
Research Design
The objectives of this study (see section 1.3) informed the choice of the interpretivists’
philosophical paradigm and the qualitative research approach for the study. Following on
93
Chapter 5- Research Methodology
from the above choices, case study was selected as the preferred methodology. One of the
primary reasons for this choice was that case study focuses on in-depth investigation of a
phenomenon of a contemporary nature in its natural setting; precisely what is required to meet
the objectives of this study (Yin, 2009) (see section 5.6).
5.7.1. Case Design
A ‘case’ has been defined as the phenomenon under study; the unit of analysis
(Denscombe, 2007; Yin, 2009). It may be an individual, an organisation, a group, an
institution, a workplace, an industry, a programme, a policy, a city or a nation; it is a specific,
complex, functioning thing (Bouma and Atkinson, 1995; Stake, 1995; Gerring, 2007). Ghana
was selected as a holistic case in this study with data collected from the State and its agencies
involved in major infrastructure project procurement and dispute resolution (hereafter referred
to as ‘the Employer’) and foreign contractors. Hammel et al. (1993) highlights the need to
distinguish the unit of analysis (the case) from the object of analysis (that is, the special
subject which is the focus of the study). Such a distinction clarifies the essence of the case
selection namely that it offers an ideal place for the study of the object of analysis. For this
study, the object of analysis was infrastructure-related construction dispute resolution. Figure
5.2 below is a visual representation of the case.
94
Chapter 5- Research Methodology
Figure 5.2: Case Description
Rationale for the choice of Ghana as the case, the population and issues about sampling are
presented next.
5.7.1.1.
Case Selection and Justification
Yin (2009) provides five justifications for a single case selection. All five reasons are
based on case characteristics. These are criticality, uniqueness, representativeness (its
typicality or exemplifying nature), the convergence of rarity and accessibility (revelatory
case) and the duration of study (longitudinal case). The critical case is useful for theorytesting. It is termed a ‘critical case’ because of its ability to affirm or disprove a hypothesis, or
offer some other alternative explanation to an existing theory. A revelatory case is the type
which, on a rare occasion, becomes accessible for inquiry. It may relate to prevalent issues
which had previously not been scientifically researched as a result of lack of accessibility
(Yin, 2003). A case may be longitudinal where it is studied at different points in time. The
extreme or unique case is one which is chosen for its exceptional nature. The unique case may
be contrasted with the representative, typical or exemplifying case which reflects everyday
occurrence and thus shares similar characteristics with several others. An in-depth study of
such a case throws more light on several other cases (see Bryman, 2008). A case with any of
95
Chapter 5- Research Methodology
the features described above may be justifiably selected on the basis of its characteristics for a
single-case research (see Miles and Huberman, 1994; Flyvbjerg ,2006; Creswell, 2007;
Bryman, 2008; Yin, 2009). Other factors such as access, time, resources and expertise may
also be taking into account when selecting a case (Stake, 1995; Seawright and Gerring, 2008).
Flyvbjerg (2006) has argued that the justifications provided are not mutually exclusive. The
selection of a case may be justified on the bases of its characteristics and also for pragmatic
and logistical reasons (its accessibility or hospitability) (see also Stake, 1995).
Ghana was selected as the case for this study for three reasons namely (a) its typicality and
exemplifying features as a developing country; (b) feasibility of in-depth investigation as a
result of accessibility and hospitability of the case; and (c) prospects of tentative
generalization (see Stake, 1995). These reasons are expanded further. Firstly, Ghana, a typical
developing country of about 25 million people, is situated on the West Coast of Africa. Since
1992, the country has been a political oasis in a region noted for its political upheavals and
has enjoyed steady and tranquil political life anchored in the rule of law. Ghana’s economy,
which has been largely dependent on agriculture (contributing above 50% of GDP over the
years) and mining, has witnessed a remarkable change during the past decade. In 2010, the
service industry grew by 6.1% and constituted 32.8% of GDP thereby displacing the
agricultural sector (which constituted 32.4% of GDP) as the largest contributor to GDP. The
industry sector including construction grew by 7% contributing about 25.7% to GDP for the
year (Government of Ghana, 2010). Overall, the economy witnessed a total GDP growth of
5.9% in 2010. The World Bank’s Global Economic Prospects report for June, 2011 projected
increased inflow of investments into the service sector, with telecommunications and the
construction industries remaining the major recipients. The Bank reported that, ‘outside the
oil sector Ghana’s economy will still register strong growth, particularly in construction
services as large infrastructure projects are carried out’ (World Bank, 2011b,p.123).
96
Chapter 5- Research Methodology
A number of factors mark Ghana as a typical developing country for purposes of this
study. Firstly, the State and its agencies are at the forefront of procurement of major
infrastructure projects (see section 2.3). Secondly, these projects are often delivered by
international construction firms since domestic firms lack the requisite skill and resources.
Thirdly, it relies heavily on foreign funding for infrastructure development. In this regard,
Ghana shares a lot in common with other developing countries.
Further, a study of the dispute resolution processes in nearly 140 developing countries was
not feasible in the context of this research. The choice of Ghana as a single case made an indepth study possible. In effect, Ghana was an exemplifying case. Consequently, the outcome
of the study holds potential for tentative generalization beyond Ghana. Finally, pragmatic and
logistical reasons played a key role in the decision to select Ghana as a case. The Government
of Ghana had been concerned with the cost of resolving disputes from international projects in
recent times (Daily Graphic, 2012; Daily Graphic, 2013). Thus, it was envisaged that public
officials would demonstrate eagerness to facilitate access to departments for data collection.
Here, Stake’s (1995) admonition on the selection of cases comes to mind, the researcher must
consider accessibility and hospitability of the cases and the site.
5.7.1.2.
Individuals and Groups relevant to the Study
Data for the study were collected from the Employer and foreign contractors. In respect of
the Employer, three sets of entities were targeted. These were Government Ministries which
regularly participated in major infrastructure projects and the resolution of related disputes
and their respective implementing agencies (MOFEP, 1997; Government of Ghana, 2010),
supporting Ministries (whose responsibilities extended to all other Ministries directly
involved in infrastructure procurement) and public institutions which played various roles in
infrastructure procurement but were not directly involved in the implementation process. The
above institutions were targeted because of their respective roles in infrastructure procurement
97
Chapter 5- Research Methodology
and dispute resolution. Regarding foreign contractors, the focus was on international design
and construction firms which were directly or indirectly involved (or had been previously
involved) in the execution of major infrastructure projects and dispute resolution. Details of
participating institutions and background of interviewees is presented under section 6.2
below.
5.7.1.3.
Sampling Techniques for the Selection of Participants
Participants for the study were selected from the institutions identified under section
5.7.1.2. Experience with past or on-going major infrastructure projects, preferably one which
had disputes or is currently experiencing disputes was a crucial criterion. The most
appropriate sampling techniques under the circumstance were purposive or judgment
sampling (see Dixon et al., 1987; Seawright and Gerring, 2008), snowball sampling ( see
Creswell, 2007) and theoretical sampling (see Glaser and Strauss, 1967). The use of
purposive sampling was relevant due to the need to select the most productive or
knowledgeable personnel within each organisation who met the set criterion for the interviews
(see Rubin and Rubin, 1995; Marshall, 1996). Secondly, apart from purposive sampling,
snowballing sampling was also used. The rationale for this sampling strategy was that
participants selected through purposive sampling volunteered information on other persons
who met the set criterion for selection. Finally, as data emerged and initial analysis
commenced, sample selection was driven more by what additional theoretical insights a
particular interviewee could add to the emerging concepts (see Glaser and Strauss, 1967).
5.7.2. Negotiating Access: Vertical/ Top-down and Horizontal Access Strategies
Marshall and Rossman (2006) and Stake (1995) admonish researchers to pay attention to
access issues, particularly gatekeepers. In this research, access to research sites was negotiated
through introductory/request letters and face-to-face meetings. Each of the institutions of the
interviewees was served an official request letter. The expectation was that these official
98
Chapter 5- Research Methodology
letters would be passed on to individuals whose line of duty related to the subject matter of
the research, who would then be interviewed. In some cases, this happened. However, this
‘top-down access strategy’ was less successful. For many organisations, the letters appeared
to have been lost in the bureaucracy of forwarding same through the organisation’s processes
to the line officer. Another reason for the failure of this access strategy was that there was
general reluctance to divulge confidential information on organisational practices.
The less than expected rate of success of the top-down strategy necessitated a rethink of
the access strategy. Beyond the initial letters and contacts with the various institutions, it was
observed that targeted organisations expedited access where an interviewee (who was an
employee) within the organisations concerned introduced other colleagues who have
experience in the subject area of the studies. Interviewees were therefore asked to identify
other professionals with experience on the research subject within and outside their
organisations. Three kinds of referrals were observed. These were as follows: (i) internal
referrals - where one initial contact (an interviewee) within an organisation set off a chain of
referrals within the same organisation;(ii) external referrals - where an interviewee in one
organisation identified and introduced other potential participants from other organisations on
the basis of the former’s knowledge of the latter’s experience with the subject matter of the
research;
and
(iii)
‘signpost’
referrals
-
where
individuals
(who
were
not
participants/interviewees themselves) familiar with person’s with expertise and experience in
the subject matter of the research within targeted organisations facilitated contact with such
potential interviewees.
In sum, whilst some interviewees were approached through their organisations, others were
identified and informed unofficially of the request to conduct interviews with them as official
permission was sought from their organisations. However, in all cases, interviews were
conducted with interviewees only when there was a written or oral permission to do so.
99
Chapter 5- Research Methodology
5.7.3. Data Collection
Data for this research was collected through two main sources namely, semi-structured
interviews and documents. Rationales for the choice of the two sources of data for this study
included their potential to offer in-depth information about the process of dispute resolution,
the phenomenon under study (see section 5.6.1).
5.7.3.1.
Semi-structured Interviews
On the basis of the reviewed literature, the research objectives and the research approach,
semi-structured interviewing was selected as one of the methods for data collection. Three
other reasons accounted for this choice. Firstly, it allowed the data collection process to be
approached with sensitising themes (Blumer, 1969). Apart from the starting question, detail
questions were emergent and developed in the course of the process. Secondly, semistructured interviews allowed for the introduction of new ideas and further development of
concepts obtained from previous interviews (Denscombe, 2007). Thirdly, most well-crafted
agreements on dispute resolution often have clauses on non-disclosure and confidentiality.
The real hurdle was how to get into the world of participants in this field and to learn at first
hand their experiences in the face of the issue of confidentiality. Qualitative semi-structured
interview offered the most promising opportunity due to the flexibility it provided for follow
on questions.
The conduct of the semi-structured interviews followed Patton’s (1990) general interview
guide technique (see section 5.6.1). The interview guide was organised into four sections each
covering one of the following themes derived from the research objectives: (i) preliminary
issues; (ii) the procurement process (choosing dispute resolution mechanisms; (iii) disputes
and the resolution process; and (iv) the interviewee’s experience with specific projects. The
theme ‘preliminary issues’ focused on securing information on the background of the
interviewees and the organisations within which they worked. The essence of the theme was
100
Chapter 5- Research Methodology
to obtain information to meet the second objective of this study on the features of the parties
to major projects (see section 1.3).
The second theme, procurement, aimed at obtaining information on the dispute resolution
systems that the parties put in place at the beginning of the construction contract. Information
obtained on this theme was to help address the third research objective on legal framework for
infrastructure procurement. Thus, questions asked revolved around the role of the
interviewees’ organisations in procurement and the contract formation process, the Conditions
of Contract in use, negotiation of dispute clauses and the selection of dispute resolution
mechanisms. The third theme, ‘disputes and their resolution’ was at the core of the data
collection process. It aimed at obtaining information on disputes, their occurrence and how
they were resolved by parties. This information was to help address the third and fourth
objectives of this study.
Under this theme questions relating to dispute resolution
mechanisms in use, the procedure for dispute resolution, problems with the extant process of
dispute resolution and how they could be remediated were explored. A copy of the interview
guide is attached as Appendix A.
Access to organisations and interviewees were negotiated through request letters
containing information on issues such as the aim and objectives of the research, why the
organisation and or a particular interviewee was selected, the nature and likely duration of
interviews and assurance of confidentiality and anonymity. Four separate request letters were
written. The first was addressed to institutions affiliated to the Employer. The aim of this
category of letters was to secure permission from the institutions concerned and access to
interviewees. A copy of this category of letters is attached as Appendix B.
The second
request letter was addressed directly to interviewees with institutions affiliated to the
Employer. The aim of this category of letters was to secure personal consent of individual
interviewees and to secure appointments (see Appendix B1). The third category of request
101
Chapter 5- Research Methodology
letters were addressed to foreign construction firms (see Appendix B2) whilst the fourth set of
request letters went to interviewees within these organisations.
All interviews conducted were face-to-face and lasted, on the average, an hour with the
longest and the shortest lasting two and a half hours and fifteen minutes respectively. The
focus was to cover all themes outlined in the interview guide. Questions did not always follow
the order in which they appeared in the interview guide and the wording of questions was not
rigidly followed. Questions were sometimes paraphrased and or amended depending on the
context of the actual interviewing process. Follow on questions were asked to clarify previous
answers and to tease out further information where necessary. On the average, four interviews
were conducted each week for a period of fourteen weeks as illustrated in Figure 5.3 below.
Additionally, a minimum of four hours were spent every week on transcription and editing.
Copies of transcripts were fed into NVivo 9 and other back-up devices. Additionally, a log
book kept for all interviews and observations which could not be audio-recorded and a
personal diary used to track the data collection trajectory became additional back-ups.
No. of Interviews
10
8
6
4
2
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Figure 5.3: Number of Interviews per Week
5.7.3.2.
Pilot Study
The opening five interviews were used as a pilot study to test the appropriateness of the
questions. Pilot-testing the interview guide provided opportunity for questions which lacked
clarity to be streamlined. It also provided a basis for the observation of the flow of questions
and the need for rearrangement (see Bryman, 2008; Yin, 2009). After the five initial
102
Chapter 5- Research Methodology
interviews, the transcripts and informal observations made during the interviewing process
were examined.
A number of issues were identified with the initial interview guide (Appendix A). Firstly,
it was observed that interviewees’ answers to questions under theme four (relating to their
specific experiences with construction dispute resolution) invariably constituted a repetition
of some of the answers previously provided under the first three themes. Interviewees often
cited examples of projects they had been (or were currently) involved in the course of
answering questions related to themes one, two and three and were often reluctant to deal with
such issues again under the fourth theme. The first interviewee who went through all the
themes and questions on the piloted interview guide was visibly tired and sounded clearly
repetitive. Secondly, the inclusion of theme four made the interviews unduly lengthy. Where
interviewees were made to address four themes, the interview duration exceeded the one hour
timeframe indicated in the request letters. These observations were used to improve the final
interview guide (see Appendix A1).
5.7.3.3.
Documents
Data collection also entailed five hours of document retrieval time every week. Sources
searched included libraries and court registries. The other major source of documentary
information was the institutions of the interviewees. Due to the sensitive nature of documents
relating to infrastructure projects and disputes, permission had to be sought from heads of
organisations prior to obtaining copies. Consequently, three categories of documents were
collected. The first were archival records. These included documents such as past project
reports, contract documents, correspondence between parties regarding past claims and
disputes. The second set of documents was contemporary documents on internal procedures
of institutions and organisations involved in infrastructure procurement and dispute
resolution. Examples of these documents included project appraisal reports, technical review
103
Chapter 5- Research Methodology
committee reports and proceedings on parliamentary hearings on arbitral awards against
Ghana, some of which related to major infrastructure projects. The third set of documents
collected were those of a legal nature such as published laws, regulations and judicial
decisions. Other documents retrieved were policy documents and newspaper cuttings on
discussions about cost of disputes in Ghana.
The issue of confidentiality restricted access to official statistics and other documentary
information on disputes. Very little information was available in terms of descriptive statistics
on the incidence and types of disputes from major projects. Similarly, there was no indication
of the existence of databases on previous or current construction disputes, cost and time-frame
for dispute resolution.
5.7.4. Sample Size
Fifty-six (56) interviewees participated in this research. This was within the limit of 60
proposed by Mason (2010) based on a review of the literature. After studying the sample sizes
used in 560 PhD theses using qualitative approaches in the United Kingdom, Mason (2010)
concluded that there was a mean sample size of 31. He however indicated that the number of
respondents does not need to be above 60. The reason is that most studies often reach
saturation after interviews with relatively small number of interviewees. The important point
in qualitative research however is that samples size is not a critical issue; what is critical is
whether saturation has been achieved (Glaser and Strauss, 1967). Corbin and Strauss (2008)
define this point of saturation as ‘when no new data are emerging’.
What factors determined saturation then? Mason’s (2010) review of the literature points to
several factors influencing how saturation is reached. The aim of the study (Charmaz, 2006),
the scope of the study, the nature of the topic, research design and data collection methods
(Morse, 2000) have all been cited as possible determinants of saturation. The decision as to
when or what time saturation will be deemed to have been reached is a subjective one and
104
Chapter 5- Research Methodology
differ depending on the level of experience of each researcher (Charmaz, 2006, Corbin and
Strauss, 2008). In this study, saturation was reached after 50 interviews were conducted. The
six additional interviews conducted after the 50 repeated information already obtained.
5.7.5. Data Analysis
Most qualitative data analysis methods share common techniques (Creswell, 2009,
pp.184-190) (see section 5.6.2). However, there are methodology-specific principles and
procedures which are often blended into the general approach to qualitative data analysis
(Creswell, 2009, p.184). Borrowing from qualitative data analysis procedures associated with
grounded theory research, this study employed procedures such as coding, constant
comparison, memoing and diagramming (hereafter referred to as grounded theory principles)
as tools for data analysis (see chapter six). The additional input that the grounded theory
approach brought to the data analysis process was the rigorous, systematic and explicit
manner in which the tools and procedures were employed to code data, create categories and
build relationships between the categories (Strauss and Corbin, 1998; Corbin and Strauss,
2008). The grounded theory principles also accorded with the tenets of the philosophy
underpinning the study. The interpretivists’ philosophical paradigm emphasises the
experiences of participants and the meanings and interpretations of such experiences. The use
of the grounded theory principles afforded the opportunity for these diverse experiences,
meanings and interpretations of participants to be examined in a systematic way. Similarly,
the method responded aptly to the inductive strategy of enquiry.
The documentary data of a legal nature such as legislations and judicial decisions were
subjected to doctrinal legal analysis. Legal research has been broadly categorized into four
classes namely, expository and theoretical research (both of which apply doctrinal legal
analysis as a methodology) and law reform and fundamental research (both of which are
interdisciplinary in character) (Arthurs, 1983; Pearce et al., 1987; Chynoweth, 2008). The
105
Chapter 5- Research Methodology
doctrinal approach (sometimes called the ‘black letter’ approach) to legal research refers to
the systematic exposition, analysis and evaluation of legal rules and doctrines. It is normative
in character and focuses on the question, what is the law in a given situation (Chynoweth,
2008). It focuses on the identification and application of legal principles to specific facts
(Adams and Brownsword, 2003). This type of legal analysis is, thus, based on the supposition
that legal rules are internally coherent. Consequently, the approach depends on contents of
formal legal materials and employs deductive, inductive and analogical reasoning and
techniques of interpretation (Chynoweth, 2008; Cownie, 2004; Adams and Brownsword,
1999).
Meeting the second, third and fourth objectives of this study (dealing with the
organisational structures of the parties to infrastructure projects and the legal framework for
procurement and resolution of disputes) required identification, exploration and analysis of
the relevant Ghanaian legislation and case law on the subject. This exercise was clearly within
the domain of the doctrinal approach to legal analysis (Cownie, 2004; Adams and
Brownsword, 1999). The approach was therefore employed to address relevant issues raised
under the second and third research objectives alongside the grounded theory approach (see
section 6.8). Figure 1.1 summarises the research design employed in this study.
5.8.
Research Evaluation: Trustworthiness
Lincoln and Guba’s (1985) credibility, transferability, dependability and confirmability are
used instead of internal validity, external validity, reliability and objectivity to establish the
criteria for trustworthiness of the research. The rationale for this choice and details of the
research evaluation process are presented in Chapter 9 on validation.
5.9.
Summary
The aim and objectives of the research led to the choice of the interpretivist philosophical
paradigm and the qualitative research approach for this study. The study used Ghana as a case
106
Chapter 5- Research Methodology
with data collected from the Employer and foreign contractors through interviews and
documents. Sampling techniques utilised to select interviewees were the purposive,
snowballing and theoretical sampling methods. Using semi-structured interviews and the
interview guide technique advocated by Patton (1990), data was collected on three key themes
derived from the research objectives, namely background of parties, the procurement process
and the dispute resolution processes. The questions contained in an initial interview guide
were piloted and the results obtained informed the preparation of a revised interview guide.
Three different sets of documents were collected. These were archival records, internal
documents of relevant institutions and documents of a legal nature such as statutes and
judicial decisions. The data were analysed using grounded theory principles and doctrinal
legal analysis. Chapter six reports the process of data analysis.
107
Chapter 6-Data Analysis
CHAPTER SIX
108
Chapter 6-Data Analysis
CHAPTER SIX - DATA ANALYSIS
6.1.
Introduction
This chapter presents the procedure for data analysis. Borrowing from qualitative data
analysis procedures and principles associated with grounded theory research, the study
employed procedures such as coding, constant comparison, memoing and diagramming
(hereafter referred to as grounded theory principles) to generate themes from the fifty-six
interviews conducted and documents collected such as past project reports, project appraisal
documents, sample contract documents and policy documents. Documents of legal nature
such as legislation, judicial decisions were analysed using doctrinal legal analysis.
Consequently, the discussion on how the data were analysed is in two parts. The first part
focuses on the analysis with grounded theory principles and the second part examines how
legal analysis was employed. The chapter provides a general overview of the data analysis
strategy. This is followed by a detailed description of the analytic procedures. As a prelude to
the presentation of the procedure, information on the background of interviewees is presented.
6.2.
Background of Interviewees
A total of fifty-six interviews were conducted for this study. Forty-five out of the fifty-six
interviewees were from Government Ministries, Departments and Agencies (MDAs) regularly
involved in infrastructure procurement (see section 5.7.1.2). Table 6.1 below presents a list of
MDAs concerned. The organisations of interviewees in the foreign contractors’ category have
been omitted for ethical reasons.
Table 6.1: Participating Ministries, Departments and Agencies with number of
interviewees in brackets (Source: Field Data)
Ministries
Departments
Authorities/Statutory
SOEs/Companies
Entities
Ministry of Roads Department of Ghana Highways
and Highways
Urban Roads
Authority
(2)
(2)
(6)
109
Chapter 6-Data Analysis
Ministries
Ministry of
Energy
(1)
Ministry of Water
Resources, Works
and Housing
(2)
Ministry
of
Finance
and
Economic
Planning
Departments
Department of
Hydrology
(2)
Legal,
Debt
Management
&Budget
Departments
(6)
Ministry
of Civil Division
Justice & the (7)
Attorney-General
Parliament
Authorities/Statutory
Entities
Volta River Authority
(4)
SOEs/Companies
Electricity Company of
Ghana (2)
Ghana Water Company
Limited
(4)
&
Architectural Engineering
Services Limited (3)
Public
Procurement
Authority
(2)
Institution (name
withheld)
(1)
Finance
Committee (1)
The large number of interviewees from Employer organisations was unexpected as it was
thought requirements of confidentiality associated with dispute resolution and government
transactions would hinder access to information from employees of the State.
Foreign
contractors involved in major project execution in Ghana were rather unresponsive. Most of
them were unwilling to allow their employees to participate in the research. Reasons for nonparticipation included lack of time, unavailability of key staff and failure to obtain permission
from management (often outside the country). Another reason was the fear that providing
information about their businesses will jeopardise their relationships with the State and its
agencies. Consequently, as shown in Figure 6.1 below, only eleven out of the fifty-six
interviewees were affiliated to foreign contractors.
110
Chapter 6-Data Analysis
Foreign
Contractors,
11
Employer, 45
Figure 6.1: Interviews by Participants (Source: Field data)
In terms of professional spread, twenty-six out of the fifty-six interviewees were persons
with legal background. This however does not imply homogeneity. The twenty-six individuals
worked in diverse environments with different experiences in practice and training. Their
involvement
in
major
project
acquisition
spanned
contract
negotiations,
project
implementation, resolving disagreements at the early stages of disputes and participation in
international arbitration. Interviewees with quantity surveying and diverse engineering
backgrounds were nine and fifteen respectively. The rest of the interviewees had backgrounds
in economics, finance and hydrology (see Figure 6.2 below).
Quantity
Surveying, 9
Not Known, 1
Economics, 1
Engineering,
15
Law, 26
Finance, 2
Hydrology, 2
Figure 6.2: Professional Background of Participants (Source: Field data)
111
Chapter 6-Data Analysis
Interviewees in this research were the type Odendahl and Shaw (2002) and Marshall and
Rossman (2006) referred to as elite participants. With varied professional backgrounds, the
interviewees occupied management positions and were well-placed to have first-hand insights
into practice within their organisations. On the other hand, their statuses made time an issue.
Because they operated under demanding schedules, interview appointments were secured with
some difficulty.
6.3.
General Overview of the Data Analysis Strategy
The interviews conducted were transcribed, edited and imported into the qualitative data
analysis tool, NVivo 9, together with the documents collected. Three types of coding were
utilised to break up, re-assemble and integrate the data. These were open, axial (development
of categories) and selective coding (data integration). With open coding, codes were freely
generated on the basis of the research objectives. Overall, six hundred and twenty-one codes
were created (see Appendix C). Using strategies such as Strauss and Corbin’s (1998) coding
paradigm, the codes generated were further re-organised into categories and sub-categories. In
all, twenty-three categories and thirty-eight sub-categories were developed. After the reorganisation, four hundred and forty-six out of the six hundred and twenty-one codes were
retained. The process of open coding and the development of categories were accompanied by
memo writing and diagraming. Memos were used to explore codes and categories, to record
thoughts about methodology and to capture the emerging story from the data analysis.
Diagrams were also used to illustrate emerging linkages between ideas explored through the
memos. Sub-categories and categories developed were integrated into themes. A total of five
themes were finally generated. Details of the individual themes and their associated
categories, sub-categories and codes have been attached as Appendix D. The five themes are
‘Features and Context of Parties to Dispute Resolution’, ‘Procurement’, ‘the Dispute
Resolution Processes’, ‘Consequences of the Extant Dispute Resolution Processes’ and
112
Chapter 6-Data Analysis
‘Remedial Strategies’. The themes together with associated memos form the basis of the
description and explanations called for by the research aim and objectives.
A detailed description of the analytic procedures using categories such as ‘claim events’
and ‘institutional structures’ and the themes ‘Features and Context of Parties to the dispute
resolution processes’, ‘the Dispute Resolution Processes’ and ‘Remedial Strategies’ as
illustrations is presented next.
6.4.
Preparing the Data for Analysis
Fifty-two out of the fifty-six interviews were audio-recorded, transcribed and edited.
Transcription and editing were carried out with the aim of ensuring that the integrity of the
recordings was preserved in the transcripts. In some limited cases, sentences were reconstructed to ensure that grammatical errors were eliminated. Where there was an indication
that changing a word or a sentence would affect the integrity of the information as provided
by the interviewees, sentences were left unedited. As part of the editing process, the names of
interviewees were anonymised. Each interviewee was assigned a specific code name. A list of
the participants, their professional background and affiliation is attached as Appendix E.
Attempts were also made to ensure that information, labels and descriptions which could be
used to identify interviewees were anonymised.
The edited transcripts and the documentary data in electronic format were fed into NVivo 9
qualitative data analysis software and stored under the label ‘internals’. Internals in NVivo 9
are folders in which all sources of information imputed into the software for analysis are
stored. Additionally, interviews which were handwritten were also transcribed, edited and
inputted into NVivo 9. Documentary data which could not be fed directly into NVivo 9 due to
format limitations were imported as ‘externals’ with links to the full text outside the software.
‘Externals’ is a folder in which links to documents outside the software including websites are
stored. Preparation of data for analysis took place as and when interviews were conducted and
113
Chapter 6-Data Analysis
documents were collected. Further interaction with the data took place at the transcription and
editing stages. After data had been fed into NVivo 9, additional time was dedicated to reading
of transcripts and documents. This afforded the opportunity for an initial appreciation of the
logic of the information in the transcripts prior to and during coding (see Creswell, 2009).
6.5.
Coding
Before the discussion on how the coding process was carried out, a brief explanation is
provided of terms used during the coding. A ‘code’ is the smallest unit into which data is
divided in this analysis. It is referred to as a ‘node’ in NVivo 9. For the avoidance of doubt, a
‘code’ or ‘node’ in this study is not synonymous with a theme or a specific objective of the
study. It represents isolated individual concepts which could be gleaned from the raw data
provided. ‘Free nodes’ are codes which are generated on the basis of information
communicated by small chunks of data within the wider scope of the research objectives.
‘Categories’ are broader ideas which unify or bring together individual concepts as captured
by nodes. In the context of NVivo 9, the categories may be equated with ‘Tree nodes’.
However, not all tree nodes were categories. Larger categories sometimes had sub-categories
and these also appeared as ‘Tree nodes’.
In the context of this work, categories were further organised into ‘themes’. Each theme
brought together all concepts, sub-categories and categories representing data which met
specific research objectives. ‘Themes’ also appeared as tree nodes in NVivo 9. From the
above description, it is apparent that whilst codes generated were many, the number of
categories was relatively smaller. Similarly, the themes generated were smaller than the
categories. Figure 6.3 below provides a visual summary of the scenario described above.
114
Chapter 6-Data Analysis
The
mes
add (5)
ress
rese
que
arch
stio
ns
Cat
e go
(23) ries
Sub
-cat
eg
(38) ories
me
The )
(5
s
arch
rese
ress
ns
add
stio
que
ries
e go
Cat 23)
(
ries
e go
-cat
Sub (38)
Cod
e
(621 s
)
es
Cod 1)
(62
Figure 6.3: Coding Hierarchy
Three different strategies of coding were employed to achieve the coding hierarchy
described above. These were open coding which involved the generation of free nodes from
the interview data, axial coding which involved the re-assembling of the free nodes under
more abstract concepts with wider explanatory power called categories and selective coding
which entailed clustering categories around a core theme.
6.5.1. Open Coding
Edited transcripts were coded appropriately using combination of line-by-line, paragraphby-paragraph and incident-by incident coding procedures. Codes were generated freely with
an eye on the research objectives as reflected by the sensitising themes which had guided the
data collection process. The sensitising themes were preliminary issues (background of
interviewees and the organisations they worked for), the procurement process (contract
formation and the selection of dispute resolution mechanisms) and disputes and their
resolution (see Appendix A1). These themes became the reference points for the coding
process and indeed the whole data analysis.
The decision to code an idea depended on its relevance to the research objectives. For
instance, during the interviews, questions were asked about conditions giving rise to claims
and disputes under the section titled ‘disputes and their resolution’. All through the open
115
Chapter 6-Data Analysis
coding, responses to this question from nineteen interviewees were identified and assigned
labels. For instance, in response to this question CPR 4 stated as follows: ‘Some of the
disputes we went into were because some people in authority somehow interfered with the
running of the project so it gave grounds for contractors to make very successful claims’. This
statement was coded under the label ‘political interference’. CPA1 also referred to
interference by politicians as a source of claims and disputes. Consequently, that response was
also coded under ‘political interference’. Other interviewees provided information on different
situations which led to claims and disputes. These pieces of information were assigned labels
such as ‘change of scope of work’, ‘delayed payments’, ‘design changes’, ‘poor definition of
scope of work’, and ‘site possession issues’. In like manner several hundreds of statements
were assigned labels (coded). The open coding process yielded six hundred and twenty-one
codes. A list of codes generated is attached as Appendix C.
The coding process was iterative. Consequently, some previously identified codes were
merged or placed under common labels. For instance, in relation to the earlier example of
questions about events giving rise to claims and disputes, both ‘site possession issues’,
‘relocation of utilities’ and ‘compensation payment issues’ were identified separately as
events giving rise to claims. A closer scrutiny of each of the three codes subsequently showed
that they all had the consequence of impeding timely possession of project sites leading to
delays in work schedules. Consequently, all the codes were eventually merged into the code
called ‘site possession issues’. In some cases new and more specific labels replaced earlier
ones. For instance, initially, the codes ‘delays’ and ‘delayed payments’ were both placed
under a common node called ‘delays’. However, reading through the statement of CPE 6
(where a distinction was made between delays in relation to payment and other types of
delays), a decision was made to separate ‘delayed payments’ from other forms of delays. In
116
Chapter 6-Data Analysis
all, eighteen codes were generated from the responses to the question on factors leading to
claims. Table 6.2 is a coding summary of the responses.
Table 6.2: Codes on question regarding claim events (Source: Field Data)
1
Nodes
Poor definition of the scope.
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Political interference
Site possession~ Access to site
Delayed payment
Delays
Ground conditions
Inadequate engineering studies on projects
Incomplete design issues
Effect of traditional procurement method
Inclement weather
Laxity in contract administration
Design changes
Extra work
Lack of coordination
Non-compliance with condition precedents
Poor preparation of contracts
17
18
Change of scope of work
Poor project preparation linked to cost
This approach to coding was used to generate all the other codes created in this study. The
next stage after the open coding was re-assembling of the codes.
6.5.2. Development of Categories
Essentially, the open coding process broke up the data into smaller chunks. The six
hundred and twenty-one individual codes carried bits and pieces of the larger story from the
data as a whole. For instance, ‘delayed payments’ as an isolated concept provided very little
insight into disputes and how they were resolved. Thus, re-assembling the broken up data
into meaningful categories and themes was the next step after open coding. This process was
also guided mainly by the research objectives. It was a gradual process involving the creation
of sub-categories and categories (umbrella concepts for narrower concepts) and the clustering
of the various categories generated around a core theme.
117
Chapter 6-Data Analysis
Returning to the earlier example of concepts such as ‘political interference’, ‘delayed
payments’, ‘delays’, ‘changes in scope of work’ and ‘site possession issues’, there was the
need to find a more abstract concept which was capable of representing these other concepts.
‘Claim events’ satisfied this requirement because it was a suitable rallying point for all codes
which could constitute the basis of a claim. It reflected the likely consequence of those
conditions, namely, claims. For instance, inability to deliver the project site on time to the
contractor could and did lead to delays which resulted in claims. Similarly, design changes
could and did lead to disruption of the schedules of contractors leading to claims. The same
logic informed the rallying of other individual codes such as ‘using incomplete design’, ‘poor
definition of scope’ and ‘laxity in contract administration’ around the category ‘claim events’.
Table 6.3 below shows the category ‘claim events’ and its codes.
Table 6.3: The Category ‘claim events’ and its child nodes (Source: Field data).
Category
Claim events
Codes
Poor definition of scope
Inclement weather
Site possession issues
Laxity in contract administration
Delayed payment
Design changes
Political interference
Extra work
Delays
Lack of coordination
Unfavourable ground conditions Non-compliance with condition
precedents
Inadequate engineering studies Poor preparation of contracts
on projects
Incomplete design issues
Change of scope of work
Effect
of
traditional Poor project preparation linked to
procurement method
cost
In some cases, there were different bases for connecting different codes to a particular
category.
For instance, some codes captured state of affairs or existing conditions
characterising a particular phenomenon. Others represented what actors involved with that
phenomenon did or were doing in response to the existing conditions (functions). Yet still,
other codes reflected the consequences of the actions of actors in relation to the phenomenon
118
Chapter 6-Data Analysis
in issue. For individual codes which were found to exhibit these features, Corbin and Strauss’
(1990) coding paradigm of conditions, actions and interactions and consequences (see section
5.6.2) was used to re-assemble them under identified categories. Since the earlier example of
‘claim events’ did not exhibit these features, another category namely ‘institutional structures’
is used to illustrate this process of developing categories.
Reading through the interviews, all the information on interviewees’ background were
coded under the node ‘interviewees’ profile’. Similarly, information about interviewees’ roles
in their respective organisations was coded under ‘interviewees’ roles’. Information provided
by interviewees about organisations they worked for such as the structure and objects of such
organizations were also coded under two separate codes namely ‘organisational structure’ and
‘objects of organisations’ respectively. There was a need to identify a category under which
all the four codes identified above will fit logically. The category, ‘institutional structures’
was adopted because it captured all information relating to the background description of
interviewees and the institutions they represented. Thus, the four codes were linked to the
category, ‘institutional structures’ (as illustrated by Figure 6.4 below) because they described
the conditions or circumstances of the institutions.
Figure 6.4: Link between ‘Institutional structures’ and child nodes (source: Field data)
Apart from the codes describing the structure and the condition of the interviewees and
their respective organisations, there were others which were linked to the category named
‘institutional structures’ because they related to how the various organisations functioned as a
119
Chapter 6-Data Analysis
result of their respective structures and conditions. Yet still, other codes were linked to the
category ‘institutional structures’ on the basis of the consequences of the actions of actors
under the given conditions. Figure 6.5 is a model reflecting the different rationales for linking
codes to the category ‘institutional structures’.
Figure 6.5: The category ‘institutional structures’ and its child nodes (Source: Field
data).
Using the two re-assembling strategies described above, twenty-three categories were
developed at various stages of the analysis. Table 6.4 below is a list of the categories.
Table 6.4: List of Categories
Categories
12
1
Institutional structures
2
3
4
5
6
7
8
9
Procurement
Contract formation and review
Selection of dispute mechanisms
Claim events
Settling of claims
Dispute causes
Meaning of disputes
Dispute resolution processes
13
14
15
16
17
18
19
20
Education and training
Setting standards for ADR use
Dispute avoidance and reduction
Increased use of ADR mechanisms
Political interference
Funding major projects
Barriers to ADRM use
Legal system
10
11
Dispute resolution procedures
Cultural influences
21
22
Parties to major construction projects
Consequences of the dispute
resolution processes
Front-end ordering
23
120
Required policy changes
Chapter 6-Data Analysis
Code memos were written to explore the emerging stories from the various categories as part
of the process of their development (see section 7 below).
6.5.3. Integration (Clustering Categories around the Core theme)
As both open coding and development of categories proceeded concurrently and
iteratively, another stage of the analysis namely the integration phase was introduced. This
entailed clustering the various categories generated around a core theme. Hence, there was a
need to identify a core theme at this stage of the analysis. One of the twenty-three categories
identified earlier namely, ‘the dispute resolution processes’ was selected as the core theme for
the following reasons. As one of the sensitizing concepts which drove the data collection
process, dispute resolution processes remained at the heart of the study. The aim of the study
was to examine the dispute resolution experiences of parties involved in infrastructure
projects in developing countries using Ghana as a case study. One of the research objectives
was to develop an explanatory framework and remedial strategies for the extant construction
dispute resolution processes (section 1.3). The questions in the interview guide essentially
aimed at obtaining information regarding interviewees’ experiences with construction dispute
resolution. Consequently, the category called ‘the dispute resolution processes’ was the
convergent point for substantial portions of the data and thus was selected as the core theme.
Under the core theme were sub-categories such as, ‘DRMs rarely used’, ‘DRMs regularly
used’, “DRMs not in Agreement but in and in use ’and ‘Procedure’.
With the core theme identified, the next stage was the exploration of how the categories
related to it. Again, Strauss and Corbin’s (1990) coding paradigm used previously to reassemble codes was utilised in the clustering process with some modification. In addition to
the core elements of the coding paradigm namely conditions (context/circumstances), actions
and interactions (resulting from the existing conditions) and consequences (of the actions and
interactions), a fourth element was added namely ‘remedial strategies’. The aim was to
121
Chapter 6-Data Analysis
capture categories on suggestions for improving the extant dispute resolution processes such
as ‘required policy changes’, ‘dispute avoidance and reduction strategies’, ‘education and
training’ and ‘setting standards for ADRM use’.
The various elements of the coding paradigm became the conduit for the exploration of
links between the categories and the core theme. At this stage, more emphasis was placed on
identifying categories which responded to the various research objectives. To achieve this,
questioning, as an analytical tool, was employed. Apart from using questions to obtain data
from the field, researchers employing grounded theory principles such as Strauss and Corbin
(1998, p.90) also recommend that researchers use questions to ‘generate ideas or ways of
looking at the data’. Consequently, questions which guided the analysis at this stage included
the following:(i) which categories provided information on the conditions or the context
within which the dispute resolution processes took place; (ii) which of the categories so
identified provided information on the context of the Employer; (iii) which of the categories
so identified provided information on the context of foreign contractors; (iv) which categories
provided information on how actors within the Employer setup and the Contractor setup acted
or interacted in response to the conditions or the context within which the dispute resolution
processes took place; (v) which categories provided information on the process of dispute
resolution and its associated procedures; (vi) which categories were about the consequences
of the current dispute resolution processes;(vii) which categories contained suggestions for
improvement of the current system?
The above questions aided the exploration of links between the core theme and the other
categories. It was observed that each of the categories related to the core theme through one or
more of the elements of the coding paradigm identified above. For instance, the category
labelled ‘institutional structures’, examined earlier on, contained data on the organisational
structures, objectives and functions of both the Employer and Foreign contractors. This
122
Chapter 6-Data Analysis
information provided insights into the nature of the parties involved in major infrastructurerelated construction dispute resolution. The ‘institutional structures’ category also represented
data which disclosed that the Employer was represented by different institutions namely, core
infrastructure procuring MDAs, the A-Gs and MOFEP, among others. The data also showed
that these organisations played different roles on behalf of the Employer. Whilst the MDAs
had roles during the early stages of dispute resolution (e.g. negotiating with contractors), the
A-Gs was the organisation responsible for conducting the right-based dispute resolution
processes on behalf of the Employer. This information on multiplicity of organisations and
functions associated with the Employer constituted part of the context or conditions within
which dispute resolution took place. Thus, it addressed the second research objective (see
section 1.3).
Other categories identified as providing information on the conditions or context within
which dispute resolution took place included ‘political influences’, ‘funding major projects’
and ‘barriers to the use of Alternative Dispute Resolution’. Categories such as ‘funding major
projects’, ‘procurement’ and ‘contract formation’ represented data on funding and
procurement conditions, nominated Conditions of Contract and the use of prescribed dispute
resolution mechanisms on contracts involving foreign contractors. These categories also
captured aspects of the context within which disputes arose and were resolved. A theme called
‘Features and Context of parties to dispute resolution’ was created to bring together all the
categories identified above as shown by Figure 6.6 below.
123
Chapter 6-Data Analysis
Figure 6.6: The theme ‘Features and Context of Parties to the dispute resolution
processes’ associated categories and some linked codes (Source: Field data).
Categories such as ‘procurement’, ‘contract formation and review’, ‘claim condition and
causes of disputes’ and ‘settling claims’ were classified under the ‘actions and interactions’
element of the coding paradigm. The reason was that, these categories reflected how actors
involved in infrastructure projects designed their dispute resolution systems and engaged with
pre-dispute resolution issues in response to the conditions within which they operated. The
categories were placed under an umbrella theme called ‘Procurement’.
Categories which represented data on the outcome of the dispute resolution processes were
captured under the third element of the coding paradigm namely ‘consequences’. Categories
on suggestions for improving the dispute resolution processes such as ‘required policy
changes’, ‘dispute avoidance and reduction strategies’, ‘education and training’ and ‘setting
standards for ADRM use’ were classified under the theme, ‘remedial strategies’ as shown in
Figure 6.7 below.
124
Chapter 6-Data Analysis
Figure 6.7: The theme ‘Remedial Strategies’ and its categories (Source: Field Data)
In sum, the categories developed during the re-assembling stage of the coding process
were clustered around the core theme, ‘dispute resolution processes’ using Strauss and
Corbin’s (1998) coding paradigm. The outcomes of the clustering process were five themes
representing data on various concepts, sub-categories and categories as shown by Figure 6.8
below.
Figure 6.8: The five themes generated through the process of clustering (Source: Field
data).
The results of the analysis based on grounded theory principles were supplemented by the
outcome of the legal analysis as explained under section 6.8 below. Table 6.5 below illustrates
how the themes generated during data analysis corresponded to the research objectives.
125
Chapter 6-Data Analysis
Table 6.5: Research Objectives and the corresponding themes and categories addressing
them
No.
Research Objectives
Themes
Categories
1.
Objective two:
Identification and examination
of features and context of the
key parties involved in
construction
and
civil
engineering contracts relating
to major infrastructure projects
Features and
Context of
Parties to the
dispute
resolution
processes
Employer
Institutional structures
Political influences
Cultural Influences
Legal system
Funding major projects
Barriers to the use of ADR
Foreign Contractors
Funding major projects
Procurement
Contract formation
2.
3.
4.
Objective three:
Procurement
Investigation into aspects of
the legal framework for
infrastructure
procurement
relating to dispute resolution
such as the contract formation
process
Legal
Framework
Contract formation
Claim events and causes of
disputes
Settling claims
Objective four:
Dispute
Examination of the legal resolution
framework
for
resolving processes
disputes arising out of major
projects
including
the
processes involved from the
emergence of a dispute to its
final determination
DRMs
DRMs rarely used
DRMs regularly used
DRMs not in Agreement but in use
NB: Response to this question is
supplemented by material from the
legal analysis.
Procedure
Consequences of the current
Consequences dispute resolution process
Cost
Delays
Destroying relationships
Missed opportunities to benefit
from intermediary ADR use
The Artesian Well Scenario
Lack of transparency
Objective five:
Barriers
Barriers to the use of ADR
Identification of challenges to
(Employer-related, Client-related
the
existing
modes
of
and Generic Barriers)
resolution including barriers to
the use of methods other than
litigation and international
commercial arbitration
126
Chapter 6-Data Analysis
No.
Research Objectives
5.
Objective six:
Remedial
Development
of
an strategies
explanatory framework and
remedial strategies for the
extant construction dispute
resolution processes
6.6.
Themes
Categories
Remedial strategies
Required policy changes
Dispute avoidance and reduction
strategies
Education and training
Setting standards for ADR use etc.
Memo Writing
The coding process discussed above was an active cognitive process involving constant
assessment of what the data being coded was communicating about the research objectives. It
was more than merely labelling chunks of data and classifying them. It entailed making
decisions about how the various pieces of information from the data connected together to
provide credible responses to the research objectives. The process of memo writing was the
means by which real time thoughts, ideas, notes and the logic of the analysis were captured.
Memo writing provided an avenue for the emerging story from the analysis to be recorded,
tracked and developed as more information was explored. This process commenced with the
coding and continued throughout the process. Three different types of memos were written as
the analysis progressed. These were code memos, methodological memos and theoretical
memos.
6.6.1. Code Memos
Code memos captured thoughts about emerging concepts and categories. These thoughts
were anchored in insights that interaction with the data provided. As the categories were
identified and developed, code memos were created to record the emerging story from the
data associated with them. The process aided the development of categories. A sample code
memo written on the category called ‘Settling claim’ is attached as Appendix F.
6.6.2. Methodological and Theoretical Memos
Other types of memos written during the data analysis were methodological and theoretical
memos. The methodological memos recorded thoughts about the process of data analysis
127
Chapter 6-Data Analysis
including the coding process. For instance, two methodological memos attached as
Appendices G and G1 captured the trend of thoughts at different stages of the coding process.
Appendix G captured the difficulties with line-by-line coding and suggested that it was
impractical to use it in the circumstance. Appendix G1 recorded a qualification to the initial
position on line-by-line coding contained in Appendix G. It provided reasons for a return to
line-by-line coding in certain cases alongside paragraph-by-paragraph and incident-byincident coding. The two methodological memos illustrate how memos were utilised during
data analysis. The third form of memo used during the analysis was theoretical memos. These
types of memos looked beyond categories to explore relationships between them. The memos
and the ideas developed through them constituted the basis of the reports on the results of the
data analysis.
6.7.
Generation of Diagrams and Models
Diagrams and models in this study were used essentially to provide visual summaries and
illustrations of ideas, structures and processes explained. Two sets of diagrams were used.
One set was generated directly from NVivo 9 and the other set with other software.
Regarding the first set of diagrams, NVivo 9 provides a tool which enables users to create
models of information in existing NVivo projects. A number of models were created as visual
representations of various sub-categories and categories using the model tool in NVivo.
Figures 6.4, 6.5, 6.6, 6.7 and 6.8 above are examples of diagrams generated directly from
NVivo. Some of the diagrams generated by this approach were used in the presentation of the
results of the study.
The second set of diagrams produced in this study was generated with other software such
as Microsoft Visio and SmartDraw using information from the data analysis. The diagrams
were developed as part of the efforts to capture the emerging story the data was telling. They
were particularly useful where processes and procedures were tracked. They constituted
128
Chapter 6-Data Analysis
supplements or visual expressions of the ideas which were captured through the process of
Memo Writing. Here is an example of how they were developed. As both documentary and
interview data on institutional structures were examined, it emerged that different
organisations played different roles in infrastructure procurement and dispute resolution. Data
explaining this phenomena were captured by codes which were subsequently linked to the
category called ‘institutional structures’ as shown by Figure 6.5. Subsequently, a Code Memo
exploring the emerging story from the category ‘institutional structures’ was written. From
this code memo, the multiplicity of organisations and their functions in infrastructure
procurement and dispute resolution were explored.
One of the processes which attracted multiple organisational involvements was that of
contract review, a component of the procurement process. The emerging story captured in the
Memo tracked the trajectory of the review process. Procurement (tendering, tender evaluation
and selection of contractors) was the function of the MDAs directly responsible for the
planning and implementation of projects. These MDAs were also responsible for contract
negotiations with selected contractors in majority of cases. Once draft construction contracts
were ready, the MDAs were under obligation to submit them to the Attorney-General’s
Department (A-Gs) for review and approval (Article 88 of the Constitution). Some of the
factors considered by the A-Gs during this process were project objectives, dispute resolution
clauses, the legal capacities of the parties and the legal implications of the obligations of the
Employer (see Table 7.1). Up to this stage of the process, all the institutions involved were
part of the Executive arm of Government. Where transactions under review required
parliamentary approval, the involvement of the legislature became inevitable and failure to do
so resulted in void contracts (see section 7.3.2.4). Contracts approved by Parliament were
referred back to the MDAs for implementation.
129
Chapter 6-Data Analysis
Having tracked the contract review process as described above through memo writing, a
diagram (Figure 6.9 below) was created as a visual representation of the process.
Executive Involvement
Parliamentary Involvement
Contract finalised and signed
between MDA & Contractor
Tendering
Process/
contracto
r selected
Contract
Negotiations
by MDA with
contractors
A-Gs review &
approval
Decide
whether
Parliamentary
approval
needed
Parliamentary
Approval
Communication of
Parliamentary
Approval
Figure 6.9: Contract Review Process –Embedded in the procurement process
The process of diagramming aided the analytical work by providing visual dimensions to
the cognitive process thereby allowing whole process and procedures to be explained in
simpler terms. Several of such diagrams generated during the analysis were used to
supplement narratives throughout the reporting process. In some instances, codes in NVivo
were extracted into tables. Again, the aim was to present ideas emerging from the analysis in
a simple easy-to-follow manner. In sum, the diagrams utilised as illustrations and visual
summaries in the presentation of results of the data analysis were generated either directly
from NVivo or pursuant to the Memo writing process as described in this section.
6.8.
Legal Analysis
Research objectives three and four required an examination of the institutional and legal
frameworks for procurement of major projects and the resolution of disputes arising
therefrom. Doctrinal legal analysis was employed to identify applicable constitutional
provisions, legislation, regulations and judicial decisions (see section 5.7.5). The legal
materials utilized in this research are outlined under the section on ‘List of Authorities’.
Constitutional provisions such as Article 181(5) on the requirement for parliamentary
approval for major infrastructure transactions between the State and foreign contractors were
130
Chapter 6-Data Analysis
explored to identify the confines of their application. Case law analysis, which constitutes an
aspect of doctrinal legal research, was used to examine judicial decisions relevant to the
research. For instance, to appreciate the true confines of Article 181(5), judicial decisions
interpreting the constitutional provision such as the A-G v. Faroe Atlantic [2005-2006]
SCGLR 271 were analysed.
The State and its agencies (the Employer) are legal entities. An examination of the relevant
constitutional and statutory provisions establishing these entities was crucial to understanding
the organisational structure of these entities as well as their functions. Consequently, laws
establishing selected entities such as Government Ministries, implementing agencies and
other relevant organs of State such as Parliament were examined to identify the source of the
legal capacities of these institutions and their functions relative to infrastructure procurement
and dispute resolution. Outputs from the analysis with grounded theory principles and the
legal analysis corroborated each other. Details of the results of the analysis are reported in
chapter seven.
6.9.
Summary
Two data analysis strategies were employed in this study. Grounded theory principles were
used to analyse both interview and documentary data. Legal analysis was employed to
examine documents which were of legal nature. Generally, the qualitative data analysis with
the procedures borrowed from grounded theory research was inductive. Data was broken
down to smaller chunks and labelled as codes under the process of open coding. A total of six
hundred and twenty-one codes were generated. The codes generated were further explored
leading to the development of thirty-eight sub-categories and twenty-three categories.
Subsequently, the categories and sub-categories were developed into five themes which
addressed the research objectives. One of the five themes, ‘the dispute resolution processes’,
was the core theme because it represented the central focus of the study. All the other themes
131
Chapter 6-Data Analysis
were explored for their connection to the central theme. The process of data analysis was
accompanied by memo writing and diagraming. The latter provided a visual dimension to the
analytical process whilst the former furnished the platform for emerging concepts and
thoughts to be developed. In addition to providing fresh insights into the subject matter of the
study, output from the legal analysis also corroborated the outcome of the analysis based on
grounded theory principles. It is this analytical framework which underpins all the findings
and representations contained in subsequent chapters of this study.
132
Chapter 7-Results of Data Analysis
CHAPTER SEVEN
133
Chapter 7-Results of Data Analysis
CHAPTER SEVEN – RESULTS OF DATA ANALYSIS
7.1.
Introduction
This chapter presents the outcomes of the data analysis. The outcomes were organised into
five themes namely, ‘Features and Context of Parties to Dispute Resolution’, ‘Procurement’,
‘the Dispute Resolution Processes’, ‘Consequences of the extant Dispute Resolution
Processes’ and ‘Remedial Strategies’. The fourth and fifth themes are examined in chapter
eight. Consequently, this chapter is divided into three main parts. The first part reports the
results of the analysis on the features and context of the main parties involved in infrastructure
procurement and dispute resolution in Ghana. The second part reports on the theme
‘Procurement’. It provides details of the outcome of the analysis on legal framework for
infrastructure procurement and dispute resolution, and the impact of the procurement process
on dispute resolution. The third and final part of the chapter deals with the theme ‘the Dispute
Resolution Processes’ and presents the results of the analysis pertaining to infrastructurerelated construction dispute resolution processes and procedures, and barriers to the use of
ADR.
The analyses reported were based on semi-structured interviews and documents (see
section 5.7.3). It emerged from the analysis that the nature of the Employer and foreign
contractors, their activities and the context in which they operated influenced their dispute
resolution choices and how infrastructure-related construction disputes were eventually
resolved. Beginning with the Employer, the distinctive features of the two main parties to
infrastructure-related construction disputes are examined together with the relevant contextual
issues.
134
Chapter 7-Results of Data Analysis
7.2.
Features and Context of Parties to Infrastructure-related Construction Disputes
The main parties to major infrastructure contracts and disputes arising out of such
transactions in Ghana were the State and its agencies (hereafter referred to as the Employer)
and foreign contractors.
7.2.1. The Employer
Legally, Ghana as a State is considered as a single entity (see the 1992 Constitution, Articles
4(1) and 58(1)). When it enters into a contract, it does so as a single entity. However, behind
the façade of the entity called the State was an elaborate bureaucracy underpinned by legal
structures. The power of the various State entities to procure major infrastructure projects or
participate in the process depended largely on their legal capacities. Section 14 of the Public
Procurement Act, 2003 (Act 663) outlined public institutions whose procurement activities
come within its purview. These were as follows:
(a) central management agencies (CMAs);
(b) Government ministries, departments and agencies (MDAs);
(c) governance institutions (GIs);
(d) sub-vented agencies;
(e) state-owned enterprises utilising public funds (SOEs);
(f) Public universities, schools and colleges;
(g) Public health institutions;
(h) Bank of Ghana and financial institutions wholly owned by the State or in which the
State is a majority shareholder; and
(i) Welfare institutions funded by the State.
Three entities constituted the CMAs. These were the Offices of the President, the Head of
Civil service and the Public Services Commission. GIs were the regional coordinating
councils, metropolitan, municipal and district assemblies (Act 663, s. 98). In practice, the
135
Chapter 7-Results of Data Analysis
above list of institutions had become the basis for categorising procurement entities (see
World Bank, 2003). These categories were not closed as the law empowered the Minister of
Finance and Economic Planning to declare other entities or persons as procurement entities, in
consultation with the Public Procurement Authority, by notice in the National Gazette (Act
663, s.16).
Each procurement entity was required by law to have a head, a tender committee and a
tender review board. The tender committees were generally responsible for procurement
activities of their respective entities. Under the First schedule to Act 663, their roles included
reviewing procurement plans, confirming the range of acceptable costs of items to be
procured, ensuring that procurement procedures were followed in strict conformity with the
Act and facilitating contract administration. The tender committees worked with tender
review boards whose main role was to review the activities related to specific procurement at
each stage of the procurement cycle. The aim was to ensure compliance with the provisions of
Act 663 and its enabling regulations. There were five different hierarchically arranged
categories of tender review boards. At the base were the district tender review boards. These
were followed by the regional tender review boards, the ministerial/headquarters tender
review boards and the central tender review board (Act 663, s.20).
Each entity, tender committee and tender review board (except the central tender review
board) was assigned a procurement value threshold (see Act 663, third schedule). By the
current value thresholds, procurements of most major infrastructure projects were handled by
the MDAs and the SOEs with the active involvement of other entities such as the Presidency
and Parliament. Consequently, the examination of the Employer’s structures for procurement
of major infrastructure projects and dispute resolution focused on the legal capacities and
roles of the Office of the President, the MDAs and the SOEs.
136
Chapter 7-Results of Data Analysis
7.2.1.1.
The Office of the President
States act primarily through their governments. Article 295 of the Constitution of Ghana
(here after called the ‘1992 Constitution’) defines ‘government’ as any authority by which the
executive power of Ghana is duly exercised. The 1992 Constitution establishes a Presidency
(the 1992 Constitution, Article 57). By Article 58 thereof, the executive authority of the State
was vested in the President who must exercise the said power in accordance with the
provisions of the Constitution. The power to enter into agreements on behalf of the State was
an aspect of executive power exercisable by the President (see the Constitution, Article 75).
This power was exercised by the President in person or through his delegated representatives
(see Article 58(3) & (4) of the 1992 Constitution). All executive acts were undertaking in the
name of the President. Article 78(1) of the 1992 Constitution mandated the President to
appoint Ministers of State to assist in the exercise of his executive powers. The Ministers so
appointed were responsible for the sectors assigned to them. The President was assisted in the
determination of general policy of government by a Cabinet (a group of Ministers).
Procurement of major infrastructure was policy driven. The initial discussions on the need
for a major infrastructure project originated from the MDAs, but such an idea could only
progress beyond the embryonic stage if it received Cabinet support (see the Constitution,
Article 76(2)). Hensengerth’s (2011) work on the construction of the 400 megawatt capacity
Bui Hydro-electric Dam confirmed the critical role the Presidency plays in major
infrastructure procurement. The fact that the power to contract emanated from the highest
echelons of power (which exercised some supervisory powers as well) underscored the chains
of consultation and approvals often required at various stages of decision-making during
infrastructure procurement.
137
Chapter 7-Results of Data Analysis
7.2.1.2.
Government Ministries and Implementing Agencies
Section 11 of the Civil Service Act, 1993 (PNDCL 327) provided that Ministries were the
highest organisations for their respective sectors. Broadly, they were required to perform the
following roles: (a) initiate and formulate policies taking into account the needs and
aspirations of the people; (b) undertake development planning in consultation with the
National Development Planning Commission; and (c) co-ordinate, monitor and evaluate the
efficiency and effectiveness of the performance of an assigned sector (PNDCL 327, section
13). By virtue of the powers vested in the Ministries by PNDCL 327 and the executive
authority delegated by the President under Article 58 of the 1992 Constitution, Ministers
(heads of Ministries) were required to represent the State in the acquisition of major projects
as Employers. It was on this basis that Ministries were often regarded as project owners. It
was for the same reason that Ministers acted as signatories to major construction contracts.
Section 20 of the State Property and Contracts Act, 1960 (C.A.6) provides that ‘the Minister
responsible for a subject or department, any other person authorised by the Minister, may
execute a contract for and on behalf of the Republic on a matter falling within the Minister’s
portfolio’.
Among the Ministries which successive Presidents had established under PNDCL 327
were five which stood out for their regular involvement in infrastructure procurement. These
were the Ministries of Finance and Economic Planning (MOFEP), Energy (MoEN), Roads
and Highways (MRH), Water Resources, Works and Housing (MWRWH) and the AttorneyGeneral and Ministry of Justice (A-Gs) (Government of Ghana, 2009; MOFEP, 1997). The
five Ministries listed above were divided into two on the basis of their roles. The MRH,
MoEN and WRWH were referred to in this study as the core infrastructure Ministries.
MOFEP and the A-Gs were called supporting Ministries because they provided specialised
support services to the core infrastructure Ministries. The Ministries were constituted by
138
Chapter 7-Results of Data Analysis
departments and divisions. Divisions provide administrative support to the Minister in the
performance of his duties (PNDCL 327, section 12). Thus, they were responsible for general
administration, planning, budgeting, co-ordination, and monitoring and evaluation of the
activities of their respective Ministries. Apart from the divisions, each ministry had agencies,
departments, authorities and SOEs (hereafter collectively called ‘implementing agencies’)
who were responsible for the initiation, planning, implementation, monitoring and evaluation
of infrastructure projects.
The components of the core ministries are briefly examined. The Ministry of Roads and
Highways had three implementing agencies for road infrastructure namely the Ghana
Highways Authority (GHA), the Department of Urban Roads (DUR) and the Department of
Feeder Roads (DFR). The Ghana Highway Authority, established under the Ghana Highway
Authority Act, 1997(Act 540), is a body corporate responsible for the administration, control,
development and maintenance of trunk roads (see Act 540, ss. 2 and 43). The DUR and the
DFR were responsible for urban and feeder road networks respectively.
The implementing agencies under the Ministry of Energy involved in infrastructure
procurement were a mixture of corporate entities created directly by statute and companies
wholly owned by the State. They included the Volta River Authority (VRA) (see the Volta
River Development Act, 1961 (Act 46)) and the Bui Power Authority (see the Bui Power
Authority Act, 2007 (Act 740)) involved mainly in electricity generation. The Ghana Grid
Company Limited was responsible for power transmission. The Electricity Company of
Ghana (ECG) and the Northern Electricity Department were in charge of power distribution.
Other entities under the Energy Ministry were the Tema Oil Refinery and the Bulk Oil
Storage and Transport Limited (involved in crude oil refinery, storage and transportation) and
the Ghana National Petroleum Corporation responsible for the exploration and production of
petroleum products. There were three main relevant agencies under Ministry of Water
139
Chapter 7-Results of Data Analysis
Resources, Works and Housing. These were Ghana Water Company limited (GWCL), the
Architectural Engineering Services Limited (AESL) and the Hydrology Department
(Government of Ghana, 2011).
Each of the implementing agencies identified above constituted an enormous bureaucracy
with departments, divisions and sub-divisions of their own and elaborate decision making
structures. For instance, the Ghana Highways Authority had three departments, eighteen
divisions and ten regional offices. The three departments were Development, Maintenance
and Administration. The department responsible for development had seven divisions. These
included Contract, Planning, Quantity Surveying and Materials Divisions. The rest were
Survey and Design, Bridges and Road Safety and Environment Divisions (see Figure 7.1
below). Each division played a crucial part in the execution of major trunk road projects.
Effective performance by GHA depended on the level of coordination and cooperation
exhibited by its sub-units. Failures at the organisational level affected inter-organisational
activities and the performance of the Employer as a unit (see section 7.2.1.3 below).
140
Chapter 7-Results of Data Analysis
Figure 7.1: The Organogram of GHA (Source: Field data)
The two supporting Ministries, MOFEP and A-Gs, were also constituted by departments
and divisions. Five agencies, departments and divisions played key roles in major
infrastructure procurement within MOFEP. These included the Public Procurement Authority,
the Controller and Accountant General’s Department and the Budget division. The other two
divisions were Debt Management and Legal Divisions. For the A-Gs, there was the Civil
Division. The multiple organisational involvements in the acquisition of major projects meant
decision-making entailed extensive consultation and approval processes which were often
fraught with difficulties.
7.2.1.3.
Multiple functions and Operational Inefficiencies
No single organisation had the power to perform all the roles of the Employer and this had
implications for coordination, cooperation and decision-making. Roles were split among
various organisations. The development of a policy framework for infrastructure acquisition
was the responsibility of Cabinet, the sector Ministry and the National Development Planning
141
Chapter 7-Results of Data Analysis
Commission (see the 1992 Constitution, Article 86, PNDCL 327, s.13). Commenting on the
role of the Ministry of Roads, one interviewee noted as follows:
Preparation for all projects under the purview of the Ministry starts from here. We are
in charge of policy and strategic planning. Need Assessment are done at the district,
municipal and metropolitan levels and these are fed into the Ministry’s
programmes…Once a need is identified, the Ministry will have meetings with donors,
have project appraisal documents (PAD) prepared and project objectives derived
(CPR1).
Technical preparations for projects were the responsibility of the implementing agencies
(see Act 540, s.3). Different pathways existed for the technical preparations depending on
whether the project was internally or externally funded. The development of the initial project
brief (project objectives, scope of project, Employer’s business case etc.) remained the
responsibility of the implementing agencies. Where a project was externally funded, the
funding organisations and consulting firms appointed by the State also played a role in the
technical preparation and implementation of such projects. A copy of the Project Appraisal
Document for road project ‘AkDA’ prepared by a consultant appointed by the Employer, in
collaboration with the GHA, disclosed that such technical preparations examined a number of
issues. These included the project concept and rationale, scope and the strategic context of the
project. Project objectives, its benefits and impacts, cost and sources of financing were also
examined (OCWD, 2001).
Procurement was the responsibility of the Ministerial and Central tender committees and
review boards (see section 7.2). The technical aspects of the procurement process were
undertaken by the implementing agencies under the supervision of the sector ministry
responsible. Describing the role of the implementing agencies in procurement, CPW5 stated
as follows: ‘Even though these projects are all Ghana Government projects we being the
technical eye of the Ministry…we lead in this procurement processes’. Where external
funding was used, various stages of the procurement process were regularly subjected to the
approval of the funding organisation. For instance, the World Bank provided elaborate
142
Chapter 7-Results of Data Analysis
procedures for staged review of procurement decisions of borrowers (see World Bank, 2011,
Appendix 1, p. 38). These procedures were rigorously adhered to.
MOFEP had a statutory obligation to pay financial liabilities of the State (see the State
Property and Contract Act, 1960, section 24). CPF1 commenting on the role of MOFEP in
relation to infrastructure procurement observed as follows:
The ministry is also responsible principally for making all government's contractual
payments and therefore it works with all the MDAs during the budget process to make
provision for the payments of all their plans, programmes and activities within certain
envelop. These payments will include necessarily payments arising from disputes
which the government or any office or agency might find itself involved with (CPF1).
Beyond paying government liabilities, MOFEP’s roles also extended to the review and
negotiation of loan agreements, seeking of Cabinet and parliamentary approval for funding
arrangements and any tax waivers associated with the funded project. Financial arrangements
for infrastructure procurement including payment for works was also a multi-organisational
activity involving Cabinet, Parliament, the sector Ministries and agencies of MOFEP at
various stages.
Contract review and negotiations also involved multiple organisations. These included the
sector Ministries, the implementing agencies, the A-Gs and Parliament. Construction
contracts were negotiated by the Ministries and implementing agencies responsible for the
particular project. Draft contracts were reviewed and approved by the A-Gs and Parliament
(see Articles 181(5) of the 1992 Constitution). A number of factors considered during the
contract review process by the A-Gs were gathered from the data. Table 7.1 below itemises
some of the issues explored during the review process at the A-Gs.
Table 7.1: Codes on Factors considered during contract review by the A-Gs
Standard Form Contract used
Changes to the general conditions
Pricing
Scope of Works or assignment
How Project implementation is reflected
in contract
Project objectives
Dispute resolution clauses
Legal capacities
Elements of a valid contract
Guarding against impleading of Ghana
before a foreign court
143
Chapter 7-Results of Data Analysis
Due diligence on parties to transaction
Engaging experts on unclear provisions
Value for money
Legal implications of Employer
obligations
Immunity provisions
Financial obligations
Termination clauses
Scrutiny of Contract for standard provisions
In the absence of guidelines on what attorneys should look out for during the review
process, they did not have access to a comprehensive list of items which needed to be
considered during the review process. Conspicuously missing from the list above was an
assessment as to whether a transaction requires parliamentary approval. Equally intriguing
was the inclusion of issues such as pricing and ensuring value for money. These outlined roles
duplicated roles which MOFEP was performing.
The review process also focused on the selection of dispute resolution mechanisms.
However, such review interventions did not result in any radical changes to standard dispute
clauses in General Conditions of Contract used. Where the transaction in issue constituted an
international business or economic transaction to which the Government of Ghana was a
party, the transaction required parliamentary approval in order to be valid (see the
Constitution, Article 181(5)). Failure to comply with the constitutional provision resulted in a
void transaction (see section 7.3.2.4).
Supervision of the construction phase of projects was by the implementing agencies, acting
as the Employer’s Representative and the Engineer. As the Employer’s representatives, their
role was to ensure that the consultant or contractor delivered in accordance with the contract
provisions. This role was played by the MDAs and in some cases, private consultants. Claim
settlement and dispute resolution were the responsibilities of the Engineer, the implementing
agencies, the sector Ministries, MOFEP and the A-Gs (see section 7.3.6). Figure 7.2 is a
visual representation of some the interactions between institutions representing the Employer
pertaining to activities prior to contract execution.
144
Chapter 7-Results of Data Analysis
Starting point
Legal opinion on Project
Cabinet
Government General Policy
Cabinet approval
MOFEP
Funding Arrangements
Central
Tender
Committee
Parliamentary
Approval
Policy direction &
Project Approval
Funding request
MRH
Policy direction
project approvals
supervision
Funding Approval
Request for legal
opinion
Contract
Negotiation &
Execution
Contractor
Opinion delivered
Ministerial Tender
Committee
A-Gs’
Legal Opinion
Policy direction&
Project Approval
Private
Consultants
Preparation
feedback
GHA
(project preparation &
implementation)
Participation in contract negotiations
Figure 7.2: Web of Roles: Visual representation of interactions between sub-units of the
Employer prior to contract execution (Source:Field data)
The non-linear nature of the functions of the various organisations involved in
infrastructure procurement and dispute resolution and the inter-organisational relationships
they engendered had implications for coordination and cooperation among the sub-units of the
Employer. There was evidence of coordination problems between the A-Gs and the MDAs.
CPA4 described the problem of lack of coordination and cooperation as ‘running battles with
all the MDAs’. Elaborating further on what this means, CPA 4 stated that MDAs fail to
cooperate with the A-Gs at the initial stages of projects. The A-Gs is consulted only when
conflicts or disputes arise and the MDAs were unable to resolve them. In response to the
‘running battles’ argument, the MDAs argued that lack of capacity at the A-Gs hampered
referral of transactions. CPR4, an interviewee from the road sector noted as follows:
The A-G’s office does not have the capacity to deal with all international contracts
coming from all sectors. They don’t really have the time. So sometimes what happens
is once our ministry gives the go-ahead, yes there is a lawyer in our ministry… a very
good lawyer. So before we sign most of the documents, they are submitted to the
ministry and she goes through it. What I know is that if there are certain things she
has to refer to the AG’s Department, she does that. So in a way, the AG’s Department
influences what we do. But I know it is not in all cases; it is only, may be, in the high
profile cases that really [receive the attention of the A-G] (CPR4)
145
Chapter 7-Results of Data Analysis
From the excerpt above, CPR4 raised two problems with the A-Gs namely, lack of time and
lack of capacity. Commenting on the same issue, CPR8 observed as follows:
Within the Authority we have contract specialists and we have engineers who have
worked with contracts so what we do is we have the Conditions of Contract which is a
standard document which guides us and that is the FIDIC Conditions of Contract. We
fashion our contracts with the FIDIC Conditions of Contract and once we are within
the ambit of the FIDIC conditions we do not go to the extent of involving other people
from other agencies like the AGs department to guide us on what we should put in the
contract.
The above extracts from the interviews conducted exposed some of the difficulties with interorganisational relationships among the various sub-units of the Employer involved in the
execution of projects.
The problem of lack of cooperation extended to dispute resolution. Five out of the seven
interviewees from the A-Gs had concerns with the stage at which disputes were referred to the
A-Gs by MDAs. To them, disputes were often referred to the A-Gs when they were ‘spoilt’ or
‘when it is too late’. In the words of CPA 1,
They will bring it [dispute] to us when the thing is spoilt. Disputes come to us when it
is too late to do anything about it. They sue them then they quickly come, ‘AG, what
do we do? That is standard. The lawyer is the last person to be called...When the
dispute is ripe then they come to us and say this people have taken us to arbitration.
Ours is just to put it together.
However, it appeared that comments on late referral of disputes to the A-Gs do not take
into consideration the MDAs’ responsibility in the dispute resolution processes. Much of the
initial attempts at resolving differences between the Employer and the contractor took place at
the level of the implementing agencies with the technical experts and sometimes the sector
ministry responsible. As noted by CPR8, because some of the issues were very technical and
the AGs department did not have the technical expertise, they invariably depended on
engineers from the MDAs. The issue of lack of coordination and cooperation was not limited
to activities pertaining to procurement of projects and dispute referrals but also information
sharing. The data as described above reveals a picture of an Employer with complex
146
Chapter 7-Results of Data Analysis
operational structures characterised by ineffective inter-organisational cooperation and
coordination.
7.2.2.
Relevant Contextual Issues
Beyond the inter-organisational issues discussed above, the Employer’s ability to prepare
and participate effectively in dispute resolution was negatively affected by the context within
which it operated. Key contextual issues identified which influenced the process of
infrastructure procurement and dispute resolution included human resource deficiencies,
political interference and fear of becoming blacklisted by the Employer. The upshots of these
contextual issues extended to foreign contractors as well.
7.2.2.1.
Human Resource Concerns and Lack of Specialisation
Article 88 of the Constitution makes the Attorney-General a Minister of State and the
principal legal advisor to the government. He is responsible for the institution and the conduct
of all civil cases involving the State. He is assisted in the performance of this role by the AGs. Thus, the roles of the A-Gs in the acquisition of major infrastructure projects can be
categorised into four parts namely provision of legal advice (the Constitution, Article 88 (1)),
contract negotiation and review (see C.A.6, section 22 and 25), approval of transactions
through the rendering of legal opinions and resolution of all disputes which were likely to
arise from the process of acquisition. The A-Gs’ involvement in the resolution of
infrastructure-related construction disputes
entailed both front-end preparations and back-
end readiness for future disputes. However, there was evidence that the A-Gs had serious
human resource problems which affected both front-end preparations and back-end readiness.
Two codes created from exact phrases used by two interviewees from the A-Gs captured how
these problems manifested in practice. These are ‘jacks of all trades’ and ‘fire-fighting’.
The code ‘jack of all trades’ was used in relation to the Civil Division which was the
section of the A-Gs directly involved in infrastructure procurement. Commenting on what
147
Chapter 7-Results of Data Analysis
pertained at the A-Gs regarding the performance of its roles in the acquisition of major
infrastructure projects and the resolution of disputes arising out of such transactions, CPA5
stated as follows:
We are jacks of all trades. Myself, today I am doing this, tomorrow, I am doing that. I
don’t focus on one thing. I am all over the place. As I speak to you, next week I will
be working on e-record keeping. Last week, I was working with the judiciary on ADR.
The week before, I was doing something else. I have done work on migration. I have
done work on our land and sea boundaries. So it is not… You see, as a human being
under normal circumstances, you should have an area of specialization, so that you can
excel in that area. But in our department here, it is one big cooking pot; we all do it
(CPA 5).
The imagery of ‘a big cooking pot’ used by the interviewee, in the Ghanaian context, conjures
in the mind's eye a big black pot, always on fire, used to cook every foreseeable dish; it
connotes lack of specialisation and excessive workload. The advice, review, approval and
resolution functions of the A-Gs were undertaken by a small number of lawyers involved in
all kinds of civil matters affecting government business. The lawyers were divided into
loosely organised working groups with each group headed by a Chief State Attorney. The
Attorneys within the working groups were periodically assigned transactions from various
MDAs. There was no indication that individual attorneys were assigned a group on the basis
of speciality. Again, the categories of transactions handled by the groups were fluid. The
working groups encountered administrative difficulties and were also hampered by excessive
workload and internal turf wars. It was to this little resourced division of the A-Gs that
disputes arising from all MDAs were referred. Inadequate human resources and lack of
specialisation resulted in inefficiencies in the execution of the A-Gs’ roles. This in turn
influenced negatively the ability of the Employer as an entity to perform its roles under
construction contracts.
The second of the two codes describing the role of the A-Gs in infrastructure procurement
and dispute resolution is ‘firefighting’. The A-Gs was regularly hard pressed for a number of
reasons namely, work load, human resource problems and lack of cooperation from MDAs
148
Chapter 7-Results of Data Analysis
leading to delayed referral of disputes. Thus, its approach to addressing disputes was often ad
hoc. As a result, lawyers who were already under a lot of pressure, had to engage in
‘firefighting’. CPA3 described the situation in the following terms:
You see, the AGs office is always hard pressed. That is what people don’t seem to
realize and … [a former Attorney-General] put it as [referred to it as] ‘firefighting’, we
are always fighting to quench the problem because by the time it gets to the AGs’
office it may be even bad. You know the problems there, shortage of staff and so on,
morale and incentive issues. And so you realize that you are working under some
pressure to get things done.
The human resource difficulties identified in the excerpt above and the resultant approach to
dispute resolution had consequences for the outcome of arbitrations against the State.
7.2.2.2.
Political Interference and Corruption
Procurement of major infrastructure is a governmental responsibility (see section 2.3).
Thus, it is impossible to conceive an acquisition process totally devoid of the influences of
political actors. The very system of governance in place in Ghana made it imperative for
every government to pay close attention to infrastructure development and sometimes bring
its influence to bear on the process. On this issue, CPR4 observed as follows:
It is a fact we must face. In a democracy every government has to show what it has
done at election time. So if perhaps promises have been made, ‘look we will complete
this road in our first term’, definitely something should be done. So, if even there are
drawings and they are not up to scratch, we can start something with it. Sometimes we
have to go in and start hoping that we will be doing the design ahead of time but once
you do that, you have already laid the grounds for claims and disputes (CPR4).
In their quest to achieve their political objectives, politicians interfered with the acquisition
and dispute resolution processes beyond the limits allowed by law. More than ten
interviewees from the MDAs interviewed independently intimated that politicians with vested
interests in projects sometimes attempted to influence the procurement process. The views of
two of the interviewees - CPR4 and CPW3- were particularly revealing. CPR 4, for instance,
stated as follows:
When it is GOG sometimes what happens is that – yes, I mean it is obvious. People in
high places may be interested in certain contractors getting the job. So sometimes
what we do is to do ‘restricted tendering’. I wouldn’t say there is much interference
because I was on a panel where – yes from all indications, what we had done there
149
Chapter 7-Results of Data Analysis
was no way we could change it. All sorts of pressures were brought on us but we
stood our ground and it was accepted.
CPW3 also noted in respect of corruption in the procurement process as follows:
I must say that unfortunately, sometimes because of the political … [interviewee
hesitates]. Let me just be frank with you, most of the contracts, there are people
behind them, most of the contracts, there are politicians behind them, so they will
push these things to be done. They will not come and push me but they will push my
MD, then he will also try to push me, you see so in some of the cases, I don’t even
agree and in those cases, I have to write officially, I have to write officially that I think
this and that should be done before the contract is signed. So what it means is that I
shift the burden back to him [the MD]. Because of that we may not have a perfect
contract. These are contracts you don’t terminate easily. Those things [hasty contract
agreements] will come and haunt you one day… Because of our experience we know
those areas where disputes can arise but there is somebody who is also pushing you to
get these things done (CPW3).
From the data on the category ‘political interference’, a number of issues were identified.
Some politicians used the infrastructure acquisition process for personal gain. Consequently,
persons responsible for project implementation were sometimes ‘coerced’ to enter into
contracts without the necessary due diligence. The consequence of such acts was the signing
of flawed contracts. There was evidence that running contracts were often terminated or
breached in certain cases without regard to contractual terms.
The issue of political interference also extended to the process of dispute resolution. For
instance, CPE5 shared that there were instances where foreign contractors resorted to
politicians when contract disputes arose. Here is an excerpt of the interview:
Q:
A:
Q:
A:
When the engineer failed or was unable to settle, what happened?
The contractor by-passed us and went to the Castle.
He went straight to the Castle?
He by-passed all the procedures and went straight to the castle. He went to
report us. He ignored everything and went to the castle. But we brought him to
book and settled.
‘Castle’ was a reference to the seat of government. Although, by virtue of their positions as
officers of the government they were not neutral parties, it was a common practice for
political actors to organise meetings between MDAs directly involved in projects and
contractors to attempt to resolve disputes. In the case of one particular institution, it was
indicated that as a result of this practice, no formal dispute had been recorded for nearly a
150
Chapter 7-Results of Data Analysis
decade and a half. However, there were indications that sometimes subordinates were
instructed to resolve disputes in a particular way. The implications of political interference on
the dispute resolution processes are further examined in chapter eight (section 8.3.3.4.3).
7.2.2.3.
Fear of Blacklist
As the major employer of infrastructure projects, the Employer was perceived as invincible
when it came to the award of construction contracts.
Contractors depended largely on
government contracts for survival. Consequently, the Employer had several options and could
therefore afford to reject, ignore or exclude contractors who were claim conscious or litigious.
A World Bank study in 2003 found that very few contractors pursued disputes against the
Employer due to fear that they will be blacklisted or side-lined (World Bank, 2003). Most
interviewees considered the fear of being blacklisted as widespread. It affected both local and
foreign contractors. It was therefore not surprising that a number of foreign contractors
contacted refused to participate in this study (see section 6.3). Three interviewees from three
different MDAs confirmed the existence of this fear. Dispute resolution destroyed
relationships and it was expensive, they claimed. Blacklisting contractors who pursued
disputes against the State was a natural outcome of the process. One of them opined as
follows:
It [dispute resolution] destroys relationships because if you take me to arbitration and
there is another job and I have a say, I won’t put you on it. I will make sure you don’t
win. And most contractors too are aware so they also shy away from it (CPR4).
CPR8 expanded the argument further in the following excerpt:
We know that some firms are litigants so in order that we will not invite firms who are
litigants we do what we call a pre-qualification for international contracts. We have to
pre-qualify, look at your litigation history. In order to play it safe we make sure that
firms that are prone to litigation we take them out of our midst at the pre-qualification
stage so that we do not involve those ones and in order that we will not run into
difficulties during the execution of the project because international arbitration can be
very expensive (CPR8).
The interviewee considered excluding claim conscious or litigious contractors as ‘playing
it safe’ and ‘avoiding running into difficulties’. He provided further justification for the
151
Chapter 7-Results of Data Analysis
existence of fear of being blacklisted: ‘No Employer will like to deal with a person who will
resort to rampant international arbitration or recourse to law…you do not want to deal with
a person like that’. (CPR8). Confirming the existence of this phenomenon and its impact on
contractor behaviour, CPE7 stated as follows:
The thing is that for the Ghanaian contractors you will be blacklisted if you misbehave
and the foreign contractors too when they come and they see that there are more
business opportunities, they know they must comport themselves, that is the
motivation. So doing things that will smear the relationship or will not motivate [name
of organisation] to continue working with you, they try to avoid that (CPE7).
Contractors were also aware of the threat and what it meant to their business. EP1,
representing a foreign contractor, stated in relation to the implications of a contractor taking a
hard line on disputes as follows:
I mean if you are talking about foreign contractors, well for the major projects there
are foreign contractors. The consequences of the contractor taking that hard line is
this, you can take that hard line but one , it will be the last project he ever does in
Ghana… There is more profit here than there [the contractor’s home country] because
there, there is competition. That is one. So given that he is making more money here,
he is not in a hurry to be kicked out (EP1).
When asked why delays and breaches suffered by a foreign contracting firm were not
submitted to the dispute resolution processes, EP3, representing a foreign consulting firm
responded as follows:
We deal with governmental levels [institutions] so he [the contractor] doesn’t want to
incur the displeasure of Government. Immediately they blacklist you, you are finished.
So I think it is a sort of intimidation. Even though the master-servant relationship
should not be there but you see it coming to play-so maybe it is the master-servant
relationship that is why disputes are minor in this [industry], but between individuals,
yes, they do occur every now and then.
The above interviewee considered the threat of blacklisting litigious contractors as amounting
to ‘intimidation’. It placed the contractor in a ‘master-servant relationship with the
Employer’. APB1, an interviewee with experience in representing foreign contractors, stated
in respect of the fear of blacklist that many contractors would rather preserve their
relationships with government than incur its displeasure by commencing a dispute resolution
process. He observed as follows: they ‘would rather sit and let the banks chase them and their
assets sold than for them to sue the government’ (APB1).
152
Chapter 7-Results of Data Analysis
Thus, even though international arbitration was part of the dispute clauses of most
construction contracts, the threat of blacklist remained an effective counter-strategy against its
use. Consequently, the Employer paid little attention to disputes. The fear of blacklist stifled
the practice of dispute resolution and hindered the growth of formal dispute resolution
processes in the construction industry in Ghana. Further implications of this practice on
dispute resolution are examined under chapter eight (see section 8.3.3.4.3).
7.2.2.4.
Funding Major Infrastructure Projects
Both documentary and interview data pointed to four main sources of funding for major
infrastructure projects in Ghana. These were Government of Ghana (GoG) funding, donors,
joint GoG and donors and private sources. GoG funding, the traditional source of funding was
made available by the State through annual budgetary allocations. However, as Government's
budgetary allocation of internal resources was unable to meet its infrastructure needs, there
was extensive reliance on external funding. As disclosed by an examination of budgetary
allocations to the energy, road and water, works and housing sectors across three annual
national budgets, huge percentages of resources allocated to infrastructure development were
from external sources (see Table 7.2, 7.3 and 7.4 below).
Table 7.2: Ghana –Budgetary Allocations for the Energy Sector (Sources: The Budget
Statements and Economic Policies of Ghana for the years 2009, 2011 & 2012).
Year
Total budgetary
GoG
Donor
Others
allocation
2009
¢317,243,469
¢6,070,589
¢286,172,880
¢25,000,000
2010
-
-
-
-
2011
¢405,495,572.00
¢4,289,022.00
¢371,206,550.00
¢30,000,000.00
2012
¢657,132,393
¢7,550,203
¢157,682,902
¢130,000,000
Table 7.3: Ghana –Budgetary Allocations for the Road Sector (Sources: The Budget
Statements and Economic Policies of Ghana for the years 2009, 2011 & 2012).
153
Chapter 7-Results of Data Analysis
Year
2009
Total budgetary
allocation
¢386,370,228
2010
-
GoG
Donor
Others
¢90,114,575
¢171,860,226
¢124395427
-
-
-
2011
¢335,960,762.00
¢81,412,702.00
¢213,023,525.00 ¢31,524,535.00
2012
¢907,794,236
¢87,340,017
¢600,394,151
¢549,355
Table 7.4: Ghana –Budgetary Allocations for the Water Resource, Works and Housing
Sectors (Sources: The Budget Statements and Economic Policies of Ghana for the years
2009, 2011 & 2012).
Year
Total budgetary
GoG
Donor
Others
allocation
2009
¢285,929,547
¢46,122,240
¢218,755,543
¢21,051764
2010
-
-
-
-
2011
¢558,625,890.00
¢16,618,212.00
¢529,903,428.00 ¢1,165,842.00
2012
¢283,176,014
¢51,318,428
¢209,245,706
¢1,611,880
External funding sources identified included bilateral and multilateral organisations.
Bilateral sources included the Danish International Development Agency (DANIDA), United
States Agency for International Development (USAID), Japan International Cooperation
Agency (JICA) and Canadian International Development Agency (CIDA). The multilateral
sources included the World Bank and the African Development Bank. Documentary data
available from one implementing agency for instance showed that between the year 2001 and
2012, thirty-one facilities made up of loans and grants were contracted for infrastructure
projects. A total of US$ 797,229,408.79 and € 390,350, 923.23 were raised to support over
thirty different projects. The facilities were obtained from both bilateral and multilateral
sources. The Netherlands, Belgium, Spain, USA and China were among the creditors. The
main multilateral sources of funds for the implementing agency concerned were the World
Bank (IDA) and the African Development Fund (ADF). The status report on development
154
Chapter 7-Results of Data Analysis
projects for another implementing agency in the road sector also disclosed that the sector
received substantial donor support from institutions such as the World Bank, ADF, African
Development Bank (AfDB), the Arab Bank for Economic Development in Africa (BADEA),
Japan International Cooperation Agency (JICA) and the EU.
Apart from projects which were wholly funded either by GoG or donors, there were
several instances where projects were jointly funded by GoG and donors. The Sankara
overpass, Tetteh Quashie-Mamfe and the Akatsi-Dzodze-Akanu road projects are examples of
this arrangement. The overpass was funded jointly by GoG and France. The Akatsi-Dzodze
section of the Akatsi-Dzodze-Akanu road was jointly funded by GoG/AfDB while the Tetteh
Quashie-Mamfe road was funded by GoG and BADEA.
Another source of external funding was private financing. Individual contractors looking
for contract awards searched for funding for projects in return for single source procurement
arrangements. Various interviewees provided insights into the practice which was widespread.
For instance, one interviewee described the process in the following terms:
We have a list of projects; we do not have the money to undertake the projects. The
Ghana Government cannot do it on its own. So people are free to come and pick and
choose which ones they could undertake. In fact when they do that… In fact there are
lots of people involved. We do that together with MOFEP [interruption]. So as I was
saying first of all we enter into MOU. After that, they come around, go and do their
feasibility studies and then decide that ok, ‘we want may be Asamankese project’. So
we sit on that. We have a technical committee. We appraise their proposals and have
negotiations with them and then after that we sign a contract. But that contract is
subject to a lot of things. It is subject to approval by Cabinet [and] by Parliament. It is
subject to what we call value for money audit. That is at the MOFEP (CPW3).
Information from one implementing agency indicated that through these financing
arrangements, several projects have been executed. For instance, at the time of the interviews,
the agency was on the verge of securing a $370 million facility to undertake a major project
through this arrangement. Essentially, such funds were borrowed by the Government and then
on-lent to the implementing agency concerned. Whether obtained from bilateral, multilateral
or private sources, external funds for projects were accompanied by conditions which
155
Chapter 7-Results of Data Analysis
invariably shaped the construction contract and influenced how disputes were resolved.
Funding arrangements for infrastructure projects often included conditions relating to
procurement, nominated Conditions of Contract and dispute clauses (World Bank, 2011, p.21;
USAID, 2003). The implications of these funding conditions on dispute system design and
resolution are examined under section 7.3.2 below.
7.2.3.
Foreign Consultants and Contractors
The data indicates that many foreign contractors operating in Ghana set up under varied
legal arrangements. Some operated through subsidiaries or representative companies in the
country. For instance, Vinci operated in the country through Sogea-Satom, Bilfinger Berger
through Razel and Taylor Woodrow, until recently, through Taysec (Bernard Krief
Consultants, 2006). In such cases, the subsidiaries or partner companies were either limited
liability companies incorporated as domestic entities with majority of their shares held by
foreign companies or partnerships set up under the Companies Act, 1963 (Act 179) and
Incorporated Private Partnership Act, 1962 (Act 152) respectively. Others set up directly as
external companies. Under Section 302 (2) & (3) of Act 179 an external company is a body
corporate formed outside Ghana but with established place of business in the country. Some
foreign contractors functioned through joint ventures or special purpose vehicles created and
duly incorporated under Ghanaian law for specific projects. An example is Gestagua, a
Spanish company set up purposely to design and install civil and water works on the
Akwapim Ridge.
Foreign contractors got involved in major infrastructure procurement in Ghana through
three different routes namely, international competitive tendering, nomination under funding
requirements and sole sourcing. Projects funded by multilateral institutions such as the World
Bank were awarded through international competitive tendering. Invariably, foreign
contractors got the nod to execute such projects. This finding accords with the conclusions of
156
Chapter 7-Results of Data Analysis
Chan and Suen (2005) on the same subject. Lack of capacity has made it impossible for the
State to depend on domestic contractors to execute major projects. Most major projects were
therefore executed by foreign entities. This challenge was not limited to Ghana (see Chen et
al., 2007). Major European construction and design companies were named among the most
prominent in the major construction market in Central and Western Africa. These included
Vinci (France), Bouygues (France), Strabag (Germany) and Veolia (France). Others such as
Bilfinger Berger (Germany), AMEC (United Kingdom) and Taylor Woodrow (United
Kingdom) also had presence across Central and West Africa (Bernard Krief Consultants,
2006).
There were foreign contractors who became involved in infrastructure projects in Ghana by
virtue of their affiliation with funding institutions. Countries providing funding for specific
projects, in some cases, also insisted that contracts for such projects should be awarded to
shortlisted companies from their jurisdictions. For instance, CPW10, commenting on how a
presidential building complex was funded, stated as follows: ‘These were loans coming from
foreign entities and they came with their conditions, the contractors came with them’. Another
interviewee with an implementing agency, observed in relation to the funding and execution
of a water project as follows:
In the ST [project name withheld] similar things, like this one, occurred. I think this
one [another project in the Ashanti region] the design was done by a different
company but also from Netherlands because the Netherlands Government had given
us the donation, they were the funding agency. So they first gave us a company, R. H.,
to do the designs. So when it was ready for construction, they brought in B.N. The
companies came from the same country. The Netherlands government was funding the
project, so they brought people to work for us (CPW5).
This practice was typical of bilateral funding arrangements. Finally, foreign contractors got
involved in major projects through the process of single source procurement as described
under section 7.2.2.4.
As of 2003, there were thirty-four (34) registered foreign works contractors in Ghana;
twenty-seven (27) in the road sector alone (World Bank, 2003b). In the past two decades,
157
Chapter 7-Results of Data Analysis
many Chinese construction companies have joined the competition for construction projects
on the African continent (Chen et al., 2007). In Ghana, Chinese construction companies such
as Shanghai Construction Company, China Railway Wuju and China International Water &
Electric Company were playing key roles in the major construction sector. Shanghai
Construction Company constructed two national soccer stadia at Sekondi and Tamale in the
western and northern regions of Ghana respectively. Sinohydro constructed the recently
commissioned Bui hydro-electric dam with an estimated project cost of $660million
(Hensengerth, 2011). Similarly, international design companies were active in the domestic
construction market. Coyne et Bellier (France) and Environmental Resource Management
(United Kingdom) conducted the feasibility studies on the Bui Dam project.
Review of previous studies disclosed that foreign contractors preferred international
arbitration when it came to construction dispute resolution (see section 4.4). However, the
literature does not capture the role of bilateral and multilateral funding organisations in the
setting up of arrangements for the eventual use of international arbitration. The interview data
disclosed that the dispute resolution processes were influenced by funding arrangements (see
section 7.3.2.1). By virtue of the involvement of foreign contractors, the context of
infrastructure-related dispute resolution extended beyond the jurisdiction of Ghana. Other
effects of the nature and preferences of foreign contractors on dispute resolution are discussed
under section 8.3.1.
7.3.
Procurement
This section reports the findings of the data analysis captured under the theme
‘Procurement’. The theme captured outcomes of the data analysis on procurement rules and
methods in use in Ghana, the formation of construction contracts and dispute resolution
system design, and the effect of procurement on dispute resolution. Other issues covered
under this section include claim events and dispute causes and the settlement of claims.
158
Chapter 7-Results of Data Analysis
7.3.1.
Procurement Rules and Methods in use
Ghana follows the common law tradition. Consequently, its legal system is modelled along
the lines of the English system. The main sources of law, as outlined under Article 11 of the
1992 Constitution, are the Constitution, legislation (Acts of Parliament and Decrees), Orders,
Rules and Regulations and the common law. The common law comprises the common law as
received from Britain and developed through judicial refinements, the law of equity as
received and customary law (the Constitution, Article 11(2)). As the Supreme law of Ghana,
the 1992 Constitution guarantees equal rights and makes the Government liable to claims in
contract and tort like a private individual, albeit subject to certain limitations (see the
Constitution, Chapter 5 & Article 293 and the State Proceedings Act, 1998(Act 555), ss. 2 &
3).
The main legislation governing procurement in Ghana is the Public Procurement Act, 2003
(Act 663). Details of this legislation have already been examined (see sections 3.5). Sections
14 and 96 of Act 663 excluded from its scope situations where a loan agreement, guarantee
contract or foreign agreement provides different procedure for the utilisation of funds. Section
96 provides as follows: ‘Despite the extent of the application of this Act to procurement,
procurement with international obligations arising from a grant or concessionary loan to the
Government shall be in accordance with the terms of the grant or loan’. In effect, there were
two sources of procurement rules in Ghana; (a) those under Act 663 which were mainly
statutory; and (b) those under contractual arrangements between the Employer and funding
organisations. Most infrastructure projects in Ghana were procured under the latter.
Procurement methods found to be currently in use in the procurement of infrastructure in
Ghana included the traditional methods, design and build, Engineer, Procure and Construct
and public-private partnerships (PPP) (GOG, 2011). Major construction works in Ghana were
procured largely through the traditional procurement method (see section 3.3.1). Half of the
159
Chapter 7-Results of Data Analysis
fifty-six interviewees who were asked to indicate which procurement methods were
commonly used for infrastructure project acquisitions mentioned the traditional methods. For
instance, CPW 11 observed as follows:
Let me give you a little bit of a reminder that our jobs are mainly government jobs.
Now, when you are dealing with government, it’s very difficult to bend. It’s extremely
difficult to bend, so we are still using the traditional procurement system. That’s what
we are still using. Traditional, that means, an Employer wants to build, consults a
consultant, a designer designs it; it is quantified and priced out. He says well, yes, you
may go ahead with procurement, we invite tenders, we open tenders, evaluate and
award to a contractor, give him a start and conclusion date, he starts. As he builds,
well, government payment system being what it is, you are normally not able to
enforce the construction schedule, so you run it like that until completion. This is what
has been going on and that’s what we are still using generally.
The common practice was that survey, design and estimation were often treated as a package
distinct from the construction phase. Different funding arrangements would usually be made
for the feasibility studies and design phase on one hand and the construction phase on the
other. In many instances, there was considerable time lag between the period when such
studies and designs were conducted and when the construction took place. Thus updating
technical reports and designs prior to construction was a common occurrence.
There were also occasions where designs had been identified to be inadequate in the course
of the construction thereby raising issues of buildability. These scenarios often led to change
of designs and sometimes extensive changes in the scope of works. The effects of such
variations on cost and delay were enormous. For instance, CPR9 gave an example of a project
which commenced with dated designs. Subsequently, the contractors discovered a large
stretch of unfavourable ground condition which was not detected by the Employer due to lack
of a thorough geo-technical test prior to execution. This resulted in a huge increase in the
contract cost.
Design and build and Engineer, Procure and Construct (EPC) procurement methods were
also in use. Some of the notable design and build and EPC projects in Ghana included the
Accra and Kumasi Sports stadia (Micheletti, 2011), two new stadia at Essipong in Sekondi
160
Chapter 7-Results of Data Analysis
and Tamale respectively, the Accra Waste Project (Taysec, 2011), the four hundred MW
capacity Hydro-electric dam at Bui, in the Brong-Ahafo region of Ghana (Hensengerth, 2011;
Baah and Jauch, 2009), and the €45 million
Tamale Water Supply Extension Project
completed in 2008 (Ghana Water Company Limited, 2011). Most of the design and build
projects were externally funded projects. Design and Build and EPC were relatively prevalent
in the Water and the energy sectors. The only collaborative procurement method identified in
the data was the Public-Private Partnership (PPP).
Procurement strategy was mainly driven by funding preferences. There was an indication
that the existing procurement process paid no attention to the potential impact that it could
have on dispute prevention and management. APA explaining why this was the case,
observed as follows:
Dispute doesn’t come into their [Employer] mind because the government is still the
largest Employer and the construction sector is almost entirely engaged by
government and there is something called blacklisting which is an unwritten rule and
if you complain too much, you will be blacklisted. So because of that there are only
few disputes that arise from government projects. Many people who are cheated or
who have reasons to raise claims don’t because they don’t want to be blacklisted.
7.3.2. The Contract Formation and Review Process
Bid documents included Conditions of Contract. It was a matter of common knowledge
among interviewees that the construction contract was not made up of a single document.
There was the agreement and then other documents were deemed to be part of it. These
included the letter of acceptance, the bid and appendix to the bid, the Conditions of Contract,
the designs and the Priced bill. These documents were hierarchically arranged in order of
importance. In this study, the focus was on the Conditions of Contract, its provisions on
dispute resolution and the dispute system design generally.
7.3.2.1.
Nominated Conditions of Contract
Both the World Bank and USAID expressly demanded the use of the FIDIC suite of
contracts on their projects (World Bank, 2011, p.21; USAID, 2003). European Union funded
161
Chapter 7-Results of Data Analysis
projects were executed under EU Conditions of Contract. Other multilateral institutions also
subscribed to the FIDIC forms. Majority of the fifty-six interviewees identified the FIDIC
suite of contract as the most popular for major infrastructure projects. The view of CPR1
captured succinctly observations made by the other interviewees:
Mostly, the FIDIC Standard forms are used. The FIDIC Red book, 1987 has been the
main standard form. In recent times, we have also used EPC for some projects. One
that comes to mind is the Adomi Bridge rehabilitation. The FIDIC forms are suitable
and widely accepted. The European Union also has its contract forms. Apart from the
EU however, most contractors are agreeable to the FIDIC forms.
FIDIC conditions were used for projects in the road, water and energy sectors. There were
also indications that bespoke contracts were used particularly for works in the energy sector.
Even so, such contracts still benefitted from insights from the FIDIC provisions. CPE5,
commenting on the use of FIDIC conditions for the procurement of thermal plants in Takoradi
and Tema, stated as follows:
I think in Takoradi it was FIDIC, that is the T1 (thermal one) contract. Other projects
that we have done like in Tema we used FIDIC but sometimes there are variations like [for instance] the T3 project that we are doing is not a FIDIC contract per se but it
is a contract which has been developed by the company themselves [bespoke contract]
so we go over all the issues and as much as possible we borrow from what is
applicable in the FIDIC because those are the standard things that you will consider.
Most of the bidding documents and the signed construction contracts sighted contained the
FIDIC conditions. In fact, the use of the FIDIC suite of contracts had become so entrenched
that even major projects funded wholly by GoG were awarded under the FIDIC Conditions of
Contract. The dominance of the FIDIC range of contracts was attributed to three reasons.
Firstly, both multilateral and bilateral funding organisation demanded that the FIDIC
conditions be used for sponsored projects. Secondly, the influx of foreign contractors and the
need to use standard forms which all parties were familiar with had also contributed to the
dominance of the FIDIC forms. Finally, most interviewees generally agreed that the
provisions in the FIDIC forms were fairly balanced and addressed concerns of both
Employers and contractors.
Generally, contractors saw the FIDIC contracts as a safer preference. The FIDIC
162
Chapter 7-Results of Data Analysis
Conditions of Contract had two main components namely the General Conditions and the
Special Conditions. The General Conditions were standard clauses often applicable to most
construction and engineering projects. These included clauses on dispute resolution.
The
Special Conditions were the project specific changes that parties agreed to make to the
General Conditions. Some of these changes also pertained to the arrangements for future
dispute resolution.
7.3.2.2.
Dispute Clauses
Dispute clauses were part of nominated Conditions of Contract. The FIDIC Conditions of
Contract for Construction (the Red book) (1987 editions) had dispute clauses which required
parties to resolve disputes by the Engineer’s determination, amicable settlement and
international arbitration (see Clause 67 of the FIDIC Red book, 1987 Edition). In subsequent
editions of the FIDIC Red book (the 1999 edition and the FIDIC MDB Harmonised
Conditions of Contract, 2010), Engineers determination has been replaced with the Dispute
board. Consequently, clause 20 of the FIDIC Red book, 1999 and the MDB Edition, 2010
identify negotiations, dispute adjudication boards, amicable settlement and international
arbitration as the mechanisms for the resolution of construction disputes arising out of
projects which are subject to the provisions of these FIDIC Conditions of Contract. The
dispute clauses in both the 1987 and the 1999 versions of the FIDIC Conditions were utilised
with little or no modification in Ghana.
For instance, the construction agreement between the GoG and Construction Pioneers
Baugesellschaft Anstalt (CP) dated 5 December, 1996 for the asphaltic concrete overlay of a
portion of the Biriwa-Takoradi Road in the western region of Ghana incorporated Clause 67
of the 1987 edition of the Red book on dispute resolution without any modification. Except
for the addition of information on project-specific issues such as rules and venue, the clause
was a verbatim reproduction of Clause 67(1) of the FIDIC Red book, 1987. Similarly, parties
163
Chapter 7-Results of Data Analysis
to the construction contract covering an aspect of the Kintampo-Paga Road incorporated the
provision of Clause 20 of the FIDIC Red book, 1999 edition. In this instance, the dispute
mechanisms used were the dispute board, amicable settlement and international arbitration.
However, in the case of the Bamboi-Bole Road Project, although the transaction was based on
the FIDIC Red book, 1987 Edition, the parties amended Clause 67 to include a Dispute
Review Expert as a replacement for the Engineer’s determination through the special
conditions. The new Clause 67(1) provided in part as follows:
If any dispute arises between the Employer and the Contractor in connection with, or
arising out of, the Contract or the execution of the Works or after their completion and
whether before or after their repudiation or other termination of the Contract,
including any disagreement by either party with any action, inaction, opinion,
instruction, determination, certificate, or valuation of the Engineer, the matter in
dispute shall, in the first place be referred to the Dispute Review Expert (‘DRE’).
Copies of construction contracts covering EU sponsored projects obtained revealed the use of
different dispute clauses. Article 68 of the EU General Conditions provided for the resolution
of disputes by amicable settlement in the first instance. If one hundred and twenty days after
notification of dispute was served parties were unable to settle, then parties will need to
pursue conciliation. Article 68(3) provided as follows:
In the absence of an amicable settlement, a Party may notify the other Party in writing
requesting a settlement through conciliation by a third person. If the European
Commission is not a party to the contract, the Commission can accept to intervene as
such a conciliator. The other Party shall respond to this request for conciliation within
30 days. Unless the Parties agree otherwise, the maximum time period laid down for
reaching a settlement through conciliation shall be 120 days from the notification
requesting such a procedure. Should a Party not agree to the other Party’s request for
conciliations, should a Party not respond in time to that request or should no
settlement be reached within the maximum time period, the conciliation procedure is
considered to have failed.
Unlike the World Bank, the European Commission was willing to act as a conciliator for
disputes which arose out of EU funded projects. When both amicable settlement and
conciliation failed, parties ‘may refer the dispute to either the decision of a national
jurisdiction or arbitration, as specified in the Special Conditions’ (Article 68(4) of the EU
General Conditions). Parties were at liberty to elect between using national courts or
164
Chapter 7-Results of Data Analysis
arbitration in the Special Conditions. For instance, the Special Conditions of the contract on
the Tarkwa-Bogoso-Ayamfuri Road, an EU project, provided that disputes arising out of
transnational contracts were to be settled by any of the following processes:
(i) if the parties to the contract so agree, in accordance with the national legislation
of the beneficiary country or its established international practices; or
(ii) by arbitration in accordance with the procedural rules on conciliation and
arbitration of contracts financed by the European Development Fund, adopted by
Decision No. 3/90 of the ACP-EEC Council of Ministers of 29th March
1990(Official Journal No L382, 31:12:1990).
Parties were required to negotiate dispute resolution clauses within the parameters provided
by these Conditions of Contract.
7.3.2.3.
Special Conditions: Negotiating Dispute Clauses
Dispute clauses in General Conditions were hardly altered in any substantial way by
parties. During contract negotiations, the most parties did was to agree on details relating to
the use of international arbitration, or in rare cases where DABs were used, agree on details
on the setting up of the DAB and its membership. As a matter of regular practice, terms on the
following were agreed by the parties: (i) the entity or body which was to administer
international arbitration; (ii) the venue; (iii) arbitration rules to be applied; (iv) the governing
or applicable law; (v) the language; and (vi) the number of arbitrators and the selection
process. The rules of arbitration often used included the UNCITRAL and the ICA rules. The
venue would often be in London, The Hague, Geneva or France. The applicable law would
usually be Ghana law even though this was not always the case. The language was always
English. The parties would either agree on an arbitrator or three arbitrators. Parties had
limited influence over the selection of dispute resolution mechanisms as they were required to
negotiate within the confines of dispute clauses in the Conditions of Contract usually
nominated by funding organisations. Other considerations which informed selection of
dispute resolution mechanisms included the nature of the parties, value of project,
enforceability, fairness and neutrality (see Figure 7.3 below).
165
Chapter 7-Results of Data Analysis
Figure 7.3: Factors influencing selection of Dispute Resolution mechanisms (Source:
Field data)
The process of designing dispute resolution systems as examined above had implications
for ownership of the dispute resolution edifice and dispute resolution practice in general (see
section 8.3.2).
7.3.2.4.
Impact of Public law requirements on Construction Contract Formation
For building and civil engineering projects involving the State, concluding contract
negotiations and signing the construction agreement was not enough for the parties to
commence execution. By virtue of the involvement of the State or its agencies, there were
additional public law requirements which parties needed to meet. One such legal requirement
was Article 181(5) of the 1992 Constitution. This provision was specifically examined in this
study because of its likely impact on the validity of construction contracts and the
implications of such impact on dispute resolution. The first five clauses of Article 181 of the
1992 Constitution are reproduced below:
(1) Parliament may, by a resolution supported by the votes of a majority of all the
members of Parliament, authorise the Government to enter into an agreement for
the granting of a loan out of any public fund or public account.
(2) An agreement entered into under clause1 of this article shall be laid before
Parliament and shall not come into operation unless it is approved by a resolution
of Parliament.
(3) No loan shall be raised by the Government on behalf of itself or any other public
166
Chapter 7-Results of Data Analysis
institution or authority otherwise than by or under the authority of an Act of
Parliament.
(4) An Act of Parliament enacted in accordance with clause (3) of this article shall
provide,
(a)
that the terms and conditions of a loan shall be laid before Parliament
and shall not come into operation unless approved by a resolution of
Parliament; and
(b)
that any monies received in respect of that loan shall be paid into the
Consolidated Fund and form part of that Fund, or into some other
public fund of Ghana either existing or created for the purposes of the
loan.
(5) This article shall, with the necessary modifications by Parliament, apply to an
international business or economic transaction to which the Government is a
party as it applies to a loan.
Failure to comply with Article 181(5) had implications for transactions which came under its
purview such as major infrastructure contracts involving foreign entities and the State. Lack
of compliance also had repercussions for the dispute resolution processes outlined under those
transactions.
In A-G v Faroe Atlantic Company Limited (the Faroe Atlantic Case) [2005-2006] SCGLR
271 the Supreme Court of Ghana held that an agreement between a company incorporated in
the United Kingdom and the Government of Ghana which required the former to generate and
supply electricity to the latter constituted an international business transaction to which the
Government of Ghana was a party and thus required parliamentary approval to be operative.
In this case no parliamentary approval was obtained prior to the execution of the contract. The
Court held that the effect of the non-compliance with Article 181(5) was that the contract in
question was void. Consequently, the Court ordered the private party to refund all payments it
had received under the contract.
In A-G v. Balkan Energy (Ghana) Limited & Ors (the Balkan Energy Case) [2012] 2
SCGLR 998, a case involving another power purchase agreement between a company
registered in Ghana with majority foreign ownership and the Government of Ghana, the
Supreme Court held that even though the company was registered in Ghana, the transaction in
question had significant foreign elements and thus constituted an international business
167
Chapter 7-Results of Data Analysis
transaction and therefore required parliamentary approval. The implication of the decision of
the court was that the PPA was void. Significantly, the Court held that the arbitration clause
under the power purchase agreement was not an international business or economic
transaction and thus survived the apparently void contract.
The subject matter of the case of Martin Amidu v A-G & 2 Ors ((The Waterville Case) Suit
Number J1/15/2012, judgment of 14 June 2013), were two contracts for the rehabilitation
(Design, Construction, Fixtures, Fittings and Equipment) of two 40,000 seating capacity
sports stadia in Kumasi and Accra and the upgrading of a third (the El Wak Stadium) also in
Accra. Both contracts were between the Republic of Ghana and Waterville Holdings (BVI)
Limited, a company incorporated in the British Virgin Islands. The contracts, signed on 26th
April 2006 as part of preparations towards the hosting of the 2008 African Cup of Nations,
were subsequently terminated. Consequently, the Contractor made a claim and eventually
secured payment through mediation led by the then Attorney-General, for work done prior to
the termination. The Applicant, a former Attorney-General of Ghana, sought a declaration that
the said contracts never received parliamentary approval prior to execution and thus
contravened Article 181(5) of the 1992 Constitution. He further sought an order directed at
the contractor to refund all payments made by the State to it pursuant to the two contracts.
The Defendants resisted the Applicant’s action arguing, inter alia, that they fully complied
with all requirements under the Public Procurement Act, 2003 (Act 663) and received the
necessary approvals from the Central Tender Board. They relied on the Court’s earlier
decision in City & Country Waste Ltd. v Accra Metropolitan Assembly (the CCWL Case)
[2007-2008] 1 SCGLR 409 (where the Court had exercised its discretion to allow restitution
under an illegal contract).
The Supreme Court held that the contracts which did not receive parliamentary approval
were null and void and ordered that money paid under them be refunded. In the recent cases
168
Chapter 7-Results of Data Analysis
of Amidu v Attorney-General & 2 Others (Isofoton Case) (21 June 2013, Supreme Court
(Unreported)) and Klomega v Attorney-General & 3 0thers (19 July 2013, Supreme Court
(Unreported)) the Supreme Court made similar orders for refund of monies paid under
contracts which did not comply with Article 181(5) of the Constitution.
Significantly,
mediation, one of the dispute mechanisms which the parties agreed at the contract negotiation
stage, incorporated into the construction contract and utilised to settle disputes arising from
the transaction, was swept aside by the decision of the Court.
The implication of the above decisions is that Conditions of Contracts agreed between
parties to infrastructure projects remained invalid until the transactions they related to
received parliamentary approval. Dispute resolution arrangements and steps taken pursuant to
such arrangements were all void on the grounds of violation of the provisions of Article
181(5) of the Constitution. The only exception is the arbitration clause. In the Balkan Energy
case, the Supreme Court upheld the validity of the arbitration clause.
7.3.3. Legal Institutions
Chapter eleven of the Constitution vested judicial power in the judiciary and gave it
jurisdiction over all civil and criminal matters. The chapter also established a hierarchically
organised court structure with the Supreme Court at the apex. Decisions from the High court
are appealable to the Court of Appeal and subsequently to the Supreme Court (see also the
Courts Act, 1993 (Act 459)). The High Court has divisions including those on land, human
rights and commercial transactions. Construction disputes are classified as commercial
disputes under the Commercial Court rules (see the High Court (Civil Procedure) Rules, 2004
(C.I. 47), Order 58). Order 58 makes mediation mandatory prior to trial.
Notwithstanding court reforms during the past decade and a half, there was still
overwhelming evidence that parties to major infrastructure projects generally avoided the
courts as means of resolving disputes. Reasons for this practice included old perceptions of
169
Chapter 7-Results of Data Analysis
inordinate delays and fear of bias in favour of the Employer (see Asouzu, 2001). Construction
contracts encountered did not designate litigation as a dispute resolution option. However, it
was found that in some instances, parties resorted to litigation in the national courts. In
Construction Pioneers Baugesellschaft Anstalt (CP) v. Government of Ghana (Case No.
12078/DB/EC, International Court of Arbitration) for instance, whilst the arbitration was ongoing there was a parallel court proceeding dealing with an issue of fraud against one of the
parties in the Ghanaian courts. A similar trend was seen with the Balkan Energy Case.
Litigation remained a very active dispute resolution process.
Apart from the courts, the Alternative Dispute Resolution Act, 2010 (Act 798) established
the Alternative Dispute Resolution Centre. The role of the Centre was to facilitate the
enforcement of the provisions of the Act (see Act 798, s.115). However, the idea of stateowned alternative dispute resolution centre appeared to be outmoded at birth. The data
revealed a general dislike for the establishment of another public institution in charge of
dispute resolution in addition to the courts. The remarks of the following interviewee on the
establishment of a State-owned centre for ADR sums up the views from the interviews:
We have the judiciary the court system which is saddled with numerous problems. The
State has not been able to solve the problems at the court; automation is still going on.
Other courts are still not automated… Now the State creates another institution. I will
put that one aside. Have you heard - may be, in the Far East but I don’t know - that
there is a State which has an arbitration institution where parties go and resolve their
dispute? What happens if the State is involved in a dispute with another entity? The
ICC is not a state entity, LCIA is not, AAA is not, and the Ghana Arbitration Centre is
not. It undermines the neutrality; it doesn’t engender neutrality in arbitration
proceedings involving the State and another party.
Beyond the State-sponsored ADR Centre, there were burgeoning private institutions
administering ADR notably the Ghana Arbitration Centre. However, there was some distrust
in the competence and capacity of local private institutions to handle disputes from major
projects involving substantial sums of money. The view of APC, an interviewee, reflected the
views of those sceptical of the ability of domestic private organisations to handle construction
disputes arising from major projects:
170
Chapter 7-Results of Data Analysis
If you are looking at dispute resolution in a contract document involving infrastructure
project of $300million, you say we should go to the Ghana Arbitration thing that has
been set up – I don’t even know if it is working-this, the local [interviewee stammers]
no contractor will…[interviewee pauses] with no disrespect to it[the Centre]... It
[dispute resolution] usually involves an arbitration process involving the ICC or one of
these kinds of bodies which are not based in Ghana.
Lack of ADR infrastructure meeting international standards was also emphasized by some
interviewees. But, it appeared that actors involved in major infrastructure procurement did not
have full knowledge of the capacity and activities of the private ADR institutions.
7.3.4. Use of Alternative Dispute Resolution
There was no legislation dealing specifically with construction dispute resolution. The
Alternative Dispute Resolution Act, 2010 (Act 798) sets out rules on arbitration, mediation,
conciliation and customary arbitration. However, it applied generally to all subject areas
except those expressly excluded under section 1 of the Act which provided as follows:
This Act applies to matters other than those that relate to
(a) the national or public interest;
(b) the environment;
(c) the enforcement and interpretation of the Constitution; or
(d) any other matter that by law cannot be settled by an alternative dispute
resolution method.
It has been argued elsewhere that this provision on arbitrability excluded major
construction transactions from its purview because invariably they constituted matters of
public or national interest (see Mante and Ndekugri, 2012). The implication of this legislation
for dispute resolution is examined under section 8.3.3.4.4.
7.3.5. Claim Events and Dispute Causes
The literature on what constitutes claims and disputes and their causes was examined under
section 4.2. In the absence of an official database cataloguing all infrastructure-related
construction disputes in Ghana, it was impossible to provide figures on prevalence.
Nevertheless, the qualitative data suggested a dispute-rife sector. The study identified several
regular claim events and dispute causes. A summary of information on fourteen of these
events is presented in Table 7.5 below.
171
Chapter 7-Results of Data Analysis
Table 7.5: Claim Events and Dispute Causes (Source: Field Data)
1
2
3
4
Poor definition of There was often a mismatch between the Employer’s requirement
and the contractor’s obligations. The statement of APC, a contract
scope
reviewer, on this issue sums up the views of interviewees. APC
observed as follows:
One of the things which immediately come to mind is poor
definition of the scope. That is a big issue. What happens is that
the owner of a project, the government side, is unable or do not
take time to state or think through the scope of projects, what in
engineering is called the Employers’ requirements. What we see a
lot of the time is that there is a dis-connect between that and what
the contractor offers. Even if they know it, they don’t state it
clearly, properly, with all the information that the contractor can
then respond to. That is a big big issue. Because as a result of
that, we as an independent party look at it and in our view, the
Employer’s needs and the contractors’ offers do not match. We
therefore have to find a way of bringing those two positions
together. In our view, a lot of those could have been shortened if
clearer definition of what they want is put out there.
This was described as a challenge which can distort everything. It
Unfavourable
affected the value of the contract, led to massive claims. Citing an
ground
on-going project as an example, CPR9 emphasized the need for
conditions
thorough geo-technical investigation prior to the award of
contracts. In the example above, the initial investigations failed to
locate a huge rock covering a whole stretch of the civil works
being undertaking. Neither the initial design nor subsequent
physical inspections by the contractor revealed its existence. The
contractor had given notice that the work required to remove the
rock has not been priced. The Employer is reluctant to accept the
situation.
Examples of Employer interference encountered included: (a)
Employer
political figures requesting aspects of signed contracts to be varied
interference
without recourse to the normal contractual channels for effecting
such variations; and (b) political figures instructing contractors to
go onto site without detailed designs (see The Waterville Case).
Many major infrastructure projects affected private properties.
Site possession
Such properties were compulsorily acquired by the State to pave
issues
way for execution. As CPR4, CPR 9 and EP3 indicated, in most
cases compensation payments for the acquired sites delay and
often remained unpaid by the time the project begins. Affected
persons see commencement of work as a trigger to agitate for
payment. According to EP3, external funding did not cover such
payments. It therefore fell to GOG to secure funds for such
purposes. Predictably, such payments often suffered delays and
this results in disruption of work.
CPR9 and EP 2 recounted various instances where relocation of
utilities posed serious time and financial challenges to projects. In
most cases, access to site was not given. For the Contractors,
idling equipment and workforce, and delay causing disruption of
172
Chapter 7-Results of Data Analysis
5
7
8
9
10
11
12
work schedules made claims inevitable.
Delayed payment This was one of the key causes of disputes in Ghana. CPR 4
commenting on causes of disputes stated as follows:
One major problem is delay in payment especially where
government of Ghana contributes to the funding; it happens that
we always delay in paying our portion. Where it is wholly GOG,
then that’s a major factor…we delay in paying so they bring
interest on delayed payments. Sometimes, the contractors give
notice and stop work. So once you pay them then they will
remobilize and start the work again. So all those stand still costs
will come in as claims. So that’s one major issue.
Design changes Design changes in the course of construction may be a normal
feature of major projects. However when they become a regular
occurrence, their impact on claim becomes visible. CPR 4, CPR8
and CPR 9 alluded to the pervasiveness of the practice in Ghana
particularly with Government projects. Excessive design changes
led to delays, alteration of work schedules, and request for
additional resources to meet the new requirements. The
consequences were claims for additional sums and extension of
time (CPR9).
These were, generally, the immediate claim triggers and were very
Delays
rife.
The Employer often instructed contractors to execute extra work
Extra work
beyond what was originally agreed and this was another source of
claims (EP1&CPE5).
Most projects commenced on the basis of inadequate engineering
Inadequate
studies. CPR4 and CPR 9 acknowledged that this situation often
engineering
resulted in outright change of scope of the original project with
studies
implications for revision of rates, extension of the completion
time, payment of additional overheads and claims for idle
equipment etc.
Related to the issue of inadequate engineering studies was the
Incomplete
challenge of awarding major projects based on incomplete,
design
outdated or non-existent designs. CPR4, for instance, admitted
that sometimes they were ‘forced’ to start projects with
incomplete designs.
Many issues matured into disputes due to the Employer’s laxity.
Laxity in
This fact was confirmed byCPA4, EP2 and CPR 9.They attributed
contract
some claims made against the Employer to officials who failed to
administration
perform their roles promptly and as a result caused unnecessary
delays on projects.
Use of traditional After presenting lower bids to secure selection, most contractors
tended to focus on aspects of the transaction which could be
procurement
exploited to make up what they have lost. CPE 5 gave two
method
examples of recently executed projects which encountered such
practices. In both cases, the projects had been successfully
completed. Then the contractors set out to identify issues related
to the projects and then set a claim process in motion. From the
interviews, many of such claims eventually resulted in disputes as
173
Chapter 7-Results of Data Analysis
13
Variations
14
Breach of
contract
the Employer often rejected such claims.
Most interviewees involved in project implementation were
unanimous on the issue of regular occurrence of substantial
variations in Government projects.
Wilful breach of contract was common. In response to a question
on the causes of disputes, CPA1 replied, ‘Non- performance,
breach of contract, you have given it to X you signed, and then
you go and give it to Y. We have plenty of that. And they are suing
us for breach of contract’. This was confirmed by CPA4 and other
interviewees.
Where the above-listed events existed, the likely consequences were claims by contractors.
Where claims based on these conditions were rejected expressly or by inference, disputes
resulted (see section 4.2).
7.3.6. Settling Claims
The Conditions of Contract determined the circumstances under which a claim was to be
admitted and processed. Though minor differences in practice were observed from one
implementing agency to another, the following represented the general procedure as gathered
from the interviews. The first point of call was the Engineer or his representative who was
either a Resident Engineer or a private consultant. The roles of the Resident Engineer or
private consultant remained as stipulated under Clause 2.2 and 2.3 of the 1987 FIDIC Red
book and Clause 3.1&2 of the 1999 edition. The claim procedure in practice very much
reflected the procedure outlined under Clause 53 of the 1987 FIDIC Red book and Clause
20(1) of the FIDIC Red book 1999. The contractor was required to serve a copy of the claim
on the Employer as well. The Resident Engineer or the consultant who received the notice of
claim and the evidence in support was obliged to ensure that the contractor had complied with
the requirements of the contract.
Once a claim was received, it was the responsibility of the Resident Engineer or the
consultant to vet them, request for additional supporting information and write an opinion
indicating whether or not the claim was justified. CPR 4 described the claim process at this
stage as it pertained to current practice as follows:
174
Chapter 7-Results of Data Analysis
I mean before we admit any claim, we ensure that it satisfied the claim procedure so
that’s what we tell our people on projects. We normally hold seminars from time to
time and claim is an issue which we discuss. We tell them that, from day one they can
stop – some of these claims are rather frivolous, they are afterthoughts. If you are
supposed to give notice within twenty-eight days, provide details within twenty-eight
days and the engineer is supposed to start taking his records – your notice is to get the
engineer informed that something is going wrong, he can stop it – he better stop it and
avoid any escalation of the situation so if you don’t follow those things when your
claim comes, they will knock it out.
At this stage, the Resident Engineer or consultant could intervene to stop the claim from
proceeding further (if there was a justification) through initial discussions with the contractor.
CPR 9 gave an example of such an intervention which resulted in the withdrawal of a claim of
about six million US dollars against the Employer. The Resident Engineer’s opinion was
usually forwarded to the implementing agency which acted as the Engineer or the Employer’s
Representative. Upon receipt of the Resident Engineer's report, a team examined the report as
against the claims from the contractor. The team was often made up of experts at the
implementing agency. If there was a need for further particulars or evidence to be sought from
the contractor, this was done.
After a thorough deliberation, the opinion of the Resident Engineer was accepted, modified
or substantially altered depending on the conclusions of the Engineer. The Engineer's
determination was subsequently prepared and this would indicate that the contractor was
entitled to its claim, part of it or was not entitled at all. There was evidence that the Engineer's
determination was forwarded to the Employer (the Ministry responsible) especially when the
determination involved payment of additional money. The Ministry’s comments would then
be considered and the final position agreed was communicated as the Engineers'
determination to the Contractor. When the Engineer's determination was accepted by the
contractor, the claim or difference was deemed settled. When the Engineer’s determination
was rejected by the contractor either expressly or by inference, a dispute was deemed to have
emerged.
175
Chapter 7-Results of Data Analysis
7.4.
Construction Disputes Resolution - Mechanisms and Procedure in Use
Three categories of dispute resolution mechanisms (DRMs) were identified from the
interviews. These were (i) DRMs incorporated into the Conditions of Contract and regularly
used by parties; (ii) DRMs incorporated into Conditions of Contract but rarely used; and (iii)
DRMs not expressly stipulated in construction contracts but in use.
7.4.1.
DRMs Regularly used
Engineers’ determination, negotiations and international arbitration were the DRMs
frequently used by parties. The findings of the data analysis in relation to these DRMs are
briefly examined below.
7.4.1.1.
The Engineer’s Determination
The first point of call for all construction disputes and differences was the Engineer. This
was partly due to the continuing use of the FIDIC Red book, 1987 for major infrastructure
projects in Ghana. The Engineer’s role as it related to dispute resolution derived from clause
67 of the FIDIC Red book, 1987 which requires that all disputes and differences between the
Employer and the Contractor be referred to the Engineer. In this regard, Seppala (1987)
distinguishes a dispute between the Engineer and the contractor from a dispute between the
Employer and the contractor. The former relates to matters the Engineer has power to address
under the Conditions of Contract such as dealing with claims. The latter on the other hand,
related to matters over which the Engineer had no prior power to address under the Conditions
of Contract.
Practice on the ground as observed through the data did not lend itself to a strict distinction
between the role of the Engineer under Clause 53 in relation to claims and his role under
Clause 67 in relation to disputes. Thus the practice regarding the Engineer’s determination of
disputes and differences followed substantially the same process as it was with claims (see
176
Chapter 7-Results of Data Analysis
section 7.3.6). The only difference was that in the case of a dispute, the contractors’ reference
expressly indicated that it was made pursuant to Clause 67 of the FIDIC Red book, 1987.
It was observed from the data that the roles of implementing agencies of Government as
Engineers of projects hampered dispute resolution. CPA4 commenting on this subject stated
as follows:
In Ghana, invariably the Employer’s representative or the Engineer is the … [an
implementing agency] that is another state institution. So the contractors don’t feel
comfortable dealing with them. So you realize that the matter is not resolved at that
level. It is hardly resolved. And so at a point in time the Ministry will refer it
[disputes] to the A-Gs.
This finding raised the question of independence of the Engineer as an arbiter of dispute
between the Employer and contractors. This concern arguably resulted in the replacement of
the Engineer with the Dispute Board under the FIDIC Red book, 1999 (see Ndekugri et.al,
2007).
Where the Engineer’s determination was rejected by the contractor, it was often followed
by series of negotiations. CPR 5 gave the sequence of events after the Engineer has made it
findings as follows:
After doing our bit at … [Employer’s representative], we have to forward our comments
to the Ministry. They are the policy makers and they sit on top of everybody. We tell them
our recommendations. They also go through, agree or disagree with us. If they disagree,
whatever amendments they suggest we make but of course, we meet and talk. Then we
arrive at a common position of the ministry and that is then communicated to the
contractor as the decision of the engineer and the Employer. Now, if the contractor is
satisfied, that ends it. If not, then he will write back and that is when we now invite them
for negotiations.
Negotiations ensued after a dispute has emerged.
7.4.1.2.
Negotiations
Negotiation was a mechanism for both dispute avoidance and resolution. It was viewed
broadly as entailing face-to face meetings where parties stated their cases, supported it with
evidence and discussed a way out of their differences. Phrases such as ‘bargaining with the
other side’, ‘engaging the other party', ‘parties resolving disputes by themselves’ and ‘settling
with the other side’, ‘no third party come between us’ were used to describe the negotiation
177
Chapter 7-Results of Data Analysis
process. It stood out that negotiations conducted after the emergence of disputes were often
formal and were undertaken by teams. For instance, CPE4 described the practice in an
implementing agency in the following words:
Most often, we get somebody from- mostly our engineers lead us to get somebody
who is best in negotiations and then we go round interviewing them and pick the best
and he will come and lead the team so we have our technical, our legal, our finance
sitting with him.
The practice of other agencies of the Employer was to use adhoc teams made up of
professionals such as quantity surveyors, engineers, contract specialists, and representatives
from the supervising Ministry, the A-Gs and MOFEP for negotiations. No single entity or
individual had complete control over the process and this often created problems with
coordination, cooperation and decision-making. Foreign contractors, on the other hand, were
often represented by company officials and their legal teams.
There was mutual willingness to cooperate to address disputes during the early stages.
Observations from CPW5, an interviewee from an Employer organisation and EP1
representing a foreign contractor are used to illustrate the cooperation and goodwill that
parties exhibited during negotiations. Speaking from the perspective of the Employer, CPW5
observed as follows:
The idea is that we here always believe that the contractor is working for our good so
we want to support them as much as possible to realize the project for us. At the end of
the day when they do a good job the people get water everybody is satisfied then we
are all moving on. So the principle is to assist them to do a good job for us and not to
have a kind of acrimony, fighting with them. So once you have this spirit you have an
open way of working. When you have a dispute and you are talking about it,
everybody knows that it is not because you are attacking personal interest but because
you want the good of the thing, so we try to sit down and look at it frankly and resolve
it rather than trying to look elsewhere. So that is normally what has helped us
(CPW5).
EP1, an interviewee representing a contractor involved with several major projects in Ghana
also commented on the cooperative approach in the following excerpt:
The people in Ghana are very friendly people, you see, very friendly people. You even
feel that the Employer is your friend because of the attitude and the smiling; you know
he is a friend. So it is not the hard line that you have over there where no one cares
about the next person. You do the job and that is it. It’s not like that. So because of
178
Chapter 7-Results of Data Analysis
this it’s very difficult for the contractors to take issue and they know that there is no
money and they know they are going to go through a lot of trouble and expense and
they will rather just let it go, if it really comes to that.
Thus, negotiations were characterized by reciprocity and consideration of the cost of possible
alternatives. Negotiations commenced with lower level organizations such as implementing
agencies, but were periodically escalated to the ministerial level and sometimes even to the
level of the Presidency. CPR1, describing the stages of engagement, stated as follows:
There are more or less two stages where amicable settlement is attempted after the
Engineers determination; the first attempt takes place at the level of the implementing
agencies and the second is at the Ministerial level. At the latter stage, the A-G’s
Department is notified and representatives from the Department become involved in
the settlement process at the ministerial level right from the onset (CPR1).
Throughout the interviews, amicable settlement and negotiation were used synonymously.
Parties attempted negotiations several times before any other dispute resolution mechanism
was considered. Majority of the 56 interviewees admitted that at one time or the other in their
experience, they had resolved a difference or dispute by negotiation.
The success of negotiation was attributed partly to the cordiality between parties to
disputes. There was a culture that promoted healthy relations between parties and encouraged
settlement. Though this culture was extra-contractual, its effect on dispute resolution was
visible. But the pervasive use of negotiations was not only due to its effectiveness but also
lack of knowledge and training in the use of other DRMs (see section 7.5). CPW 5
commenting on the widespread use of negotiation stated as follows:
So once that works for us now why not use it because if you go to try something else
and you don’t know much about it… but we must also be frank that may be we need
more training to deal with these things. More exposure should be given to people who
handle projects regarding some of these other opportunities or other alternatives. I
don’t have the alternatives. If I have it, probably I may want to use it, but so far as
negotiation is working for us I think we can use it.
Again, negotiations were not always cordial. The cooperation that characterized
negotiations sometimes gave way to brinkmanship. There were instances where parties
resorted to threats when negotiations over disputes became difficult and intractable.
Recounting his experience with an on-going project, CPR5, for instance, stated as follows:
179
Chapter 7-Results of Data Analysis
The contractor is still not satisfied, so it has written for a final decision on the matter
before it goes to arbitration. So we are preparing that final decision to be given to
MOFEP to convey to the contractor our position. If they are still aggrieved, then they
can go to arbitration. The contractors are also very careful. Sometimes, their resorts to
arbitration are threats, not real. They may not carry it out because there are other
issues. Negotiations may border on the issues at stake but there could be other external
issues to be discussed at that high level. What is the next step from here? You are in
this country to do business. Is it the end of story? The contractor may be implored to
consider other assistance he has received from the State previously, the future
opportunities. These factors may also come into play outside the technical issues to
arrive at an amicable resolution; if those [implorations] fail, then of course arbitration.
Usually when negotiations involving foreign contractors and representatives of the Employer
broke down, the next step was international arbitration.
7.4.1.3.
International Commercial Arbitration
International commercial arbitration (ICA) was the preferred choice of dispute resolution
for foreign contractors (see sections 4.4). The absence of a database and issues of
confidentiality made it impossible for an accurate quantitative assessment to be made of how
many disputes ended up at international arbitration each year. For similar reasons it was
difficult to have an overall picture of what kinds of disputes often ended up at ICA or how
much, in terms of cost, the Employer had incurred in participating in ICA proceedings. Again,
there was no database on how long these cases took to resolve at ICA. This study therefore
relied on the qualitative data obtained through interviews to address some of these issues. The
result of the analysis of the data on the sub-category called ICA is divided into five parts
namely: (i) selection and use of ICA by parties; (ii) cost and ICA; (iii) delay and ICA; (iv)
perception of bias versus playing victims; and (v) other perceptions.
7.4.1.3.1.
Selection and use of ICA by parties
Factors which influenced the selection of DRMs have already been presented under section
7.3.2.3.
For ICA, the primary factor accounting for its use was funding requirements.
Questions were hardly raised about the suitability or otherwise of ICA as a dispute resolution
mechanism. This outcome was in keeping with the observation of Capper and Bunch (1998)
that suitability of ICA is hardly examined by parties using the mechanism. Asked whether the
180
Chapter 7-Results of Data Analysis
Employer considers the suitability of ICA for specific projects during contract negotiations,
CPA 5 responded as follows:
[I]f we don’t accept international commercial arbitration (ICA) which one will we do
[accept]. That is also another problem if we say we don’t want ICA, which one do
you want and if you are not ready with something like that then why would you go and
stick out your neck (CPA 5).
Regardless of the nature of the transaction in question, ICA remained a constant part of most
Conditions of Contract. During contract negotiations, the issue for negotiation was not
whether ICA was suitable but where the arbitration was to take place, the number of
arbitrators and how they were to be appointed, and the institution to administer the arbitration
(see section 7.3.2.3).
7.4.1.3.2.
Cost and ICA
The literature pointed to cost of ICA as one of the generic concerns about the dispute
resolution mechanism (see section 4.4.1). For an Employer with a relatively small economy
which relied heavily on external funding, the cost of ICA was an important issue. Fifteen
interviewees with personal encounters with different ICA processes shared the view that ICA
proceedings were expensive. CPA3 had been involved in at least four major international
arbitrations and his verdict on the process in terms of cost was that, ‘they were all very
expensive’. CPA4, who had also been involved in a number of arbitrations opined as follows:
they will say they need a neutral ground so we have to go to UK or some western
country and because their laws are different we need to engage a lawyer there and you
know, it’s not easy; it’s expensive.
CPA5 in a similar situation as the earlier interviewees stated, ‘I mean we are in all sorts of
arbitrations and they are so expensive’. CPE5, an engineer with experience in ICA
commenting on the cost stated as follows:
Typically it is supposed to take three arbiters and then (you pay them). These are
international lawyers that you are talking about, international judges… they were thus
expensive. You go and hire all those venues so it was expensive... Our lawyers in
London were doing all those things and were passing them [the cost] on to us; huge
costs.
CPR1 also asserted,
181
Chapter 7-Results of Data Analysis
[i]international arbitration is very expensive. All the hype about cheaper resolution at
arbitration is unfounded. As a party, you may end up paying administrative cost which
may be able to settle the dispute itself.
Costs associated with ICA identified by interviewees included lawyers’ fees, arbitrators’ fees,
cost of venues for arbitration and other administrative costs. There was also the cost of
travelling, accommodation and upkeep of representatives of the State and witnesses. Attempts
to get specific figures on spending regarding international arbitration were unsuccessful. As
an indication, figures from MOFEP revealed that between May, 2007 and February, 2010, the
Employer paid nearly US$ 2 million as professional fees in a single construction arbitration
involving the State. The views on cost of arbitration indicates that Asouzu’s (2001) findings
regarding the cost of ICA in Africa still remain true nearly a decade and half on.
However, there were no indications that the issue of cost was considered (as a matter of
policy) during contract negotiations. For instance, when asked if cost was one of the factors
considered during contract negotiation, CPA 1 responded as follows:
‘We don’t really think of the costs when it comes to going to the arbitral tribunals.
Then we realize that this thing is expensive, because arbitration is expensive. But you
don’t think about it when you are drafting your … [interviewee begins a new
sentence] May be now we will.
7.4.1.3.3.
Delays
ICA was slow and time consuming. The views of four interviewees in particular (three
from the Employer’s side and one adjunct professional representing a foreign contractor) sum
up the general view of other interviewees on ICA and delays. When asked about some of the
challenges with ICA in practice, APB1, currently representing foreign contractors involved in
construction arbitration, stated as follows:
International arbitration is not fast, it’s not quick...If anybody said it was going to
shorten the dispute, the person lied. It is not. We are doing one and we’ve been
pleading for two years. Pleading will close in 2013. We are addressing the arbitral
panel next year. Now if that case had gone to trial in Ghana, we would have been done
with the High Court hearing in a year or two but pleadings are not going to close till
next year and the first hearing is in [month withheld] next year. So you would realize
that… arbitration seems to get all the attention. But it is time consuming and it is
expensive.
182
Chapter 7-Results of Data Analysis
In the experience of APB1, litigation in Ghana compared favourably to ICA as far as speed is
concerned. Another interviewee, CPE 1, currently involved in international arbitration at a
destination in Europe intimated that just preparations for hearing at the arbitration alone have
taking two years. CPE5 asserted that an ICA process in which he was involved took over ten
years to complete. Asked why this was the case, CPE 5 responded as follows:
Because that is the sheer time they just take, I mean you go and book an appointment,
you arrange to meet and it is not typically saying we will meet at 9:00am; we will
meet in three months’ time, we will meet in five months’ time, that kind of thing. They
have all the time in the world that they want.
According to CPA 3, none of the four international arbitrations he was involved took less than
two years to complete. So he wondered, ‘what is there about arbitration that people think is
better than litigation? And it is the same long processes’.
7.4.1.3.4.
Perception of Bias versus Playing Victims
The interviews were replete with different expressions of how unfavourable and unsuitable
ICA had been to the cause of the Employer over the years. For some interviewees, the
Employer had a culture of losing ICA and this made it unsuitable. For instance, when asked
about the effectiveness of ICA as a dispute resolution mechanism for the Employer, CPA5, a
dispute resolution professional with the Employer observed as follows:
It [ICA] hasn’t helped us all these years. It hasn’t helped us. It has only wasted plenty
of money. I don’t really see who it is benefitting, apart from paying all that the people
[the contractors] say we owe them all the time. Then we have to pay the arbitrator’s
fees. We have never won any substantial…[interviewee begins a new sentence] Only
grand total of one I remember we have won properly so to speak. Which one else have
we won? I can’t remember which of them we won. Being within the ... [name of
entity], I keep hearing of them most of the time. They are still on-going. CP what did
we get? We just got huge sums of money [debts]. We didn’t win any substantial
victory. The people rather got money out of us.
Although from other interviews, the government had won some previous cases on arbitration,
the views of CPA 5 conveyed the frustration with the consistent poor performance of the
Employer when it comes to international arbitration. If ICA was meant to achieve a fair and
balanced dispute resolution, then in the experience of many interviewees affiliated to the
Employer, this was not the case (CPR3 and CPR8). CPR 3, recounting his own experiences
183
Chapter 7-Results of Data Analysis
with two ICA hearings, concluded that the process was aimed at embarrassing the Employer
and persons affiliated to it. He remarked as follows:
People who come there (Arbitrators) have already made up their minds; you are only
wasting your time travelling all the way there and so on. You are wasting your time;
they’ve already made their minds.
The above narration on perception of bias essentially confirms the findings by Asouzu (2001)
that there is a strong perception that ICA does not favour African States.
But there were contrary views which attributed the perennial lack of success in ICA
proceedings to the Employer’s ill-preparation. These views, championed by CPW11 and
APL, asserted that regardless of the generally negative perceptions against ICA, it still had
positive sides to it. They argued that as compared to the other mechanisms such as litigation,
arbitration was swifter and less costly depending on how it was conducted. In their opinion,
the problems that the Employer had with ICA stemmed from lack of knowledge and expertise
and ill-preparation. To them, the perception of bias held by many was a reflection of the
culture of ‘victim play’.
7.4.1.3.5.
Other Perceptions about ICA
Beyond the issues of cost, delays and perception of bias, it was found that contractors who
served notices of arbitration and pursued their disputes using international arbitration were
more likely to be excluded from future government contracts than others. In such cases, ICA
came across as ultimately destroying relationships. There were also indications that
involvement in ICA was viewed as bad international publicity for the State. It exposed the
country to ridicule and served as a disincentive not just to contractors but to investors seeking
to do business in Ghana.
7.4.2.
DRMs Rarely used
There were other DRMs agreed by parties which were rarely utilized in practice. Examples
of these DRMs are DABs, mediation and Expert Determination.
184
Chapter 7-Results of Data Analysis
7.4.2.1.
Dispute Adjudication Boards
DABs were introduced to the Ghanaian construction industry through the World Banks’
use of the FIDIC Red book, 1999. Though there was evidence that this FIDIC Condition of
Contract was in use in Ghana as far back as 2004, knowledge of DABs was sparse and
superficial. When asked whether in his experience his organisation has used the DAB process
before, CPR4, head of an implementing agency, answered, ‘no, up to date, no’. The responses
of interviewees with other organisations to similar questions were the same. Under the
construction contract signed in 2004 which incorporated provisions on DAB, the parties failed
to set up the required DAB. This issue did not come up until disputes emerged and the parties’
initial attempts to resolve them failed. CPR1 summed up what happened in the following
excerpt:
The DAB should be set up at the beginning of the Project. But in practice, it is not
often done. In the ... Project, for instance, the DAB was not set up until the Contractor
exercised his rights to terminate. The danger with the DAB not being set up at the
beginning of the project is that, the DAB did not have the opportunity to deal with
emerging disputes. Eventually, the parties agreed to set up the DAB. However, before
this was done, the disputes were settled.
The story of CPR1 was corroborated by CPR 10 who was involved with the project in issue.
Three reasons were offered for the rare use of DABs. Firstly, the DRM is relatively new.
Knowledge on how it operated and its advantages were now being acquired by parties.
Secondly, failure to set up DABs on projects which agreed to use them was attributed to sheer
inadvertence on the part of officials with that responsibility. Therefore, it took some further
prompting to get the DABs set up.
Finally, the few occasions on which the issue of setting up the DAB had come up, parties,
especially contractors had been reluctant to do so. Spending on the board prior to the
occurrence of any dispute has been a difficulty for most contractors. APE cited an instance
involving a Government agency where a three-member DAB set up at the beginning of the
project was disbanded after two site meetings. The foreign contractors (a joint venture)
185
Chapter 7-Results of Data Analysis
responsible for the board’s expenses objected to further attendance by the DAB, insisting that
there was no need. It is worth noting that there was no indication at all of the use of Dispute
Review Boards in the construction industry in Ghana. However, there was evidence of
regular use of adjudication but this was in relation to minor domestic contracts.
7.4.2.2.
Expert Determination/Independent Experts
Few agreements were sighted which mentioned expert determination as an intermediary
process before ICA. Apart from one agreement from the road sector, most of the discussions
on the use of expert determination related to the energy sector. Interviewees from the sector
confirmed the use of expert determination (sole experts/independent experts). CPE 2, for
instance, attributed the use of sole experts to the specialised nature of the subject matter of
agreements in the energy sector and the fact that issues for resolution were often of a technical
nature and thus required someone with a specific expertise.
On how often this DRM was used, only CPE1 attempted to volunteer information on the
subject. The interviewee indicated that a sole expert has been used only once during the last
decade by the Employer. For reasons of confidentiality, details of this singular experience
were not disclosed.
7.4.2.3.
Conciliation and Mediation
Negotiation, mediation and arbitration were by far the best known DRMs in Ghana.
Mediation and arbitration had received statutory endorsement under Act 798. However, unlike
negotiations and arbitration, mediation and conciliation were rarely used in the construction
industry in Ghana especially in relation to major projects. Most of the construction
agreements sighted did not expressly name mediation and conciliation as DRMs to be used.
There were three instances encountered where mediation and conciliation were attempted.
Firstly, CPR 4 recounted a situation where EU appointed conciliator was able to resolve
disputes which had emerged between parties to an EU sponsored project in Ghana. This was
186
Chapter 7-Results of Data Analysis
because the EU Conditions of Contract which the parties had utilized listed conciliation as
one of the dispute resolution mechanisms. CPE 5 also narrated his experience with mediation
of a dispute which arose from a $120 million dollar project involving a State agency and a
well-known international equipment supplier. He observed as follows:
They sued us [commenced arbitration against the agency] and we also put in a
counter-claim. After negotiations, the case went to arbitration. When we got to
arbitration they decided that we should go and do mediation. So we started with
mediation but we did not get very far because when we started all the parties held
entrenched positions and nobody wanted to move so we stopped and went back to
arbitration.
Series of mediations took place in London, Brighton and New York but were unsuccessful.
Therefore, the parties returned to ICA. The final example of mediation related to the
Waterville Case (see section 7.3.2.4).
A company which had its construction contracts
abrogated six months into the transaction by the Employer invoked the mediation clause in
the agreement. The parties agreed to appoint a local mediator to help resolve the disputes. The
mediation was successful.
However, the Supreme Court subsequently declared the
construction contract in issue void on grounds of unconstitutionality thereby impliedly
rendering the mediation process a nullity (see section 8.4.3).
Notwithstanding these examples, the use of mediation in the industry was rare. The views
of some individuals involved directly with dispute resolution in the construction industry were
generally dismissive of the use of mediation and conciliation. In their opinion, conciliation
and mediation were mechanisms often used when dealing with worker's rights and not major
construction disputes. The following statement of CPA1 exemplified this view:
Conciliation and mediation normally are things that are used when you are dealing
with persons; when you are dealing with workers. When you are actually dealing with
contracts - the types that you are looking at - we don’t use those things. I have never
seen those mechanisms here [in Ghana] unless you have a portion that deals with how
to deal with workers’ rights and things like that. But when it comes to the actual
construction contract and the terms in there and issues that you have to deal with,
invariably, the dispute resolution mechanisms are those in the FIDIC. We use the
FIDIC dispute [resolution] format. So invariably conciliation and mediation they don’t
really play (CPA1).
Elaborating on the above statement further, CPA 1 added:
187
Chapter 7-Results of Data Analysis
Can you imagine doing mediation in respect of a dispute we have on a road that a
contractor had messed up? The terms of his contract have not been dealt with [he has
not complied with the terms of his contract] and then you say you are going to
mediation? The most we can do is to negotiate. If you negotiate and it doesn’t work
you go straight to an expert and from there international arbitration, but conciliation
and mediation in construction, I don’t know. I don’t think, because you need
somebody to come to a conclusion and tell you that this is it. The non-binding, I am
not comfortable with that when it comes to construction (CPA1).
Another interviewee, CPA 4 described the general approach to dispute resolution in relation
to infrastructure projects as excluding the intermediary mechanisms such as mediation and
conciliation. CPA4 observed as follows:
It depends on the language and the text [construction contract]; if the Agreement does
not say so and invariably most of them that I have seen they start with good faith
negotiations and if those negotiations fail, they go to full blown arbitration. Most of
them don’t use the intermediary steps; it is not that common, you don’t see it.
Some interviewees such as CPA5 and APC wondered which experts in the country had
capability to handle complex construction conciliation or mediation. They doubted if the
foreign parties would be willing to use conciliation and mediation to resolve disputes which
involved substantial sums of money.
From the analysis, it stood out that amicable settlement was not considered as signifying or
pointing to the use of mediation or conciliation or any other intermediary mechanism; it was
all about negotiations. Dated views regarding the use of mediation and conciliation as DRMs
for minor disputes were prevalent. A statutory change equating settlements resulting from
mediation to arbitral awards (see section 82 of the ADR act, 2010, Act 798) was still yet to
change perceptions even among practitioners.
7.4.3.
DRMs not agreed by Parties but in use
There were two categories of DRMs which were found to be in use even though parties did
not expressly agree to use them. These were litigation and what is referred to here as informal
resolution mechanisms. How litigation was used in the context of infrastructure related
construction dispute resolution in Ghana has already been discussed under sections 7.3.3. The
use of informal resolution mechanisms took the form of intervention by political officeholders
188
Chapter 7-Results of Data Analysis
in the resolution of disputes. These interventions sometimes took the form of playing informal
mediatory roles (‘pseudo-mediation’). The practice of resorting to informal resolution
mechanisms has been discussed under section 7.2.2.2. This multifarious resolution process
was unregulated, often behind closed doors and therefore difficult to assess. They were not
captured in any literature or report. The quality of such resolutions was difficult to gauge as
they were often not based on the merits of the parties' cases. Figure 7.4 below provides a
summary of all the DRMs discussed above.
Figure 7.4: Dispute Resolution Mechanisms in use (Source: Field Data)
Significantly, the three DRMs regularly used in Ghana - the Engineer’s determination,
negotiations and ICA - were the same as the DRMs stipulated in the Conditions of Contract
commonly used in the industry, namely the FIDIC Red book, 1987. The implication is that
parties generally stuck to DRMs they agreed at the beginning of their contractual
relationships. Again, nearly a decade and half after the replacement of Engineer’s
determination with DABs under the FIDIC Red book, 1999, parties involved in constructionrelated infrastructure disputes in Ghana had not made that transition yet.
189
Chapter 7-Results of Data Analysis
7.4.4.
Procedure for Dispute Resolution
This section focuses on the procedure for dispute resolution prior to reference to ICA.
When disputes arose, the first point of call was the Engineer (see section 67 of the FIDIC Red
book 1987). The procedure regarding how engineers handled such disputes until a
determination is made is outlined under sections 7.3.6 and 7.4.1.1 above. Where the
Engineer’s determination does not resolve the dispute, representatives of the implementing
agency concerned would invite the representatives of the contractor to a series of meetings
aimed at resolving the pending dispute. When the initial meetings showed promise of
settlement, the process proceeded until a resolution was reached or disputed issues were
narrowed.
There were instances where discussions between the Employer's representatives and
contractors broke down very early due to entrenched positions. In such cases, contractors
proceeded to serve Notice of Arbitration. Where contractors were amenable to further
negotiations with higher officials of the Employer, additional negotiations ensued between
teams of the Employer and contractors prior to any engagement at ICA. Depending on the
nature of the dispute, the Employer’s team was constituted by a combination of experts from
the sector ministry responsible, the implementing agency involved (the Employer's
representative), the A-Gs, MOFEP and funding organisations. Implications of the
involvement of multiple organisations in the dispute resolution processes are discussed in
chapter eight.
Post-notice of arbitration negotiations often took place at the behest of the A-Gs. CPA 4
described the procedure in the following excerpt:
Once it [the dispute] is starting I think the MDAs do try to engage the contractors;
they try to see if they can settle but if the contractors are being difficult and are
making some outrageous demands then they [MDAs] will say okay you go ahead and
do whatever you want to do. Then they will call their bluff. Yes, so the Contractor
will then proceed to the tribunal by filing the notice of arbitration. They will serve
them [the MDAs] and then they will bring it [Notice of Arbitration] to the [A-Gs] and
190
Chapter 7-Results of Data Analysis
we will try and do some ... we will write to them [the contractors] and tell them
maybe, we want to look at it [the dispute] again, take a second look at it as lawyers or
that government has mandated us to look at the thing [dispute] and see if we can settle
the matter instead of going through the arbitration. In such cases, a team will be set up
and then we will try and see if we can resolve it.
The general dispute procedure presented in this study varied depending on the nature of the
dispute, the contractor involved and the MDAs responsible. Regardless of the dispute
procedural route taken, negotiation was the last step before full blown ICA. Figure 7.5 below
captures the different procedural routes currently in regular use.
ICA Pleadings and hearing
Further Negotiations break down
Consultation with
Sector Ministry
START
Contractor
Submits notice of
dispute under
Clause 67 of FIDIC
1987
No agreement
Resident Engineer
or Consultant
receives Notice of
Dispute and
attempts to
resolve issues
with contractor.
Notice escalated
to Engineer
Additional evidence of
dispute
may be requested
and received
Contractor serves
Notice of Arbitration
Notice of Dispute
is received by the
Engineer
(Government
Agency)
Resident
Engineer’s report
and Other
documents
examined
Formal Negotiation between Employer’s
team(sector Ministry, MOFEP,A-Gs, Employer’s
Rep. etc.) and Contractor
Preliminary Negotiations between Employer’s
Representative and Contractor
Determination
communicated
Contractor
Rejects Engineer’s
determination
Engineer makes its
determination on
dispute
Figure 7.5: Dispute Resolution Procedure (Source: Field data)
Using an adapted version of the dispute resolution step by Groton (1992) and Cheung (1999),
Figure 7.6 illustrates the dispute resolution trajectory as discussed in this chapter.
Intermediary mechanisms did not play a substantial role in the resolution process.
191
Chapter 7-Results of Data Analysis
International Arbitration
Di s
pu
ol u
es
r
e
tio
te
ou
nr
Adjudication/DAB/ Expert
Determination
t
Early Neutral Evaluation/ DRB
DRMs rarely used
Mediation/Conciliation
Series of Negotiations
Engineer’s Determination
Figure 7.6: Dispute resolution Route (Source: Adapted from Groton (1992) and Cheung
(1999) based on field data)
7.5.
Barriers to the Use of Alternative Dispute Resolution Mechanisms
Factors identified as inhibiting the use of intermediary DRMs in Ghana were categorized
into three classes namely, Employer-related, contractor-related and generic factors.
7.5.1. Employer-related barriers
In all, ten inhibiting factors directly associated with the Employer were identified (see
Figure 7.7 below). Five of the ten factors namely the Employer as a single largest client, the
threat of blacklist, lack of institutional cooperation, lack of expertise and sticking to old mindsets have already been examined (see sections 7.2.1.3, 7.2.2.1,7.2.2.2 & 7.4.2.3). Details of
the other five inhibiting factors namely lack of policy and guidelines on use of DRMs, lack of
stance on alternatives to ICA, public suspicion, failure of political leaders to take
responsibility for settlements and poor record keeping are now presented.
Firstly, the Employer had no policy and guidelines on the use of DRM on infrastructurerelated construction disputes. At the general level, Act 798 was passed to replace the
Arbitration Act, 1961 (Act 38). Although section 135 of the Act defined ‘Alternative Dispute
Resolution’ as ‘the collective description of methods of resolving disputes otherwise than
through the normal trial process’ only arbitration, customary arbitration, mediation, and
conciliation received attention. Apart from arbitration and mediation, none of the construction
192
Chapter 7-Results of Data Analysis
specific DRMs such as adjudication, DAB and Expert determination were specifically
provided for in Act 798. Again, there are no guidelines on the use of ADR by public
institutions. On the contrary, section 1 of Act 798 exempt disputes relating to subject-matters
of public and national interest from its purview (Mante and Ndekugri, 2012). Ten
interviewees from entities representing the Employer admitted that there was no specific
policy or guideline on the use of ADR by public institutions in Ghana. For instance, when
asked about the existence of such a policy, CPA 3, an experienced dispute resolution
practitioner with the Employer responded as follows:
No, not that I know of. Normally when you have a file and you think this is how I
want to go about it, you may put up a written memo to the AG, ‘this is what I want to
do and I think we can resolve this in this way’. So it goes up to the Solicitor-General,
to the AG and if they are okay with it, it will come back to you that go ahead so that is
normally what happens. We don’t have any policy guideline that you have to do a, b,
c. It has not really been done.
Whilst CPA 1 was of the view that such a policy was not the responsibility of his
organisation, CPR1 thought such a policy was not necessary. Dispute resolution as far as
CPR1 was concerned should be governed by precedent. However, other interviewees such as
CPA 3, CPA4, CPR4 and CPA5 were of the view that there was the need for such guidelines.
Recounting his experience with the use ADR, CPF1 observed as follows:
The AG attempted to settle some of the disputes so that we don’t go through the
expense but maybe we are all learning now. May be what we are to establish are
proper guidelines for settling any matter… With the benefit of hindsight now it is very
important that the case is made for the establishment of guidelines and procedures…
There is a need for the establishment of clear, well defined workable guidelines for
executing or administering ADR that did not go to the formally instituted bodies but
are done through conciliation and negotiation outside the formal forum. So that there
will be no allegations of bias and suspicion of corruption. Because when we were
doing this things [negotiations], when they brought the thing for me to comment, I
was doing it on top of my head, what I knew as the policy. But now we are …
[interviewee states consequences of the steps taken] because some people have alleged
that there was bias, collusion, and so on. But if we have had clear guidelines and a
checklist provided for reviewing such steps then we would have been seen to have
gone through all those at least. So that there will be no suggestion of collusion in
resolving this matters.
The above excerpt illustrates some of the difficulties public officials seeking to use ADR
encountered in the absence of guidelines.
193
Chapter 7-Results of Data Analysis
Secondly, the absence of clearly outlined guidelines for the use of ADR had also
heightened public suspicion regarding the use of ADR by workers of the Employer. Data
collection for this study coincided with a period of intense public outcry over debts that the
Government had incurred as a result of judicial decisions and arbitral awards against it for
various breaches (Daily Graphic, 2012; Daily Graphic, 2013). As part of these discussions,
many including Parliament questioned certain settlements that the Government had reached
with some construction companies (see Parliament of Ghana, 2012). CPA1, CPA3, CPA4 and
CPF1 variously observed that it was frustrating to use ADR in cases involving the Employer
because of public suspicion of corruption and collusion. There was less suspicion when
disputes were resolved by the courts or through international arbitration.
Thirdly, closely linked to the issue of public suspicion was the failure of key public
officials to take responsibility for settlements resulting from ADR use. Interviewees avoided
using ADR in practice because political superiors sometimes failed to take responsibility for
dispute settlements arrived through ADR methods which they had authorised. There were
instances where public officials giving evidence before the Public Accounts Committee of
Parliament attempted to dissociate themselves from settlements reached, creating the
impression that the use of ADR was improper (Parliament of Ghana, 2012).
Furthermore, the data analysis revealed a culture of poor record keeping. Records on
transactions were not properly kept and correspondences were not filed. The problem of poor
record keeping was widespread and systemic. Interviewees cited examples where use of ADR
had been thwarted by lack of information on transactions in dispute (CPA4, CPA3 and
CPR5). For instance, CPA4 described the state of record keeping at the various MDAs as
‘woefully inadequate’, ‘porous’ and ‘terrifying’ and observed that in some instances, the
Employer’s lawyers had to attend negotiations without the full complement of records of the
transactions. Invariably, contractors attended such settlement meetings with up to date
194
Chapter 7-Results of Data Analysis
records. Figure 7.7 below provides a visual summary of the Employer-related barriers to the
use of DRMs discussed above.
Figure 7.7: Employer-related Barriers (Source: Field data)
7.5.2. Contractor-related factors
For many contractors, avoiding any form of dispute with the Employer was the natural
response to the threat of blacklist. When disputes arose, the initial option was to resolve
amicably. For those who were involved in many projects or were entertaining the possibility
of securing future jobs from the Government, the strategy was that they served all required
notices, kept up-to-date record or evidence in support of claims, and continued to negotiate
with the Employer. In some cases, such lingering claims became bargaining chips for new
contracts. Even foreign contractors who were exposed to the workings of ADR such as
mediation in the construction industry elsewhere did not use such mechanisms.
7.5.3. Generic Barriers
Six generic inhibiting factors of ADR were identified from the data in addition to the
party-related barriers. These were: (i) the knowledge gap; (ii) the adversarial culture; (iii)
Negative perceptions/ Trust deficit for ADR; (iv) lack of ADR infrastructure and expertise;
(v) lack of information on use of ADR and success rates; and (vi) the extra expense argument.
The data on lack of ADR infrastructure has already been presented under section 7.3.3. These
factors are examined separately below.
195
Chapter 7-Results of Data Analysis
Firstly, lack of adequate knowledge of the various DRMs was pervasive. Promotional
activities largely centred on three main mechanisms namely Arbitration, Mediation and
Negotiation. These promotions were led mainly by private groups and the judiciary. Courtannexed ADR processes have been incorporated into the High Court (Civil Procedure) Rules C.I. 47. Consequently, judges at the commercial division of the High Court engaged in court
assisted mediation. Even so, lawyers were ill-prepared when it came to the use of ADR.
APB1 speaking of the knowledge of legal practitioners of ADR observed as follows:
Let me say that the level of understanding of ADR even by the Ghanaian lawyer is a bit
behind time so sometimes, it even depends on the firm that they [contractors] choose
because it’s the firm that might come out to say, you know what, don’t just rush into
arbitration, have this or the other as a pre-condition.
Training and promotional activities regarding the use of ADR to resolve construction disputes
were championed by professional bodies such as the Ghana Institution of Engineers (GhIE)
and the Ghana Institution of Surveyors (GhIS). However such activities also concentrated
mainly on the use of arbitration and contractual adjudication. APL, APT and APN,
interviewees with extensive experience in ADR teaching and practice were united in their
view that the problem of lack of use of ADR in the construction industry was due to lack of
sufficient knowledge of the range of dispute resolution mechanisms.
No database on the use of ADR mechanisms in the construction industry existed. No
known information existed on how often parties used ADR to resolve disputes from major
projects and the success rate. Parties to major projects could be encouraged by statistics
pointing to savings that others have made in using ADR, but this information did not exist.
The main reason proffered for the absence of a database was the issue of confidentiality and
privacy.
Secondly, the adversarial culture of the construction industry also acted as a barrier to the
use of ADR. There were instances where parties indicated that they litigated or arbitrated just
to prove a point. On this issue, CPR9 narrated his experience in the following words:
196
Chapter 7-Results of Data Analysis
I have known cases where you sometimes see that the contractor has put in a very bad
case and if he is to take it up further it could result in him falling out of the project. So
we go down that lane, for want of a better word, to make him look foolish.
Others avoided non-adjudicatory dispute resolution mechanisms because they could not trust
the other party to comply with terms of settlement.
Thirdly, ADR outcomes were viewed as less authoritative than judicial decisions or arbitral
awards. Whilst views from interviewees such as CPA3, CPA4, CPR 4, CPR5, CPR8, CPR9
and CPR10 supported ADR as a means of resolving construction disputes, there were others
who were sceptical. For instance, CPA1 was of the view that any mechanism that will not
render definitive outcome will not be useful to the construction industry.
Finally, ADR was viewed as adding a further layer of cost and time to the dispute
resolution processes. To proponents of this view, ADR outcome was hardly final and were
often challenged either in litigation or on arbitration. Commenting on why parties to
construction disputes in Ghana did not utilize the various forms of ADR, CPA4 and CPE1
observed that time spent on negotiation, mediation, dispute review boards and the other
intermediary mechanisms constituted additional time that will invariably be spent on a
binding process. Consequently, such processes merely prolonged the process of dispute
resolution.
7.6.
Summary
This chapter has reported on the findings of this study as encapsulated by the themes
‘features and context of parties to the dispute resolution processes’, ‘Procurement’, ‘the
dispute resolution processes’ and aspects of the theme ‘consequences’. Regarding the theme
on the nature and context of parties to infrastructure-related construction disputes, it was
found that the main parties were the State and its agencies (the Employer) and Foreign
Contractors. The Employer emerged as a complex entity which executed its actions under
197
Chapter 7-Results of Data Analysis
construction contracts through its agencies (sub-units). Each sub-unit is assigned a unique role
by law. The Employer’s performance of its obligations under construction contracts required
cooperation among its sub-units and coordination of their activities. This was often a
challenge as the unduly lengthy consultations and approvals led to delays in decision-making
and, in some cases, inefficiencies. Problems of the Employer were further exacerbated by
contextual factors such as human resource deficiencies, lack of specialisation, political
interference and the fear of blacklist held by contractors. Foreign contractors were often
cautious of how future dispute were to be resolved. They preferred international arbitration
because it offered them the options of neutrality, fairness and enforcement beyond the
jurisdiction of the Employer.
The legal framework for the resolution of infrastructure-related disputes was based on
contract. Funding for projects was accompanied by a requirement to use particular Conditions
of Contract which contained clauses on how disputes were to be resolved. Parties were
required to make their dispute resolution choices within the parameters of the dispute clauses
in the General Conditions of Contract and this was usually influenced by the nature and the
context within which the transactions took place. It was also found that the Employer neither
had guidelines for this process nor considered challenges with previous dispute clauses during
negotiation of new ones.
On the mechanisms for dispute resolution, it was found that parties regularly used
engineer’s determination, negotiations and international arbitration. They rarely employed
intermediary mechanisms such as DAB, Expert determination and mediation. Some of the
reasons for the lack of interest in intermediary mechanisms identified included lack of
adequate knowledge of these mechanisms, lack of policy direction and guidelines for their
use, negative perceptions about the use of ADR and the threat of blacklist. Intervention by
198
Chapter 7-Results of Data Analysis
politicians and litigation were examples of DRMs which parties did not expressly incorporate
into their contracts but which were in use.
199
Chapter 8- Discussions: Implications of Results and Remedial Strategies
CHAPTER EIGHT
200
Chapter 8- Discussions: Implications of Results and Remedial Strategies
CHAPTER EIGHT - DISCUSSIONS: IMPLICATIONS OF RESULTS AND
REMEDIAL STRATEGIES
8.1.
Introduction
In this chapter the results of the data analysis reported in the preceding chapter are
discussed. The chapter explores the consequences of the extant dispute resolution processes,
peculiar obstacles preventing efficient and effective resolution of disputes in the context of
major infrastructure construction and how such obstacles can be remedied. From the results of
the analysis, it can be deduced that the process of dispute resolution in the context of major
infrastructure construction projects in Ghana is a product of the interaction between the major
parties and the context within which they operated. The remedial strategies therefore took
account of the factors associated with the parties and their context which negatively impact
the extant dispute resolution processes and proposed ways to improve them.
8.2.
Evaluation of the extant dispute resolution processes
From the results of the data analysis, some of the problems that the extant dispute
resolution processes encountered included limited use of intermediary mechanisms (see
section 7.4.2), cost of dispute resolution (see section 7.4.1.3.2), delays (see section 7.4.1.3.3)
and party dissatisfaction with resolution outcomes (see section 7.4.1.3.4). A dispute resolution
process may be adopted for several reasons including speed, cost reduction, preservation of
relationships, confidentiality and parties’ satisfaction with the outcome (Cheung, 1999;
Gaitskell, 2006; Ndekugri et al., 2009; Blake et al., 2011). Its efficiency and effectiveness has
to be assessed relative to the extent to which the process achieves the desired goals (Tyler,
1988). Evaluating a dispute resolution process against these party expectations can be difficult
since most dispute resolution systems and procedures are not explicit on the precise objectives
parties have for establishing them.
However, the literature does provide some indicators for judging the efficiency of a dispute
resolution process (Constantino and Merchant, 1996; Smith and Martinez, 2009). Brett et al.
201
Chapter 8- Discussions: Implications of Results and Remedial Strategies
(1990) captures sufficiently the key evaluation criteria for an efficient and effective dispute
resolution process found in the literature. They outlined four factors which must be
considered when evaluating dispute resolution processes within an organisation:
(i) transaction cost - This is not just about money, but time and emotional energy
expended on the resolution process, the opportunities lost and resources wasted;
(ii) satisfaction with outcome - This has two dimensions; firstly, the extent to which
parties’ interests (needs, concerns and desires) has been catered for and secondly, the
extent to which the parties consider the extant system as being fair;
(iii) effect on relationships - The long term outcome or effect of the dispute mechanism in
use on the parties’ future relationship; and
(iv) reoccurrence of disputes - This can take three different forms – same disputes, same
parties; same dispute, different parties and different disputes, same parties.
Although Brett et al. (1990) provided these evaluation criteria in the context of dispute
resolution systems within organisations, they are useful in the context of this study as well
because the principles underlying the criteria presented entail key objectives for many a
dispute resolution process including those used in the construction industry.
In addition to assessing the efficiency of dispute resolution processes from the perspective
of the results they produce, other studies have focused on the elements of a dispute resolution
system which may signal the existence of an efficient and effective process. Smith and
Martinez (2009) have synthesised the principles from various dispute and conflict resolution
models (see Conbere, 2001 for a review of the models) into six key features that should be
present in every effective and efficient dispute resolution system. These are as follows:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
availability of multiple DRM options including both right-based and interestbased options;
freedom to move back and forth between the interest-based options and the
right –based options;
substantial involvement of stakeholders or parties in the design of the system;
voluntary participation, confidential process and the involvement of third party
neutrals;
transparency and accountability; and
education and training of stakeholders on the use of the system (Ury et al.,
1988).
The elements of an efficient dispute resolution system (Smith and Martinez, 2009) and the
criteria for assessing the output of such system (Ury et al., 1988) outlined above are merged
202
Chapter 8- Discussions: Implications of Results and Remedial Strategies
into a common framework for evaluating the effectiveness of the extant dispute resolution
processes. How do the extant dispute resolution processes measure up to the elements of an
efficient dispute resolution process identified above? How do the outputs of the extant dispute
resolution processes measure up in terms of transaction cost, impact on relationships and
satisfaction with outcomes? The following sub-sections examine the results of the data
analysis on the extant dispute resolution processes in the light of the elements of an effective
dispute resolution process identified from the literature. The evaluation begins with the
features of the dispute resolution system and concludes with and examination of the outputs.
8.2.1. Availability of multiple DRM options
Although Conditions of Contract in use in Ghana invariably contained multiple DRMs,
these were largely limited to the Engineer’s determination, amicable settlement (construed
generally as negotiations) and international arbitration (see section 7.4.1). The first and the
third options (engineer’s determination and international arbitration) were right-based whilst
the second option, negotiation was the only interest-based option.
The dispute resolution literature from developing countries particularly, Africa provides
justification for the reliance on international arbitration. Asouzu (2001) considered litigation,
conciliation, mediation and international arbitration in the African context and concluded that
international arbitration is the most suitable dispute resolution process. Other authors such as
Asante (1998), Sempasa (1992) and Cotran and Amissah (1996) hold similar views (see
section 4.2). Asouzu (2001) dismissed litigation on the basis of the lack of trust in national
courts. Mediation and conciliation were dismissed on the basis that they cannot be relied on to
achieve binding and internationally enforceable decisions. To Asouzu (2001), therefore, the
most plausible mechanism for resolving international commercial disputes in developing
countries, particularly Africa, is international arbitration. Whilst Asouzu’s (2001) arguments
may be cogent, his approach to dispute resolution appears to discard all other DRMs as
203
Chapter 8- Discussions: Implications of Results and Remedial Strategies
unsuitable. These conclusions treat the various dispute resolution mechanisms as mutually
exclusive; but they are certainly not.
In the context of construction dispute resolution, the use of multi-tiered DRMs is a
common phenomenon (Gaitskell, 2005; Gaitskell, 2006). There is scarcely an author on
dispute resolution in the construction industry in the developed world who does not
acknowledge the varied dispute resolution options available today apart from arbitration.
Majority acknowledge the usefulness of other DRMs (see e.g. Fenn et al., 1997; Levin, 1998;
Gould, 1999; Hibberd and Newman, 1999; Gaitskell, 2005). The results of the data analysis
(see section 7.4) confirm that multiple DRMs were used in the resolution of construction
disputes in Ghana.
The problem with infrastructure-related construction dispute resolution in Ghana was the
over-reliance on limited number of DRMs and the failure to use intermediary DRMs such as
mediation, conciliation, DRBs and DABs. The implications of this failure was that most of the
opportunities and benefits that the use of intermediary processes could have brought such as
cost reduction, speedy settlement and parties’ control over the resolution process were lost
(see Blake et al., 2011). Relying exclusively on negotiation, Engineer's determination and
international arbitration means parties failed to operationalize clause 67 (2) of the FIDIC Red
book, 1987 on amicable settlement which offered them the opportunity to explore and utilise
intermediary mechanisms such as mediation, DRBs and DABs. For an Employer who was
dissatisfied with international arbitration, the use of intermediary mechanisms could add
additional buffer to existing efforts at dispute resolution prior to international arbitration. This
would also provide the Employer the opportunity to participate in the crafting of solutions to
disputes. Some right-based intermediary mechanisms such as DAB provide an opportunity
for parties to assess the viability of their claims and weigh the likely prospects of success on
arbitration. DABs provide the additional advantage of proximity to the physical project site
204
Chapter 8- Discussions: Implications of Results and Remedial Strategies
and therefore offer a real prospect of cutting down cost of dispute resolution.
8.2.2. Freedom to move back and forth between Mechanisms
There was evidence that in some instances parties had the freedom to move back and forth
between the interest-based dispute resolution options namely negotiation and mediation and
the right-based options (Engineer’s determination and international arbitration) (see section
7.4.2.3). The issue here is that parties’ options in terms of right and interest-based resolution
mechanisms were limited.
8.2.3. Substantial involvement of Parties in the design of dispute system
The actual parties to major construction transactions had little influence over the process of
dispute resolution system design. Funding institutions nominated Conditions of Contract for
projects, which in turn, contained the dispute clauses (see section 7.3.2). The involvement of
the actual parties to construction contracts in the selection of dispute resolution mechanisms
was limited to providing project specific details to operationalise mechanisms already
provided in the Conditions of Contract (see section 7.3.2.3). Very little effort was invested in
evaluating dispute clauses in terms of parties’ dispute resolution goals, incentives for use, the
cost of operationalizing them and the outcomes in terms of expeditious results and party
satisfaction (see Smith and Martinez, 2009).
8.2.4. Voluntary participation, confidential process and involvement of third party
neutrals
The resolution processes were confidential but, there were issues regarding voluntary
participation of parties and the involvement of third party neutrals. Fear that contractors who
pursued dispute resolution processes against the Employer risked being blacklisted was
widespread (see section 7.2.2.3). The implications of this phenomenon are considered under
section 8.3.3.4.3. Suffice it to state that voluntary participation in dispute resolution was
stifled by this phenomenon.
205
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Regarding the use of third party neutrals, the only time that neutrals were introduced into
the dispute resolution processes was at the stage of international arbitration or litigation. The
Engineer was hardly a third party neutral in the Ghanaian context (see section 7.4.1.1). The
implication of the absence of third party neutrals at the early stages of the dispute resolution
processes was that issues festered and developed into intractable disputes before there was
any opportunity for a third party to explore them objectively. Insights that early use of third
party neutrals would have provided to enable parties to consider their interests, rights and
options objectively were all lost.
8.2.5. Transparency and accountability
Further, some aspects of the dispute resolution processes lacked transparency and
accountability. There were indications that some parties who failed to settle disputes through
negotiations and yet were reluctant to proceed to international arbitration found solace in the
use of informal mechanisms such as appealing to politicians (see section 7.2.2.2 and 7.4.3).
The main challenge with the use of informal dispute resolution mechanisms was lack of
transparency, formality and accountability. It was impossible to tell whether Government
officials intervened in disputes for personal gain or in the national interest. It was difficult to
quantify how much was lost or gained when political superiors instructed employees of the
State to compromise on a dispute and settle.
8.2.6. Education and training
Whilst parties to major projects appeared conversant with negotiation, Engineer’s
determination and international arbitration, there was evidence that most of them had
insufficient knowledge of other dispute resolution mechanisms such as DRB, DAB,
construction dispute mediation and conciliation, early neutral evaluation and expert
determination (see section 7.5.3). There were indications of sporadic training of practitioners
and parties in the use of dispute mechanisms but there was lack of systematic and continuous
206
Chapter 8- Discussions: Implications of Results and Remedial Strategies
education and training. The implication was that parties stuck to dispute mechanisms they
were comfortable with. International arbitration was handled by appointed professionals.
How did the features of the extant dispute resolution processes affect their output? Brett et
al.’s (1990) four factors outlined earlier (see section 8.2) namely transaction cost, party
satisfaction, effect on relationship between parties and the re-occurrence of disputes are used
to briefly examine the outcomes of the extant dispute processes as revealed by the data
analysis.
8.2.7. Transaction Cost
The outcome of the data analysis pointed to the existence of costly dispute resolution
processes. Though quantitative data was not available to back this claim, the qualitative data
on international arbitration, for instance, pointed to an expensive (see section 7.4.1.3.2) and
time consuming (section 7.4.1.3.3) process. Though there were positive comments about the
effectiveness of negotiation as a dispute mechanism, there were clear indications that lots of
efforts and time went into the process as they were often repeated at different levels of the
Employer’s organisational structure. Further research will be required to determine the cost of
negotiations in the context of construction dispute resolution.
8.2.8. Satisfaction with Outcome and Party relationships
Regarding parties’ satisfaction with outcomes of the dispute resolution processes, both the
Employer and contractors were satisfied with negotiated outcomes (see section 7.4.1.2). There
was, however, marked difference between the satisfaction levels of the Employer and
contractors in the case of international arbitration. The Employer was mostly dissatisfied with
international arbitration outcomes (see section 7.4.1.3.4). The consequence of the
dissatisfaction with outcomes of international arbitration was that relationships between the
Employer and Contractors who used the resolution mechanism were destroyed leading to loss
of future jobs from the Employer (see section 7.2.2.3).
207
Chapter 8- Discussions: Implications of Results and Remedial Strategies
In sum, limited dispute resolution options, lack of substantial involvement of parties in the
design of the dispute resolution system, threats to voluntary participation and limited
utilisation of third party neutrals affected the efficiency and effectiveness (the realisation of
satisfactory outcomes and party objectives) of the dispute resolution processes. Additionally,
lack of education and training of stakeholders on the use of dispute mechanisms impeded
effective utilisation of the arrangements for dispute resolution contained in Conditions of
Contract. Consequently, the extant dispute resolution processes were characterised by high
cost (see section 7.4.1.3.2), low parties’ satisfaction with outcomes (see sections 7.4.1.3.3)
and destruction of relationships (section 7.4.1.3.5). To deal with the challenges of the current
dispute resolution processes, there was the need to explore the factors which accounted for the
existing dispute resolution processes.
8.3.
Factors Accounting for the Extant Dispute Resolution Processes
From the results of the data analysis, the dispute resolution processes discussed under
section 8.2 were the product of the nature of the parties involved in infrastructure
procurement, the context within which they operated and their responses to the context. A
number of specific factors which have shaped the dispute resolution processes were identified
in chapter seven. These factors included dispute resolution preferences of foreign contractors,
external funding requirements, the complex structure and operations of the Employer and the
human resource problems of the Employer. Political interference, threat of blacklist and the
legal framework for procurement and dispute resolution were the other factors which have
shaped the existing dispute resolution processes. The repercussions of the enumerated factors
on dispute resolution can be seen from three different perspectives namely, dispute
occurrence, dispute resolution system design and the workings of the dispute resolution
processes.
208
Chapter 8- Discussions: Implications of Results and Remedial Strategies
8.3.1. Foreign Contractors and the dispute resolution processes
The nature of foreign contractors had implications for how disputes were resolved. Unlike
domestic contractors, foreign contractors were subjects of different States and did not
consider themselves as natural beneficiaries of the protection of the Employer as a sovereign
State. Indeed, to the foreign contractor, the Employer was an adversary, particularly in the
context of dispute resolution. Consequently, having an effective and efficient mechanism for
dispute resolution was an important consideration. Not only was the process required to be
effective, it was also expected to be fair and neutral. Hence, the preference for international
arbitration in construction disputes. This dispute resolution preference of foreign contractors
was invariably reflected by Conditions of Contract nominated by funding institutions.
8.3.2. Influence of funding requirements on Dispute System design
In theory, employers and contractors can select, negotiate and adopt any dispute resolution
process they deem appropriate (see Photo Production Ltd v. Securicor Transport Ltd [1980]
1All 556 at 566 HL). They may make provision for the resolution of future disputes in their
construction contract or agree on a suitable mechanism when a dispute arises by entering into
an agreement to submit such dispute to a particular resolution process (Redfern, 2004).
Instances of the second approach are rare because at the time a dispute occurs, parties may be
too incensed with each other to sit down and select a suitable mechanism to resolve that
dispute. Hence, in major construction transactions involving the Employer and foreign
contractors, the process by which future disputes were resolved were pre-ordered. This made
the contract formation process a crucial factor to dispute resolution. Consequently, entities
concerned with future dispute resolution found it expedient to influence the contract
formation process. The influence of funding institutions on the contract formation process and
contract negotiation has already been examined (see sections, 7.3.2.1and 7.3.2.3). Clauses on
dispute resolution in the FIDIC Red book were not the type which the parties could change at
209
Chapter 8- Discussions: Implications of Results and Remedial Strategies
will. Such clauses reflected choices of funding institutions on dispute resolution and could be
substantially modified only with the permission of such institutions (see World Bank, 2011,
p.21). Consequently, not much room was left for parties to alter the General Conditions on
dispute resolution. The limited changes or additions that parties were able to make to dispute
clauses were examined under section 7.3.2.3. Notably, there were no indications at all that
parties provided details of what they were to do or the mechanisms they were to use during
the amicable settlement period. It was therefore not surprising that in practice, the period of
amicable settlement was viewed as a period for further negotiations. For the Employer,
concerns with dispute resolution such as cost, speed, effectiveness of process and impact on
relationships (see section 8.2) were all scarcely considered.
Dispute clauses were agreed as a matter of practice and not out of deliberate policy to
address previous dispute resolution concerns or to achieve a specified dispute resolution
objective. In effect, contract negotiations on dispute clauses merely served the purpose of
enabling parties to agree on project specific details regarding how to implement dispute
mechanisms prescribed in the General Conditions. There was limited opportunity for parties
to consider the viability or suitability of other mechanisms. It was therefore not surprising that
the dispute resolution mechanisms mostly used by the parties were the pre-determined options
contained in General Conditions of Contracts.
Whilst acknowledging the existence of some limitations on the parties’ ability to alter the
dispute resolution structure prescribed by funding organisations, it is argued that parties failed
to explore possibilities to improve the dispute resolution system design. The contract
formation process is a creative process. As Poole (2012, p.13) noted, ‘it does not merely
provide the means of resolving disputes which may arise when certain events happen: it
provides the mechanism whereby things can be made to happen’. Beyond agreeing on the
prescribed dispute resolution mechanisms, the institutions to administer them, venue, rules
210
Chapter 8- Discussions: Implications of Results and Remedial Strategies
and the governing law, parties can still do more to order the dispute resolution processes in
such a way as to achieve optimal results through less costly and timely procedures without
violating requirements of funding organisations (see Scott and Triantis, 2005). Parties can
agree to adopt or modify existing rules regarding cost, venue, rules, and other procedures
currently contributing to cost and delays.
A number of other steps can be taken to improve the quality of the dispute resolution
system design. For example, during negotiations, parties can agree on how and where they
will want witness statements or evidence to be taken even though the seat of Arbitration may
be elsewhere. Parties can also agree on issues of cost and determine how it is to be shared.
Parties can agree to use specific dispute resolution mechanisms during the period for amicable
settlement. In essence, the contract formation process can be used to manage and shape the
dispute resolution processes at the back-end without offending the rules prescribed by funding
organisations. At the moment, this is not the case. For the Employer, the impression created
that the structure for future dispute resolution is imposed by third parties has created a sense
of lack of ownership of the structure. Consequently, with the exception of the dispute
mechanisms which were administered by entities under it (e.g. Engineer’s determination) or
those it had some control over (e.g. negotiation), the Employer’s approach to the use of
mechanisms under the current dispute resolution arrangement in practice, has been pedestrian
at best.
However, the Employer’s attitude to dispute resolution in practice has not only been down
to lack of opportunity to contribute to the dispute resolution system design. The very nature
of the Employer, the actions of its sub-units and the context within which they operated also
contributed negatively to the dispute resolution system design and the dispute resolution
processes (see section 8.3.3.3).
211
Chapter 8- Discussions: Implications of Results and Remedial Strategies
8.3.3. The Employer as a Monolith
The Employer, like the contractor, is considered as a single unit. This consideration
sometimes takes for granted the structure and the operational mechanisms of the State. As
demonstrated under section 7.2 above, the State consisted of several organisations. Each
entity played different but crucial roles in the performance of the contractual duties of the
Employer (see section 7.2.1.3). No single entity could exercise all the powers of the Employer
at any given time without consulting or seeking the approval of other organisations. Unlike
private sector Employers, the State operates an elaborate legal system which determined the
functions of each sub-unit and consultations and approvals necessary.
Consequently, the Employer’s performances under construction contracts naturally
suffered delays due to the complex nature of its decision-making processes. For instance,
section 65 of the Public Procurement Act, 2003 (Act 663) and clause 8 of the 1999 FIDIC
Conditions of Contract for building and engineering works (the Red book) provide timetables
for the execution of written contracts and commencement of works respectively. For major
construction projects such as those which were the subject of this study, parliamentary
approval under Article 181(5) of the Constitution was required (see section 7.3.2.4). A
contract signed in compliance with the timetable under section 65 of Act 663 remained
unenforceable until parliamentary approval was obtained. Similarly, any commencement of
work pursuant to the default position under clause 8 of the 1999 FIDIC Red book prior to
Parliament’s approval of such transactions was void (see A-G v Faroe Atlantic Company
Limited [2005-2006] SCGLR 271). Thus, the demands of the legal system of the Employer
necessarily prolonged timeframes for decision-making by the Employer and this had
implications for its responsiveness to dispute situations.
The Employer’s ability to perform its roles under construction contracts efficiently and in a
timely manner were also negatively affected by other contextual problems such as lack of
212
Chapter 8- Discussions: Implications of Results and Remedial Strategies
effective cooperation and coordination among its sub-units (see section 7.2.1.3), human
resource deficiencies (see section 7.2.2.1) and internal turf wars. There were also the
difficulties posed by political interference in the process of infrastructure procurement and
dispute resolution (see section 7.2.2.2) and the fear of being blacklisted (see section 7.2.2.3).
Implications of the above-listed contextual problems for the dispute resolution processes are
discussed under three themes namely: (i) occurrence of disputes; (ii) dispute resolution system
design; and (iii) dispute resolution processes in practice.
8.3.3.1.
Implications for the Occurrence of Disputes
Disputes are by no means peculiar to the Ghanaian construction industry. Studies from
several countries reviewed provided different lists of potential sources of disputes (see Table
4.1). Some of the sources of disputes identified included changes in owners’ requirement,
poor definition of scope of work, variations, site possession issues, poor quality of documents
(design errors and contractual problems), delays and payment issues. Many of the factors
identified as causing disputes were associated with the actions and behaviour of the Employer
and its representatives. For instance, Aibinu and Odeyinka (2006) identified variation orders,
slow decision-making and cash flow problems as some of the client-related issues causing
delays on projects in Nigeria. After studying disputes from 130 projects in Jordan, AlMomani (2000) concluded that delays in owner decision-making, payment by owners/cash
flow problems during construction, design changes and design errors were among the main
dispute causes. Cheung and Yiu (2007) identified seven client-related potential dispute
causes. These included disagreements on acceleration cost, failure to pay variation claims,
general site possession issues and errors in documentation. The other potential causes were
substantial changes in bills of quantities, changes of scope and late instructions from the
Employer's representatives (see also Love et al., 2011).
The outcome of the data analysis disclosed similar dispute causes in Ghana (see section
213
Chapter 8- Discussions: Implications of Results and Remedial Strategies
7.3.5). These included poor definition of scope of work, frequent design changes, variations,
delayed payments and laxity in contract administration. Poor definition of scope of work,
delays in delivering project sites and delayed payments are used here to illustrate how the
nature and the context of the Employer influenced occurrence of disputes. Consensus ad idem
(when two parties to an agreement have the same understanding of the terms of the
transaction they are entering into) is a basic requirement of a valid contract which signifies
meeting of minds. Where this is not the case, there is a likelihood of future disputes. APC
alluded to the existence of poor definition of scope of works by the Employer leading to a
mismatch between the Employer’s requirements and the Contractors’ responsibilities. The
effect of this lapse was the occurrence of preventable claims and disputes. Examples of
situations where parties had encountered disputes as a result of poor definition of scope were
given by CPW5 and CPR3 in respect of two different projects. In both situations, there were
indications that the parties had different understanding of the scope of the works expected to
be carried out under the contract.
Again, it was the responsibility of the Employer to deliver project sites to contractors. The
data revealed delays in the delivery of project sites. There were instances where delays were
attributed to lack of coordination and cooperation between implementing agencies and other
State institutions responsible for the relocation of utilities (see item 4 in Table 7.5). The
consequences of such delays were claims against the Employer.
Furthermore, it was the duty of the Employer to ensure that there were adequate resources
to pay for work executed by contractors. The data analysis revealed that although funding
arrangements for projects were required to be made prior to award of contracts, the Employer
was unable to honour (on time) its payment obligations under many construction contracts.
Such delays were attributed to the Employer’s penchant to commit to several projects without
an honest assessment of its ability to pay for them. Consequently, delay in honouring
214
Chapter 8- Discussions: Implications of Results and Remedial Strategies
payments for works executed by contractors was among the common sources of dispute.
Even where the resources were available, administrative bottlenecks also occasioned delays.
Duplication of roles and unduly lengthy chains of inter-organisational consultations and
approvals hindered prompt processing of certificates. This view supports findings of previous
related studies on the subject (World Bank, 2003; Anvuur, 2006; Osei-Tutu and Sarfo
Mensah, 2008). One such study on procurement practice in Ghana commissioned by the
World Bank identified erratic release of funds from Government coffers without regards to
payment schedules and cumbersome payment approval processes as some of the reasons for
payment delays (World Bank, 2003). Central to the cumbersome payment system was the
involvement of multiple organisations leading to excessively protracted approval procedures.
A common feature which runs through all three examples cited above was lack of effective
coordination among sub-units of the Employer leading to ineffective and tardy decisions.
Every so often, transactions which were proceeding according to contract were interfered
with by politicians. In some cases, these resulted in the termination of such contracts. There
were also instances where interference by politicians went beyond abrogating contractual
obligations to taking technical decisions. Contractors were sometimes instructed to commence
projects prior to the execution of the construction contract (see Martin Amidu v A-G & 2 Ors.
examined under section 7.3.2.4). The consequences of these interferences were that
contractual requirements were ignored thereby providing bases for aggrieved parties to make
claims or commence dispute resolution processes.
8.3.3.2.
Dispute Prevention
The use of avoidance and reduction strategies to curb disputes is a well-established
practice in construction industries across the world. The literature on the subject has been
examined under section 4.3.1. Avoidance strategies identified included the use of standing
neutrals (Harmon, 2003, Yates and Duran, 2006 and Ng et al., 2007), collaborative
215
Chapter 8- Discussions: Implications of Results and Remedial Strategies
procurement strategies (Cowan, 1991; Construction Industry Institute, 1991; Crowley and
Karim, 1995; C.I.B, 1997; Critchlow, 1998; Stehbens et al., 1999; Bresnen and Marshall,
2000; Hinchey, 2012), effective project management (Yates and Duran, 2006; Ng et al.,
2007;Morgan, 2008) and efficient planning and preparation (Mitropoulos and Howell,2001).
Additionally, there was a trend towards dispute prediction as a means of reducing dispute
occurrence (Diekmann et al., 1994; Diekmann and Girard, 1995). Fenn (2007) has argued that
effective dispute avoidance will require prediction.
The dispute resolution processes in Ghana did not pay attention to dispute avoidance and
management. Notably, there was no policy which specifically targeted dispute prevention or
reduction. As a result, there was no dispute consciousness during the early stages of
construction transactions. MDAs implementing projects did not have adequate strategies in
place to curb disputes. Consequently, steps which could have been taken to avoid or reduce
construction disputes such as those identified from the literature were not taken. Accordingly,
the Employer was exposed to claims and disputes. The process of infrastructure procurement
was primarily driven by funding needs. Using the procurement process as a means to achieve
dispute prevention or reduction was not a priority. There were challenges with project
planning, preparation and management.
In the absence of clear structures for dispute avoidance, the ideal starting point will be
for the Employer to have a clear policy on dispute reduction and management. Such a policy
must consider and incorporate avoidance strategies such as the use of collaborative
procurement methods, the utilisation of standing neutrals and the enhancement of project
planning, preparation and management.
8.3.3.3.
Implications for Dispute Resolution System Design
Contract formation and the impact of third parties on the design of dispute resolution
system for infrastructure projects have already been discussed (see section 8.3.2). Beyond the
216
Chapter 8- Discussions: Implications of Results and Remedial Strategies
impact of funding requirements, there were internal problems which affected the Employer’s
ability to influence the design of the dispute resolution structures. Four of these difficulties
namely lack of policy on construction dispute resolution and an overriding dispute resolution
objective(s), lack of alternatives to dispute clauses in General Conditions, lack of knowledge
and expertise, and human resource constraints are discussed in succession.
Firstly, the Employer’s dispute resolution objectives were unclear. There was no policy on
construction dispute resolution which drove the process. From the evidence, delays, cost,
destruction of relationships and parties’ dissatisfaction with the outcome of processes were
major concerns that the Employer had with the existing dispute resolution processes. By
inference, it is argued that speed, cost reduction, preservation of relationships and parties’
satisfaction with outcome of the process were among the critical objectives that may inform
the Employer’s approach to dispute resolution mechanism selection. However, there were no
indications that negotiations over dispute clauses were informed by such objectives.
Secondly, the Employer did not have any viable alternatives to the dispute resolution
mechanisms or procedures provided in nominated Conditions of Contract. Regarding this
issue, CPA5 observed as follows:
‘[I]f we don’t accept international commercial arbitration (ICA) which one will we do
[accept]. That is also another problem. If we say we don’t want ICA, which one do
you want and if you are not ready with something like that then why would you go and
stick out your neck’.
CPA5’s response revealed one of the problems negotiators representing the Employer faced
during contract negotiations, namely lack of alternatives to extant dispute clauses.
‘Alternatives’ as used here does not necessarily imply a departure from the extant dispute
clauses but considerations which will ensure that the current structures address the
Employer’s dispute resolution objectives.
Thirdly, lack of knowledge and expertise on the range of dispute resolution mechanisms
limited the contribution that the Employer was able to make to the dispute resolution design
217
Chapter 8- Discussions: Implications of Results and Remedial Strategies
process (see section 7.5.3). From the results of the data analysis, contracts were negotiated by
the implementing agencies in many instances (see section 7.2.1.3). Some interviewees from
the implementing agencies acknowledged that there was lack of knowledge of the range of
dispute resolution options. For instance, CPW5, APG and ABP1, among others, admitted that
more training on the other DRMs was required for all involved in projects including staff of
both the Employer and contractors (see section 7.4.1.2).
Further, the Employer’s ability to influence the process of dispute system design also
depended on its human resource strength. The challenges posed by inadequate human
resource to the Employer have been highlighted under section 7.2.2.1. The Employer may
address the human resource problem in three ways namely training existing staff, devoting a
section of the A-Gs to contract review and recruiting new staff. Firstly, the Employer will
need to offer regular training to personnel from the implementing agencies at the forefront of
contract negotiations. This will ensure that contract negotiators at the MDAs are wellinformed of the dispute resolution objectives of the Employer. Additionally, such training
sessions will need to focus on equipping the negotiators with the requisite skills for their
assigned tasks. Furthermore, training can also focus on the areas where the Employer has
opportunity to influence the dispute system design (as outlined under 8.3.3.3). The provision
of sporadic training, as is the case currently, will not suffice. The training must be designed as
part of a wider programme for continuous professional development which will count towards
promotion and future performance assessment.
Secondly, in view of the legal requirement of contract review, the need for human
resource improvements at the A-Gs is crucial. At the moment, the over-burdened staff divide
their attention between other responsibilities and contract review. Consequently, the time and
expertise needed to ensure that dispute clauses were properly vetted were lacking. The need
for a section of the A-Gs to be devoted solely to contract review was echoed by some
218
Chapter 8- Discussions: Implications of Results and Remedial Strategies
interviewees including CPA 2, CPA3 and CPA4. The responses of CPA 5 to series of
questions about the A-Gs’ role in contract review (reproduced below) summed up views on
the need for this unit:
We have a huge number of contracts here; that I can say, plenty that move in and out
of this house every day. In fact we are even thinking that due to their sheer numbers
we need a department for just that. You see, because they are many and they are
varied. They need some kind of expertise. So we are calling for a department for that,
just that, and to train people for just that, then it will take a huge chunk of the work off
the Solicitor-General.
Q.: What other reasons will you give for advocating for the setting up of that office
apart from the fact that these contracts are many and require expertise?
A: The expertise required is so specialized that you don’t just leave it and also
because of them we end up paying huge sums of money so it is worth looking into.
We can end up saving much money from that side of things because if we had people
who look into these things very well and make sure that every single contract passed
here and it was handled timeously, many of the problems we have wouldn’t have
happened. You understand, because those same people will then advise if you were
going to do something against that contract, ‘please don’t! This is what the contract
says if you do this, this is the implication. We will not end up paying damages for
wrongful termination and that kind of thing. Huge sums of money you hear us paying
because we don’t have an office dedicated to do that and everybody does anything
they like. And once they start telling them that every contract should come here then
we need to put the infrastructure in place to receive the contract. Right now we are not
standing that strong to be receiving the sheer numbers that they are receiving right
now.
The role of such a unit will be to ensure that the contract review role of the A-Gs is carried
out efficiently. However, the establishment of such a unit will be feasible only when there is
improvement in staff numbers and quality. Consequently, the final suggestion is fairly
straightforward; the Employer will need to embark on a recruitment drive to appoint
individuals with relevant expertise to augment the existing workforce at the A-Gs and the
various MDAs.
8.3.3.4.
Implications for Dispute Resolution Practice
Section 7.4 reported on how construction disputes involving the Employer and foreign
contractors were resolved in practice. The dispute resolution processes were substantially
influenced by the dispute resolution choices the parties made at the contract formation stage.
However, the analysis also pointed to other factors including lack of inter-organisational
219
Chapter 8- Discussions: Implications of Results and Remedial Strategies
cooperation and coordination, human resource constraints and political interference (see
section 8.3.3). To achieve clarity, the consequences of each of the factors on the dispute
resolution processes and likely remedial options are examined separately.
8.3.3.4.1.
Lack of Inter-organisational Cooperation and Coordination
Lessons from the data analysis relating to three dispute resolution mechanisms namely
negotiation, international arbitration and mediation are used to demonstrate how lack of
cooperation and coordination among the sub-units of the Employer influenced the extant
dispute resolution processes in practice. As reported in section 7.4.1.2, negotiations often took
place at different levels of the political strata of the Employer progressing from the lowest to
the highest. Consequently, it was normal to have unsuccessful negotiations between
implementing agencies and contractors escalated to the ministerial level. Negotiations
required the participation of various entities representing the Employer such as the resident
engineer, the implementing agency concerned, the sector Ministry, MOFEP’s representatives
and lawyers from the A-Gs. This was because each entity played a unique role within the
Employer organisation. However, the involvement of multiple organisations with diverse
functions had implications for inter-organisational cooperation and decision-making and this
in turn affected expeditious resolution of disputes.
During dispute negotiations, the difficulty encountered by the Employer related to
participation by relevant organisations and the availability of relevant information. For
instance, where the A-Gs were leading the negotiation process, they relied on the
implementing agency concerned to furnish information on the dispute. In some cases, line
managers of implementing agencies whose responsibility it was to present such information
failed to do so. The consequence of this practice was that the Employer was often unable to
pull together all the relevant information required to support its case. Ultimately, the effect of
lack of cooperation among entities representing the Employer on negotiations included
220
Chapter 8- Discussions: Implications of Results and Remedial Strategies
delays, tardy decision-making leading to poor negotiation outcomes.
It is acknowledged that negotiation is informal and not subject to strict rules and
procedures. However, it is important that the Employer develop guidelines for its practice as
part of General Guidelines for the use of alternative dispute resolution mechanisms by
government agencies (see section 8.5 on remedial strategies). The importance of such dispute
resolution guidelines, as underscored in section 7.5.1, is that persons acting on behalf of the
Employer will have some benchmark or guidance on the use of the various alternative dispute
resolution mechanisms. Such guidelines may consider timelines for negotiations, who should
be involved and the responsibilities of various entities participating in the process.
In relation to international arbitration, the effect of poor coordination and cooperation
between entities representing the Government had far reaching consequences. Failure of
implementing agencies to provide required information on disputes affected the Employer’s
ability to file appropriate defences to claims. In such situations, the Employer was also
deprived of the opportunity to provide evidence in support of its case. Delayed release of
relevant information by implementing agencies resulted in failure by the Employer to meet
deadlines of arbitral tribunals. In some cases, entities in charge of projects failed to respond to
claims by contractors, inspect progress of projects or attend important project meetings. These
lapses eventually impacted on the ability of the Employer to conduct a robust and successful
dispute resolution process. Other repercussions of such institutional lapses included award of
cost against the Employer for filing processes out of time, losing arbitrations and being
saddled with huge arbitral awards. It was therefore not surprising that cost of dispute
resolution (see section 7.4.1.3.2), frequently losing arbitration cases (see section 7.4.1.3.4)
and issues of mounting judgment debt against the Employer were among some of the
concerns interviewees expressed in the data on the use of international arbitration.
Regarding the effect of the Employer’s nature on mediation, it is often emphasized that the
221
Chapter 8- Discussions: Implications of Results and Remedial Strategies
representatives of the parties to a mediation process must either have or be accompanied by a
person with authority to settle. Securing the authority to settle a matter involving the
Employer posed an enormous challenge due to the involvement of different entities in the
decision-making process. In an earlier example referred to under section 7.4.2.3 on
conciliation and mediation, the mediator involved had to personally consult two Ministers of
State as part of the process, even though the State had a dedicated representative attending the
mediation regularly. It was however unclear if the chains of consultation leading to prolonged
decision-making and delays had anything to do with the limited use of mediation in resolving
construction disputes in Ghana. What is certain, however, was that the chains of consultation
and approvals associated with the workings of the Employer slowed down decision-making
considerably.
To address the problem of cooperation and coordination, the Employer will have to
streamline the roles of the various entities involved in dispute resolution. This can be achieved
through identification of individual institutional roles and the provision of timeframes for
their performance.
8.3.3.4.2.
Impact of Human Resource Constraints on current Dispute resolution
processes
Human resource problems of the Employer such as shortage of staff and lack of expertise
have already been examined in relation to their impact on establishing the structure for future
dispute resolution (see section 8.3.3.3). These deficiencies also impacted on the resolution of
disputes. A small team of lawyers had the responsibility of resolving disputes from diverse
fields of Government business. The workload of the team responsible for dispute resolution
was such that very little time was available for a thorough professional assessment of the
nature of disputes and how they could be resolved cost effectively. The approach to dispute
resolution at the A-Gs was compared to the process of firefighting (see section 7.2.2.1).
222
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Limited resources and lack of expertise coupled with excessive workload meant the limited
expertise available was channelled to where they were needed most at any given time. Once
the urgency associated with a particular problem was reduced, the team moved on to other
burning issues. There was no dedicated team responsible for the resolution of construction
disputes.
However, it is well known that construction contracts and disputes are very
technical and require the services of technical specialists (Capper and Bunch, 1998). At the
MDAs, there was evidence that individuals who handled claims and differences were not
sufficiently equipped with knowledge of conflict and dispute management techniques (see
7.4.1.2 and 7.5.3).
Dealing with the human resource problems of the Employer can enhance its chances at
better dispute resolution. It is recommended that personnel of the various MDAs involved in
contract administration should be offered regular training in dispute reduction and
management.
It is expected that as
staff
apply
dispute avoidance and management
techniques and skills acquired, the number of disputes which will eventually be referred to the
A-Gs will reduce. Nevertheless, disputes which are eventually referred to the A-Gs will also
need to be dealt with efficiently. As the body with the legal mandate to represent the State and
its agencies in disputes, the A-Gs will also need to be sufficiently equipped with the necessary
human resource to perform its dispute resolution role.
Apart from investing in additional staff, it is suggested that a unit similar to the one for
contract review (see section 8.3.3.3) be established at the A-Gs. Such a unit will have the
responsibility of focusing on disputes arising from construction and engineering projects
involving the Government which are referred to the A-Gs from the MDAs. With the relevant
expertise, the unit will be better placed to provide technical advice on dispute resolution
options to the Attorney-General. The unit can also play a useful role in post-dispute resolution
evaluation by the Employer.
223
Chapter 8- Discussions: Implications of Results and Remedial Strategies
8.3.3.4.3.
Impact of Threat of Blacklist and Political Interference on Dispute Resolution
Information on both political interference and threat of blacklist was examined under
sections 7.2.2.2 and 7.2.2.3 above. In this section the focus is on how these practices have
contributed to shape the extant dispute resolution processes. Contractors regularly appealed
to politicians for their intervention in brewing disputes with the Employer. Interventions from
politicians pursuant to such appeals often lacked transparency and formality. The implication
is that it is impossible for the Employer to determine whether such dispute resolution
approach was beneficial to its cause or not (see section 8.2 above). It was evident that this
practice was filling a gap in the extant dispute resolution processes, namely the absence of use
of intermediary dispute resolution mechanisms involving third party neutrals. Under the
current dispute resolution processes, when negotiations between contractors and MDAs over
disputes break down, the next option available to parties was international arbitration. For
parties who were unwilling to take such drastic steps, the search for a way to resolve such
disputes led them to political actors.
To reduce the practice of using political actors to resolve disputes, parties will have to
incorporate into their contracts express provisions on specific intermediary mechanisms
which they will fall on in case negotiations failed and they were not ready for international
arbitration. Whilst this suggestion may not stop appeals for political interventions, it may help
contractors who resorted to political interventions as a result of lack of formal intermediary
mechanisms.
Regarding the fear of being blacklisted, contractors who envisaged future business
opportunities refrained from any adjudicatory dispute process which pitched them against the
Employer. Consequently, there was a view that the phenomenon had resulted in fewer
disputes against the Employer. Beneath the seeming absence of disputes was a practice by
contractors which ensured that disputes were kept alive as long as they possibly could whilst
224
Chapter 8- Discussions: Implications of Results and Remedial Strategies
business opportunities were utilised. The threat of blacklist had three implications on the
extant dispute resolution processes. Firstly, it gave the Employer a false sense of security
from disputes thereby creating the impression that there were few infrastructure-related
construction disputes in Ghana. Secondly, it led to the ‘bottling up’ of disputes. Finally, the
phenomenon had stifled growth and use of dispute resolution mechanisms because parties did
not make regular use of the range of mechanisms available.
8.3.3.4.4.
Impact of the Legal System on Infrastructure-related Construction Dispute
Resolution
The legal framework for infrastructure-related construction dispute resolution was based
on contract law. Nonetheless, the involvement of the Employer as a State introduced
additional public law requirements. Lack of clarity of the confines of Article 181(5) of the
Constitution which required international business or economic transactions to which the
Government of Ghana was a party to receive parliamentary approval had spawned a number
of judicial decisions in the Supreme Court (see section 7.3.2.4). In spite of the attempt by the
judiciary to clarify the confines of this law, it is still difficult to identify with certainty which
transactions will require parliamentary approval.
This situation is worrying for private parties especially those involved in borderline
transactions.
This is more so since the effect of non-compliance is that the affected
transaction is void. Declaring contracts void for non-compliance with constitutional
provisions had the collateral effect of stifling the enforcement of contractual obligations and
contractually agreed dispute mechanisms which were otherwise valid.
Another element of the legal system which had implications for the extant dispute
resolution processes was the effect of section 1 of the Alternative Dispute Resolution Act,
2010 (Act 798) which excluded matters relating to national and public interest from the
purview of the Act. Transactions such as those involving the Employer and foreign
225
Chapter 8- Discussions: Implications of Results and Remedial Strategies
contractors invariably entailed public and national interest elements. By implication, these
transactions were excluded from the purview of the law. This is the case even though there
were other legislations, such as the Ghana Investment Promotion Centre Act, 2013 (Act 865),
which allowed disputes between the State and foreign investors to be resolved by international
arbitration. Other implications of the current position of the law on construction and
engineering contracts involving foreign contractors are discussed elsewhere (see Mante and
Ndekugri, 2012). To encourage foreign contractors to settle disputes in Ghana, the laws on
domestic arbitration need to be harmonised. In addition to the factors discussed above, a
number of other factors which stifled the development and use of dispute resolution
mechanisms have already been identified and examined under section 7.5 above.
8.4.
Summary of Key Features of the Extant Dispute Resolution Processes
In chapter seven, the dispute resolution processes for major infrastructure projects in
Ghana were described. The chapter also identified and discussed factors which had shaped the
said dispute resolution processes. Some of the key features of the dispute resolution processes
identified are as follows:
(i)
absence of clearly defined objective for infrastructure-related dispute resolution;
(ii) absence of policy dealing specifically with construction disputes arising from major
projects;
(iii)
lack of recognition of the specialised nature of the subject-matter (construction);
(iv)
procurement driven mainly by funding and not considered crucial to dispute resolution
outcomes;
(v)
funding requirements determined Conditions of Contract and the dispute resolution
mechanisms to be used;
(vi)
negotiations over dispute clauses took place within the parameters provided by the
nominated Conditions of Contract;
226
Chapter 8- Discussions: Implications of Results and Remedial Strategies
(vii)
dispute clauses often tailored to suit contractor preferences;
(viii)
human resource constraints and the absence of dedicated expertise for contract
negotiations;
(ix)
operational inefficiencies of the Employer’s sub-units made it prone to disputes;
(x)
main dispute mechanisms in use were engineer’s determination, negotiation and
international arbitration;
(xi)
intermediary dispute resolution mechanisms such as mediation, dispute review boards,
dispute adjudication board, expert determination, and early neutral evaluation were
rarely used;
(xii)
minimal use of third party neutrals. Only time third party neutrals were employed was
when the parties were resolving disputes either by litigation or arbitration;
(xiii) dispute resolution processes were characterised by high cost, low parties’ satisfaction
with outcomes and destruction of business relationships;
(xiv)
fear of being blacklisted stifled dispute resolution practice;
(xvi)
absence of information on previous dispute resolution efforts to guide future steps–
poor record keeping; and
(xvii) absence of a mechanism or programme to evaluate dispute resolution processes after
disputes were resolved.
8.5.
Remedial Strategies
Recommendations by interviewees on how to improve the extant dispute resolution
processes (see Figure 6.7 above) related to structural or contextual issues, contract formation
(negotiating dispute clauses) and actual dispute resolution. The structural issues focused on
improving the general context within which disputes occurred and were resolved. These
included recommendation on policy changes, education and training and development of
standards for the use of dispute resolution mechanisms by government agencies. The
227
Chapter 8- Discussions: Implications of Results and Remedial Strategies
categories ‘front-end ordering’ and ‘dispute avoidance and reduction’ harboured all the
recommendations relating to contract formation and the design of the structures for future
dispute resolution (negotiating dispute clauses). ‘Increased use of DRMs’ and ‘DRM Practiceweighing your options’ deal with recommendations on the actual resolution process.
Considering the discussions on the state of the existing dispute resolution processes (see
section 8.2), the factors accounting for it (see sections 8.3), the results of the data analysis on
remedial strategies and the relevant literature, it is submitted that creating an effective and
efficient dispute resolution process will entail adopting a holistic approach which pays
attention to four key components namely; (i) structural and contextual issues; (ii) dispute
resolution system design; (iii) dispute avoidance and resolution; and (iv) post-dispute
resolution- evaluation of outcome.
8.5.1. Paying Attention to Structures and Context
The discussions under section 8.3.3 above have underscored the relevance of the nature of
the Employer, the activities of its sub-units and the environment within which they operated
to the dispute resolution processes. Similarly, it has been demonstrated that the nature of the
foreign contractor has also contributed to shape the current dispute resolution processes (see
section 8.3.1). Consequently, it is important for the parties, particularly the Employer to take
specific steps to prepare the context within which major infrastructure procurement takes
place and to establish adequate structures to ensure that it can effectively deal with disputes.
Table 8.1 below outlines a number of suggestions (derived from the data) for preparing the
infrastructure project setting for dispute resolution.
228
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Table 8.1: Recommendations on Front-end Preparations for Dispute Resolution
Recommendations
1. Learning
from
Experiences
Past
2. Investigating the cost of
disputes
and
their
resolution
3. Need for a Specific Policy
and
clear
overriding
objectives for dispute
resolution in the context of
major projects
Details
Keeping a database of previous disputes and how
they were resolved and using the lessons from such
experiences to enrich current processes (CPR8 &
CPR9)
(i)
This process will provide material for a
database of dispute resolution and
encourage policy makers to develop
policy for dispute resolution as a matter of
priority.
(ii)
It will also unearth the real cost of
disputes and their resolution and this is
likely to prompt the Employer to pay
attention to the dispute resolution
processes (CPE6)
(i)
Currently, there is neither a clear dispute
resolution objective nor a specific policy
on how the Employer approaches
infrastructure related dispute resolution.
Such a policy will set clear overriding
objectives for the process. Objectives may
include saving expense (by ensuring that
cases are dealt with in ways which are
proportionate to the amount of money
involved, reflect the importance of the
case and the complexity of the issues) and
ensuring speedy resolution.
(ii)
(iii)
4. Impact
of
relevant
contextual factors must be
considered
In addition to the policy, General
Guidelines on the use of the diverse forms
of dispute mechanisms to resolve
infrastructure-related
construction
disputes is also required (see section
7.5.1).
A checklist for contract negotiations
relating to dispute clauses will need to be
developed with a clear goal to achieve the
overriding objectives set for dispute
resolution.
(CPA3, CPE6, CPA 4, CPA5, CPF1 etc.)
(i)
Policy, Guidelines and or the Checklists
must consider factors such as funding
requirements,
legal
and
statutory
requirements, the political and cultural
environment in which Employer exist and
identify how the effects of these factors
229
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Recommendations
(ii)
(i)
5. Promoting regular use of
Alternative
dispute
resolution mechanisms
(ii)
(i)
6. Legal Reform
(ii)
(iii)
7. Developing Standards for
the use of less known
dispute
resolution
mechanisms
(iv)
230
Details
on dispute resolution can be either
curtailed or utilised to achieve the dispute
resolution objectives of the Employer.
Policy must also take into account the
international dimensions of disputes from
major construction projects and ensure
fairness to all parties.
Mediation, Conciliation, DRBs, DAB,
Expert
determination
and
other
mechanisms must be explored and utilised
based on their suitability to specific
situations. This will enhance their
visibility. The data revealed strong
discomforts with international arbitration.
Yet, there were also strong indications
that neither contractors nor funding
institutions are willing to play down the
prominent role of international arbitration.
The Employer has the option to place
more emphasis on the use of negotiation
and intermediary dispute mechanisms so
as to reduce the number of disputes which
may end up at international arbitration.
The law which requires that contracts
which constitute ‘international business
and economic transactions to which the
government is a party’ must receive
parliamentary approval must be clarified
to avoid the current confusion which is
generating disputes and stifling the
implementation of contracts (see section
7.3.2.4);
Section 1 of the ADR Act, 2010 must be
amended to enable suitable matters of
public and national interest to come under
the purview of the legislation (see section
8.3.3.4.4 above).
Professionals should be furnished with
standards which will guide decisions
regarding the use of particular dispute
resolution mechanisms.
The proposed standards may address
issues such as weighing the options
available, selecting a mechanism,
providing justification based on the
dispute resolution objectives set out in the
policy, using cost-benefit analysis as a
basis for mechanism selection etc.
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Recommendations
8. Streamlining institutional
roles in dispute resolution
9. Education and Training
10. Dispute
Avoidance/Reduction
Details
This will entail:
(i)
Improving the ADR capacity of personnel
involved in infrastructure procurement
and dispute resolution at the MDAs;
(ii)
Establishing two specialist units within
the Attorney-General’s Department to be
responsible for the review and negotiation
of construction and engineering contracts,
and disputes arising out of such contracts ;
(iii)
Providing guidelines on coordination and
cooperation between MDAs and the A-Gs
in relation to information flow and dispute
handling; and
(iv)
Identifying timelines for dispute handling
by the various institutions. This may
include providing some indications as to
when differences/disputes must be
transferred to the A-Gs.
(i)
Provision of structured formal and
informal training of Employer’s staff to
develop expertise in construction-related
dispute mechanisms and also to
continuously update their knowledge on
current trends (see section 8.3.3.4.2);
(ii)
Training must also focus on helping staff
to understand the Employer’s dispute
resolution objectives and to provide
updates from evaluations of past disputes
resolution experiences and lessons arising
therefrom;
(iii)
Putting together plans and strategies to
consciously work towards the removal of
other barriers affecting dispute resolution
(see sections 7.5) through education.
(i)
An aspect of the policy on the resolution
of infrastructure–related construction
disputes must address the dispute
avoidance and reduction;
(ii)
Considering the use of collaborative
procurement strategies and standing
neutrals (see section 8.3.3.2);
(iii)
Enhancing contract management and
administration, adopting a pro-active
stance towards claim minimisation and
settlement
231
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Most of the suggestions on subjects such as education and training, and learning from
previous experiences will require continuous improvement. The gains from such
improvements will provide a favourable environment for contract formation (including the
negotiation of dispute clauses) and dispute resolution. For instance, it is likely that
specialisation will lead to a more thorough consideration of contract terms and conditions;
parties will be able to identify and explore more options in contract negotiations.
8.5.2.
The Contract Formation Stage – Designing the Dispute Resolution Structure
The design of the dispute resolution structure takes place during contract formation. Often
the period of contract negotiations also offer the parties the opportunity to provide project
specific details for the dispute resolution structure. What transpires at this stage as far as the
situation in Ghana is concerned has been discussed under sections 7.3.2 and 8.3.2 above.
It is suggested that personnel involved in negotiations on dispute clauses must move
beyond the current practice of limiting attention to the selection of venue, governing law and
rules, language, and selection of third party neutrals. Such negotiations must have a number of
aims. Firstly, it must focus on establishing a dispute resolution framework capable of
achieving the overriding dispute resolution objectives of the Employer. Secondly, it must aim
at addressing problems observed with previous dispute resolution experiences. In other words,
lessons from previous dispute resolution experiences must inform new negotiations on dispute
clauses. For example, since cost is identified as a problem, clauses on cost-sharing and
capping of interest recoverable can be explored and negotiated into new dispute clauses.
Bespoke rules on evidence aimed at cost and time reduction can be explored, negotiated and
incorporated into Special Conditions.
Thirdly, negotiations on dispute clauses need to incorporate new terms on possible
intermediary resolution mechanisms which parties will utilise during the period of amicable
settlement. As explained under section 7.4.1.2 on negotiations, the current practice was that
232
Chapter 8- Discussions: Implications of Results and Remedial Strategies
parties continued to negotiate during the period for amicable settlement. There was no
evidence of use of any intermediary dispute resolution mechanism during the period for
amicable settlement. Parties using the FIDIC forms, for example, should identify a range of
mechanisms they will employ during the amicable settlement period, discuss procedures for
their use and incorporate them into the contract as Special Conditions.
Pre-determined dispute resolution clauses have their own challenges. The mechanism or
the procedure agreed upfront may be unsuitable for the actual dispute that may arise in the
future (Sime, 2007). Albeit, parties can build into the Special Conditions mechanisms which
will enable them to employ different methods and procedures in case those originally agreed
are unsuitable. Essentially, the proposal here is that parties need to spend a lot more time and
resources to craft a detailed dispute resolution agreement which is context-sensitive, multitiered, procedurally rich and flexible enough to allow changes where necessary. This should
be done even if it means separating the dispute clauses into a distinct dispute resolution
agreement which will be acknowledged as a separate but integral part of the main
construction agreement.
Two other recommendations on training personnel involved in contract negotiations at the
MDAs and the establishment of a unit within the A-Gs for contract review on behalf of the
Employer have already been discussed above (see section 8.3.3.3). The aim of these
recommendations is to enhance the Employer’s ability to utilise the contract formation period
effectively to contribute to the design of the dispute system.
8.5.3.
Dispute Avoidance and Resolution
The literature on construction dispute prevention has been discussed under section 4.3.1
and 8.3.3.1. Five sets of avoidance approaches were identified. These are the use of standing
neutrals ( Gerber, 2000; Fenn et al., 1997; Harmon, 2003; Yates and Duran, 2006 and Ng et
al., 2007), the use of procurement and relational contracting strategies such as partnering and
233
Chapter 8- Discussions: Implications of Results and Remedial Strategies
alliancing (Harmon, 2003; Doug, 2006; Ross, 2009; Kratzsch, 2010; Le Nguyen, 2011;
Hinchey, 2012), use of effective project management strategies such as cost and schedule
control, quality management and constructability (Fenn et al., 1997; Yates and Duran, 2006;
Ng et al., 2007; Morgan, 2008) and general project planning and preparation (Mitropoulos
and Howell,2001). A fifth strategy, dispute prediction, has been canvassed mainly by Fenn
(2007) who has argued that ability to predict dispute is essential to dispute prevention. This
study has revealed issues with project preparation and management (see sections 7.3.5 and
7.5.1). It has also found that procurement is primarily driven by funding needs; dispute
prevention or avoidance was not an issue considered during procurement. There was limited
use of intermediary mechanisms and third party neutrals (see sections 8.2.4). The idea of
using standing neutrals was new and rarely used. Generally, there was limited emphasis on
dispute prevention.
Every effective and efficient dispute resolution strategy must, first of all, aim at preventing
or reducing the occurrence of disputes; parties must start right (Diekmann and Girard, 1995).
This is because an effective dispute avoidance regime has the potential to reduce the number
of disputes which eventually end up for resolution. Options available to the Employer for
dispute prevention or reduction were discussed under section 8.3.3.2. These included
developing a policy on dispute prevention and reduction, using procurement methods and
strategies which encourage parties to focus on building collaborative relationships so as to
reduce disputes, using standing neutrals such as Dispute Review Boards or Dispute
Resolution Experts and training staff responsible for projects to be aware of and comply with
the Employer’s policy on avoidance.
To deal with the human resource issues affecting dispute resolution, the Employer must
enhance dispute prevention, management and resolution capacities of the MDAs. It must also
establish a unit within the A-Gs which will be responsible for the handling of construction and
234
Chapter 8- Discussions: Implications of Results and Remedial Strategies
engineering disputes referred to the A-Gs. The unit will become the ‘technical eye and brain’
of the Attorney-General who is ultimately required by law to represent the State during
dispute resolution. Additionally, in cases where the use of international arbitration is
inevitable, the unit will explore and implement cost-cutting measures such as arranging for
arbitration hearings to take place in Ghana or securing an agreement for local witnesses of the
Employer to give evidence via video link or before a local judge for subsequent transmission
to the Arbitral tribunal.
8.5.4.
Post-Dispute resolution - Evaluation of Outcome
A policy on construction dispute resolution must develop criteria for evaluating the
outcome of every dispute resolution process. Essentially, such a process must compare
outcomes with the specific dispute resolution goals set for the project and the aims and
objectives set out in the national policy. Reasons for meeting the required objectives or failure
to do so must be identified. Based on lessons from a particular project, remedial strategies or
recommendations can be made and fed into a national database on disputes. Such information
will then become part of the pre-contract contextual information available for future projects.
Table 8.2 below provide a summary of the key factors to be considered under each set of
remedial strategies.
Table 8.2: Summary of the Four Sets of Remedial Strategies
Remedial Strategies
Paying Attention to
Structure and Context
(10 Elements )
Designing the
DR System (5
Elements )
Dispute Avoidance
and Resolution (6
Elements )
Evaluation of
Outcome-Post
DR (5 Elements)
Learning from Past
experiences
Focus on
agreeing a DR
framework
capable of
Develop policy on
Prevention
Compare
outcomes with
project goals on
DR and National
Investigating the cost of
DR
235
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Need for Policy and
overriding objectives for
Infra-related DR
delivering DR
objectives of the
Employer
Considering impact of
contextual factors-e.g.
funding, political
interference, legal
framework etc.
Use collaborative
procurement
policy objectives
on infra-related
DR
Use Standing neutrals
Promoting ADR use
Developing standards for Aim at
the use of ADR by
addressing
government entities
previous DR
challenges
Training staff at the
MDAs in ADR
practice
Streamlining
institutional roles on
infra-related DR
Identify, agree,
incorporate
specific
mechanism to be
used during the
period for
amicable
settlement
Establish a unit for
Infrastructure-related
DR
Identifying
failures/why
Improving project
planning and
management
Making
recommendations
for future projects
Focusing on dispute
avoidance and
management
Training of
Personnel
Cutting cost of
Arbitration – e.g.
implementing cost
sharing agreement
Legal reform
Setting up a
Contract review
unit
Instituting a
forum where
failures and
successes of
DRMs utilized
will be discussed
among relevant
staff of Employer
Education and Training
8.5.5.
Identifying
successes / why?
The Dispute Resolution Efficiency Cycle
The four sets of remedial strategies suggest various actions that the Employer can take at
various stages of a dispute resolution cycle to improve the process. In this study, a dispute
resolution cycle refers to relevant phases in a project cycle when critical decisions about
disputes are made. This cycle is divided into four stages namely the pre-project stage, the
dispute resolution system design stage, the actual dispute resolution stage and the post236
Chapter 8- Discussions: Implications of Results and Remedial Strategies
resolution evaluation stage. Each of the four sets of remedial strategies targets one of the
components of the cycle. The first of the four strategies namely paying attention to structures
and context focuses on general improvements (structural and operational) which the Employer
can make to enhance its capacity to deal with disputes (see section 8.5.1). This set of
strategies is fundamental to any improvement in the dispute resolution processes and must
necessarily be the starting point. Improvements from the first set of remedies are expected to
be incremental and continuous.
However, it is expected that resulting changes will enhance the ability of the Employer to
participate effectively in activities related to dispute resolution at all stages of the dispute
resolution cycle, particularly the second stage. The second set of strategies (see section 8.5.2)
corresponds to the second stage of the dispute resolution cycle. They aim at getting the
Employer to actively participate in the crafting of the structure for future dispute resolution
processes. Again, improvements made to the Employer’s practices at this stage will ensure
that appropriate dispute mechanisms and procedural details are in place for future dispute
resolution. The third set of remedial strategies concentrates on suggestions to improve the
actual dispute resolution process. It is at this stage that all previous preparations and
arrangements for effective resolution are to be implemented. Once the process of resolution is
completed, it is expected that the fourth set of remedial strategies namely post-resolution
evaluation will be undertaken. Consequently, the strategies proposed are reduced into a
model called the Dispute Resolution Efficiency Cycle as illustrated by Figure 8.1 below. As
continuous improvements are made at each stage and impacts of such enhancements influence
other stages of the cycle, it is expected that a more effective and efficient process of dispute
resolution will be attained.
237
Chapter 8- Discussions: Implications of Results and Remedial Strategies
Starting point
Pre-C
ontra
ct Sta
ge(co
ntext
ual Is
sues)
Dispute
Dispute
Resolution
Resolution
Efficiency
Efficiency
Cycle
Cycle
Inefficiency
Continues
Ou
tco
m
opp Misse
ort
d
uni
ties
e-E
val
uat
ion
ion
uat
val
e
No
nt - pute
r eme
is
Procu tions (d
a
egoti reement)
g
ract N
Cont olution a
res
Imp Expec
fed rovemted
into
e
cyc nts
le
Recom
m
e
nd
impro
ve m e e d
nts
s
roces
tion P
resolu
e
t
u
isp
The D
Figure 8.1: The Dispute Resolution Efficiency Cycle (DREC)
The implementation of the DREC by the Employer will necessarily entail making policy,
institutional and operational changes to the current process of infrastructure procurement and
dispute resolution (see section 10.5).
8.5.6. Contribution of Foreign contractors and Funding Organisations
The use of right-based dispute resolution mechanisms by contractors in a dispute involving
the Employer carried the risk of destroying business relationships. This is not in the interest of
the foreign contractors. Supporting the recommendations above particularly those on dispute
reduction and regular use of intermediary mechanisms will reduce recourse to international
arbitration and consequently help sustain business relationships. Funding organisations will
do well to discuss dispute resolution policies they attach to funds with the Employer and
adopt them with the interest of all parties in mind. This will ensure that both parties own the
dispute resolution processes. It will also reduce the perception of bias currently associated
with the extant dispute processes.
8.6
Summary
In this chapter, the infrastructure-related dispute resolution processes in Ghana have been
evaluated on the basis of the literature. The evaluation shows that the existing processes fall
238
Chapter 8- Discussions: Implications of Results and Remedial Strategies
short of some of the standards expected of an efficient and effective dispute resolution process
such as substantial involvement of parties in the design of the dispute system, voluntary
participation, involvement of third party neutrals and education and training. Consequently,
the dispute resolution processes were characterised by high transaction cost and lack of
satisfaction with outcomes. From the analysis, it emerged that the existing dispute resolution
processes were the product of the nature of the parties to infrastructure contracts, the context
within which they operated and their responses to the context. Factors such as lack of
coordination among the Employer’s sub-units, human resource constraints, the existing legal
structures, political interference and threat of blacklist (associated with the Employer)
generally had negative impacts on dispute occurrence, dispute resolution system design and
dispute resolution. To deal with these challenges and achieve an efficient and effective
dispute resolution process, the Dispute Resolution Efficiency Cycle (DREC) is proposed.
239
Chapter 9- Validation
CHAPTER NINE
240
Chapter 9- Validation
CHAPTER NINE - VALIDATION
9.1.
Introduction
As is the case with all other aspects of the research process, the overarching influence of
the philosophical paradigms reflects how research is validated. Quantitative research has
widely accepted and well established criteria for assessing the quality of research. These
include validity, reliability and generalizability. Validity has to do with the credibility and the
accuracy of the conclusions of the research. Reliability deals with the extent to which the
research can be replicated. Generalizability focuses on the extent to which the findings of the
research can be generalized.
However, different perspectives exist on how qualitative
research is validated (Creswell, 2007; Bryman, 2008). In this chapter, a brief survey of the
qualitative literature on validation and research evaluation generally is presented leading to
the examination of the procedure utilized to validate the outcome of this study, namely
triangulation and respondent validation (member-checking) among other methodological
steps taken throughout the research process.
9.2.
Validation in Qualitative Research
Schwandt (1997) defines validity in qualitative research as the extent to which the findings
of the research reflect accurately participant’s reality of the phenomena studied. Generally,
there is lack of consensus on the criteria for validating qualitative research (Creswell, 2007;
Pyett, 2003; Angen, 2000). Broadly, the approaches range from those which advocate the use
of quantitative standards such as validity and reliability (Bryman, 2008; Mason, 1996;
LeCompte and Goetz, 1982) to those which advocate alternatives to the quantitative options
(Lincoln and Guba, 1985). These differences in approach are based on philosophical loyalties.
Within the range, there are several other approaches. Angen (2000) refers to Silverman (1993)
and Hammersley (1995) as examples of the mid-range approaches. For researchers in this
category, their approach to validation straddles the philosophical paradigms of realism and
241
Chapter 9- Validation
interpretivism. They admit the existence of an objective reality independent of the knower but
also accept that reality can be known from individual perspectives (see Angen, 2000).
Hammersley (1995), for instance, define validity as ‘confidence’ rather than ‘certainty’ and
advocates plausibility, relevance and importance as criteria for assessing validity. Silverman
(1993) on the other hand, suggest careful case selection, hypothesis-testing, inductive analysis
and quantifying through counting as criteria for measuring validity. Whitmore et al. (2001)
argue for a synthesis of the differing perspectives.
An example of the perspectives which advocate for the use of distinct terminologies to
validate qualitative research is Lincoln and Guba (1985). Strauss and Corbin (1998) also
subscribe to this view. Lincoln and Guba (1985) advocated for the use of standards of
evaluation more suitable to the naturalistic framework. To them, qualitative research must be
measured in terms of its trustworthiness and authenticity (Guba and Lincoln, 1994). They
defined trustworthiness as entailing ‘credibility’, ‘transferability’, ‘dependability’, and
‘confirmability’. Authenticity was defined in terms of the impact of the research. Whilst the
above criteria can be viewed as qualitative equivalents of the quantitative criteria, the criteria
of trustworthiness and authenticity were fashioned to accommodate one of the central ideas of
interpretivism, namely the existence of multiple accounts of social reality (see Table 9.1
below). Consequently, this study used the validation criteria proposed by Lincoln and Guba
(1985) because of its leanings towards interpretivism.
Table 9.1: Lincoln and Guba’s (1985) criteria for qualitative validation compared with
Quantitative Approaches (Source: Adapted from Bryman, 2012)
Elements
of Quantitative
Meaning
Trustworthiness Equivalent
Credibility
Internal
validity
Are the findings plausible? Feasibility or credibility rather
than a single conclusion (in causal terms) is what will lead
to the acceptance of the findings of a research in view of the
existence of multiple accounts of social reality.
Transferability
External
validity
Do the findings apply to other context? Contextual
uniqueness rather than generalizability is the preoccupation
of qualitative research. However, certain features of
qualitative studies can ensure that findings are generalised.
242
Chapter 9- Validation
Elements
of Quantitative
Trustworthiness Equivalent
Meaning
Credibility
Internal
validity
Are the findings plausible? Feasibility or credibility rather
than a single conclusion (in causal terms) is what will lead
to the acceptance of the findings of a research in view of the
existence of multiple accounts of social reality.
Transferability
External
validity
Dependability
Reliability
Confirmability
Objectivity
Do the findings apply to other context? Contextual
uniqueness rather than generalizability is the preoccupation
of qualitative research. However, certain features of
qualitative studies can ensure that findings are generalised.
Are the findings likely to apply at other times? Stability of
research findings must be assessed based on the assumption
that such findings are subject to change and instability since
social reality cannot be ‘frozen’.
Has the investigator’s values and prejudices intruded into
his findings beyond reasonable limits? Objectivity is
impossible in social research but the researcher must act in
good faith.
Research Impact: Fairness
Authenticity
9.3.
Procedures for Validation
The literature identifies a number of procedures that can be used to assess the validity of
qualitative research. Whittemore et al. (2001) identified 29 different validating techniques
employed throughout the research process. At the design stage, the authors identified
triangulation or sample adequacy among other techniques. At the data collection stage,
Whittemore et al. (2001) referred to making explicit data collection decisions, prolonged
engagement or demonstrating saturation, among other techniques. Member-checking,
memoing and exploring rival explanations are some of the validation techniques suggested by
Whittemore et al. (2001) at the data analysis stage. Creswell (2007) on the other hand focused
on eight different procedures including triangulation, member-checking, reflexivity
(clarifying researcher bias) and peer review. The other four procedures suggested by Creswell
(2007) are external audit, explaining negative cases, rich, thick description and prolonged
engagement in the field. Reviewing the qualitative literature, it appears some of the
procedures are commonly used by qualitative researchers than others. These include
243
Chapter 9- Validation
triangulation, respondent validation, reflexivity and peer review (Bryman, 2012; Angen, 2000,
Creswell and Miller, 2000). These procedures are briefly outlined below.
9.3.1
Triangulation
This refers to the use of multiple sources of data, methods, theories and researchers to
study a phenomenon (Miles and Huberman, 1994). The essence of triangulation is to verify
the extent to which different methods, data sources and investigators corroborate or contradict
the findings of each other when used to study a common phenomenon. The assumption is that
using different data sources, investigators or methods will help eliminate bias, result in a
convergence of patterns of meaning or understanding of the phenomenon under study thereby
strengthening the validity of the research (Angen, 2000; Mathison, 1988).
Denzin (1978) identified four different types of triangulation namely, data, methods,
investigator and theories triangulation. Data triangulation refers to using different data sources
with person, time and space in mind. Investigator triangulation entails using more than one
investigator in a research whilst theories triangulation advocates the use of different
theoretical lenses to study a social phenomenon. Similarly, methodological triangulation
refers to the use of different methods to study a common social phenomenon. Denzin (1978)
distinguished between two types of methodological triangulations namely, within-method and
between-method. Regarding the latter, separate methods are employed to study a common
phenomenon and the outcome compared. In respect of the former, different techniques are
used within the confines of one method. Though useful as a technique for validation,
triangulation has also been viewed as having the potential to produce as much contradictory
outcomes as it could convergent findings (Mathison, 1988; Angen, 2000).
9.3.2
Reflexivity
This technique of validation entails self-reflection by researchers on the implications of
their knowledge, methods, decisions and biases on the outcome of a study and making such
244
Chapter 9- Validation
claims explicit at the onset of the research. By expressly admitting of the existing biases and
prejudices with which the researcher approaches a study, it is expected that this will
contribute to creating a distance between the researcher and the object of study and thus
contribute to objectivity. This view of the notion of reflexivity has been criticized as being
misguided since the inquirer and the subject of inquiry are not separated merely by such
declarations (Angen, 2000).
9.3.3
Peer Review
This involves a third party whose responsibility is to act as a check on the researcher. His
role entails asking the researcher hard questions about choices that the latter has made during
the research process (Lincoln and Guba, 1985). Whilst a peer reviewer can help evaluate the
cogency and persuasiveness of the researcher’s arguments, he will not have adequate
knowledge of the subject matter of the research sufficient to enable him to have the ability to
judge the interpretations that the researcher has developed from the data (Angen, 2000;
Morse, 1994).
9.3.4
Respondent validation
Respondent validation focuses on obtaining the views of interviewees on the credibility of
the research outcomes (Creswell, 2007). Lincoln and Guba (1985, p.314) consider this
technique as ‘the most critical for establishing credibility’. With this technique, outcomes of
data analysis, conclusions and recommendations are referred back to participants for their
comments. In such cases, the role of the participants is to judge the accuracy and plausibility
of the outcomes. Feedback from the participants may be obtained through different channels.
These include organizing a focused group where the findings are discussed or interviewing
participants on the research outcome.
Whilst this technique may provide useful feedback on the findings and interpretations of a
study, it also has its challenges. Since the social environment is not static, participants may
245
Chapter 9- Validation
change their minds (Morse, 1994). They may have encounters or experiences which may
change their perspective on issues. Where findings are not favourable to participants, they
may even go on the defensive (Bryman, 2012).
9.4.
Validation in this study
Respondent validation and triangulation were the main validation techniques used in this
study. Two considerations informed the choice of validation strategy. The first was the
philosophical assumptions underpinning the study. The second was the need for the research
participants to comment on the findings and interpretation (Creswell and Miller, 2000).
Different data sources were triangulated. Three different categories of documentary data were
collected. These were archival records, internal documents of organisations and institutions
involved in the study and documents of a legal nature.
Past project reports, contract
documents, project appraisal reports, proceedings on parliamentary hearings on arbitral
awards, published laws and judicial decisions were among the documents collected (see
section 5.5.3.3). In addition to the documentary sources, interviews were conducted with 56
participants from diverse backgrounds with varied experiences. Accounts from each of these
diverse data sources were corroborated by accounts from other sources. For instance, accounts
relating to the complex nature and operations of the State as an Employer were obtained not
only from statutory sources but also from interviews.
Two methodologies, case study and grounded theory were employed. Though used
together, they offered the opportunity for wider methodological focus and application. For
instance, whilst case study offered depth and focus, adherence to grounded theory principles
ensured that theoretical insights were not missed. Beyond the between-method strategy, there
was also within-method triangulation. For instance, different data collection methods
(interviews and documents), sampling techniques (purposive, snowball and theoretical) and
246
Chapter 9- Validation
data analysis methods (grounded theory principles and legal analysis) were employed together
thereby providing diverse lenses through which the subject of dispute resolution was studied.
Regarding respondent validity, in addition to the initial steps taken during data collection
to obtain confirmation from participants of information received from previous interviewees,
the outcomes of the study were also sent back to interviewees for their feedback. Limited time
and resource constraints made it impossible for a wider audience to be consulted either
through focus group meetings or face-to-face interviews. However, a summary of findings
and request for feedback were sent by e-mail to forty-two out of the fifty-six interviewees.
Additionally, the views of three individuals who were not interviewed previously were also
sought. This brought the total number of individuals contacted for feedback to forty-five.
9.5.
Feedback from Interviewees
Out the forty-five individuals contacted for feedback, fifteen responses were received
constituting a response rate of about thirty-three per cent.
9.5.1. Background of Interviewees
Ten of the responses received were from interviewees affiliated to the Employer who had
previously participated in the research. Two individuals who could not be reached for
interviews during the initial data collection also responded. This brought the total of
interviewees from organisations affiliated to the Employer to twelve. Three of the fifteen
responses were from individuals from organisations affiliated to foreign contractors. During
the main interviews, about twenty per cent of the participants were from the foreign contractor
group whilst eighty per cent were from the Employer. The responses from the foreign
contractor group on the summary of findings constituted twenty per cent of the total number
of respondents (see Figure 9.1).
247
Chapter 9- Validation
Foreign
Contractors
20%
Employer
80%
Figure 9.1: Validation by Participants (Source: Field Data)
In terms of professional affiliation, nine of the participants had law background, three were
engineers and two were quantity surveyors (see Figure 9.2 below).
Quantity
Surveying
13%
Engineering
20%
Law
67%
Figure 9.2: Professional background of Participants (Source: Field data)
The interviewees were asked to answer three questions on the summary of findings. These
were as follows: (i) whether there were other features of the extant dispute resolution
processes which had not been captured by the summary report; (ii) whether there were other
factors accounting for the extant dispute resolution processes other than those identified in the
summary of findings; and (iii) whether the proposed remedial strategies were feasible.
Interviewees’ responses were coded and analysed under three themes representing the three
questions namely ‘features of the extant dispute resolution system’, ‘factors accounting for it’
and the ‘feasibility of remedial strategies’.
248
Chapter 9- Validation
9.5.2.
Results of Analysis
All 15 interviewees stated that the features of the extant dispute resolution processes
captured were comprehensive. For instance, APG observed as follows: ‘The summary
captures the salient features of the extant dispute resolution processes’. PPA1 also stated as
follows: ‘The summary is comprehensive’. Additional comments made by interviewees
related to issues such as lack of adequate knowledge of DRMs, the use of Expert
determination in the energy sector, the use of diplomatic channels to resolve disputes arising
out of projects which are outcomes of bilateral relations between two States and the
relationship between funding and the selection of DRMs. Comments on lack of knowledge of
DRMs and expert determination repeated issues which had already been covered (see sections
7.4.2.2 and 7.5.3). On the use of diplomatic channels, it was observed that, even within such
contexts, the bilateral parties resort to mediation or negotiations. In effect, the use of
diplomatic channels underscored the need for ADR preparedness.
Comments relating to the relationship between funding and the selection of DRMs
stemmed from the finding that DRM selection was imposed by funding agencies. Whilst
CPE3 insisted that the Employer had a role in the selection of DRMs, CPR1 was not
comfortable with the idea of ‘imposition’. CPR1 provided a clarification on the issue in the
following excerpt:
The choice or selection of any dispute resolution mechanism is not made by third
parties (funding agencies). The Contract Agreements in use in the construction
industry (eg the road sector) are the FIDIC conditions of contract or are modelled on
FIDIC and the tiers or the various forms of dispute resolution mechanisms are
provided in those contract forms and therefore parties exercise their choice or choices
of a dispute resolution mechanism within the parameters of those provided in any
particular form of contract. The choice is not foisted on parties by the funding
agencies. Parties have to work with and within the set of applicable documents tied to
a loan or a grant. Ultimately the funding source determines the gamut of documents
that drive the implementation of the project both in form and substance. I also think
the funding agencies perceive that international arbitration is the most transparent as
compared with the others.
What is missing in the excerpt is the fact that the FIDIC forms attached to grants and loans
249
Chapter 9- Validation
invariably reflected the dispute resolution policies of the funding organisations (see Gerber,
2001; Ndekugri et al., 2014). The FIDIC Conditions of Contract provided parameters within
which parties selected DRMs. Negotiations relating to DRMs were held within the confines of
those provisions in the FIDIC form. In effect, funding requirements had a major impact on
which DRMs parties eventually agreed.
Again, the fifteen interviewees found the factors accounting for the current dispute
resolution processes enumerated to be comprehensive. Additional comments covered issues
such as causes of disputes, the threat of blacklist and disputes between contractors and subcontractors. Whilst the last issue is outside the scope of this work, the other issues had already
been addressed (see section 7.3.5 and 7.2.2.3).
The feedbacks on the remedial strategies were equally positive. The interviewees were
unanimous in their endorsement of the feasibility of the strategies. CPF1 observed as follows:
The proposed remedial strategies are deemed to be smart, pragmatic and practical…As
designed, formulated and structured the Dispute Resolution Efficiency Cycle is
considered a workable mechanism that will refine the extant dispute resolution
processes’.
To APN, the ‘remedial strategies outlined are critical to the successful implementation of
a holistic infrastructure dispute resolution process’. On his part, APG noted as follows: ‘I
endorse the remedial strategies proposed and have nothing to add. I think an application of
the strategies would enhance competence in the dispute resolution process as envisage in
your findings’. CPA2 also observed thus: ‘I think the remedial measures suggested are broad
enough and your suggestions on how to remedy the shortfalls you have identified are very
apt’.
However, interviewees such as CPE3, APE, CPA9V and APN were of the view that a
successful implementation of the remedial strategies will depend on political will. For
instance, APN observed that the political oversight of the A-G, who may not have expertise in
the subject of infrastructure-related construction dispute resolution, may well stifle effective
250
Chapter 9- Validation
implementation. The establishment of special units within the A-Gs also received a number of
comments. Whilst two-thirds of the interviewees were optimistic that the units will be useful,
the other third were of the view that its success will depend on getting the right mix of
expertise, overcoming the problem of lack of coordination between A-Gs and MDAs and
insulating the proposed units from political interference. Some concern with overstaffing at
the A-Gs was expressed but this was countered by another view which insisted that the A-Gs
must spearhead efforts at improving dispute resolution because they eventually possess the
legal mandate to deal with such disputes.
As an addition to the recommendations on post-dispute resolution evaluation, it was
suggested that the A-Gs may consider instituting ‘a forum annual or otherwise, at which the
failures and successes of any dispute resolution mechanism involving GOG as a party could
be shared and discussed to inform future ADR processes’ (CPR1). In sum, feedbacks on the
summary of findings from interviewees were positive, with interviewees largely endorsing the
outcome of the study as reflecting their experiences. The remedial strategies were deemed
feasible.
9.6.
Transferability
This concept is the qualitative equivalent of generalizability. Stake (1995) posits that the
primary essence of case study is not to understand other cases. He writes, ‘our first obligation
is to understand this one case’ (Stake, 1995, p.4). This assertion is true of qualitative studies
generally. Contextual uniqueness rather than generalizability is the preoccupation of
qualitative research. However, Flyvbjerg (2006) holds the view that the findings from a single
or small number of cases can be generalised as much depends on the case in question and how
it is chosen. Flyvbjerg (2006) argues further that many well-known scientific experiments
were single-case experiments which did not involve randomly selected large samples. Case
study findings can also be used to adjust grand generalisations (Stake, 1995). Flyvbjerg
251
Chapter 9- Validation
(2006), on the same issue, indicates that case study can be used for generalisation using Karl
Popper’s (1959) test of ‘falsification’. Borrowing Popper’s example of the black swan, he
argues that where the position remains that “all swans are white”, a discovery of a black swan
will falsify the earlier proposition and lead to a revision of the theory on swans. Such a
contribution by the single case will have general implications for the pre-existing proposition,
thereby leading to a revision of the generalisation. He concludes that case study is particularly
better placed to identify the ‘black swan’ as it emphasises on depth.
Notwithstanding the fact that the findings of this study stemmed from Ghana as a case,
there is a possibility of naturalistic generalization. As Stake (1995, p.85) put it, ‘people can
learn much that is general from single cases. They do that partly because they are familiar
with other cases and they add this one in, thus making a slightly new group from which to
generalize…’ Readers from other developing countries who may be interested in this study
are likely to be familiar with related experiences. The findings in this study will either add to
such experiences or help modify previous generalizations.
9.7.
Dependability and Confirmability
The concept of dependability is akin to the quantitative concept of reliability. Whilst
transferability focuses on whether the findings will be applicable to other context, the concept
of reliability address the question whether the findings will apply at other times. In other
words, can the findings be replicated? The concept of dependability admits of the changing
nature of social reality and thus requires that any future attempts at replication will bear this
fact in mind. Actors can change their minds. They may be influenced by new experiences and
may therefore interpret their world differently at a different time. However, with this
assumption in mind, steps were taken in this study to leave an audit trail of steps and
procedures followed in this study. Explicit descriptions of the research design, data collection
252
Chapter 9- Validation
and analysis have been provided. Materials used in this study have also been securely kept for
future reference.
Confirmability is about objectivity; whether a neutral party going through a similar process
will arrive at similar conclusions. The challenge objectivity poses in qualitative research is
acknowledged. In this study, attempt at confirmability was through constant self-reflection.
The steps taken to ensure credibility, transferability, dependability and confirmability of the
research outcomes are summarized in Table 9.2 below.
Table 9.2 : Practical Steps towards ensuring Quality of the Research
Evaluation Criteria
Credibility
Transferability
Dependability
Confirmability
9.8.
Practical Steps
Different data sources (documentary sources, archival records
and interview transcripts) were triangulated. Corroborative
evidence was sought from different participants to confirm the
identified categories.
Findings from the data collection as reflected in categories
were subjected to verification by key participants (member
checking).
A chain of evidence was built from the case study questions
through to the case study conclusion.
At the data analysis stage, rival explanations were addressed to
ensure that the account was plausible.
To ensure tentative generalizability, a robust framework
grounded in the data collected emerged at the end of the study.
Rich, thick description is used to convey the findings.
A database of research material has been kept from the
beginning of the research till the end.
The procedures being followed throughout this work have also
been documented.
Transcription was checked to ensure accuracy and avoid
mistakes.
The findings have been scrutinised by at least one external
auditor.
Research Impact
Dissemination of the findings of the studies through publications is one of the principal
means through which the research may make an impact on society. So far, one journal article
entitled ‘Arbitrability in the Context of Ghana’s new Arbitration Law’ has been published in
253
Chapter 9- Validation
the International Arbitration Law Review, an internationally recognised refereed journal. Two
other journal papers on ‘the interplay between contract and public law and the implications
for major infrastructure transactions’, and ‘the complex nature of the Employer and the
implications for claims and disputes’ are currently under review. Refereed journals targeted
include the Public Procurement Law Review and the International Journal of Project
Management.
In addition to three journal papers, two peer reviewed papers were presented at two
separate conferences namely the RICS Construction and Property Conference (COBRA,
2011) and the Annual Association of Researchers in Construction Management (ARCOM,
2012) Conference. Feedbacks from reviewers of the first of the two papers titled ‘Resolution
of Disputes arising from Major Infrastructure Projects in Developing Countries’ were taken
on board in the design of the study. The second paper titled, ‘The Influence of Procurement
Methods on Dispute Resolution Mechanism Choice in Construction’ examined the
relationship between procurement methods and dispute resolution mechanisms. The feedback
from this paper also influenced the discussions on the relationship between procurement and
dispute avoidance and resolution in this study.
There have been indications that the journal paper on arbitrability is currently part of the
teaching materials in use at the Ghana School of Law. Again, the second article on interplay
between contract and public law addresses one of the critical national constitutional issues
which have had enormous impact on international transactions involving Ghana. It is expected
that the paper will make contributions towards policy change.
9.9.
Summary
In this study, Lincoln and Guba’s (1985) credibility, transferability, dependability and
confirmability were used, instead of internal validity, external validity, reliability and
objectivity, to establish the trustworthiness of the research. Respondent validation and
254
Chapter 9- Validation
triangulation were the main techniques employed to validate the research outcome. Feedback
on the summary of research findings sent to interviewees for their comments were positive.
255
Chapter 10- Findings, Conclusions and Recommendations
CHAPTER TEN
256
Chapter 10- Findings, Conclusions and Recommendations
CHAPTER TEN - FINDINGS, CONCLUSIONS AND RECOMMENDATIONS
10.1.
Introduction
This study examined the resolution of infrastructure-related construction disputes in
developing countries using Ghana as a case study. In this chapter, a brief overview of the
study and how the objectives of the research have been met is presented (section 10.2). This is
followed by an outline of the summary of the research findings (section 10.3). A number of
contributions that the research has made to knowledge are also discussed from two
perspectives; general addition to the body of knowledge (10.4.1) and contribution to practice
(section 10.4.2). The implications of the research findings and limits of the research are also
highlighted (section 10.5 and 10.6). Finally, recommendations for further research are made.
10.2.
Research Overview
This study aimed at a critical examination of developing countries’ experiences of
infrastructure-related construction dispute with the view to develop strategies for efficient and
effective resolution. To achieve this aim, a number of objectives were set and pursued. These
were as follows:
1. a critical review of the literature on the state and trends of infrastructure development
in developing countries, the processes relating to major project acquisitions and how
construction disputes arising out of such transactions were resolved;
2. identification and examination of features and context of the key parties involved in
construction and civil engineering contracts relating to major infrastructure projects;
3. an investigation into aspects of the legal framework for infrastructure procurement
relating to dispute resolution such as the contract formation process, procurement
methods and the impact of procurement on dispute resolution;
257
Chapter 10- Findings, Conclusions and Recommendations
4. examination of the legal framework for resolving disputes arising out of major
projects including the processes involved from the emergence of a dispute to its final
determination;
5. identification of challenges to the extant modes of resolution including barriers to the
use of methods other than litigation and international commercial arbitration; and
6. development of an explanatory framework and remedial strategies for the extant
construction dispute resolution processes.
Sections 10.2.1 and 10.2.2 below and the section on summary of research findings (section
10.3) outline how the research objectives were achieved.
10.2.1.
Objective One
The first objective was achieved through review of previous studies as reported in Chapters
two, three and four. Chapter two examined the current state and trends in infrastructure
development in developing countries. The review disclosed that growing research has found a
critical linkage between infrastructure development and economic development in developing
countries. Consequently, many States and bilateral and multilateral development organisations
have focused attention on infrastructure projects in developing countries during the past two
decades. Ghana was no exception to this development. In the face of huge infrastructure
deficits, the State has stepped up emphasis on infrastructure development. In Chapter three, a
review of the literature on infrastructure projects procurement (methods and practices) in
Ghana was presented. The traditional procurement method was dominant in infrastructure
projects delivery. There was also information on the use of other methods such as design and
build, EPC and PPP. Where donor funds were involved, procurement guidelines of funders
were used. There were several deficiencies with the existing procurement process and these
resulted in claims and disputes. Further, it was observed that procurement was mainly driven
by funding needs and its impact on dispute resolution was hardly considered.
258
Chapter 10- Findings, Conclusions and Recommendations
In chapter four, a review of the literature relating to how construction-related disputes
arising from major infrastructure projects were resolved was presented. The evaluation
focussed on both developed and developing countries. This approach was adopted to provide
a comparative basis for assessing practice in developing countries, including Ghana.
Construction-related disputes were common occurrences in both developed and developing
countries (see section 4.2.3). However, there is a general move towards resolving such
disputes by less costly ADR mechanisms other than litigation and arbitration in developed
countries. Mechanisms such as mediation, expert determination, adjudication and DRBs are
increasingly being used to resolve construction related disputes in the United Kingdom,
United States, Hong Kong, Australia and Singapore. The same cannot be said for developing
countries. Evaluation of the relevant literature disclosed that international arbitration was the
main dispute resolution mechanism for infrastructure-related construction disputes arising
from major infrastructure projects. There was limited literature on resolution mechanisms
which were employed by parties prior to recourse to international commercial arbitration.
10.2.2.
Objectives two to six
These objectives were achieved through collection and analysis of field data. Using a
qualitative research approach informed by the interpretivist paradigm, data were collected
through interviews and documents and analysed using grounded theory principles and
doctrinal legal analysis (see chapters five and six). The outcomes of the data analysis are
reported in chapter seven. The above objectives were addressed by themes which emerged as
outcomes of the data analysis. The theme ‘Features and Context of Parties to the dispute
resolution processes’ addressed the second objective of the study (see sections 7.2, 10.3.2.1
and 10.3.2.2). The ‘Procurement’ theme responded to the third objective of the study (see
sections 7.3 and 10.3.2.3). The fourth and fifth research objectives were addressed under the
themes ‘the Dispute Resolution Processes’ (see sections 7.4 and 10.3.1) and ‘Barriers to the
259
Chapter 10- Findings, Conclusions and Recommendations
use of ADRMs’ (see sections 7.5 and 10.3.2.5). The sixth objective of the study was
addressed under the theme titled ‘Remedial strategies’ (see sections 8.5 and 10.3.3).
10.3.
Findings
The findings of the study are divided into three parts namely, the extant dispute resolution
processes, factors accounting for them and remedial strategies.
10.3.1. The Extant Dispute Resolution Processes
The study found that Engineer’s determination, negotiation and international arbitration
were the most regularly used dispute resolution mechanisms (DRMs) by parties to major
infrastructure projects in Ghana. Other mechanisms such as Dispute Adjudication Boards
(DAB), Expert determination, Mediation and Conciliation were rarely used. The implication
is that a whole category of intermediary dispute resolution mechanisms were often not
utilised. The only time third party neutrals got involved in the process of dispute resolution
was when arbitration was used or the parties found themselves in court. This made the
resolution process expensive and time consuming. In some cases, the resolution process
oscillated between interest-based options and right-based options. For instance, parties who
were arbitrating were able to continue with negotiations, and in exceptional cases, attempted
mediation whilst the arbitration was on-going.
The dispute resolution processes suffered from specific difficulties including high dispute
resolution cost (in terms of money and time expended), delays, low satisfaction with
international arbitration outcomes and negative effect of international arbitration on
relationships between parties. The study also disclosed substantial challenges with dispute
resolution system design. Actual parties to major construction transactions had limited
influence over the selection of dispute resolution mechanisms and procedures. Dispute
resolution clauses were negotiated within the parameters of the clauses in nominated
Conditions of Contract. The Employer neither had policies in place to guide the process nor
260
Chapter 10- Findings, Conclusions and Recommendations
did it have overriding dispute resolution objectives in place to help negotiators make decisions
about dispute system design. The Employer had resigned to the fact that funders made choices
about dispute clauses and literally went along with such preferences. No effort was made to
identify opportunities to ensure that previous dispute resolution challenges did not recur.
Some aspects of the dispute resolution processes also lacked transparency and
accountability. Parties who failed to settle disputes through negotiations and were reluctant to
proceed to international arbitration often appealed to politicians for their intervention. It was
difficult to judge the usefulness of such interventions as they were usually informal and bereft
of any accountability. Absence of systematic and continuous education and training of
professionals also resulted in a situation where parties stuck to dispute resolution mechanisms
they were comfortable with, such as negotiations.
There was no national policy on infrastructure-related construction dispute resolution.
Construction and engineering disputes were treated like any other dispute despite their
peculiar features. There was no written policy or guideline on the use of ADR by the
Employer on disputes arising out of public projects. Essentially, State attorneys who decided
to use dispute resolution mechanisms other than litigation and arbitration had no written
guidance as to choice or procedure.
10.3.2. Factors Accounting for the Extant Dispute Resolution Processes
It was found that the dispute resolution processes were not merely the product of the
parties’ agreement but their features, actions and context. The main parties involved in the
process were the Employer (the State and its Agencies) and foreign contractors.
10.3.2.1.
The Complex Employer
The Employer was constituted by several institutions (sub-units). Each of these entities
played different but vital roles in the performance of the contractual duties of the Employer.
This made consultations between sub-units and approval seeking a normal part of the
261
Chapter 10- Findings, Conclusions and Recommendations
Employer’s operations (see section 7.2.1.3). Consequently, the Employer’s performances
under construction and engineering contracts naturally suffered delays due to the complex
nature of its decision-making processes (see section 8.3.3). The implications of the complex
nature of the Employer on dispute resolution were amplified by deficiencies associated with
the operations of its sub-units.
For instance, the A-Gs suffered operational difficulties during resolution of disputes as a
result of lack of effective cooperation and coordination between them and other MDAs.
Again, lack of information flow between the A-Gs and other MDAs affected the former’s
ability to respond to disputes against the Employer and these affected efforts at settlement and
effective dispute resolution (see section 7.2.1.3 and 8.3.3.3).The Employer also had serious
human resource deficiencies. The roles of the A-Gs in dispute resolution were indicatively
described under the in vivo codes ‘jacks of all trades’ and ‘fire-fighting’. The few legal
professionals at the Civil Division of the A-Gs were saddled with the roles of providing legal
advice to all the other agencies of State, negotiating and reviewing contracts from the MDAs
and representing the Employer at all dispute resolution forums. There was no dedicated team
of experts in charge of construction and engineering disputes. The MDAs involved with the
initial stages of dispute resolution also lacked the requisite training.
By virtue of its very nature as a political organisation and its practices, political
interference in procurement and dispute resolution were regular occurrences. Political
interference was cited as one of the major sources of disputes. In some cases, politicians
usurped the roles of technical entities responsible for managing major projects and gave
instructions to contractors to move to site prior to the conclusion of contracts. There was
evidence of resort by contractors to political officeholders for solutions to construction
disputes (see sections 7.2.2.2). Again, there was evidence some aggrieved contractors did not
pursue claims or disputes against the Employer for fear of being blacklisted. This
262
Chapter 10- Findings, Conclusions and Recommendations
phenomenon had a particularly telling effect on the process of dispute resolution as it stifled
the use of DRMs (see sections 7.2.2.3). As the Government's budgetary allocation of internal
resources was unable to meet its infrastructure needs, there was extensive reliance on external
funding and this, in turn, influenced decisions on choice of procurement strategies and
selection of dispute clauses.
10.3.2.2.
Foreign Contractors
By virtue of their nature, origin and perception of the domestic justice delivery system,
foreign contractors generally opted for international arbitration. Fairness, effectiveness and
efficiency, confidentiality and neutrality were some of the other reasons offered for the
general preference for ICA (see section 7.2.3).
10.3.2.3.
The Legal Framework for Procurement and Dispute System Design
The main legislation governing procurement in Ghana was the Public Procurement Act,
2003 (Act 663). However, the provisions of Act 663 did not apply where an applicable loan
agreement, guarantee contract or foreign agreement provided different procedure for the
utilisation of such funds (see section 14 and 96). In effect, there were two sources of
procurement rules: (a) those under Act 663 which were mainly statutory; and (b) those under
contractual arrangements between the Employer and funding organisations (see section
7.3.1).The procurement process for major infrastructure projects was largely driven by
funding requirements. There were four main sources of funding for major infrastructure
projects in Ghana. These were Government of Ghana (GoG), donors/bilateral and multilateral
funding organisations, joint GoG and donors and private sources. GoG funding, the traditional
source of funding was made available by the State through annual budgetary allocations.
However, as Government's budgetary allocation of internal resources was unable to meet its
infrastructure needs, there was extensive reliance on external funding (see section 7.2.2.4).
263
Chapter 10- Findings, Conclusions and Recommendations
External funding arrangements for infrastructure projects often came with conditions
relating to procurement, the use of nominated Conditions of Contract and selected dispute
resolution clauses. Regarding Conditions of Contract, both the World Bank and USAID
expressly demanded the use of FIDIC suite of Conditions of Contracts on their projects.
European Union funded projects were executed under EU Conditions of Contract. Other
multilateral institutions also subscribed to the FIDIC Conditions of Contract. Most of the
fifty-six interviewees for this study identified the FIDIC suite of contract as the most popular
for major infrastructure projects in Ghana (see section 7.3.2.1).
Clause 67 of the FIDIC Red book, 1987 Edition required parties to resolve disputes by
Engineer’s determination, amicable settlement and international arbitration. Clause 20 of the
FIDIC Red book, 1999 and the MDB Editions replaced engineer’s determination with DAB.
During negotiations on dispute clauses, the most parties did was to agree on project-specific
details aimed at operationalising the dispute mechanisms outlined in the General Conditions.
As a matter of regular practice, the following terms were agreed by the parties: (i) the entity
or body which will administer the international arbitration; (ii) the venue; (iii) the arbitration
rules which will apply; (iv) the governing or applicable law; (v) the language; and (vi)the
number of arbitrators and the selection process. Notably, there were no indications at all that
parties provided details of what they were to do or mechanisms they were to use during the
amicable settlement period. It was therefore not surprising that in practice, that period was
utilised for further negotiations. The parties, especially, the Employer regularly failed to
explore possibilities to improve the dispute resolution system design.
Another aspect of the existing legal framework on procurement of major infrastructure
project which had a bearing on the extant dispute resolution processes was the interplay
between public law requirements and major construction and engineering contracts. Beyond
satisfying the requirements of contract law, parties to major infrastructure transactions
264
Chapter 10- Findings, Conclusions and Recommendations
involving the State were obliged to comply with the public law requirement of seeking
parliamentary approval for such projects (see section 7.3.2.4). Failure to do so rendered the
affected transaction void. Declaring a contract void for non-compliance with constitutional
provisions had the collateral effect of stifling the enforcement of contractual obligations and
contractually agreed dispute mechanisms. Lack of clarity of the public law requirement was
also a source of disputes between the Employer and foreign contractors (see the Faroe
Atlantic, Balkan Energy and Waterville Cases).
10.3.2.4.
The Legal Framework for Infrastructure-related Dispute Resolution
The legal framework for dispute resolution was essentially contract-based. As part of the
construction contract, parties determine how future disputes were to be resolved. There was
no specific legislation regulating how construction dispute were to be resolved. The
provisions of the Alternative Dispute Resolution Act, 2010 (Act 798) generally applied to all
cases including construction disputes, except those specifically excluded under section 1 of
the Act such as matters relating to the enforcement and interpretation of the Constitution, the
environment or public and national interest. The question still remains as to whether this
exclusion does not preclude parties to major infrastructure-related construction disputes
involving the State from resolving such disputes by the mechanisms and procedures
advocated under the Act.
The ADR Act established an Alternative Dispute Resolution Centre. It was apparent that in
establishing the Centre, the legislators did not have cases where the Government of Ghana
was a party in mind. The Centre (if set up) was thus likely to suffer the same fate as the
national courts since they will be perceived as lacking neutrality. Local private infrastructure
for administering ADR was burgeoning. However, even the few entities which stood out as
well-established organisations such as the Ghana Arbitration Centre and Gamey and Gamey
Group were yet to gain the trust of parties to major infrastructure disputes.
265
Chapter 10- Findings, Conclusions and Recommendations
10.3.2.5.
Factors inhibiting use of Alternative Dispute Resolution Mechanisms
There were other factors which influenced the dispute resolution processes by inhibiting
the use of intermediary ADR. These included public suspicion regarding the use of ADR to
resolve public disputes, fear of failure to meet expectations if ADR is used instead of
litigation or arbitration, the Employer’s lack of policy and guidelines for the use of ADR by
its sub-units and poor record keeping (see sections 7.5.). Limited knowledge of the wide range
of dispute resolution mechanisms available, the adversarial culture, negative perceptions
about ADR and limited ADR infrastructure and expertise were some of the other barriers to
the use of intermediary mechanisms in construction disputes.
10.3.3. Remedial Strategies
In response to the current state of the dispute resolution processes and the factors identified
as accounting for it, four sets of remedial strategies were proposed. These were to help
improve the effectiveness (achieving set objectives) and efficiency (employing well-organised
and efficacious procedures) of the dispute resolution processes (see section 8.5). The remedial
strategies are as follows: (i) addressing structural and contextual issues; (ii) paying attention
to dispute resolution system design; (iii) focusing on dispute avoidance and streamlining the
resolution process; and (iv) conducting post-dispute resolution evaluation of outcome.
10.3.3.1. Addressing structural and contextual issues
Parties to major infrastructure contracts, particularly the Employer, need to take specific
steps to prepare the context within which major infrastructure procurement and related dispute
resolution take place. A number of suggestions for preparing the infrastructure project setting
for dispute resolution have been made (see Table 8.2). These include learning from past
experiences (create database of past disputes and how they were resolved, challenges etc.),
investigating the current cost of dispute and dispute resolution and developing specific policy
with clear overriding objectives for dispute resolution in the context of infrastructure projects.
266
Chapter 10- Findings, Conclusions and Recommendations
In crafting policy and negotiation positions, it is expected that the relevant contextual factors
will be considered. Other suggestions for preparing the dispute resolution context include
developing standards for the use of less known dispute mechanisms, streamlining institutional
roles in dispute resolution and providing required expertise. Additionally, regular formal and
informal education and training of parties and practitioners is required. So is improvement in
contract management practices.
10.3.3.2. Paying attention to Dispute Resolution System Design
Five specific strategies are recommended for adoption and utilisation during contract
negotiations, particularly the aspect on dispute clauses. Firstly, beyond the current practice of
limiting attention to the selection of venue, governing law and rules, language, and selection
of third party neutrals, negotiations on dispute clauses must focus on establishing a dispute
resolution framework or structure capable of achieving the overriding dispute resolution
objectives of the Employer. Secondly, negotiations on dispute clauses must aim at addressing
problems observed with previous dispute resolution experiences. Thirdly, negotiations on
dispute clauses need to incorporate new terms on specific possible intermediary resolution
mechanisms which parties will utilise during the period of amicable settlement. Further, staff
of the MDAs must receive regular training to keep them abreast with their contract
negotiation responsibilities. Finally, the A-Gs must have a dedicated team whose main
responsibility will be to perform its contract review role.
10.3.3.3.
Dispute Avoidance and Resolution
It is recommended that the Employer focuses on enhancing dispute avoidance and
management. Strategies which can be employed to realise this focus include developing a
policy on dispute prevention and management, using procurement methods which encourage
parties to focus on reducing disputes, using standing neutrals and training staffs responsible
for projects to be aware of and comply with the Employer’s policy on dispute avoidance and
267
Chapter 10- Findings, Conclusions and Recommendations
management (see section 8.3.3.1). The Employer must consider having a dedicated team at
the A-Gs which will focus specifically on the resolution of construction and engineering
disputes which are referred to the organisation by MDAs. The Employer must also focus on
the use of intermediary dispute mechanisms in appropriate cases. The decision to use a
particular dispute resolution process must be made in accordance with the proposed
Guidelines on the use of ADR. Finally, the Employer must take active cost-cutting measures
during international arbitration proceedings by implementing agreements on cost-sharing,
cost-capping and introducing rules of evidence which will make it possible for evidence to be
taking from witnesses in Ghana or have hearings conducted in Ghana.
10.3.3.4.
Post dispute resolution –Evaluation of Outcome
There must be an active evaluation process after every dispute resolution process. Such
process must focus on ascertaining the extent to which the process achieved the dispute
resolution objectives of the Employer, the shortfalls or underperformances, the innovations
and lessons to improve future processes.
10.3.3.5.
The Dispute Resolution Efficiency Cycle
The four sets of remedial strategies above constitute the components of what is referred to
in this study as the Dispute Resolution Efficiency Cycle. The Cycle has been explained in
detail under section 8.5.5. The structural and contextual issues focus on the pre-project stage.
The dispute system design strategies focuses on the contract formation stage where the parties
agree on arrangements for future dispute resolution. The third and final sets of strategies
target the actual dispute resolution stage and the post-resolution evaluation stage respectively.
Improvements at each stage affect the other stages of the Cycle. Consequently, continuous
improvements at each stage will eventually lead to overall improvement in the dispute
resolution processes over time (see Figure 8.1). The reverse is also true. Lack of improvement
at one stage will impact activities at the other stages.
268
Chapter 10- Findings, Conclusions and Recommendations
10.4.
Contribution to Knowledge
An original contribution to knowledge is a key criteria in judging doctoral research
(Phillips and Pugh, 2005; Wellington, 2010). A study of institutional policies of twenty
universities in the United Kingdom revealed that all the policies examined identified original
contribution to knowledge as a key criterion for judging doctoral work (Tinkler and Jackson,
2000). The concept of making an original contribution to knowledge has been interpreted to
cover various activities. Phillip and Pugh (2005) and Wellington (2012) identify nine and
seven ways respectively in which originality can be demonstrated. These include conducting
an empirical work that has not been done before, applying new methods or approaches to an
existing area of study, using a well-known method or technique to study a new subject,
employing a mixture of different methods in a study or replicating an earlier study. The
contribution that this study has made to knowledge is examined from two perspectives
namely, substantive contribution to the field of dispute resolution particularly in the context of
infrastructure-related construction disputes and contribution to practice. Section 9.8 provides
details on dissemination of the outcomes of the study.
10.4.1 Contribution to the Field of Dispute Resolution
The study has contributed to the body of knowledge on infrastructure-related construction
dispute resolution in the developing world, particularly, Ghana. Prior to this inquiry, there was
no known empirical research which specifically examined the extant dispute resolution
processes for infrastructure-related construction disputes. The study has provided empirical
evidence which addresses some of the gaps identified in the literature. For instance, the
literature identified ICA as the main dispute resolution process. There was dearth of
information on all the other resolution mechanisms available to parties involved in such
transactions. What transpired between parties from the emergence of a dispute to its eventual
submission to international arbitration remained largely unexplored. By investigating the
269
Chapter 10- Findings, Conclusions and Recommendations
Ghanaian experience, this study has made available new insights into how parties to
infrastructure projects in developing countries dealt with such disputes prior to resort to ICA.
The study has provided a critical evaluation of the extant dispute resolution processes in
Ghana. It has found that there was lack of emphasis on the use of intermediary mechanisms
and third party neutrals. This implied that parties had limited dispute resolution options. Apart
from providing descriptive data on the existing dispute resolution processes, the study has
also explored factors which have shaped the dispute resolution processes. Again, this is the
first known study on the subject in Ghana.
Much of the literature on dispute resolution from both developed and developing countries
place considerable emphasis on identification of appropriate dispute resolution processes,
their characteristics and how they were to be utilised (Cohen and Gould, 1998; Brown and
Marriot, 1999; Hibberd and Newman, 1999; Gaitskell, 2005; Chapman, 2006; Gaitskell,
2006; Blake et al., 2011). There was limited emphasis on the extent to which the dispute
system design and the context in which transactions took place affected the dispute resolution
processes at the back-end. The study of the Ghanaian experience has shown that effective and
efficient dispute resolution is not just about the actual back-end resolution processes but also
the front-end planning (which determines the systems, processes and procedures for future
dispute resolution). Thus, the study has contributed to broadening understanding of factors
that influence dispute resolution.
Again, whilst the literature indicated that disputes emerging from major infrastructure
projects in the developed world are increasingly being resolved by less costly and formal
methods such as mediation, expert determination and adjudication, there was limited
information on the viability of such alternatives in the developing world. There was also lack
of information on why construction disputes were not resolved by ADR methods. This study
has identified a number of factors which inhibited the use of ADR methods in the Ghanaian
270
Chapter 10- Findings, Conclusions and Recommendations
context (see section 7.5). Though identified in the Ghanaian context, these factors are
indicative of the barriers to ADR use in other developing countries.
10.4.2 Contribution to Practice
The study has also contributed to practice in two specific ways. Firstly, it has identified
some of the main characteristics and difficulties with the existing construction dispute
resolution processes (see sections 8.2 and 8.3). Secondly, remedial strategies have been
identified (see section 8.5). Four sets of strategies integrated into a single theoretical model
called the Dispute Resolution Efficiency Cycle have been recommended. It is expected that
the diagnosis of the problems with the dispute resolution processes will provide impetus for
the implementation of the proposed remedial strategies.
10.5.
Implications of the Research Findings
The research findings have policy, legal and institutional, and geographical implications.
Firstly, the findings call for policy changes. Although further inquiry may be needed to
determine the broad confines of the required changes, it is submitted that the proposed
remedial strategies can be a valuable starting point. The policy must establish an overriding
objective or set of objectives for all construction dispute resolution processes. It must also
establish or demand the drawing up of guidelines on the use of ADR mechanisms by public
institutions. The objectives and guidelines will become the reference point for dispute
resolution goals of individual projects and will also provide guidance on the dispute resolution
system design.
Secondly, the findings of the study imply a need for institutional and legal reforms.
Streamlining institutional arrangements for dispute handling will be particularly crucial. This
will involve providing guidelines on when MDAs will have to refer disputes or differences to
the A-Gs and the kind of cooperation that must exist among various government institutions
for purposes of dispute resolution. Legal reforms
271
must
focus on the following: (a)
Chapter 10- Findings, Conclusions and Recommendations
streamlining the law on infrastructure procurement; (b) establishing standards for the use of
dispute resolution mechanisms by public entities; (c) providing guidelines on conditions under
which the use of specific dispute resolution mechanisms should be encouraged; (d) improving
contract administration; (e) setting standards for contract negotiations generally and
negotiation of dispute clauses in particular; (f) establishing dedicated teams responsible for
specific technical disputes such as construction and engineering disputes; and (g) establishing
and maintaining databases on disputes resolution. The knowledge of staff whose schedules
touch on dispute resolution must be upgraded through properly tailored continuing
professional development programmes, which emphasise practice. Specific measures need to
be employed to deal with barriers to the use of intermediary dispute resolution mechanisms
(see section 7.5).
For foreign contractors, there is the need for policy rethink. The findings suggested that
contractors had two options after negotiations had failed; they either refrained from pursuing
disputes against the Employer or submitted disputes to international arbitration. The
consequence of the first option was that contractors could not obtain redress for disputed
claims for fear of being blacklisted. For those who submitted disputes to international
arbitration, the consequence was the likelihood of loss of future business opportunities. There
was a middle ground which was hardly explored and encouraged by contractors, that is, using
intermediary dispute mechanisms such as mediation and DABs more regularly. The findings
in this study imply that contractors will need to consider the middle ground which is likely to
save business relationships with the Employer and still enable them to receive due
compensation for breaches.
Finally, the findings also have implications for other developing countries. As
demonstrated by the literature, ICA remains the dominant resolution mechanism for
infrastructure-related construction disputes in many developing countries especially those in
272
Chapter 10- Findings, Conclusions and Recommendations
Africa (Cotran and Amissah, 1996; Asouzu, 2001). This study has shown that creating
effective dispute resolution systems in developing countries require more than the dominant
use of ICA. A holistic approach as captured by the Dispute Resolution Efficiency Cycle is
required (see section 8.5.5). Firstly, developing countries need to pay attention to structural
and contextual issues which shape their respective dispute resolution processes. Secondly,
developing countries must pay attention to the process of dispute system design. Thirdly,
there is the need for a renewed focus on dispute prevention and management in addition to
resolution. This can be achieved through policy and regulatory reforms of procurement
strategies and contract administration. Finally, mechanisms for post-dispute resolution
evaluation should be established to draw out lessons which may eventually be useful to future
projects.
10.6.
Limitations of Findings
The outcomes of this study have three sets of limitations, namely geographical,
methodological and subject-matter limitations.
10.6.1 Geographical Limitation
The findings of this study are primarily applicable to the resolution of construction
disputes from major infrastructure projects in Ghana. However, it is worth noting that the
study focused on Ghana because of certain specific characteristics such as its status as a
developing country, the involvement of the State and its agencies in infrastructure
development and the reliance on external funds and foreign contractors to execute projects.
For developing countries which share similar characteristics as those outlined, the findings of
this study will be a useful guide to further inquiries into their specific situations (see section
9.6). This argument is strengthened by the fact that grounded theory principles were used to
analyse the data. This made it possible for the findings to be abstracted into concepts which
can easily be identified under the systems of other jurisdictions.
273
Chapter 10- Findings, Conclusions and Recommendations
10.6.2 Methodological Limitations
The findings of this inquiry are also subject to two methodological limitations namely
concerns with the philosophical paradigm employed and issues of representativeness and
generalisation of the findings. The interpretivist philosophical paradigm employed in this
inquiry operate on the basis of the assumption that individuals or groups make meaning of
their world and are able to contribute to efforts to understand it (see section 5.2.2). Social
realities and their meanings are constructed by social actors as they interact with each other in
their natural settings (Berger and Luckmann, 1967; Bryman, 2008). Thus, it admits of
multiple accounts of social reality. Accordingly, findings of this study must be judged with
the perspective of the underpinning philosophical paradigm in mind.
The limitations associated with case study research have already been examined under
section 9.6). The findings of this study will be useful for naturalistic generalisation. Other
developing countries who may have construction dispute resolution processes similar to those
identified in this research may find the remedial strategies proposed (see section 8.5)
informative and relevant to their own situation.
10.6.3 Subject-Matter Limitation
Three kinds of limitation are considered under this sub-section namely types of dispute,
parties and projects. The study primarily focused on the resolution of infrastructure-related
construction disputes. The process of major infrastructure procurement in developing
countries is often fraught with various kinds of disputes relating to issues such as labour, land
ownership, compensation claims and resettlement issues. The study did not extend to these
types of disputes. Further, the investigation concentrated on main parties to major
infrastructure procurement in Ghana namely the State and its agencies and foreign
contractors. It is acknowledged that, disputes may and do erupt between parties other than the
main parties identified above. There are instances where disputes may arise between a foreign
274
Chapter 10- Findings, Conclusions and Recommendations
design firm and a foreign construction firm or a foreign contractor and a domestic subcontractor. There is also a possibility of multi-party disputes involving three or more parties
(Draetta, 2011). However, the focus of the study was on construction disputes between the
State or its agencies and foreign contractors.
Additionally, the study was confined to specific types of projects described as major
infrastructure projects (see Chapter 2). These are public projects involving the government or
its agencies as clients, and foreign contractors. Nevertheless, some transactions involving
contractors incorporated in Ghana may qualify as major infrastructure projects under this
study, so long as the place of central management and control of the contractor is situated
outside the jurisdiction of Ghana or the transaction has significant foreign elements (see the
Balkan Energy Case).
10.7.
Self-Reflection
The need for researcher self-reflection in qualitative research has already been discussed
under section 9.3.2. The drive to conduct this research was inspired by experiences from
legal practice relating to effects of disputes on businesses and individuals. Approaches to
dispute resolution were often adversarial and generally acrimonious. Lawyers took centre
stage and drove such disputes through the quagmire of court rules sometimes to the detriment
of the interest of their own clients. The observation made in relation to infrastructure-related
construction dispute resolution was that, it appeared to be a matter removed from the domain
of the national courts and handled exclusively outside the jurisdiction by international arbitral
tribunals. These apparent emphases on litigation and international arbitration led to the
question as to why disputes were handled this way. To some extent, the study was approached
with an attitude that questioned the status quo and sought to explain the rationale for it and
possible alternatives. This approach by this researcher undoubtedly influenced how the entire
research was conceptualised. Again, this researcher’s familiarity with the setting of the study
275
Chapter 10- Findings, Conclusions and Recommendations
facilitated access to sites and the interpretation of the data. Familiarity with local jargons and
cultural nuances resulted in a better appreciation of the qualitative data. Consequently, the
researchers motivations, familiarity with the case and legal background undoubtedly
contributed to shape the perspectives on dispute resolution expressed in this work.
Looking back at the trajectory of this research, a number of observations can be made.
Firstly, the review of previous studies rightly focused on identification of the gaps in the
literature. However, little was done to use the rich information from the literature to develop a
conceptual map for the rest of the study. For instance, having reviewed the comparative
literature on dispute resolution from developed countries, the emerging issues such as the
debate on causes of dispute, dispute prevention and management and the increasing use of
ADR could have been used to construct a conceptual framework earlier in the study to guide
the rest of the research.
Secondly, the sampling approach adopted for this study was suitable to the nature of the
problem under investigation but certain initial assumptions made about foreign contractors did
not hold out. It was assumed that foreign contractors were more likely to participate in
research concerning their activities than the Employer. The reverse rather turned out to be the
case. The study could have benefitted from more participation of foreign contractors.
Furthermore, the balance between structure and flexibility led to the choice of Patton’s (1990)
interview guide technique. Reflecting on the semi-structured interviews conducted, it appears
that more attention was given to flexibility than structure. This resulted in the collection of
rich but less structured data. This, in turn, prolonged the period for data analysis. These
valuable lessons will inform the planning of future research.
Finally, time and resource constraints made validation of the research outcome by a wider
population impossible (see section 9.4). Given another opportunity, a broader consultation on
the outcomes of the research, preferably through focus groups, will be considered.
276
Chapter 10- Findings, Conclusions and Recommendations
10.8.
Recommendations for further Research
The study recommends a holistic approach to dispute resolution. Some details of how this
is to be achieved will still need to be critically examined in further studies. These include the
following:
(i)
cost of dispute resolution - a quantitative investigation into the cost of dispute
resolution will complement the qualitative findings in this study (see section 9.4.3).
The emphasis of such an inquiry may be on the quantification of the amount of
money, time and energy expended on dispute resolution. Findings from such an
inquiry will highlight the need to pay more attention to infrastructure-related dispute
resolution;
(ii)
the extent to which streamlining institutional roles and efficient contract
administration can reduce dispute occurrence and enhance dispute resolution in major
infrastructure construction transactions;
(iii)
how to remove barriers to the use of ADR identified in this study. Such further studies
may examine critically how to package continuing education and training for
professionals and parties involved in dispute resolution so as to gradually deal with the
knowledge deficiencies identified in this research;
(iv)
testing out the remedial strategies identified in this study on a live project to refine its
scope and to examine its strengths and weaknesses; and
(v)
exploring the extent to which dispute resolution strategies used in collaborative
procurement strategies such as partnering can enhance resolution of construction
disputes within the context of Ghana and other developing countries.
Efficient dispute resolution processes can be complemented greatly by an effective dispute
prevention policy. Further research in this area will be in line with developments in many
277
Chapter 10- Findings, Conclusions and Recommendations
other jurisdictions (Diekmann et al., 1994; Fenn, 2007; McGeorge et al., 2007; Brewer, 2007;
Danuri et al., 2010).
This study may be replicated in other developing countries. The outcome of such further
inquiries will not only add to the existing literature on the subject but also to the common pool
of known cases from which emerging general principles with wider global application can be
distilled (Stake, 1995).
10.9.
Summary
In this chapter, the key findings, conclusions and recommendations from this study have
been presented. The chapter also specifies how the objectives of the research have been met.
The findings were in three parts namely the state of infrastructure-related construction dispute
resolution processes in Ghana, the factors accounting for them and remedial strategies.
Construction disputes were regularly resolved by Engineer’s determination, negotiations and
international arbitration. On limited occasions, intermediary mechanisms such as mediation
and DABs were used. The process was characterised by high cost of resolution, delays, low
satisfaction with international arbitration outcomes and negative effect of international
arbitration on relationships between parties. It was also found that the dispute resolution
processes were the product of the features, actions and context of the main parties to major
infrastructure projects. The study proposes a holistic approach to efficient and effective
dispute resolution. Four sets of remedial strategies have been proposed. Firstly, contextual and
structural issues affecting dispute resolution need to be addressed. These include creating
databases to capture past experiences, developing a specific policy on infrastructure-related
construction dispute resolution with clear overriding objectives and streamlining roles of
institutions involved in dispute resolution. Secondly, parties need to pay attention to the
design of the dispute resolution system. Additionally, emphases need to be placed on dispute
278
Chapter 10- Findings, Conclusions and Recommendations
avoidance and management in addition to dispute resolution. Finally, post-dispute resolution
evaluation is critical to future improvements.
The study has made contribution to knowledge in the area of infrastructure-related dispute
resolution and practice. The findings have policy, legal and institutional implications for the
parties, especially, the Employer. Notwithstanding the focus on Ghana, the impact of the
study is likely to be far reaching as developing countries with similar characteristics will find
it a useful starting point in their own quest to address their dispute resolution challenges.
Finally, the study has spawned the need for further research into several other issues such as
the need to establish a framework for dispute avoidance and reduction, investigations into the
actual cost of disputes and detail assessment of how barriers to the use of alternative dispute
resolution can be removed.
279
References
REFERENCES
Abd El-Razek, M., Bassioni, H. and Mubarak, A. (2008) Causes of delay in building
construction projects in Egypt. Journal of: Practical Steps towards ensuring Quality
of the Research construction engineering and management, 134(11), pp.831-841.
ADB, JBIC and World Bank (2005) Connecting East Asia: A New Framework for
Infrastructure.
World Bank, 1818 H Street NW, Washington, DC: World
Bank/ADB/JBIC.
Addo-Abedi, F. (1999) Sustainable development of the local contracting industry in a
developing country. Proceedings: The 2nd International Conference on Construction
Industry Development and 1st Conference of CIB TG 29 on Construction in
Developing Countries. Rotterdam, The Netherlands 27-29 October. Rotterdam: The
University of Edinburgh.
Agenor, P.-R., Bayraktar, N., Aynaoui, K. and Moreira, E.P. (2005) Achieving The
Millennium Development Goals In Sub-Saharan Africa: A Macroeconomic
Monitoring Framework. [online]. [Access:8th June, 2011]. Available at:
<http://elibrary.worldbank.org/content/workingpaper/10.1596/1813-9450-3750>.
Agénor, P.-R.. and Moreno-Dodson, B. (2006) Public Infrastructure and Growth: New
Channels
and
Policy
Implications.
[online].Available
at:
<http://elibrary.worldbank.org/content/workingpaper/10.1596/1813-9450-4064>.
Aibinu, A.A. and Odeyinka, H.A. (2006) Construction Delays and Their Causative Factors in
Nigeria. Journal of Construction Engineering & Management, 132(7), pp.667-677.
Akintoye, A., Beck, M. and Hardcastle, C. (2003) Public-private partnerships. Wiley Online
Library.
Al-Momani, A.H. (2000) Construction delay: a quantitative analysis. International Journal of
Project Management, 18(1), pp.51-59.
Ameyaw, C. (2011) Comparative performance evaluation of the traditional design-Bid-Build
(DBB) and Design-Build (DB) procurement methods in Ghana. MSc Thesis, Kwame
Nkrumah University of Science and Technology, Ghana.
Andrés, L.A., Guasch, J.L., Haven, T. and Foster, V. (2008) The Impact of Private Sector
Participation in Infrastructure: Lights, Shadows, and the Road Ahead. 1818 H Street
NW, Washington DC 20433: The World Bank.
Angen, M.J. (2000) Evaluating interpretive inquiry: Reviewing the validity debate and
opening the dialogue. Qualitative Health Research, 10(3), pp.378-395.
Annez, P.C. (2006) Urban Infrastructure Finance from Private Operators: What Have We
Learned
from
Recent
Experience
[online].
Available
at:
<http://elibrary.worldbank.org/search?value1=infrastructure+projects&option1=keyw
ords>.
Anvuur, A., Kumaraswamy, M. and Male, S. (2006) Taking forward public procurement
reforms in Ghana. CIB W107 Construction in Developing Economies International
Symposium -“Construction in Developing Economies: New Issues and Challenges”
Santiago, Chile 18th – 20th January, 2006. Santiago.
Arrowsmith, S. (2005) The Law of Public and Utilities Procurement. 2nd ed. London: Sweet
and Maxwell.
Arrowsmith, S. (ed.) (2010) Public Procurement Regulation: An Introduction. EU Asia InterUniversity Network for Teaching and Research in Public Procurement Regulation
Consortium.
[Accessed
20th
August,
2011].
Available
at:
<http://www.nottingham.ac.uk/pprg/documentsarchive/asialinkmaterials/publicprocur
ementregulationintroduction.pdf>.
280
References
Arthurs, H. (1983) Consultative Group on Research and Education in Law, Law and
Learning: Report to the Social Sciences and Humanities Research Council of Canada.
Ottawa: Minister of Supply and Services.
Asante, S.K.B. (1993) The perspectives of African countries on international commercial
arbitration. Leiden Journal of International Law, 6(02), pp.331-356.
Asante, S.K.B. (1998) Some Key Issues in Negotiating International Joint Ventures. Banking
and Financial Law Journal of Ghana, 1(1), pp.52-71.
Aschauer, D.A. (1989) Is public expenditure productive? Journal of Monetary Economics,
23(2), pp.177-200.
Asiedu, W. (2009) Assessing Construction Project Performance in Ghana: Modelling
Practitioners’ and Clients’ Perspectives. PhD. Thesis, Technology Universiteit
Eindhoven.
Asouzu, A.A. (2001) International commercial arbitration and African states: practice,
participation, and institutional development. Cambridge Univ Pr.
Asouzu, A.A. (2006) Some Fundamental Concerns and Issues about International Arbitration
in Africa. African Development Bank Law Development Review, Vol. 1, p.p.81.
Baah, A.Y. and Jauch, H. (2009) Chinese investments in Africa. Chinese Investments in
Africa: A Labour Perspective, p.35.
Bassioni, H.A., El-Razek, M.E.A. and El-Salam, W.A.A. (2007) Avoiding Claims in
Egyptian Construction Projects: A Quantitative Survey. In: Boyd, D (Ed) Procs 23rd
Annual Association of Researchers in Construction Management,(ARCOM)
Conference Belfast, UK 3-5 September 2007, pp.147-156.
Berger, P.L. and Luckmann, T. (1967) The social construction of reality. Doubleday, New
York.
Bernal, D.S. (2009) International Arbitration in Latin America. National Law Center for
Inter-American Free Trade, May, 15.
Bernard Krief Consultants (2006) Europe and the new partnerships for the Construction and
Civil Engineering sector in Africa (Central and West Africa – CWA). Pro€Invest –
CDE.
Blackaby, N., Partasides, C., Redfern, A. and Hunter, M. (2009) Redfern and Hunter on
international arbitration. Oxford Univ Pr.
Blake, S.H., Browne, J. and Sime, S. (2011) A practical approach to alternative dispute
resolution. Oxford University Press.
Blumer, H. (1969) Symbolic Interactionism: Perspective and Method. Englewood Cliffs, NJ:
Prentice Hall.
Blunt D. and Osborne, R. (2011) back to basics. Computers & Law, pp.32-35.
Bockstiegel, K.-H. (1999) Practical problems in resolving disputes in an international
construction and infrastructure project. International Business Lawyer, pp.196-199.
Bower, D. (2003) Management of procurement. Thomas Telford Services Ltd.
Bresnen, M. and Marshall, N. (2000) Partnering in construction: a critical review of issues,
problems and dilemmas. Construction management and economics, 18(2), pp.229238.
Brett, J.M., Goldberg, S.B. and Ury, W.L. (1990) Designing systems for resolving disputes in
organizations. American Psychologist, 45(2), p.162.
Briceno-Garmendia, C., Estache, A. and Shafik, N. (2004) Infrastructure Services in
Developing Countries: Access, Quality, Costs and Policy Reform. World Bank.
Bristow, D.I. (1995) The new CCDC 2: facilitating dispute resolution of construction projects.
Construction Law Journal, 11(2), pp.95-117
Brinberg, D. and McGrath, J.E. (1985) Validity and the research process.
281
References
Brooker, P. (2007) An investigation of evaluative and facilitative approaches to construction
mediation. Structural Survey, 25(3/4), pp.220-238.
Brown, H.J. and Marriott, A.L. (1999) ADR principles and practice. London: Sweet &
Maxwell, pp.xxxvi, 457 p.
Brown, H.J. and Marriott, A.L. (2012) ADR: principles and practices. London: Sweet &
Maxwell.
Bryman, A. (2008) Social research methods. 3rd ed. ed. Oxford: Oxford University Press,
pp.xlii, 748 p.
C.I.B (1997) Partnering in the Team. CIB Great Britain, Working Group, 12.
Calderón, C. and Servén, L. (2010) Infrastructure and Economic Development in Sub-Saharan
Africa. Journal of African Economies, 19(suppl 1), pp.i13-i87.
Calderón, C. and Servén, L. (2010) Infrastructure in Latin America. in Ocampo, J. A. and
Ros, J. (eds.) Handbook of Latin American Economies Oxford, UK: Oxford University
Press.
Canning, D. and Pedroni, P. (1999) Infrastructure and long run economic growth. Consulting
Assistance on Economic Reform II Discussion Paper, 57.
Capper, P. and Bunch, A. (1998) Construction Industry Arbitrations. in Bernstein, R.,
Tackaberry, J., Marriott, A. and Wood, D. (eds.) Handbook of Arbitration Practice.
London: Sweet & Maxwell, pp.335-372.
Chan, E.H.W. and Suen, H. (2005) Dispute Resolution Management for International
Construction Projects in China Journal of Management Decision, Vol.43 (2), pp.589602.
Chan, E.H.W., Suen, H. and Chan, K.L. (2006) A MAUT-based Dispute Resolution Selection
Model Prototype for International Construction Projects, . J. Constr. Engrg and Mgmt.
, Vol. 132, (No. 5,), pp. pp.444-451.
Chapman, P. (2006) Dispute Boards on major infrastructure projects. Management,
Procurement and Law, 162.
Chappell, D., Powell-Smith, V. and Marshall, D. (2001) Building contract dictionary. WileyBlackwell.
Charmaz, K. (2006) Constructing grounded theory: A practical guide through qualitative
analysis. Sage Publications Ltd.
Chen, C., Chiu, P., Orr, R. and Goldstein, A. (2007) An empirical analysis of Chinese
construction firms’ entry into Africa. Sydney, Australia.
Cheung, S.O. (1999) Critical factors affecting the use of alternative dispute resolution
processes in construction. International Journal of Project Management, 17(3),
pp.189-194.
Cheung, S.-O. and Yeung, Y.-W. (1998) The effectiveness of the dispute resolution advisor
system: a critical appraisal. International Journal of Project Management, 16(6),
pp.367-374.
Cheung, S.O. and Yiu, K.T. (2007) A study of construction mediator tactics—Part I:
Taxonomies of dispute sources, mediator tactics and mediation outcomes. Building
and environment, 42(2), pp.752-761.
Cheung, S.O. and Yiu, T.W. (2006) Are construction disputes inevitable? Engineering
Management, IEEE Transactions on, 53(3), pp.456-470.
Chynoweth, P. (2008) Legal research. in Knight, A. and Ruddock, L. (eds.) Advanced
Research Methods in the Built Environment, Wiley-Blackwell, Oxford. Ley-Blackwell,
pp.28-38.
Clamp, H., Cox, S. and Lupton, S. (2007) Which Contract?: Choosing the Appropriate
Building Contract. RIBA Publishing.
282
References
Clark, D.P. (1992) Distributions of official development assistance among developing country
aid recipients. The Developing Economies, 30(3), pp.189-197 at p. 190.
Cohen, M. and Gould, N. (1998) ADR: appropriate dispute resolution in the UK construction
industry. Civil Justice Quarterly, 17(Apr), pp.103-127.
Conbere, J. P. (2001). Theory building for conflict management system design. Conflict
Resolution Quarterly, 19(2), 215-236.
Conlin, J., Langford, D. and Kennedy, P. (1996), The relationship between construction
procurement strategies and construction contract disputes. 1 Taylor & Francis, p.
360.
Constantino, C.A. and Merchant, C.S. (1996) Designing conflict management: A guide to
creating productive and healthy organizations. Jossey-Bass.
Construction Industry Institute (1991) In Search of partnering Excellence, CII Special
Publication Austin, TX: Construction Industry Institute.
Corbin, J.M. and Strauss, A. (1990) Grounded theory research: Procedures, canons, and
evaluative criteria. Qualitative sociology, 13(1), pp.3-21.
Corbin, J.M. and Strauss, A.L. (2008) Basics of qualitative research: techniques and
procedures for developing grounded theory. 3rd ed. ed. Thousand Oaks, Calif.: Sage
Publications, Inc., pp.xv, 379 p.
Cotran, E. and Amissah, A. (1996) Arbitration in Africa. Kluwer Law International.
Cowan, C.E. (1991) A strategy for partnering in the public sector. ASCE, pp. 721-726.
Creswell, J.W. (2007) Qualitative inquiry & research design: Choosing among five
approaches. Sage Publications, Inc.
Creswell, J.W. (2009) Research design: Qualitative, quantitative, and mixed methods
approach. Sage Publications, Inc.
Creswell, J.W. and Miller, D.L. (2000) Determining validity in qualitative inquiry. Theory
into practice, 39(3), pp.124-130.
Critchlow, J. (1998) Making partnering work in the construction industry. Chandos.
Crotty, M. (1998) The foundations of social research: Meaning and perspective in the
research process. Sage Publications Ltd.
Crowley, L.G. and Karim, M. (1995) Conceptual model of partnering. Journal of
management in engineering, 11(5), pp.33-39.
Daily Graphic (2012) Judgment Debt Sole Commissioner Appointed. Daily Graphic [online].
[Accessed 9th October, 2012]. Available at: <graphic.com.gh>.
Daily Graphic (2013) Ghana paid GH¢218 million in judgment debts in 2011. Daily Graphic
[online].
Available
at:
<http://edition.myjoyonline.com/pages/news/201302/101122.php>.
Denscombe, M. (2007) The good research guide: for small-scale social research projects.
Open University Press.
Denzin, N.K. (1978) The research act: A theoretical orientation to sociological methods.
New York: McGraw-Hill.
Denzin, N.K. and Lincoln, Y.S. (2000) The discipline and practice of qualitative research.
Handbook of qualitative research, 2, pp.1-28.
Denzin, N.K. and Lincoln, Y.S. (2005) The Sage handbook of qualitative research. Sage
Publications, Inc.
Denzin, N.K. and Lincoln, Y.S. (2008) Collecting and interpreting qualitative materials.
Sage.
Dey, I. (2004) Grounded Theory in Seale, C., Gobo, G., Gubrium, J. F. and Silverman, D.
(eds.) Qualitative research practice. Sage Publications Ltd.
DFID (2011) Multilateral Aid Review- Ensuring Maximum Value for money for UK Aid
through Multilateral Organisations, DFID[online].[Accessed 31 August,2011].
283
References
Available
at:
<http://www.dfid.gov.uk/Documents/publications1/mar/multilateral_aid_review.pdf>.
Diekmann, J.E. and Girard, M.J. (1995) Are Contract Disputes Predictable? Journal of
Construction Engineering & Management, 121(4), p.355.
Diekmann, J.E. and Nelson, M.C. (1985) Construction claims: frequency and severity.
Journal of construction engineering and management, 111(1), pp.74-81.
Diekmann, J.E., Girard, M.J. and Abdul-Hadi, N. (1994) DPI--disputes Potential Index: A
Study into the Predictability of Contract Disputes. The Institute.
Diekmann, J.E., Girard, M.J. and Abdul-Hadi, N. (1994) DPI--disputes Potential Index: A
Study Into the Predictability of Contract Disputes. The Institute.
Dixon, B.R., Bouma, G.D. and Atkinson, G.B.J. (1987) A handbook of social science
research. Oxford University Press Oxford.
Draetta, U. (2011) Dispute resolution in international construction linked contracts.
International Business Law Journal, (1), pp.69-83.
DRBF (2012) Database on the Use of DRB by Country -2006.
Dundas, H.R. (2008) Expert determination: recent developments and the effective way
forward in energy disputes. International Energy Law Review, (5), pp.162-168.
Egan, J. (1998) Rethinking Construction. London: Department of the Environment, Transport
and the Regions.
Egan, J. (2002) Accelerating Change. London: Department of the Environment, Transport and
the Regions.
Ehrenhaft, P.D. (1977) Effective International Commercial Arbitration. Law & Pol'y Int'l
Bus., 9, p.1191.
Estache, A. (2004) A selected survey of recent economic literature on emerging infrastructure
policy issues in developing countries. The World Bank.
Estache, A. and Fay, M. (2007) Current Debates On Infrastructure Policy. [online]. pp.1-43.
Available at: <http://elibrary.worldbank.org/content/workingpaper/10.1596/18139450-4410>.
Estache, A. and Vagliasindi, M. (2007) Infrastructure for accelerated growth for Ghana:
needs and challenges.
Eyiah, A.K. and Cook, P. (2003) Financing small and medium-scale contractors in developing
countries: a Ghana case study. Construction Management and Economics, 21(4),
pp.357-367.
Fellows, R. and Liu, A. (2008) A Culture-based Approach to the Management of Conflict on
Multi-national Construction Projects: Participants and Performance. International
Conference on Multi-national Projects - 'Securing high Performance through Cultural
awareness and Dispute Avoidance'. Shanghai, China 21st -23rd November, 2008.
Shanghai.
Fenn, P. (2002) Why construction contracts go wrong (or an aetiological approach to
construction disputes). A paper delivered at a meeting of the Society of Construction
Law in Derbyshire on 5th March.
Fenn, P. (2007) Predicting construction disputes: an aetiological approach. Proceedings of the
ICE - Management, Procurement and Law [online]. 160, pp.69-73. Available at:
<http://www.icevirtuallibrary.com/content/article/10.1680/mpal.2007.160.2.69>.
Fenn, P. and Gameson, R. (1992) Construction conflict management and resolution. Taylor
& Francis.
Fenn, P., Davies, E. and O'Shea, M. (1998) Dispute resolution and conflict management in
construction: an international review. Taylor & Francis.
Fenn, P., Lowe, D. and Speck, C. (1997) Conflict and dispute in construction. Construction
Management and Economics, 15(6), pp.513-518.
284
References
Fink, A. (2002) The Survey Kit (2nd ed.).Thousand Oaks, CA; Sage
Flyvbjerg, B. (2006) Five misunderstandings about case-study research. Qualitative inquiry,
12(2), p.219.
Foster, V. and Briceño-Garmendia, C. (2010) Africa’s Infrastructure: A Time for
Transformation. 1818 H Street, NW, Washington, DC 20433: The World Bank/
Agence Française de Développement.
Foster, V. and Pushak, N. (2011) Ghana’s Infrastructure: A Continental Perspective The
World Bank.
Foster, V., Butterfield, W., Chen, C. and Pushak, N. (2009) Building Bridges: China’s
Growing Role as Infrastructure Financier for Sub-Saharan Africa. 1818 H Street
NW, Washington DC 20433: The World Bank/PPIAF, p. xi.
Franks, J. (1998) Building Procurement Systems - A Client's guide. 3rd ed. Ascot: Chartered
Institute of Building/ Englemere Limited.
Fryer, B.E. and Ellis, C. R. and Gorse, C.(2004) The practice of construction management.
Oxford, Blackwell Publishing.
Fuest, V. and Haffner, S.A. (2007) PPP-policies, practices and problems in Ghana's urban
water supply. Water Policy, 9(2), pp.169-192.
Fuller, L. (1971) Mediation- Its Forms and Functions. S. Cal. L. Review, 44, pp.305 at 308309.
Gaitskell, R. (2005) Current trends in dispute resolution. Arbitration, 71(4), pp.288-299.
Gaitskell, R. (2006) Engineer's dispute resolution handbook. Thomas Telford.
Gerber, P. and Rogers, L. (2000) The Changing Face of Construction Dispute Resolution in
the International Arena: Where to From Here? Australian Construction Law
Newsletter (73).
Ghana Statistical Service (2012) Revised Gross Domestic Product 2011. Accra: GSS.
Ghana Water Company Limited (2011) Projects - Tamale Water Supply Expansion [online].
[Accessed 22/11/11]. Available at: <http://www.gwcl.com.gh/projects.php>.
Giang, D.T.H. and Sui Pheng, L. (2011) Role of construction in economic development:
Review of key concepts in the past 40 years. Habitat International, 35(1), pp.118-125.
Glaser, B.G. (1978) Theoretical sensitivity: advances in the methodology of grounded theory.
Sociology Press, Mill Valley, CA.
Glaser, B.G. and Holton, J. (2004) Remodeling grounded theory. FQS, 5(2).
Glaser, B.G. and Strauss, A.L. (1967) The discovery of grounded theory. The British Journal
of Sociology, 20(2).
GOG (2011) National Policy on Public Private Partnerships [online]. Accra: MOFEP.
Gould, N. (1999) Dispute resolution in the UK construction industry: processes, perceptions
and predictions. International Construction Law Review, pp.574-587.
Government of Ghana (2008) Budget Statement and Economic Policy of the Government of
Ghana for the 2009 Financial Year. Accra: Government Publishers/Assembly Press.
Government of Ghana (2009) Budget Statement and Economic Policy of the Government of
Ghana for the 2010 Financial Year. Accra: Government Publishers/Assembly Press.
Government of Ghana (2010) Budget Statement and Economic Policy of the Government of
Ghana for the 2011 Financial Year. Accra: Government Publishers/Assembly Press.
Government of Ghana (2011) Ministry of Water Resources, Works and Housing [online].
[Accessed
23/11/11].
Available
at:
<http://www.ghana.gov.gh/index.php?option=com_content&view=article&id=324:mi
nistry-of-water-resources-works-a-housing&catid=74:ministries&Itemid=224>.
Griffith, A., Knight, A. and King, A. (2003) Best practice tendering for design and build
projects. Institute of Civil Engineers Pub.
285
References
Groton, J.P. (1992) Supplementary to Alternative Dispute Resolution in the Construction
Industry. USA: Wiley Law Publications.
Guba, E.G. and Lincoln, Y.S. (1994) Competing paradigms in qualitative research. Handbook
of qualitative research, 2, pp.163-194.
Gubrium, J.F. and Holstein, J.A. (2002) Handbook of interview research: Context and
method. SAGE Publications, Incorporated.
Hammersley, M. (1993) Social research: philosophy, politics and practice. Sage Publications
Ltd.
Hanna, A.S. (2007) Risk Allocation and Increased Claims in the Construction Industry.
Journal of Professional Issues in Engineering Education & Practice (133 ed.). pp.4344.
Harmon, K.M. (2003) Resolution of construction disputes: A review of current
methodologies. Leadership and Management in Engineering, 3(4), pp.187-201.
Harmon, K.M.J. (2009) Case Study as to the Effectiveness of Dispute Review Boards on the
Central Artery/Tunnel Project. Journal of Legal Affairs and Dispute Resolution in
Engineering and Construction, 1, p.18.
Harris, C. (2003) Private participation in infrastructure in developing countries: trends,
impacts, and policy lessons. World Bank Publications.
Hawker, G., Uff, J. and Timms, C. (1986) The Institution of Civil Engineers' Arbitration
Practice. Telford.
Heath, B., Hills, B. and Berry, M. (1994) The origin of conflict within the construction
process.
Hensengerth, O. (2011) Interaction of Chinese institutions with host governments in dam
construction -The Bui dam in Ghana.
Bonn: Deutsches Institut für
Entwicklungspolitik.
Herrmann, G. (1983) UNCITRAL's Work Towards a Model Law on International
Commercial Arbitration. Pace L. Rev., 4, p.537.
Hibberd, P.R. and Newman, P. (1999) ADR and adjudication in construction disputes.
Wiley-Blackwell.
Hinchey, J.W. (2012) Rethinking Conflict In Construction Project Delivery and DIspute
Resolution. International Construction Law Review, 29(1), pp.24-50.
Hobeck, P., Mahnken, V. and Koebke, M. (2008) Time for Woolf reforms in international
construction arbitration. International Arbitration Law Review, 11(2), pp.84-99.
Hoellering, M.F. (1986) The UNCITRAL Model Law on International Commercial
Arbitration. International Law 20, p.327.
ICSID (2011) The ICSID Caseload – Statistics.
Ilter, D. (2012) Identification of the relations between dispute factors and dispute categories in
construction projects. International Journal of Law in the Built Environment, 4(1),
pp.45-59.
Jepma, C.J. (1991) The tying of aid. Development Centre of the Organisation for Economic
Co-operation and Development; Washington, DC: OECD Publications and
Information Centre [distributor].
Jones, D. (2006) Construction project dispute resolution: options for effective dispute
avoidance and management. Journal of Professional Issues in Engineering Education
and Practice, 132(3), pp.225-235.
Kessides, C. (1993) The contributions of infrastructure to economic development: a review of
experience and policy implications. World Bank Publications.
Kessides, I.N. (2004) Reforming infrastructure: Privatization, regulation, and competition. A
World Bank Publication.
286
References
Kheni, N.A. (2008) Impact of Health and Safety Management on safety Performance of Small
and Medium-sized Construction Businesses in Ghana [online]. PhD, Loughborough.
[Accessed 24th October, 2011]. Available at: <https://dspace.lboro.ac.uk/>.
Kirkpatrick, C., Parker, D.S. and Zhang, Y.-F. (2006) foreign direct investment in
infrastructure in developing countries: does regulation make a difference?
Transnational Corporation, 15(1), pp.143-171.
Kratzsch, S. (2010) ICC Dispute Resolution Rules: ICC dispute boards and ICC Pre-Arbitral
Referees. Construction Law Journal, 26(2), pp.87-97.
Kumaraswamy, M. and Yogeswaran, K. (1998) Significant sources of construction claims.
Int. Constr. Law Rev., 15(1), pp.144-160.
Kumaraswamy, M.M. (1997) Common categories and causes of construction claims.
Construction Law Journal, 13(1), pp.21-34
Latham, M. (1994) Constructing the Team - Joint Review of Procurement and Contractual
Arrangements in the United Kingdom Construction Industry: Final Report. London:
Department of the Environment.
Le Nguyen, H. (2011) Partnership Strategies: Pro-active and Pre-active Approach in Conflict
Management in International Joint Ventures. International Journal of Business &
Management, 6(9).
Leahy, E.R. and Pierce, K.J. (1985-86) Sanctions to Control Party Misbehavior in
International Arbitration. Va. J. Int'l L., 26, pp.291, 293.
LeCompte, M.D. and Goetz, J.P. (1982) Problems of reliability and validity in ethnographic
research. Review of educational research, 52(1), p.31.
Levin, A. (1998) PFI contracts: providing for disputes and choosing the "right" remedies.
Journal of International Banking Law, 13(6), pp.193-198.
Lincoln, Y. and Guba, E. (1985) Naturalistic Inquiry (Beverly Hills, CA, Sage Publications).
Linda Snyder and Sarah Bowman, 117.
Lincoln, Y.S. and Guba, E.G. (2000) The only generalization is: There is no generalization.
Case study method, pp.27-44.
Love, P., Davis, P., Ellis, J. and Cheung, S.O. (2010) Dispute causation: identification of
pathogenic influences in construction. Engineering, Construction and Architectural
Management, 17(4), pp.404-423.
Love, P., Davis, P., Jasper, T., Lopez, R., Tresise, P. and Ellis, J. (2009) Causal ascription of
disputes in construction projects. Disputes Avoidance and Resolution Program, CRC
Construction Innovation, Report, (2007-006).
Love, P.E.D., Davis, P.R., Ellis, J.M. and Cheung, S. (2010) A systemic view of dispute
causation. International Journal of Managing Projects in Business, 3(4), pp.661-680.
Love, P.E.D., Davis, P.R., Sai On, C. and Irani, Z. (2011) Causal Discovery and Inference of
Project Disputes. Engineering Management, IEEE Transactions on, 58(3), pp.400411.
Love, P.E.D., Skitmore, M. and Earl, G. (1998) Selecting a suitable procurement method for a
building project. Construction Management & Economics, 16(2), pp.221-233.
Mahama, A. ( 22 March, 2012) Duffuor Fingers Betty. In CP’s €94m Cash. Daily Guide
[online].
[Accessed
9th
October,
2012].
Available
at:
<http://www.dailyguideghana.com/?p=42818>.
Mante, J. and Ndekugri, I. (2012) Arbitrability in the Context of Ghana's New Arbitration
Law. International Arbitration Law Review, 15(2), pp.31-41.
Mante, J., Ndekugri, I., Ankrah, N. and Hammond, F. (2012) The Influence of Procurement
Methods on Dispute Resolution Mechanism Choice in Construction In: Smith, S.D
(Ed) Proceedings 28th Annual ARCOM Conference, 3-5 September 2012, Edinburgh,
UK, Association of Researchers in Construction Management, 979-988. [online].
287
References
Mante, J., Ndekugri, I. and Ankrah, N. (2011) Resolution of Disputes arising from major
infrastructure projects in developing countries. In RICS Construction and Property
Conference. School of Built Environment, Salford 12 -13 September, 2011. Salford,
UK, p.126.
Marshall, C. and Rossman, G.B. (2006) Designing qualitative research. 4th ed. Sage
Publications, Inc.
Mason, M. (2010) Sample Size and Saturation in PhD Studies Using Qualitative Interviews.
In Forum: Qualitative Social Research (Vol. 11, No. 3) 11.
Masterman, J.W.E. (2002) Introduction to building procurement systems. Taylor & Francis.
Mathison, S. (1988) Why triangulate? Educational researcher, 17(2), pp.13-17.
Matyas, R.M., Mathews, A., Smith, R.J. and Sperry, P. (1996) Construction dispute review
board manual. McGraw-Hill New York.
McLaughlin, J.T. (1979) Arbitration and Developing Countries. Int'l Law, 13, p.211.
McMillan, D.D. and Rubin, R.A. (2005) Dispute Review Boards: Key Issues, Recent Case
Law, and Standard Agreements. Constr. Law., 25, p.14.
Menkel-Meadow, C., Love, L.P. and Schneider, A.K. (2005) Dispute resolution: beyond the
adversarial model. New York: Aspen Publishers, pp. l, 993 p.
Micheletti (2011) Projects [online]. [Accessed 21st November, 2011]. Available at:
<http://michelettighana.com/projects.php>.
Miller, R. and Lessard, D.R. (2000) The strategic management of large engineering projects:
Shaping institutions, risks, and governance. The MIT Press.
Miles, M.B. and Huberman, A.M. (1984) Qualitative data analysis: A sourcebook of new
methods. Sage publications.
Mitropoulos, P. and Howell, G. (2001) Model for understanding, preventing and resolving
project disputes. Journal of Construction Engineering & Management, 127(3), p.223.
Moavenzadeh, F. (1978) Construction industry in developing countries. World Development,
6(1), pp.97-116.
MOFEP (1997) Public Expenditure Review 1996 - The Delivery of Economic Infrastructure
[online]. Accra: MOFEP.
MOFEP (2011) MOFEP-Functions [online]. [Accessed 10th November, 2011]. Available at:
<http://www.mofep.gov.gh/>.
Morgan, D.B. (2008) Dispute Avoidance: A non-confrontational approach to the management
of construction contracts. RIBA Publishing.
Morledge, R., Smith, A. and Kashiwagi, D.T. (2006) Building procurement. WileyBlackwell.
Morse, J.M. (1999) Qualitative generalizability. Qualitative Health Research, 9(1), pp.5-6..
Morse, J.M. (2000) Determining sample size. Qualitative Health Research, 10(1), pp.3-5.
Mottier, V. (2005) The interpretive turn: History, memory, and storage in qualitative research.
Forum: Qualitative Social Research, 6(No.2), pp.2-05.
Murdoch, J. and Hughes, W. (2008) Construction contracts: law and management.
Routledge.
National Audit Office (2001) Modernizing Construction (HC87 Session 2000-2001). London:
National Audit Office.
Ncube, M. (2010) Financing and Managing Infrastructure in Africa. Journal of African
Economies, 19(suppl 1), pp.114-164.
Ndekugri, I. and Russell, V. (2006) Disputing the existence of a dispute as a strategy for
avoiding construction adjudication. Engineering, Construction and Architectural
Management, 13(4), pp.380-395.
Ndekugri, I. and Turner, A. (1994) Building procurement by design and build approach.
Journal of Construction Engineering and Management, 120, p.243.
288
References
Ndekugri, I., Chapman, P., Smith, N. and Hughes, W. (2013) Best Practice in the Training,
Appointment and Remuneration of Members of Dispute Boards for Large
Infrastructure Projects. Journal of Management in Engineering.
Ndekugri, I., Smith, N. and Hughes, W. (2007) The engineer under FIDIC's conditions of
contract for construction. Construction Management and Economics, 25(7), pp.791799.
Ndekugri, I.E., and Rycroft, M.E. (2009) The JCT 05 Standard Building Contract: Law and
Administration. Elsevier/Butterworth-Heinemann.
Nelson, R.M. (2010) Multilateral Development Banks: Overview and Issues for Congress
[online]. Washington, USA: Congressional Research Service, United States of
America
Neuman, W.L. (2003) Social work research methods: Qualitative and quantitative
approaches. Allyn and Bacon.
Newey, J. (1992) The construction industry In Fenn, P. and Gameson, R. (ed.) Construction
Conflict Management and Resolution. E & FN SPON.
Odams, A.M. and Higgins, J. (eds.) (1996) Commercial Dispute Resolution. Construction
Law Press.
Ogunlana, S.O., Promkuntong, K. and Jearkjirm, V. (1996) Construction delays in a fastgrowing economy: comparing Thailand with other economies. International Journal
of Project Management, 14(1), pp.37-45.
Oh, B.S. (1981) Some Problems in International Commercial Arbitration with Developing
Countries. Seoul Law Journal, pp.144- 173.
Osotimehin, K.O., Akintoye, E.Y. and Olasanmi, O.O. (2010) The Effects of Investment in
Telecommunication Infrastructure on Economic Growth in Nigeria (1992-2007).
Oxford Business and Economics Conference. St. Hugh's College, Oxford University
28th - 29th June, 2010. Oxford, UK.
Parliament of Ghana (29 February, 2012) The Hansard: Public Account Committee Sitting Consideration of the Report of the Auditor-General on the Public Accounts of Ghana
(Consolidated Fund), 2009. Accra: Parliament of Ghana.
Patton, M.Q. (1990) Qualitative evaluation and research methods. SAGE Publications, Inc.
Paulsson, J. (1996) Accepting International Arbitration in fact- And not only in words. in
Cotran, E. and Amissah, A. (eds.) Arbitration in Africa. London: Kluwer Law
International, pp.31-45.
Pearce, D.C., Campbell, E. and Harding, D. (1987) Australian law schools: A discipline
assessment for the Commonwealth Tertiary Education Commission. AGPS Canberra,
pp.paras 9.10 - 19.15.
PEI (February, 2011) Infrastructure Investor Africa: An Intelligence Report. London: PEI
Media.
Perloff, S. (1992) Ties that Bind: The Limits of Autonomy and Uniformity in International
Commercial Arbitration, The. U. Pa. J. Int'l Bus. L., 13, p.323.
Phillips, E.M. and Pugh, D.S. (2005) How to get a PhD: A handbook for students and their
supervisors. 4th ed. Berkshire, England: Open University Press, pp.61-62.
Poole, J. (2012) Textbook on contract law. 11th ed. OUP Oxford.
Popper, K. (1959). The logic of scientific discovery. New York: Basic Books.
Powell-Smith, V. and Stephenson, D.A. (1999) Civil engineering claims. Wiley-Blackwell.
Prud'Homme, R. (2004) Infrastructure and development. World Bank.
Pyett, P.M. (2003) Validation of qualitative research in the “real world”. Qualitative Health
Research, 13(8), pp.1170-1179.
Rana, R. (2009) Is Adjudication killing Arbitration. Arbitration, 75(2), pp.223-230.
289
References
Redfern, A. (2004) Law and practice of international commercial arbitration. Sweet &
Maxwell.
Rosenfeld, Y. (2014) Root-cause analysis of construction-cost overruns. Journal of
Construction Engineering and Management, 140(1).
Ross, D. (2009) The use of partnering as a conflict prevention method in large-scale urban
projects in Canada. International Journal of Managing Projects in Business, 2(3),
pp.401-418.
Rubin, H.J. and Rubin, I. (1995) Qualitative interviewing: The art of hearing data. Sage
Publications, Inc.
Sanchez Robles, B. (1998) Infrastructure investment and growth: some empirical evidence.
Contemporary Economic Policy, 16(1), pp.98-108.
Sanders (1973) International Commercial Arbitration. Neth. Int'l L. Rev, 20, p.37.
Sarkodie, K. (2011) Arbitration in Ghana- The Alternative Dispute Resolution Act, 2010.
International Construction Law Review.
Schwandt, T.A. (2007) The Sage dictionary of qualitative inquiry. Sage Publications, Inc.
Schwartz, E.A. (1995) Resolution of International Construction Disputes. Int'l Bus. Law, 23,
p.149.
Seawright, J. and Gerring, J. (2008) Case selection techniques in case study research. Political
Research Quarterly, 61(2), pp.294-308.
Sempasa, S.L. (1992) Obstacles to international commercial arbitration in African countries.
International & Comparative Law Quarterly, 41(02), pp.387-413.
Semple, C., Hartman, F.T. and Jergeas, G. (1994) Construction claims and disputes: causes
and cost/time Overruns. Journal of construction engineering and management, 120(4),
pp.785-795.
Seppala, C. (2005) The Arbitration Clause in FIDIC Contracts for Major Works. International
Construction Law Review, 22.
Seppala, C.R. (2009) The pre-arbitral procedure of the settlement of disputes in the FIDIC
(civil engineering) conditions of contract. International Business Law Journal, (6),
pp.579-606.
Sime, S. (2007) A practical approach to civil procedure. Oxford University Press, USA.
Sims, J. and Bunch, T. (2003) Construction Industry Arbitrations. in Tackaberry, J. and
Marriott, A. L. (eds.) Bernstein's Handbook of Arbitration and Dispute Resolution
Practice. Fourth ed. London: Sweet & Maxwell, pp.533-589.
Smith, S. and Martinez, J. (2009) Analytic Framework for Dispute Systems Design, An.
Harv. Negot. L. Rev., 14, p.123.
Stake, R.E. (1995) The art of case study research. Sage Publications, Inc.
Stehbens, K.L., Wilson, O.D. and Skitmore, M. (1999) Partnering in the Australian
construction industry: breaking the vicious circle.
Stitt, A. (2004) Mediation: a practical guide. Routledge Cavendish.
Strauss, A. and Corbin, J. (1998) Basics of qualitative research: Techniques and procedures
for developing grounded theory. SAGE Publications, Thousand Oaks, USA.
Sykes, J. (1996) Claims and disputes in construction. Construction Law Journal, 12(1), pp.313.
Tackaberry, J. and Marriott, A.L. (2003) Bernstein's Handbook of Arbitration and Dispute
Resolution Practice. Fourth ed. London: Sweet & Maxwell.
Taysec (2011) Projects [online]. [Accessed 21st November,2011]. Available at:
<http://www.taysec.net/gh/?page=Design+and+Build&page_id=21>.
Thompson, R.M. and Vorster, M.C. (2000) Innovations to Manage Disputes: DRB AND
NEC. Journal of Management in Engineering, 16(5), p.51.
290
References
Tiewul, S.A. and Tsegah, F.A. (1975) Arbitration and the Settlement of Commercial
Disputes: A Selective Survey of African Practice. International & Comparative Law
Quarterly, 24(03), pp.393-418.
Tinkler, P. and Jackson, C. (2000) Examining the Doctorate: Institutional policy and the PhD
examination process in Britain. Studies in Higher Education, 25(2), pp.167-180.
Torgbor, E. (2011) Ghana outdoors: the new Alternative Dispute Resolution Act 2010 (Act
798): a brief appraisal. Arbitration, 77(2), pp.211-291 at 212.
Turner, A. (1990) Building Procurement. London: Macmillan Press Limited.
Tyler, T.R. (1988) Quality of Dispute Resolution Procedures and Outcomes: Measurement
Problems and Possibilities, The. Denv. UL Rev., 66, p.419.
UNCTAD (2008) World Investment Report, 2008 New York, Geneva: United Nations.
UNCTAD (2010) Investor–State Disputes: Prevention and Alternatives to Arbitration. ISBN
978-92-1-112793-5. New York and Geneva: United Nations.
Ury, W.L., Brett, J.M. and Goldberg, S.B. (1988) Getting disputes resolved: Designing
systems to cut the costs of conflict. Jossey-Bass.
USAID (2003) Automated Directive System (ADS) 305 - Country Contracting Handbook Chapter 2: Procurement of Construction Services [online]USAID. [Accessed 24-112012].
Available
at:
<http://transition.usaid.gov/policy/ads/300/305.pdf,
http://transition.usaid.gov/policy/ads/300/305mab.pdf>.
Vorster, M. (1993) Dispute prevention and resolution. Construction Industry Institute.
Watts, V.M. and Scrivener, J.C. (1993) Review of Australian building disputes settled by
litigation. Building Research & Information, 21(1), pp.59-63.
Wellington, J. (2012) Searching for ‘doctorateness’. Studies in Higher Education, (ahead-ofprint), pp.1-14.
Wellington, J.J. (2010) Making Supervision Work for You: A Student's Guide. Sage.
Whitfield, J. (1994) Conflicts in construction: Avoiding, managing, resolving. Macmillan.
Whittemore, R., Chase, S.K. and Mandle, C.L. (2001) Validity in qualitative research.
Qualitative health research, 11(4), pp.522-537.
World Bank (1994) Infrastructure for development. Oxford: Oxford University Press.
World Bank (2003) Country Procurement Assessment Report -Ghana, Vol1 of 5. Washington
DC: Ghana Country Department, The World Bank.
World Bank (2003) Country Procurement Assessment Report -Ghana, Vol 2 of 5. Washington
DC: Ghana Country Department, The World Bank.
World Bank (2008) Sustainable Infrastructure Action Plan FY 2009-2011 [online]. 1818 H
Street NW Washington DC 20433: The International Bank for Reconstruction and
Development /The World Bank Group [Accessed 17th July,2011].Available at:
<http://web.worldbank.org/WBSITE/EXTERNAL/TOPICS/EXTSDNET/0,,
contentMDK:22493665~menuPK:6395187~pagePK:64885161~piPK:64884432~theS
itePK:5929282,00.html>.
World Bank (2011) Country and Lending Groups [online]. [Accessed 27/12/11]. Available at:
<http://data.worldbank.org/about/country-classifications/country-and-lendinggroups>.
World Bank (2011) Data-How we Classify Countries [online]. [Accessed 27/12/11].
Available at: <http://data.worldbank.org/about/country-classifications>.
World Bank (2011) Global Economic Prospects - Navigating Strong Currents, Vol. 2.
Washington DC The International Bank for Reconstruction and Development / The
World Bank.
World Bank (2011) Global Economic Prospects -Maintaining Progress amid Turmoil.
Washington DC The International Bank for Reconstruction and Development / The
World Bank.
291
References
World Bank (2011) Guidelines: Procurement of Goods, Works, and Non-Consulting Services
under IBRD Loans and IDA Credits and Grants by World Bank Borrowers. 1818 H
Street, N.W. Washington, D.C. 20433, U.S.A: The International Bank for
Reconstruction and Development /The World Bank, p. 21.
World Bank and PPIAF (2010) Private Participation in Infrastructure Database. World
Bank/ PPIAF.
Yates, J. and Duran, J. (2006) Utilizing dispute review boards in relational contracting: A case
study. Journal of Professional Issues in Engineering Education and Practice, 132(4),
pp.334-341.
Yelpaala, K. (2006) In Search of a Model Investment Law for Africa. African Development
Bank Law for Development Review, Vol. 1, p.2.
Yin, R.K. (2009) Case study research: Design and methods. Sage publications, Inc.
Yusof, A.M., Ismail, S. and Chin, L.S. (2011) Procurement Method as Conflict and Dispute
Reduction Mechanism for Construction Industry in Malaysia. 2nd International
Conference on Construction and Project Management. 2011IACSIT Press, Singapore.
292
Appendices
APPENDICES
Appendix A - Interview Guide
Interview Guide
Resolution of Construction Disputes Arising From Major
Infrastructure Projects in Developing Countries – A Case Study of
Ghana
Brief Instructions to Interviewees:
This is a qualitative study. Participants’ knowledge of the subject-matter of the research,
views, experiences and opinions are central to the study. Therefore, participants are
encouraged to answer the main and follow-up questions as exhaustively as they possibly can
so that their rich experiences can be captured in this study. Anonymity and confidentiality of
all responses is assured/ guaranteed.
Name of Interviewee
Organisation
Position
No. of years employed
Venue of Interview
Date
:
:
:
:
:
:
1. Preliminary Issues
1.1. The Organisation (Nature and objects)
1.2. Interviewee’s role(s) in the organisation. Number of years the interviewee has been
performing roles.
293
Appendices
1.3. Organisation’s involvement in the acquisition of major infrastructure projects in Ghana.
What role did/has it played? How long has it been playing this/these roles?
2. Procurement Process – Choosing Dispute mechanism(s)
2.1. The role of the interviewee’s organisation in the procurement of major projects.
Procurement strategies often used for major projects acquisition in interviewee’s
organisation. Why the particular strategy or strategies? Who are involved in the making
of procurement decisions? Are the organisation’s decisions provisional or final? If
provisional, who has the final say on issues such as procurement strategy and selection
of consultants and contractors?
2.2. Standard form contracts most/regularly used. Whose decision? Why the particular
standard form(s)?
2.3. Negotiation of terms in special conditions of contract. Whose duty? How is it conducted?
2.4. Typical dispute resolution mechanisms used- Arbitration/mediation/ dispute boards etc.
why the choice? Why not others?
2.5. Negotiation on dispute resolution terms – How often? At what stage?
2.6. Factors considered in selecting dispute resolution mechanisms.
3. Disputes and the Resolution Process
3.1. Nature/ types of claims
3.2. Conditions which occasion/lead to disputes –
3.3. Procedure for dealing with disputes in interviewee’s organisation. Any written policy or
guide on dispute resolution?
294
Appendices
3. 4. From interviewee’s experience, what are the various stages that disputes will often go
through before they are finally resolved?
3.5. Where parties decide to use international commercial arbitration (ICA) how is the period
preceding ICA utilised to attempt a resolution? In the interviewee’s opinion do parties
utilise the period for amicable settlement effectively? If so how? If not, why?
3.6. To what extent do parties utilise non-binding alternative resolution mechanisms such as
negotiation, mediation, dispute review boards etc? What challenges, if any, have you
encountered in practice with the use of these mechanisms? From your experience, what
are the barriers to the use of these methods in major project construction disputes?
3.7. What are the challenges associated with the current modes of construction dispute
resolution – interviewee’s experiences.
3. 8. In your opinion, what can be done to prevent/reduce the occurrence of construction
disputes in major infrastructure projects in Ghana?
4. Interviewee’s experience of how specific past construction disputes were
resolved – the process
4.1. Nature of Project(s)
4.2. Description of Project(s) (Project objectives etc.)
4.3. Nature of the Parties involved (State entities, international companies etc.)
4.4. Other interested parties (Donors/ Lenders) and their roles, if any.
295
Appendices
4.5. Interviewee’s experience with the project – procurement strategies, contract negotiations,
dispute resolution clauses (any negotiations?), why a particular arrangement was preferred to
others, disputes, how they were resolved, stages etc.
4.6. Lessons and suggestions for an efficient dispute resolution process based on
interviewee’s previous encounters.
4.9. Is there anything else the interviewee thinks I should know to understand major project
dispute resolution processes better?
4.10. Reference/ recommendations – to whom should I talk to find out more about resolution
of disputes arising from major projects?
Concluding remarks: Thank you- confidentiality of responses - prospects of future interviews.
296
Appendices
Appendix A1 - Updated Interview Guide after pilot
Interview Guide
Resolution of Construction Disputes Arising From Major
Infrastructure Projects in Developing Countries – A Case Study of
Ghana
Brief Instructions to Interviewees:
This is a qualitative study. Thus, participants’ knowledge of the subject-matter of the
research, views, experiences and opinions are central to the study. Participants are therefore
encouraged to answer the main and follow-up questions as exhaustively as they possibly can
so that their rich experiences can be captured in this study. Anonymity and confidentiality of
all responses is assured.
Name of Interviewee
Organisation
Position
No. of years employed
Venue of Interview
Date
:
:
:
:
:
:
1. Preliminary Issues
1.1. The Organisation (Nature and objects)
1.2. Interviewee’s role(s) in the organisation. Number of years the interviewee has been
performing roles.
1.3. Organisation’s involvement in the acquisition of major infrastructure projects in Ghana.
What role did/has it played? How long has it been playing this/these roles?
2. Procurement Process – Choosing Dispute mechanism(s)
2.1. The role of the interviewee’s organisation in the procurement of major projects.
Procurement strategies often used for major projects acquisition in interviewee’s
organisation. Why the particular strategy or strategies? Who are involved in the making
of procurement decisions? Are the organisation’s decisions provisional or final? If
297
Appendices
provisional, who has the final say on issues such as procurement strategy and selection
of consultants and contractors?
2.2. Standard form contracts most/regularly used. Whose decision? Why the particular
standard form(s)?
2.3. Negotiation of terms in special conditions of contract. Whose duty? How is it conducted?
2.4. Typical dispute resolution mechanisms used- Arbitration/mediation/ dispute boards etc.
why the choice? Why not others?
2.5. Negotiation on dispute resolution terms – How often? At what stage? What role(s) do
your organisation play?
2.6. Factors considered in selecting dispute resolution mechanisms.
3. Disputes and the Resolution Process
3.1. Nature/ types of claims
3.2. Conditions which occasion/lead to disputes –
3.3. Procedure for dealing with disputes in interviewee’s organisation. Any written policy or
guide on dispute resolution?
3. 4. From interviewee’s experience, what are the various stages that disputes will often go
through before they are finally resolved? Please give details.
3.5. Where parties decide to use international commercial arbitration (ICA) how is the period
preceding ICA utilised to attempt a resolution? In the interviewee’s opinion do parties
utilise the period for amicable settlement effectively? If so how? If not, why?
3.6. To what extent do parties utilise non-binding alternative resolution mechanisms such as
negotiation, mediation, dispute review boards etc? What challenges, if any, has the
interviewee encountered in practice with the use of these mechanisms? From his/her
experience(s), what are the barriers to the use of these methods in major project
construction disputes?
298
Appendices
3.7. What are the challenges associated with the current modes of construction dispute
resolution – interviewee’s experiences.
3. 8. In the interviewee’s opinion, what can be done to prevent/reduce the occurrence of
construction disputes in major infrastructure projects in Ghana?
3.9.
Lessons and suggestions for an efficient dispute resolution process based on
interviewee’s previous encounters.
3.10. Is there anything else the interviewee thinks I should know to understand major project
dispute resolution processes better?
3.11. Reference/ recommendations – to whom should I talk to find out more about resolution
of disputes arising from major projects?
Concluding remarks: Thank you, confidentiality of responses, prospects of future interviews
etc.
299
Appendices
Appendix B - A sample Request Letter to Institutions affiliated with the Employer
……………..
……………..
…………….
Dear Mr. …………,
Application for Permission to Conduct Interviews
I am by this letter humbly requesting your institution to participate in a research I am
conducting as part of the requirements for my doctorate degree in the School of Technology,
University of Wolverhampton. The research is under the supervision of Professor Issaka
Ndekugri, Professor of Construction and Engineering Law and Director of the Construction
Law and Dispute Resolution Programme of the School. Below are details regarding the aim
and objectives of the research, reasons for selecting your institution for study, what activities
will occur on your site during the research, issues of confidentiality and anonymity and the
likely benefits that your institution may gain from participating in this research.
The World Bank and the other Multilateral Development Banks (MDBs) have identified
infrastructure development as a necessary component of any effective strategy for economic
development in the developing world. Unfortunately, disputes often arise from major
infrastructure projects in the developing world that are resolved at great cost by courts and
arbitral tribunals constituted from the most expensive legal professionals in the developed
world. Whilst similar projects in the developed world also suffer from the challenge of costly
disputes, there is a growing trend of resolving them by less costly Alternative Dispute
Resolution Methods (ADR) such as mediation, expert determination and dispute boards.
Compounding the difficulties of developing countries is the general lack of empirical
evidence regarding practical steps in the resolution of construction disputes arising from
major projects in developing countries.
300
Appendices
The aim of this research is to carry out a critical examination of the Ghanaian experience
of the resolution of construction disputes from major infrastructure projects and thereby
develop strategies for dispute reduction and cost- effective resolution. To achieve the aim of
the research, the study will focus on the following objectives: (a) describe the state, trends and
the context of major infrastructure development in Ghana; (b) examine the main parties
involved in the major construction industry in Ghana; (c) investigate the framework for major
infrastructure procurement and the impact of the process on dispute resolution; (d) examine
the legal and institutional framework for resolving disputes from major projects including the
processes and stages involved from the emergence of a dispute to the final determination of
same; (e) study critically some international arbitration cases relating to major infrastructure
projects in Ghana; and (f) identify the challenges to the extant modes of resolution, barriers to
the determination of construction disputes by methods other than international commercial
arbitration and litigation, and remedial strategies.
Your institution is one of the few in Ghana which are regularly involved in major
infrastructure projects and the resolution of disputes arising therefrom. Your key personnel
have experienced the emergence and the resolution of many disputes and are better placed to
share such experiences as they relate to the outlined objectives of this research.
The study will entail the conduct of interviews with your personnel, who have been
involved in project planning, procurement, contract negotiations and administration, project
management and dispute resolution. Attached is an interview guide. Each interview is
expected to take at least one hour at an agreed location. With your permission or that of the
interviewees, the said interviews will be audio recorded and subsequently transcribed. This is
to ensure that the interviewee’s contributions are accurately captured. The interviewee’s right
to refuse to answer a question or participate in this research remains intact and shall be
respected.
301
Appendices
Any information provided during the interview or in documentary form shall remain
confidential, anonymous and shall remain securely stored. Access to such data shall only be
available to the supervisory team and me. Portions of the data collected (the source of which
shall remain anonymous) may be quoted in the thesis, reports and journal publications
emanating from this research. There are no known risks, current or anticipated, to your
staff/personnel as participants in this research.
It is expected that the outcome of this study will not only benefit your institution but also
the State by bringing into sharp focus the need for policy and guidelines on diversified dispute
resolution strategies for effective and efficient reduction and resolution of construction
disputes
from
major
projects.
For
further
information,
please
contact
me
at
j.mante@wlv.ac.uk or mantecj@gmail.com. You can also reach my Supervisor, Prof.
Ndekugri at the School of Technology, University of Wolverhampton, City Campus South,
Wulfruna Street, Wolverhampton, WV1 1LY, United Kingdom, tel.: +44 (0) 1902 321000.
I await your response. Thank you in advance.
Yours Faithfully,
302
Appendices
Appendix B1 - Request Letters addressed to Interviewees with Institutions affiliated
to the Employer
……………..
……………..
Dear Mr. …………,
Application for Permission to Conduct Interviews
I am by this letter humbly requesting you to participate in a research I am conducting as
part of the requirements for my doctorate degree in the School of Technology, University of
Wolverhampton. The study is under the supervision of Professor Issaka Ndekugri, Professor
of Construction and Engineering Law and Director of the Construction Law and Dispute
Resolution Programme of the School. Below are details regarding the aim and objectives of
the research, reasons for selecting you to be part of the study and your involvement, issues of
confidentiality and anonymity and the likely benefits of the research.
The World Bank and the other Multilateral Development Banks (MDBs) have identified
infrastructure development as a necessary component of any effective strategy for economic
development in the developing world. Unfortunately, disputes often arise from major
infrastructure projects in the developing world that are resolved at great cost by courts and
arbitral tribunals constituted from the most expensive legal professionals in the developed
world. Whilst similar projects in the developed world also suffer from the challenge of costly
disputes, there is a growing trend of resolving them by less costly Alternative Dispute
Resolution Methods (ADR) such as mediation, expert determination and dispute boards.
Compounding the difficulties of developing countries is the general lack of empirical
evidence regarding practical steps in the resolution of construction disputes arising from
major projects in developing countries.
The aim of this research is to carry out a critical examination of the Ghanaian experience
of the resolution of construction disputes from major infrastructure projects and thereby
develop strategies for dispute reduction and cost- effective resolution. To achieve the aim of
303
Appendices
the research, the study will focus on the following objectives: (a) describe the state, trends and
the context of major infrastructure development in Ghana; (b) examine the main parties
involved in the major construction industry in Ghana; (c) investigate the framework for major
infrastructure procurement and the impact of the process on dispute resolution; (d) examine
the legal and institutional framework for resolving disputes from major projects including the
processes and stages involved from the emergence of a dispute to the final determination of
same; (e) study critically some international arbitration cases relating to major infrastructure
projects in Ghana; and (f) identify the challenges to the extant modes of resolution, barriers to
the determination of construction disputes by methods other than international commercial
arbitration and litigation, and remedial strategies.
You have been identified as one of the few in Ghana who have acquired much experience
regarding acquisition of major infrastructure projects and the resolution of disputes arising
therefrom over the years. Therefore, you are better placed to share such experiences as they
relate to the outlined objectives of this research.
The study will entail the conduct of an interview with you at an agreed time and location.
This is expected to take at least one hour. The interview will tap into your experiences, views
and opinions about the resolution of construction disputes arising from major projects.
Attached is an interview guide. With your permission, the said interview will be audio
recorded and subsequently transcribed. This is to ensure that your contributions are accurately
captured. Your right to refuse to answer a question or participate in this research remains
intact and shall be respected.
Any information provided during the interview or in documentary form shall remain
confidential, anonymous and shall remain securely stored. Access to such data shall only be
available to the supervisory team and me. Portions of the data collected (the source of which
shall remain anonymous) may be quoted in the thesis, reports and journal publications
304
Appendices
emanating from this research. There are no known risks, current or anticipated, to you as
participant in this research.
It is expected that the outcome of this study will not only benefit your institution but also
the State as a whole by bringing into sharp focus the need for policy and guidelines on
diversified dispute resolution strategies for effective and efficient reduction and resolution of
construction disputes from major projects. For further information, please contact me at
j.mante@wlv.ac.uk or mantecj@gmail.com. You can also reach my Supervisor, Prof.
Ndekugri at the School of Technology, University of Wolverhampton, City Campus South,
Wulfruna Street, Wolverhampton, WV1 1LY, United Kingdom, tel.: +44 (0) 1902 321000.
I await your response. Thank you in advance.
Yours Faithfully,
305
Appendices
Appendix B2- A sample Request Letter to Foreign Contractors and adjunct
organisations
……………..
……………..
…………….
Dear Ms …………,
Application for Permission to Conduct Interviews
I am by this letter humbly requesting your company/institution to participate in a research. I
am conducting as part of the requirements for my doctorate degree in the School of
Technology, University of Wolverhampton. The study is under the supervision of Professor
Issaka Ndekugri, Professor of Construction and Engineering Law and Director of the
Construction Law and Dispute Resolution Programme of the School. Below are details
regarding the aim and objectives of the research, reasons for selecting your
company/institution for study, what activities will occur on your site during the research,
issues of confidentiality and anonymity and the likely benefits that your company/institution
may gain from participating in this research.
The World Bank and the other Multilateral Development Banks (MDBs) have identified
infrastructure development as a necessary component of any effective strategy for economic
development in the developing world. Unfortunately, disputes often arise from major
infrastructure projects in the developing world that are resolved at great cost by courts and
arbitral tribunals constituted from the most expensive legal professionals in the developed
world. Whilst similar projects in the developed world also suffer from the challenge of costly
disputes, there is a growing trend of resolving them by less costly Alternative Dispute
Resolution Methods (ADR) such as mediation, expert determination and dispute boards.
Compounding the difficulties of developing countries is the general lack of empirical
evidence regarding practical steps in the resolution of construction disputes arising from
major projects in developing countries.
306
Appendices
The aim of this research is to carry out a critical examination of the Ghanaian experience
of the resolution of construction disputes from major infrastructure projects and thereby
develop strategies for dispute reduction and cost- effective resolution. To achieve the aim of
the research, the study will focus on the following objectives: (a) describe the state, trends and
the context of major infrastructure development in Ghana; (b) examine the main parties
involved in the major construction industry in Ghana; (c) investigate the framework for major
infrastructure procurement and the impact of the process on dispute resolution; (d) examine
the legal and institutional framework for resolving disputes from major projects including the
processes and stages involved from the emergence of a dispute to the final determination of
same; (e) study critically some international arbitration cases relating to major infrastructure
projects in Ghana; and (f) identify the challenges to the extant modes of resolution, barriers to
the determination of construction disputes by methods other than international commercial
arbitration and litigation, and remedial strategies.
Your company/institution is one of the few in Ghana which are regularly involved in the
execution of major infrastructure projects and the resolution of disputes arising therefrom.
Your key personnel have experienced the emergence and the resolution of many disputes and
are better placed to share such experiences as they relate to the outlined objectives of this
research.
The study will entail the conduct of interviews with your personnel, who have been
involved in project planning, procurement, contract negotiations and administration, project
management and dispute resolution. Attached is an interview guide. Each interview is
expected to take at least one hour at an agreed location. With your permission or that of the
interviewees, the said interviews will be audio recorded and subsequently transcribed. This is
to ensure that the interviewee’s contributions are accurately captured. The interviewee’s right
307
Appendices
to refuse to answer a question or participate in this research remains intact and shall be
respected.
Any information provided during the interview or in documentary form shall remain
confidential, anonymous and shall remain securely stored. Access to such data shall only be
available to the supervisory team and me. Portions of the data collected (the source of which
shall remain anonymous) may be quoted in the thesis, reports and journal publications
emanating from this research. There are no known risks, current or anticipated, to your
staff/personnel as participants in this research.
It is expected that the outcome of this study will not only benefit your company/institution
but also the State by bringing into sharp focus the need for policy and guidelines on
diversified dispute resolution strategies for effective and efficient reduction and resolution of
construction disputes from major projects. For further information, please contact me at
j.mante@wlv.ac.uk or mantecj@gmail.com. You can also reach my Supervisor, Prof.
Ndekugri at the School of Technology, University of Wolverhampton, City Campus South,
Wulfruna Street, Wolverhampton, WV1 1LY, United Kingdom, tel.: +44 (0) 1902 321000.
I await your response. Thank you in advance.
Yours Faithfully,
308
Appendices
APPENDIX B2 -Request Letters addressed to Interviewees with Institutions affiliated
to the Contractors and adjunct organisations
……………..
Dear Ms. …………,
Application for Permission to Conduct Interviews
I am by this letter humbly requesting you to participate in a research I am conducting as part
of the requirements for my doctorate degree in the School of Technology, University of
Wolverhampton. The study is under the supervision of Professor Issaka Ndekugri, Professor
of Construction and Engineering Law and Director of the Construction Law and Dispute
Resolution Programme of the School. Below are details of the aim and objectives of the
research, reason(s) for selecting you to be part of the study and your involvement, issues of
confidentiality and anonymity and the likely benefits of the research.
The World Bank and the other Multilateral Development Banks (MDBs) have identified
infrastructure development as a necessary component of any effective strategy for economic
development in the developing world. Unfortunately, disputes often arise from major
infrastructure projects in the developing world that are resolved at great cost by courts and
arbitral tribunals constituted from the most expensive legal professionals in the developed
world. Whilst similar projects in the developed world also suffer from the challenge of costly
disputes, there is a growing trend of resolving them by less costly Alternative Dispute
Resolution Methods (ADR) such as mediation, expert determination and dispute boards.
Compounding the difficulties of developing countries is the general lack of empirical
evidence regarding practical steps in the resolution of construction disputes arising from
major projects in developing countries.
The aim of this research is to carry out a critical examination of the Ghanaian experience
of the resolution of construction disputes from major infrastructure projects and thereby
309
Appendices
develop strategies for dispute reduction and cost- effective resolution. To achieve the aim of
the research, the study will focus on the following objectives: (a) describe the state, trends and
the context of major infrastructure development in Ghana; (b) examine the main parties
involved in the major construction industry in Ghana; (c) investigate the framework for major
infrastructure procurement and the impact of the process on dispute resolution; (d) examine
the legal and institutional framework for resolving disputes from major projects including the
processes and stages involved from the emergence of a dispute to the final determination of
same; (e) study critically some international arbitration cases relating to major infrastructure
projects in Ghana; and (f) identify the challenges to the extant modes of resolution, barriers to
the determination of construction disputes by methods other than international commercial
arbitration and litigation, and remedial strategies.
You have been identified as one of the few in Ghana who have acquired much experience
regarding execution of major infrastructure projects and the resolution of disputes arising
therefrom over the years. Therefore, you are better placed to share such experiences as they
relate to the outlined objectives of this research.
The study will entail the conduct of an interview with you at an agreed time and location.
This is expected to take at least one hour. The interview will tap into your experiences, views
and opinions about the resolution of construction disputes arising from major projects.
Attached is an interview guide. With your permission, the said interview will be audio
recorded and subsequently transcribed. This is to ensure that your contributions are accurately
captured. Your right to refuse to answer a question or participate in this research remains
intact and shall be respected.
Any information provided during the interview or in documentary form shall remain
confidential, anonymous and shall remain securely stored. Access to such data shall only be
available to the supervisory team and me. Portions of the data collected (the source of which
310
Appendices
shall remain anonymous) may be quoted in the thesis, reports and journal publications
emanating from this research. There are no known risks, current or anticipated, to you as
participant in this research.
It is expected that the outcome of this study will not only benefit your company but also
the State as a whole by bringing into sharp focus the need for policy and guidelines on
diversified dispute resolution strategies for effective and efficient reduction and resolution of
construction disputes from major projects. For further information, please contact me at
j.mante@wlv.ac.uk or mantecj@gmail.com. You can also reach my Supervisor, Prof.
Ndekugri at the School of Technology, University of Wolverhampton, City Campus South,
Wulfruna Street, Wolverhampton, WV1 1LY, United Kingdom, tel.: +44 (0) 1902 321000.
I await your response. Thank you in advance.
Yours Faithfully,
311
Appendices
Appendix C –List of Codes
14-Dec-13 11:43 AM
Name of Codes
1
A turn around experience
2
Abstract Concepts on DR-sense making
3
Acceleration
4
Actions and interactions (connecting rationale)
5
6
Actions-Interactions
Added cost
7
8
9
Additional payments for no added benefit
Adjudication
Adjudication-contractual for minor or local projects
10 Adjudication-procedure
11 Administering Major Projects
12 Adversarial culture
13 A-Gs dispute handling roles
14 A-Gs role in Procurement
15 AGs’ triple role of advising, reviewing and approving contracts
16 AGs-Procedure for handling disputes
17 Amicable settlement
18 Approach of Foreign Contractors
19 Approach to dispute differ depending on the origin of contractor
20 Approval of contract documentation
21 Arbitration
22 Arbitration and litigation compared
23 Arbitration and mediation compared
24 Arbitration- challenges
25 Arbitration compared
26 Arbitration -not helpful to client all these years
27 Arbitration Preferred by Client
28 Arbitration preferred in construction- rationale
29 Arbitration- terrible
30 Arbitration too expensive
31 Arm twisting
32 Assessing Int. Arbitration
33 Attitudes of Foreign Contractors
34 Attitudes to Dispute Resolution
35 Authoritarianism
36 Avoid formal dispute resolution processes
37 Bad international publicity for Client
312
Appendices
38 Balkan Energy
39 Barriers to the use of intermediary DR mechanisms
40 Barriers to using ADRMs
41 Being claim-conscious
42 Being selective and avoiding dispute prone contracts
43 Being tardy with responses to ICA notices
44 Benefitting Project Executors not Client
45 Binding outcome
46 Blacklist -victimization
47 Blacklisting
48 Breach of Contract
49 Brinkmanship
50 Budgetary allocation for MDAs infrastructure programmes
51 Budgeting
52 Burnt fingers
53 Business-minded
54 Buy-out
55 Cabinet directive on contract review by A-Gs
56 Cabinet's role in Procurement
57 Calling of bluffs
58 Capacity building
59 Cape Coast to Takoradi road
60 Carrot and Stick
61 Causes of Disputes
62 Challenges with Sole sourcing
63 Change of scope of work
64 Changes to the general conditions
65 Claim conditions & Causes of Disputes
66 Claims
67 Claims minimization policy
68 Claims not covered by external funds
69 Claims unhindered
70 Client
71 Client Interference
72 Client producing first draft of contract
73 Client's Approach to Process
74 Client's Attitude
75 Clients blatant disregard of Contractor's claim
76 Client's delay in making a decision over a long period
77 Client's failure or inability to make a decision
78 Client's failure to give the Contractor feedback on claim within a reasonable time
313
Appendices
79 Client's indecision on a claim
80 Clients or Owners
81 Client's views on attitudes of foreign contractors to dispute resolution
82 Collaborative method - PPP
83 Comfort of Contractors
84 Communicating Project finance to Cabinet
85 Compensation payments issues
86 Complete lack of interest by Contractors both foreign and Local
87 Components of the Construction Contract
88 Conceptual Hooks
89 Conciliation
90 Condition for amicable settlement- cost -benefit
91 Conditions for privately sourced funding
92 Conditions of contract - selection and use
93 Conducting lender due diligence
94 Conducting VfM Audits
95 Confidence in the infrastructure for settlement
96 Confidence in the mechanism
97 Confidentiality
98 Connection between contract interpretation and DR
99 Conscious of possibility of disputes
100 Consequence of current contract review process
101 Consequence of lack of PAB or multi-sectorial Committee
102 Consequences of barriers
103 Consequences of breach of contract
104 Consequences of disputes
105 Consequences of Extant dispute Resolution Process
105 Consequences of external funding
106 Consequences of poor dispute resolution practices
107 Considering dispute clauses in VfM audit
108 Constitutional Lacunae in contract review system in Ghana
109 Construction
110 Consultants
111 Consulting for major infrastructure acquisition
112 Contract administration challenges
113 Contract Formation
114 Contract Preparation
115 Contract review
116 Contract review - factors considered
117 Contract review - litigation in foreign forum abhorred
118 Contract review by A-G - background
119 Contract review entailing drafting and redrafting of COPA
314
Appendices
120 Contract type - selection and use
121 Contractor Attitude
122 Contractor drafts accepted due to lack of expertise
123 Contractor v. Contractor DR
124 Contractor-related inhibitors
125 Contractor Preferences
126 Contractors producing first draft of contracts
127 contractual game
128 Cooperation
129 COPA Ghana -terms
130 Cost
131 Cost of amicable settlement
132 Cost of Arb incentive for DRM practice in Ghana
133 Cost v. nature of transaction
134 Cost-benefit analysis v. Public accountability
135 Court referred arbitration
136 Creating a contract review infrastructure
137 Cultural limitations
138 Culture
139 Culture of losing arbitrations
140 Cutting losses on DR
141 DAB
142 Data Protection
143 Database of foreign contractors
144 Debt Management Division
145 Debt sustainability Analysis
146 Deceleration
147 Default Strategy
148 Deficiencies with the current procurement
149 Definition of claims.
150 Delayed Payment
151 Delays
152 Delegating power to take legal decisions
153 demand their pound of flesh
154 Describing major road networks in Ghana
155 Design
156 Design and Build
157 Design Changes
158 Designers
159 Destroying relationships
160 Developing local expertise in Arbitration
170 Developing local expertise in Arbitration (2)
171 Developing strong relationship with contractors
172 Differences
173 Disagreement
315
Appendices
174 Dispute after engineer's decision is rejected
175 Dispute avoidance & reduction
176 Dispute Avoidance strategy - using PAB
177 Dispute Frequency
178 Dispute handling- organisational structure - A-Gs
179 Dispute Handling roles
180 Dispute Query
181 Dispute resolution
182 Dispute resolution infrastructure
183 Dispute Resolution Process -Parties' response to disputes
184 Dispute Resolution Process -Parties' response to disputes (lead to) Consequences of barriers
185 Disputes
186 Disputes - Paying attention to disputes
187 Disputes are pursued only when contractors are exiting the system
188 Disregard of or lack of attention for the contractual provisions and their implementation
189 Distinguishing between externally funded projects and ordinary construction project
190 Doing due diligence on foreign contractors
191 doing due diligence on foreign contractors
192 Donor choice
193 Donor Partner funding
194 Donor-driven strategies
195 Drafting & Negotiating COPA -MDAs - Weak capacity
196 DRB
198 DRM Practice - Weighing your options
199 DRMs
200 DRMs regularly used
201 DRMs not in agreement but in use
202 DRMs rarely used
203 Dropping - suspending pursuit of disputes
204 Dropping - suspending the claims
205 Due diligence & culture familiarity
206 Due diligence on personnel involved
207 Education
208 Effect of traditional procurement method
209 Effective contract preparation
210 Effectiveness
211 Efficient and cost effective Resolution- Opinions on how and what
212 Eliminating Litigants through Procurement process
213 Employer-related inhibitors
316
Appendices
214 Employer's views on ICA
215 Energy Infrastructure
216 Enforceability
217 Enforcement of contract provisions
218 Engaging with Experts on the subject matter
219 Engineer or Consultant's role
220 Engineer's Determination
221 Entrenched positions
222 Environment favour settlement
223 EPC
224 Equating their job with their life - Implying Seriousness
225 EU Practices on Projects
226 Executing Major Projects
227 Executors
228 Exhausting all resolution possibilities
229 Exigencies -driven strategies
230 Expert Determination
231 Exploiting contractual leeway
232 Exploiting weakness in traditional procurement methods
233 Extension of time
234 External Influence on major projects delivery
235 Extra expense
236 Extra work
237 Face to Face meeting after notice is served
238 Factors influencing DRM selection
239 Failure of Parliamentary scrutiny of contracts
240 Failure to correspond with Contractor
241 Failure to patronize local DR institutions
240 Fairly Balanced provisions
241 Fairness
242 Familiarity of Process to Contractors
243 Favoring Litigation-rationale
244 Fear of being blacklisted or blackmailed
245 Fear of being branded a Litigant
246 Fear of Failure to meet expectations
247 Fear of loss of future jobs
248 Fear of trying something new
249 Features and Context of Parties to Dispute Resolution
250 Features and Context of Parties to Dispute Resolution (affect) Dispute avoidance & reduction
317
Appendices
251 Features and Context of Parties to Dispute Resolution (determine) Dispute Resolution Process -Parties' response to disputes
252 Features and Context of Parties to Dispute Resolution (have influence on) Dispute Resolution Process -Parties' response to
253 Feet-dragging
254 Few disputes
255 Finance Committee
256 Financial conditions
257 Financial obligations
258 Financing infrastructure Acquisition
259 Firefighting
260 Fiscal policy
261 'Forced settlements'
262 Foreign Executors
263 Form of Contract
264 Formalizing the use of multi-sectoral committees through policy
265 Front End ordering
266 Funders - Influencing the procurement process
267 Funders assisting in training local expertise
268 Funder's choice
269 Funders' choice of conditions of contract
270 Funder's involvement in dispute resolution
271 Funders position on payment of avoidable claims
272 Funders with conditions- lots in the system
273 Funding Major Projects
274 Funding requirement
275 Funding sources for infrastructure development
276 Funding sources for infrastructure development (affect) Procurement methods
277 Funding sources for infrastructure development (determine) Procurement Strategies
278 Further research -what is the cost of disputes & Resolution
279 Game playing
280 Generic Inhibitors
281 Ground conditions
282 Growing more on paper than in reality
283 Guarding against impleading the State before a foreign court
284 Employer hardly pays attention to DR clauses
285 Harmonising fiscal and monetary policy
286 Having political influence and connections
287 Ignoring correspondence from Executors
288 Ignoring Notices of Arbitration
318
Appendices
289 Ills of GOG funding
291 Immunity clauses
292 Impact of delay payments
293 Impeccable record-keeping – Foreign Contractors
294 Implementing contract review outcomes
295 Improved contract administration providing early warning signals
296 In charge of economic policies
297 Inadequate engineering studies on Projects
298 Inadequate infrastructure for contract review
299 Incidence of urgency contracts
300 inclement weather
301 Incomplete Design issues
302 Inconsiderate of client's position
304 Increased use of DRMs
305 Enculturation
306 Independent Experts
307 Indexicality
308 Inefficient inter-organisational cooperation
309 Inevitability
310 Influence of Culture on Construction Dispute resolution
311 Informal resolution mechanisms
312 The information game
313 Infrastructure Database
314 Institutional cooperation on dispute resolution
315 Institutional Involvement in major infrastructure projects - AGs
316 Institutional involvement in resolving 'problems' on projects
317 Institutional roles in dispute resolution
318 Institutional roles in major Projects procurement
319 Institutional structures
320 Institutional structures (Reflect) Client's Attitude
321 Insufficient advice on ADRM choices
322 Integrated methods -procurement
323 Interest claims will compensate
324 Internal turf wars
325 International Arbitration
326 International Arbitration receiving more attention-rationale
327 International best practice
328 International ownership
329 Interviewee's Profile
330 Interviewee's role
331 Initiating Major Projects
332 Introducing a new contract provision as a result of an experience had
333 Investment Protection
334 Involving management
319
Appendices
335 Involving management in resolution
336 jacks of all trades
337 Joint- funding
338 Justifying selection of Arbitration
339 Justifying the need for COPA Negotiation
340 Keeping up-to-date record of claims
341 Knowledge Gap of dispute professionals
342 Lack of alternative dispute resolution infrastructure
343 Lack of attention for dispute resolution at the front end by Client
344 Lack of attention to dispute resolution at the front end by Client
345 Lack of capacity
346 Lack of coordination
347 Lack of expertise- Arbitrators, Mediators
348 Lack of exposure for handlers
349 Lack of Good will
350 Lack of information on use and success rate
351 Lack of Innovation in Procurement
352 Lack of institutional cooperation
353 Lack of knowledge
354 Lack of expertise
355 Lack of Popularity -ADR
356 Lack of Specialisation hampering dispute handling
357 Lack of stance on alternatives to ICA -Employer
358 Lack of training
359 Lack of understanding
360 Lacking control over choice of mechanism
361 Lacking focus on disputes
362 Largest Employer
363 Laxity in contract administration
364 Learning from claim and dispute experiences
365 Learning from past experience
366 Learning from past experiences
367 Legal implications of Obligations
368 Legal system
369 Likely to dispute with Government
370 Link between political influence and DR practice
371 Link between poor contract preparation and review and claims and disputes
372 Link between poor planning and disputes
373 Linking claim conditions to political pressure
374 Linking claim reduction to pre-contractual activities
375 Linking contract to DR practice
376 Linking funding agency rules and requirements to ADRM choice
320
Appendices
377 Linking government policy to DR choices
378 Linking individual interests and choices to DR Practices
379 Linking institutions to dispute resolution
380 Linking Parties, DR and Blacklist
381 Linking Political influences to disputes
382 Linking pre-contractual negotiations &contract administration lapses to claim and dispute reduction
383 Linking procurement to Dispute Resolution
384 Linking the various claim conditions to each other, delay, costs and claim
385 Litigating in the local court
386 Litigation favoured by some businesses
387 Litigation not a choice
388 Local contractors' attitude towards dispute
389 Looking out for all the elements of a valid contract
390 Maintaining Business relationships
391 Maintaining relationship as a basis for dropping claims
392 Making a Case for a firm stance on dispute resolution choices
393 Making Procurement decisions
394 Malfunctioning joint ventures - contractors
395 Water Expansion Project
396 Material failure during warranty period
397 MDAs role in dispute handling
398 Meaning of 'dispute'
399 Mediating Major Project dispute - an example
400 Mediation
401 Merging general and special conditions for medium to small works PPA docs
402 MOFEP - Pay dispute related cost and expenses
403 MOFEP's Conditions for funding Projects
404 MOFEP's requirements for non-GOG funding
405 MOFEP's role
406 Multi sectoral approach to dispute resolution - downside
407 Multi sectoral approach to dispute resolution- advantages
408 Multiple-mechanisms found in boiler plate contracts often unchanged
409 Multi-sectoral Approach to dispute resolution preferred
410 Multi-sectoral Committee to report to MDA
411 Nature of construction disputes
412 Nature of Parties
413 Negative Perceptions about ICA
414 Negative perceptions of ADR -non-binding, waste of time
415 Negotiating COPA
321
Appendices
416 Negotiating COPA -Contractors' experience v. MDAs' experience
417 Negotiating COPA- extent of A-G's involvement
418 Negotiating COPA- the VRA Approach - the committee strategy
419 Negotiating dispute resolution clauses
420 Negotiating stepped delivery of possession of site
421 Negotiating with the Lender
422 Negotiation
423 Neutrality
424 No claim pursuit
425 No deliberate consideration of factors influencing DRM Selection
426 No disputes scenario
427 No infrastructure for major dispute resolution
428 No interest pursuit
429 Non performance
430 Non-Payment
431 Non-performance, breach of contract linked to Political interference
432 Not thinking dispute – Employer
433 Notice of arbitration issued
434 Objects of the Interviewee's organisation
435 One-sided consideration
436 Open support by the judiciary of DRM decisions
437 Open Tendering
438 Operationalizing Knowledge
439 Opting for Arbitration as first resort
440 Organisational structure
441 Other background information
442 Out to make money –Foreign contractor
443 PAB-paying attention to dispute resolution clauses
444 Paternalism
445 Partial possession of site
446 Parties' preferences
447 Parties to major construction projects
448 Party attitudes
449 Pay attention to pre-contractual negotiations
450 Pay dispute related cost and expenses
451 Paying attention to dispute resolution at the front end by Client
452 Pending issues between Client and Contractor
453 Perception of bias against Developing countries
453 Playing an advisory role on major Project acquisitions - A-G
454 Playing hardball
322
Appendices
455 Playing the past benefit card
456 Playing Victims
457 Playing victims in international arbitrations
458 Policy and guidelines on dispute resolution
459 Policy and or guidelines on dispute resolution
460 Policy and or guidelines on dispute resolution -Making a case for it
461 Policy on contract review, negotiation and approval
462 Policy on dispute handling and resolution at the AGs
463 Policy on dispute resolution advocated
464 Political Interference
465 Political Pressure
466 Politically tainted settlements
467 Poor at record keeping
468 Poor definition of the scope.
469 poor preparation of contracts
470 Poor project preparation linked to cost
471 Poor record keeping
472 Popularizing the other ADR
473 Post notice of claim
474 Post notice of claim - DUR
475 Power play
476 Power to make final decisions on resolution proposals
477 PPP - rationale
478 PPP as a strategy
479 Pre-contractual fixation on ICA by client
480 Pre-Contractual Negotiations
481 Prefer to go to international arbitration
482 Preference for a Sole Arbitrator
483 Pricing
484 Priority Projects
485 Privately solicited external funding
486 Procedure –Dispute resolution
487 Procedure for external funding
488 Procedure for GOG funding
489 Procedure for Sole sourcing
490 Process aim at embarrassing Client -ICA
491 Procurement
492 Procurement approvals required
493 Procurement by MOU
494 Procurement by MOU distinguished from Sole sourcing
495 Procurement history
323
Appendices
496 Procurement methods
497 Procurement Procedure
498 Procurement Strategies
499 Producing standard ADR Clauses for contracts
500 Profit making
501 Profitable environment
502 Profit-oriented
503 Projects - Examples
504 Project Executors
505 Project objectives
506 Project preparation
507 Promotion of DRMs
508 Public Agreement Board -opposition to it by MDAs
509 Public Agreements Board
510 Public Agreements Board- recent efforts to revive it
511 Public suspicions
512 Quick resolution of an emerging dispute
513 Quick to accede to funding conditions
514 Rationale for a Contract review Infrastructure
515 Rationale for a multi-sectoral Committee
516 Rationale for contractor attitudes towards claims
517 Rationale for external funding
518 rationale for failure
519 Rationale for Contract review
520 Rationale for the no dispute claim - Intimidation
521 Rationale for VfM audit
522 Readiness to explore Client's record-keeping challenges
523 Recommendations
524 Recommended Approach to contract review
525 Refusal to accept defeat
526 Regular Project Meetings
527 Relocation of utilities
528 Remedial Strategies
529 Required policy changes
530 Resolving during Preliminary discussions
531 resolving problems- the impact of good working relationship
532 Resort to arbitration as threats
533 Responsible for government's contractual payments
534 Resulting action~ interaction
535 Resulting actions
536 Resulting actions and interactions
537 Resulting actions and reactions
324
Appendices
538 Resulting Actions, reactions and no actions
539 Reticence- taciturn towards disputes
540 Review financial contracts for Infrastructure acquisition
541 Road sector -Technical Preparations
542 Rushing projects
543 Sanctioning lax officials
544 Scope of works or assignment
545 Scrutiny of contract provisions on issues such as dispute resolution
546 Sector ministry making a formal request for A-Gs no objection
547 Seeing Client as a Partner
548 Seeking Anonymity
549 Seeking approval for tax and duty waivers
550 Seeking funding - procedure
551 Seeking legal advice early
552 Seeking Parliamentary approval of project finance
553 Selection and use of ICA
554 Selective tendering
555 Setting Standards for DRM use
556 Settling Claims - The Engineer's role
557 Settling Claims within the Contract
558 Shoddy work - cutting corners
559 Shying away from formal DR processes
560 Site Meetings
561 Site Possession~ Access to Site
562 Irregular training
563 Sole Sourcing major projects
564 Sorting out compensation issues ahead of projects
565 standard and acceptable tried and tested
566 Standards for project set by implementing agency
567 State of cases at the point of reaching the A-Gs
568 State of Infrastructure
569 State playing a reactive role in choice of mechanisms
570 Sticking to old mindset
571 Strategic positioning
572 Strong reservation –dispute clauses
573 Submitting contract documents for review
574 Suppliers Credit
575 Tactical neglect
576 Taking responsibility for ADR use or settlements
577 Team Work
578 Teamwork as a driver for the contract review process
325
Appendices
579 Tendering and Consultant & Contractor Selection Methods
580 Term sheet
581 Termination Clauses
582 The Artesian Well Scenario - Likely future impact
583 the Chinese approach to DR - promoting settlement and maintaining relationships
584 The Enforceability issue
585 The master-servant relationship
586 Think through DR clauses before Agreeing to use them
587 Threat of blacklist
588 Thresholding impractical
589 Traditional Methods
590 Training for lawyers
591 Training for the Government's personnel
592 Training required
593 Transactions are naturally very relational
594 Transfer of expertise
595 Treading on dangerous grounds.
596 Trust deficit for ADRs
597 Uncertain contractual provisions
598 Understanding Contracts before signing them
599 Unsolicited Proposals
600 Using ext. of time -non-monetary claim strategy
601 Using foreign lawyers, a matter of course
602 Using local expertise
603 Using the FIDIC DR provisions
604 Using threat of DR to achieve compliance
605 Value for money
606 Value of Project
607 VfM audit -procurement
608 Waiving condition Precedents
609 Wasting money and time –Dispute resolution
610 Water Infrastructure
611 Waterville v. GOG Mediation - Accra & Kumasi Sports Stadia Rehab
612 Weighing the factors -Cost v. Confidence in mechanism and process
613 Well researched forms
614 Western approach to DR- claim oriented
615 When a claim is rejected by the engineer
616 When the case is Spoilt or too late
617 Why DABs not set up
326
Appendices
618 Why FIDIC
619 Why negotiations
620 Willing to settle
621 Works
327
Appendices
Appendix D – Themes, Categories, Sub-categories and Codes
Themes
Categories/Sub-categories
Codes
Features and
Context of Parties
to Dispute
Resolution
Institutional Structures
Objects of Interviewee's
organisation
Organisational Structure
Interviewee’s Profile
Interviewee’s Role
Institutional roles in dispute
resolution
Institutional roles in major
infrastructure procurement
Institutional roles in major Cabinet's role in Procurement
infrastructure procurement
MDAs roles
A-Gs’ role in Procurement
MOFEP's role
Multi-sectorial
Committee
review
Responsible for
policy formulation
MOFEP's role
economic
Communicate financial details
of Projects to Cabinet
Seeks parliamentary approval
for loans and other financial
arrangements
Seeks parliamentary approval
for tax and duty waivers
Conduct value for money audit
Conduct
lenders
due
diligence
on
Negotiate with Lenders
Conduct debt sustainability
328
Appendices
Themes
Categories/Sub-categories
Codes
analysis
Review financial contracts
Arranging for Finance for
infrastructure projects
Responsible for Government’s
contractual payment
Harmonising
fiscal
monetary
policies
Government
and
of
Budgeting
A-Gs’ role in Procurement
Advise, review and approve
major
infrastructure
transactions
Jacks of all trades
Institutional roles in dispute A-G’s role
resolution
Fire Fighting
MDA’s role
handling
in
dispute
MOFEP’s
role
–paying
Government’s dispute related
cost and expenses
Consequences of Institutional Inefficient inter-organisational
structure and roles
cooperation
Internal turf wars
Lack
of
specialisation
hampering dispute handling
Funding Major projects
Rationale for external funding
Conditions
for
sourced funds
privately
Externally funded projects v.
ordinary self- funded projects
329
Appendices
Themes
Categories/Sub-categories
Codes
Procedure for external funding
MOFEP’s requirements
non-GoG funding
for
Procedure for GoG funding
MOFEP’s role
Consequences
funding
of
external
Ills of GoG funding
Claims not covered by external
funds
Funding
sources
for GoG
infrastructure development
Donor funding
Private external funding
Joint funding
External Influence on major EU Practices on Projects
projects delivery
Funders-influencing
procurement process
the
Funders assisting in training
local expertise
Funders' choice of conditions
of contract
Funder's
involvement
dispute resolution
in
Funders position on payment
of avoidable claims
Funders with conditions
Political Interference
Political pressure
Political interference
Consequences
330
Appendices
Themes
Categories/Sub-categories
Codes
Procurement
(see theme on procurement)
Parties to major projects
Employer
Foreign contractors
Legal System
Influence of Culture on Environment
Construction dispute resolution settlement
favours
Authoritarianism
Reticencedisputes
taciturn
towards
Transactions are naturally very
relational
Attitudes to Dispute resolution
Employer’s Attitudes to Dispute Blacklisting
Resolution
Buy out
Forced settlement
Involving management
Politically tainted settlement
Resolving
discussions
at
Preliminary
Litigating in local court
Ignoring notices of Arbitration
Being tardy with responses to
ICA processes
Ignoring correspondence on
disputes from contractors
Willing to settle
Client's views on attitudes of Being claim conscious
foreign contractors to dispute
Impeccable record keeping
331
Appendices
Themes
Categories/Sub-categories
resolution
Codes
Conscious of possibility of
future disputes
Readiness to explore client’s
record-keeping challenges
Profit-oriented
Business-minded
Having political influence and
connections
Exploiting weaknesses of the
traditional
procurement
method
Avoid
formal
resolution processes
dispute
Use threat of DR(ICA) to
achieve compliance
Exploiting contractual leeway
Prefer to ICA
Foreign contractors’ attitude to Maintaining good relationship
dispute resolution
with the Employer
Avoid dispute prone contracts
See client as a partner
Enculturation
Rationale
for
contractor Profit
attitudes towards disputes
Fear of loss of future jobs
Interest
claims
compensate
Disputes
exit plan
Barriers
to
the
use
332
of
will
pursued as part of
Appendices
Themes
Categories/Sub-categories
intermediary DR mechanisms
Codes
Employer-related barriers
Largest Employer
Blacklist-victimization
Sticking to old minds
Lack of stance on alternatives
to ICA
Lack
of
cooperation
institutional
Taking of responsibility for
ADR use or settlement
Fear of failure
expectations
to
meet
Poor record keeping
Public suspicion
Lack of Specialisation
Lack of Policy and guidelines
on dispute resolution
Contractor-related barriers
Failure to pursue disputes for
fear of being branded litigant
The enforceability issue
Knowledge Gap of dispute
professionals
Generic barriers
Lack of popularity
Lack of information on use and
success rate
Cultural limitations
Profitable environment
The extra expense argument
333
Appendices
Themes
Categories/Sub-categories
Codes
Lack of expertise
Negative perception of the use
of ADR
Adversarial culture
Lack of alternative dispute
resolution infrastructure
Refusal to accept defeat
Trust deficit
Skewed training
Procurement
Contract Formation& Review
Contract preparation
Client producing first draft of
contract
Contract Formation
Contractor drafts accepted due
to lack of expertise
Contractors producing
draft of contracts
first
Doing due diligence on foreign
contractors
Pre-Contractual Negotiations
Pre-Contractual NegotiationsApproach
of
Foreign
Contractors
Lack of attention to dispute
resolution at the front end by
Client
Negotiating COPA
COPA Ghana –terms
Drafting & Negotiating COPA
-MDAs - Weak capacity
Justifying the need for COPA
334
Appendices
Themes
Categories/Sub-categories
Codes
Negotiating
COPA
Contractor’s' experience
MDAs' experience
v.
Negotiating COPA- extent of
A-G's involvement
Negotiating COPA- the VRA
Approach - the committee
strategy
Negotiating dispute resolution
clauses
State playing reactive role in
selection of dispute resolution
mechanisms
Components
of
Construction Contract
the
Conditions of contract
selection and use
-
Conditions of contract selection and use\Why FIDIC
FIDICFairly
provisions
Balanced
Conditions of contract selection
and
use\Why
FIDIC\Familiarity
Conditions of contract selection
and
use\Why
FIDIC\Funder's choice
Conditions of contract selection
and
use\Why
FIDIC\International ownership
Conditions of contract selection
and
use\Why
FIDIC\standard and acceptable
tried and tested
Conditions
335
of
contract
-
Appendices
Themes
Categories/Sub-categories
Codes
selection
and
use\Why
FIDIC\Well researched forms
Contract type - selection and
use
Incidence of urgency contracts
Merging general and special
conditions for medium to small
works PPA docs
Suppliers Credit
Linking claim reduction to precontractual activities
Cabinet directive on contract
review by A-Gs- recent
development
Contract Review
Consequence of lack of PAB
or multi-sectorial Committee
Constitutional Lacunae
contract review system
Ghana
in
in
Contract review by A-G –
background
Drafting & Negotiating COPA
-MDAs - Weak capacity
Failure
of
Parliamentary
scrutiny of contracts
PAB-paid attention to dispute
resolution clauses
Public Agreement Board opposition to it by MDAs
Public Agreements Boardrecent efforts to revive it
Rationale for Contract Review
Consequence
336
of
current
Appendices
Themes
Categories/Sub-categories
Codes
contract review process
Inadequate infrastructure for
contract review
Link between poor contract
preparation and review and
claims and disputes
Creating a contract review
infrastructure
Rationale for Contract review
Infrastructure
Rationale for a multi-sectoral
Committee
Approach to contract review
Teamwork as a driver for the
contract review process
Approval
of
documentation
contract
Litigation in foreign forum
abhorred
Entailing
drafting
redrafting of COPA
and
Due diligence on personnel
involved
Engaging with Experts on the
subject matter
Financial obligations
Form of Contract
Guarding against impleading
the State before a foreign court
Immunity clauses
Implementation
337
Appendices
Themes
Categories/Sub-categories
Codes
Legal
implications
obligations
of
Looking out for all the
elements of a valid contract
Pricing
Project objectives
Scope of works or assignment
Scrutiny of contract provisions
on issues such as dispute
resolution
Termination clauses
Value for Money
Doing due diligence on foreign
contractors
Implementing contract review
outcomes
Multi-sectoral Committee to
report to Sector Ministry
Submitting contract documents
for review
Factors
Influencing
Selection
DRM Comfort of Contractors
Confidence
in
the
infrastructure for settlement
Nature of Parties
Confidence in the mechanism
Neutrality
Cost
Fairness
Strong reservation
338
Appendices
Themes
Categories/Sub-categories
Codes
Value of Project
Weighing the factors -Cost v.
Confidence in mechanism and
process
Investment protection
Cost v. nature of transaction
One-sided consideration
Lack of knowledge
Donor choice
International best practice
Outcome of Mechanism
Familiarity of
Contractors
Process
to
Culture
State playing a reactive role in
choice of mechanisms
Claim events & Causes of
Disputes
Claim Events
Change of scope of work
Political interference
Delayed payment
Design changes
Delays
Extra work
Ground conditions
Inadequate engineering studies
on project
339
Appendices
Themes
Categories/Sub-categories
Codes
Inclement weather affecting
work
Incomplete design issues
Laxity
in
administration
contract
Poor definition of the scope
Poor preparation of contracts
Poor project preparation linked
to cost
Site possession-Access to site
Non-compliance
condition precedents
with
Negative effect of traditional
procurement methods
Lack of coordination
Causes of Disputes
Breach of Contract
Client interference
Consequences of breach of
contract
Delayed payments
Non-performance
Uncertain contract provisions
Indexicality
Failure to communicate with
contractors
Material
failure
warranty period
Disregard
provisions
340
of
during
contract
Appendices
Themes
Categories/Sub-categories
Codes
Laxity
in
administration
contract
Non-payment
Malfunctioning
ventures
of
joint-
Paying attention to disputes
Disputes
Meaning of disputes
Nature of construction disputes
Inevitability
Dispute frequency
No disputes
Consequences of Disputes
Meaning of Disputes
Differences
Client's delay in making a
decision over a long period
Client's indecision on a claim
Client's failure to give the
Contractor feedback on claim
within a reasonable time
Clients blatant disregard of
Contractor's claim
Dispute
after
engineer's
decision is rejected
Pending issues between Client
and Contractor
When a claim is rejected by
the engineer
Disagreement
Non-payment
341
Appendices
Themes
Categories/Sub-categories
Settling
Claims
Engineer's role
-
Codes
The Face-to-face meeting
notice is served
after
Post-notice of claim – DUR
Engineer or Consultant’s role
Keeping up to date records of
claim
Definition of claims
Maintaining relationship as a
basis for dropping claims
Claim minimization policy
Using ext. of time -nonmonetary claim strategy
Lack of knowledge of the law
Dropping - suspending the
claims
Procurement
Procurement strategies
Procurement history
Funders-Influencing process
Procurement methods
Linking
Procurement
dispute resolution
to
Making procurement decisions
Procurement procedure
Tendering and Consultant &
Contractor Selection Methods
Deficiencies with the current
procurement
Lack
342
of
Innovation
in
Appendices
Themes
Categories/Sub-categories
Codes
Procurement
Procurement strategies
Default strategies
driven procurement
–donor
Unsolicited Proposals
PPP as a strategy
PPP-rationale
Traditional Methods
Procurement methods
Integrated
and build
methods –design
Integrated method –EPC
Collaborative methods -PPP
Tendering and Consultant & Procurement
Contractor Selection Methods
distinguished
sourcing
by
from
MOU
Sole
Sole Sourcing major projects
Open Tendering
Selective tendering
Sole Sourcing/single
procurement
source Challenges with Sole sourcing
Rationale for VfM audit
Procurement by MOU
Procedure for Sole sourcing
VfM audit –procurement
Considering dispute clauses in
VfM audit
Dispute Resolution Dispute resolution mechanisms
Process
(DRMs)
Engineer’s determination
DRMs regularly used
343
Appendices
Themes
Categories/Sub-categories
Codes
Negotiations
International
Commercial
Arbitration (ICA)
Selection and use of ICA
ICA
Cost
Negative
ICA
perceptions
about
Delays
Perception of bias
developing countries
against
Playing victims
Selection and use of ICA
Funding requirements
Confidence in the mechanism
Value of project
Confidence
in
the
infrastructure for resolution
Binding outcome
Enforceability
Nature of Parties
Fairness
Strong reservation
Investment protection
International best practice
Familiarity
contractors
of
process
Comfort of contractors
Neutrality
344
to
Appendices
Themes
Categories/Sub-categories
Codes
Cost
Arbitration too expensive
Cost of arbitration incentive
for ADR practice in Ghana
Negative perceptions about ICA Wasting money and time
Arbitration-challenges
Benefitting project executors
not Employer
Destroying relationships
Arbitration not helpful
Employer all these years
to
ICA-terrible
Bad international publicity for
Employer
ICA
process
aimed
embarrassing Employer
at
Negotiations
Negotiations
Amicable settlement
Preliminary discussions
Effectiveness
Why Negotiations
Fear of trying something new
Lack of training
Lack of exposure to other
DRMs
Lack of
expertise
knowledge
Natural first choice
Mediation
DRMs rarely used
DAB
345
and
Appendices
Themes
Categories/Sub-categories
Codes
Conciliation
DRB
Independent experts
Adjudication
Expert determination
Mediation
Mediating
Major
dispute - an example
DAB
Why DABs not set up
Litigation
Litigation
choice
not
a
Project
preferred
Litigation favoured by some
other businesses
Favouring litigation-rationale
Procedure
Adjudication
DRMs not in agreement but in Informal resolution
use
Politically tainted settlements
Informal resolution
Forced settlement
Buy-outs
Involving management
Abstract concepts on dispute Conceptual hooks
resolution –sense making
Strategic positioning
Game playing
Acceleration
Game playing
Deceleration
Information game
346
Appendices
Themes
Categories/Sub-categories
Codes
Carrot and stick
Power play
Brinkmanship
Arm twisting
Calling off bluffs
Tactical neglect
Burnt fingers
Playing hardball
Playing the past benefit card
Threat of blacklist
Procedure
General Procedure
Engineer/Consultant’s role
Face to face meetings
Post-notice of claim
Site meeting
Consequences
Consequences of the Extant Cost of
Dispute resolution process
expensive
Arbitration
too
Cost of Arb incentive for DRM
practice in Ghana
Delays
Destroying relationships
Dropping - suspending pursuit
of disputes
Dropping - suspending pursuit
of disputes due to Lack of
knowledge of the law
Maintaining relationship as a
basis for dropping claims
347
Appendices
Themes
Categories/Sub-categories
Codes
Few disputes
The Artesian Well-Scenario –
Likely future impact
Remedial Strategies
Increased use of DRMs
Negotiations
Mediation
DAB
Conciliation
Producing
ADR
clauses for use
specific
Promotion of ADR
Required Policy changes
Formalizing the use of multisectoral committees through
policy
Further research -what is the
cost of disputes & Resolution
Making a Case for a firm
stance on dispute resolution
choices
Open support by the judiciary
of DRM decisions
Policy and or guidelines on
dispute resolution
Policy and or guidelines on
dispute resolution – Rationale
Policy revision on contract
review,
negotiation
and
approval
Policy on dispute handling and
resolution at the AGs
Policy on dispute resolution
advocated
348
Appendices
Themes
Categories/Sub-categories
Codes
Sanctioning lax officials
Setting a threshold
Dispute
reduction
Avoidance
and Claims minimization policy
Dispute Avoidance strategy using PAB
Due diligence
familiarity
&
culture
Effective contract preparation
Improved
contract
administration providing early
warning signals
Linking
pre-contractual
negotiations
&
contract
administration lapses to claim
and dispute reduction
Negotiating stepped
of possession of site
delivery
Pay attention to pre-contractual
negotiations
Paying attention to dispute
resolution at the front end
Quick resolution
emerging dispute
of
an
Regular Project Meetings
Seeking legal advice early
Sorting out compensation
issues ahead of projects
Team work
Understanding
Contracts
before signing them
Introducing
349
new
contract
Appendices
Themes
Categories/Sub-categories
Codes
provisions to address previous
challenges
Education and Training
Capacity building
Education
Developing local expertise in
Arbitration
Learning from past experience
Training
personnel
for
Government
Training for lawyers
Promotion of DRMs
Operationalizing Knowledge
Transfer of expertise
Front-end ordering
Paying attention to dispute
resolution at the front end –
Employer
Understanding
Contracts
before signing them
Effective contract preparation
Team work
Negotiating stepped
of possession of site
delivery
Pay attention to pre-contractual
negotiations
Consider DR clauses before
Agreeing to use them
Producing standard
Clauses for contracts
ADR
Introducing a new contract
provision as a result of an
experience had
350
Appendices
Themes
Categories/Sub-categories
Codes
Setting standards for DRM use
DRM Practice - Weighing
your options
Cost-benefit analysis v. Public
accountability
Condition
for
amicable
settlement- cost –benefit
Conciliation
DAB
351
Appendices
Appendix E- List of Interviewees and their Code Names
Code
Professional Background
Case Affiliation
CPA 1
Law
Employer
CPA 2
Law
Employer
CPA3
Law
Employer
CPA4
Law
Employer
CPA 5
Law
Employer
CPA 6
Law
Employer
CPA7
Law
Employer
CPR 1
Law
Employer
CPR2
Quantity Surveying
Employer
CPR 3
Engineering
Employer
CPR 4
Engineering
Employer
CPR 5
Quantity Surveying
Employer
CPR 6
Engineering
Employer
CPR 8
Engineering
Employer
CPR9
Engineering
Employer
CPR10
Quantity Surveying
Employer
CPW 1
Law
Employer
CPW2
Quantity Surveying
Employer
CPW3
Law
Employer
CPW4
Engineering
Employer
CPW5
Engineering
Employer
CPW6
Engineering
Employer
CPW7
Hydrology
Employer
CPW8
Hydrology
Employer
352
Appendices
Code
Professional Background
Case Affiliation
CPE 1
Law
Employer
CPE3
Law
Employer
CPE2
Law
Employer
CPE4
Engineering
Employer
CPE 5
Engineering
Employer
CPE6
Engineering
Employer
CPE 7
Engineering
Employer
CPW 9
Quantity Surveying
Employer
CPW 10
Quantity Surveying
Employer
CPW 11
Quantity Surveying
Employer
CPP
Finance
Employer
APC
Engineering
Contractors
CPF 2
Law
Employer
CPF3
Law
Employer
CPF4
Law
Employer
CPF5
Economics
Employer
CPF6
Finance
Employer
CPF1
Law
Employer
CPP1
Law
Employer
CPP2
Quantity Surveying
Employer
APB 1
Law
Contractors
APB2
Law
Contractors
APA
Law
Contractors
APT
Law
Contractors
APN
Law
Contractors
353
Appendices
Code
Professional Background
Case Affiliation
APE
Engineering
Contractors
EP 1
Quantity Surveying
Contractors
EP2
Contractors
CPE
Law
Employer
APF
Law
Contractors
EP3
Engineering
Contractors
APG
Law
Contractors
354
Appendices
Appendix F - Sample Code Memo
Settling Claims
29 September, 2012 6:01PM
Settlement of claims in the major construction industry in Ghana is not a straight
forward subject. The various conditions of contract provide claim procedure to be
followed in case a party to the contract chooses to make a claim. The Conditions of
Contract also determine the conditions under which a claim will be admitted and
processed. In the context of Ghana, practice as identified through the interviews
conducted differ depending on the MDA involved. What is common among all the
MDAs is that the claim or dispute procedure is multi-sectorial. It may start with the
resident engineer on the particular project, proceed to the Agency, Authority or
company responsible for the project, then proceed further to the sector ministry
involved in the project and sometimes the Attorney - General's Department. A prudent
treatment of the subject may require a sectorial approach. The aim is to find out
whether there is any significant difference in approach. In this regard, this work will
examine the procedure of claim by responsible institutions under three sectors noted
for major infrastructure project execution. These sectors are road, water and energy.
The Road Sector
The main entities involved in claim processing in the road sector are the Ministry
of Roads and Highways (MRH) representing the State as the Client and the Ghana
Highway Authority (GHA) which acts as the Client's representative and the Engineer
on such projects. The GHA will often have a resident Engineer directly responsible for
the supervision of the project or a private consultant who will still be reporting to the
GHA. In both cases, the practice is in line with the provisions of Clause 2.2 and 2.3 of
the 1987 FIDIC Conditions for Civil Engineering Works ( 1987 Red book) and Clause
355
Appendices
3.1&2 of the 1999 FIDIC Conditions of Contract for Building and Engineering Works
designed by the Employer (the Red book, 1999). The claim procedure in practice
within the road sector very much reflect the procedure outlined under Clause 53 of the
FIDIC Conditions of Contract for work, 1987 which is the dominant conditions of
contract in use in the road sector. In recent times, the industry has seen a gradual
introduction of contracts based on the FIDIC 1999 conditions. The former however
remains dominant.
The first point of call for any claim remains the Engineer or his representative who
is either a resident Engineer for the particular project or a private consultant employed
to oversee the execution of the project (EP3). In the case of major road projects in
Ghana, the data obtained reveals that most such projects will have either a resident
engineer or a private consultant on the ground. Both the resident engineer and the
private engineer report to GHA which is the Engineer for these projects. The only
exception is with the EU Conditions where a private consultant reports to the national
authorising officer and not GHA. The contractor is also required to serve a copy of
the claim on the Client, which is the MRT. The resident engineer or the consultant
receiving the notice of claim and the evidence in support are required to ensure that
the contractor has complied with the requirements of the contract. A participant, who
is currently a resident engineer on a project, shared his experience:
Let us take the project supervision that I am handling right now, when there is a
claim, [it] is submitted to the office of the resident engineer. Now the resident
engineer will receive the claim. But first of all there are certain conditions that the
contractor or the claimant should meet and if those conditions are not met we can
reject the claim outright. For any occasion giving rise to that claim, the engineer
356
Appendices
should have been notified in advance that this is what is happening and it is likely to
result in a claim.
A claim made by a contractor must comply with Clause 53 of the FIDIC 1987
Condition of contract or Clause 20(1) of the FIDIC 1999 especially the timelines. An
official with enormous expertise in the area of claims in the road sector, described the
practice in the following terms:
I mean before we admit any claim, we must ensure that it satisfies the claim
procedure so that’s what we tell our people on projects. We normally hold seminars
from time to time and claim is an issue which we discuss. We tell them that, from day
one they can stop – some of these claims are rather frivolous, they are afterthoughts if
you are supposed to give notice within twenty-eight days; provide details within
twenty-eight days and the engineer is supposed to start taking his records – your
notice is to get the engineer informed that something is going wrong, he can stop it –
he better stop it and avoid any escalation of the situation so if you don’t follow those
things when your claim comes, they will knock it out.
Once a claim is received, it is the responsibility of the resident engineer or the
consultant to vet the claim, request for supporting information and write an opinion
indicating whether or not the claim is justified. At this stage, the resident engineer or
consultant can intervene to stop the claim from proceeding further, if there is
justification for such a step, through initial discussions with the contractor. CPR8 gave
an example of such an intervention which resulted in a claim running into several
millions of US dollars being withdrawn. When the resident engineer or the contractor
is ready with his opinion, this is forwarded to GHA. The practice confirmed by a
number of experienced persons in management within the road sector is that when the
resident engineer's report is received, a team is constituted at the GHA to examine the
357
Appendices
resident engineer's opinion as against the claims from the contractor. At this stage, the
resident engineer still has the opportunity to further explain his position. Other experts
in cost and contract also have the opportunity to examine the claims as against the
opinion of the consultant or the resident engineer. If there is the need for further
particulars or evidence to be sought from the contractor, this is done.
Some participants indicated that in some cases, the contractor is also invited and
heard again. The aim of this invitation is to attempt to reach a position acceptable to
both parties. In such cases, the issue may be resolved and the parties' agreed position
will be captured as the settlement for the claims in issue. Where the informal
settlement efforts afore-described fail or do not take place at all, then the normal
procedure is as follows: After a thorough deliberation, the opinion of the resident
engineer is either accepted, modified or substantially altered depending on the
conclusions of the team at GHA. The engineer's determination is subsequently
prepared and this may indicate that the client is entitled to his claim, entitled to part of
it or is not entitled at all. There was an indication that the engineer's determination is
forwarded to the Client or Employer, the MRH, especially when it involves payment
of additional money. The MRH's comments are considered and the final position
agreed is communicated as the engineers' determination to the Contractor. If the
engineer's determination is accepted by the contractor, the claim is deemed settled. If
it is rejected or contested by the contractor, a dispute is deemed to have emerged
(CPR1, 4, 5 8&9).
358
Appendices
Appendix G - Line-by-line coding an impractical tedium for this work
10-Oct-12 12:33 PM
The initial data collection process was guided by the research objectives. These interviews
therefore produced a somewhat chunked information along the lines of the initial sensitizing
concepts which albeit flowed coherently as the story of the participants on their experiences
with dispute resolution. After initial data had been collected the immediate challenge was how
to get the analysis going. Turning to the literature on grounded theory, the overwhelming
suggestion was for the researcher to start with some initial analysis referred to as open coding
(Corbin & Strauss, 1990) or substantive coding (Glaser & Strauss, 1967; Glaser, 1978). Most
of the literature on the subject agrees on an initial coding process though there are
considerable differences in how this is to be done. Corbin and Strauss (2008) suggest line-byline initial coding. Charmaz (2006) expand the list to include word-by-word coding and
incident -by- incident coding. The choice of initial coding strategy is however left to the
researcher to make. Heath and Crowley (2004) like many other grounded theory researchers
faced with this challenge opted for neither line-by-line coding nor casual notes on data. The
former had the potential to produce what they referred to as "word overload" whilst the latter
was likely to be pedestrian and superficial. The issues was how detailed should the analysis be
at this stage? They chose an approach akin to paragraph -by- paragraph coding where one or
two key themes remain the focus.
The analysis in this study commenced with a line-by-line coding. Having used this strategy
for some time, some disadvantages have become obvious. Firstly, for time-bound projects,
this approach is impractical as it is time-consuming and confusing (see Allan, 2003).
Secondly, word overload led to the relevant issues being drowned in the researcher's
indulgence in the micro-analysis. Finally, some lines, standing alone, carried very little value
in terms of conceptual contribution to the work.
359
Appendices
A combination of paragraph -by- paragraph coding and incident -by incident coding have
been found to be more realistic and useful. Key ideas contained in such paragraphs are either
giving in vivo codes or generated codes. In some cases chunks of data dealing with a specific
incident is all together coded under a concept deducible from the narration of the incident.
360
Appendices
Appendix G 1- A Return to Line-by-line coding inevitable in certain circumstances
15-Oct-12 2:11 PM
After identifying a considerable number of codes from a number of interviews, axial
coding commenced coupled with memoing. The intention was to use the memoing process to
aid in the raising of axial codes or categories and identifying their sub-categories. This
process meant revisiting some of the earlier data chunks coded. As the process of reading over
previously coded data chunks progressed, the process of re-coding portions of these
previously chunked data became inevitable. Earlier chunks of data contained other rich
information previously not identified. These pieces of information contained additional
properties and dimensions of emerging categories obviously embedded in the data. Line-byline coding became inevitable as it has the potential to enrich the coding process. Its relevant
is most conspicuous as already coded data are re-read and analysed (Charmaz, 2006).
361
Appendices
Appendix H – Request for Feedback on Findings (Interviewees)
Dear Sir/ Madam,
Re:
Research on the Resolution of Construction Disputes arising from Major
Infrastructure Projects in Developing Countries – Request for Feedback on
Findings
I wish to express my appreciation to you once again for your participation in the data
collection process I embarked upon sometime between April and July, 2012 as part of my
PhD research on the above-mentioned subject. As you will recall, the aim of the research was
to critically examine the Ghanaian experience of resolution of construction disputes arising
from major infrastructure projects and thereby develop strategies for efficient and effective
resolution.
A number of findings have since been made on the basis of analysis of the data collected.
The findings identify the nature of the extant dispute resolution process, factors accounting
for it and strategies for reform (see attached Summary of Findings). It is expected that the
findings of the research will contribute to the on-going discourse on effective dispute
resolution and offer suggestions to improve the extant resolution process.
Consequently, I would be grateful if you could respond to the three questions at the end of
the attached Summary of Findings. Your response will help establish the trustworthiness of
the research outcome. Kindly send
your response to me by electronic mail
j.mante@wlv.ac.uk ormantecj@gmail.com ) or by post at the following address:
Joseph Mante
Room MI 228
School of Technology
University of Wolverhampton
WV1 1LY, United Kingdom
Mobile: +447551 908 364
362
Appendices
Alternatively, feedback by telephone or Skype will be appreciated. Please notify me by
email if this is your preferred option so arrangements can be made for such an interaction.
I will appreciate if your feedback can reach me by 7th February, 2014.
As was the case with the interviews, any feedback or comment provided shall remain
confidential.
I await your response. Thank you in advance.
Yours Faithfully,
Joseph Mante
363