list of drawings - Hindustan Petroleum Corporation Limited
list of drawings - Hindustan Petroleum Corporation Limited
list of drawings - Hindustan Petroleum Corporation Limited
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
HINDUSTAN PETROLEUM CORPORATION LIMITED<br />
VISAKH REFINERY<br />
VISAKHAPATNAM<br />
Tender document No.7000109-HD-46002/DBS<br />
TENDER DOCUMENT<br />
FOR<br />
REPLACEMENT OF CONVECTION SECTION AND STACK<br />
FOR<br />
HEATERS 11-F-01 AND 12-F-01<br />
PROJECT MANAGEMENT CONSULTANTS<br />
CEPS<br />
COSMOS ENGINEERING PROJECT SERVICES PRIVATE LTD.<br />
HIG – 22, SHEELANAGAR,<br />
VISAKHAPATNAM – 530 012.
PART - I<br />
UNPRICED BID
INDEX<br />
PART – I – UNPRICED - BID<br />
Sl.No. DESCRIPTION PAGE No.<br />
1. BIDDER PREQUALIFICATION CRITERIA I<br />
2. TENDER INVITATION LETTER 1 - 8<br />
3. INSTRUCTIONS TO TENDERERS 9 -13<br />
4. TERMS AND CONDITIONS OF CONTRACT 14 -28<br />
5. SPECIAL TECHNICAL CONDITIONS 29 -200<br />
6. GENERAL TERMS AND CONDITIONS OF 201-251<br />
WORKS CONTRACT.<br />
7. HPCL COMMERCIAL TERMS AND CONDITIONS 252-253<br />
ATTACHMENT<br />
8. LIST OF DRAAWINGS 254-258
I<br />
BIDDER PREQUALIFICATION CRITERIA<br />
1. The bidder shall be a manufacturer <strong>of</strong> Convection section and Stack <strong>of</strong> Furnaces.<br />
2. Bidder shall have engineered, manufactured, assembled, supplied, erected and<br />
tested at least one no. convection section and stack (both refractory lined) <strong>of</strong><br />
fired heater in a running refinery/ petrochemical complex, with a minimum single<br />
basic order value <strong>of</strong> not less than Rs. 960 Lakhs (Rupees Nine hundred and sixty<br />
lakhs only).<br />
OR<br />
Two similar completed works <strong>of</strong> not less than Rs.600 lakhs (Rupees Six hundred<br />
lakhs only) each.<br />
OR<br />
Three similar completed works <strong>of</strong> not less than Rs. 480 lakhs (Rupees four<br />
hundred and eighty lakhs only) each.<br />
3. The vendor shall have experience in all <strong>of</strong> the following :<br />
Material <strong>of</strong> construction <strong>of</strong> Convection section tubes (studded / plain) SA<br />
335 P5 or P9.<br />
Fabrication <strong>of</strong> Steam coils with SA 106 Gr. B with IBR Inspection and IBR<br />
approval.<br />
Convection section weighing minimum 80 MT in either one module or two<br />
modules put together.<br />
Pg. 1 <strong>of</strong> 5
4. Bidder shall have dismantled and erected convection section and stack (both<br />
refractory lined) at least one set done during shut down period in a running Refinery<br />
/ Petrochemical complex.<br />
Bidder shall have completed the above Sl.No. 1 to 4 during the last 7 years ending<br />
the last day <strong>of</strong> the month previous to this notification.<br />
5. Bidder shall have an annual turnover <strong>of</strong> not less than Rs.12 Crores (Rupees Twelve<br />
Crores only) in any one <strong>of</strong> the financial years ie. 2004-05, 2005-06 and 2006-07.<br />
The complete documentary evidence, duly attested by a notary <strong>of</strong> purchase order,<br />
completion certificates, TPIA certificate, As built <strong>drawings</strong> and balance sheets etc.,<br />
shall be provided along with the technocommercial bid in support <strong>of</strong> the bidder<br />
prequalification criteria as given above.<br />
6. Parties who are affiliates <strong>of</strong> one another can decide which Affiliate will make a bid.<br />
Only one affiliate may submit a bid. Two or more affiliates are not permitted to make<br />
separate bids directly or indirectly. If 2 or more affiliates submit a bid, then any one<br />
or all <strong>of</strong> them are liable for disqualification.<br />
However up to 3 affiliates may make a joint bid as a consortium shall apply to them.<br />
“Affiliate” <strong>of</strong> a part6y shall mean any company or legal entity which:<br />
(a) Controls either directly or indirectly a party, or<br />
(b) Which is controlled directly or indirectly by a party; or<br />
(c) Is directly controlled by a company, legal entity or partnership which directly<br />
or indirectly controls a party.<br />
“Control” means actual control or ownership <strong>of</strong> at least a 50% voting or other<br />
controlling interest that gives the power to direct, or cause the direction <strong>of</strong>, the<br />
management and material business decision <strong>of</strong> the controlled entity.<br />
Pg. 2 <strong>of</strong> 5
7. Bids may be submitted by:<br />
(a) a single person / entity (called sole bidder);<br />
(b) a newly formed incorporated joint venture (JV) which has not completed 3<br />
financial years from the date <strong>of</strong> commencement <strong>of</strong> business;<br />
(c) a consortium (including an unincorporated JV) hving a maximum <strong>of</strong> 3 (three)<br />
members;<br />
(d) an Indian arm <strong>of</strong> a foreign company.<br />
8. Fulfillment <strong>of</strong> eligibility criteria and certain additional conditions in respect <strong>of</strong> each <strong>of</strong><br />
the above 4 types <strong>of</strong> bidders is stated below, respectively:<br />
(a) The sole bidder (including an incorporated JV which has completed 3<br />
financial years after date <strong>of</strong> commencement <strong>of</strong> business) shall fulfill each<br />
eligibility criteria.<br />
(b) In case the bidder is a newly formed and incorporated joint venture and<br />
which has not completed three financial years from the date <strong>of</strong><br />
commencement <strong>of</strong> business, then either the said JV shall fulfil each eligibility<br />
criteria or any one constituent member / promoter <strong>of</strong> such a JV shall fulfil<br />
each eligibility criteria. If thye bid is received with the proposal that one<br />
constituent member / promoter fulfils each eligibility criteria, then this<br />
member / promoter shall be clearly identified and he/it shall assume all<br />
obligations under the contract and provide such comfort letter / guarantees<br />
as may be required by owner. The guarantees shall cover inter alia the<br />
commitment <strong>of</strong> the member / promoter to complete the entire work in all<br />
respects and in a timely fashion, being bound by all the obligations under the<br />
contract, an undertaking to provide all necessary technical and financial<br />
support to the JV to ensure completion <strong>of</strong> the contract when awarded, an<br />
undertaking not to withdraw from the JV till completion <strong>of</strong> the work, etc.<br />
(c) In case <strong>of</strong> bidder(s) is / are a consortium (including an unincorporated JV),<br />
then the following conditions shall apply:<br />
1) Each member in a consortium may only be a legal entity and not an<br />
individual person;<br />
Pg.3 <strong>of</strong> 5
2) The bidder shall specifically identify and describe each member <strong>of</strong><br />
the consortium;<br />
3) The consortium member descriptions shall indicate what type <strong>of</strong> legal<br />
entity the member is and its jurisdiction <strong>of</strong> incorporation (or <strong>of</strong><br />
establishment as a legal entity other than as a corporation) and<br />
provide evidence by a copy <strong>of</strong> the articles <strong>of</strong> incorporation (or<br />
equivalent documents);<br />
4) One participant member <strong>of</strong> the consortium shall be identified as the<br />
“Prime member” and contracting entity for the consortium;<br />
5) This prime member shall be solely responsible for all aspects <strong>of</strong> the<br />
Bid/Proposal including the execution <strong>of</strong> all tasks and performance <strong>of</strong><br />
all consortium obligations;<br />
6) The prime member shall fulfill each eligibility criteria;<br />
7) A consortium shall be given from each <strong>of</strong> the consortium member in<br />
the form <strong>of</strong> a letter signed by a duly authorized <strong>of</strong>ficer clearly<br />
identifying the role <strong>of</strong> the member in the Bid and the member’s<br />
commitment to perform all relevant tasks and obligations in support<br />
<strong>of</strong> the prime / lead member <strong>of</strong> the consortium and a commitment not<br />
to withdraw from the consortium;<br />
8) No change shall be permitted in the number, nature or share holding<br />
pattern <strong>of</strong> the Consortium members after pre-qualifications, without<br />
the prior written permission <strong>of</strong> the owner.<br />
9) No change in project plans, time tables or pricing will be permitted as<br />
a consequence <strong>of</strong> any withdrawal <strong>of</strong> failure to perform by a<br />
consortium member;<br />
10) No consortium member shall hold less than 25% stake in a<br />
consortium;<br />
11) Entities are affiliates <strong>of</strong> one another are allowed to bid either as a<br />
sole bidder or as a consortium only;<br />
Pg. 4 <strong>of</strong> 5
12) Any person or entity can bid either singly or as a member <strong>of</strong> only<br />
one consortium.<br />
(d) In case the bidder is an Indian arm (Subsidiary, authorized agent, branch<br />
<strong>of</strong>fice or affiliate) <strong>of</strong> a foreign bidder, then the foreign bidder shall have to<br />
fulfill each eligibility criteria. If such foreign company desires that the contract<br />
be entered in to with the Indian arm, then proper back to continuing (parent<br />
company) guarantee shall be provided by the foreign company clearly<br />
stating that in case <strong>of</strong> any failure <strong>of</strong> any supply or performance <strong>of</strong> the<br />
equipment, machinery, material or plant or completion <strong>of</strong> work in all respects<br />
and as per the warrantees / guarantees that may have been given, then the<br />
foreign company shall assume all obligations under the contract. Towards<br />
this purpose, it shall provide such comfort letter/ guarantees as may be<br />
required by Owner. The guarantees shall cover inter alia the commitment <strong>of</strong><br />
the foreign company to complete the entire work in all respects and in a<br />
timely fashion, being bound by all the obligations under the contract, an<br />
under taking to provide all necessary technical and financial support to the<br />
contract when awarded, an undertaking not to withdraw from the contract till<br />
completion <strong>of</strong> the work, etc.<br />
9. Bidder shall submit EMD for Rs. 20 Lakhs (Rupees Twenty Lakhs only) in the form<br />
<strong>of</strong> D.D payable to M/s HPCL, Visakhapatnam or irrevocable B.G for equivalent<br />
amount from a scheduled bank (other than cooperative bank) valid for 8 months,<br />
the format <strong>of</strong> which is provided in the tender document. Public sector enterprises<br />
and vendors registered with National Small Scale Industries <strong>Corporation</strong> (NSIC) are<br />
exempted from submitting EMD for this purpose, in the event <strong>of</strong> the tendering<br />
company being Public Sector Enterprise, a declaration to that effect and in the case<br />
<strong>of</strong> vendor registered with NSIC, a copy <strong>of</strong> the registration certificate should be<br />
submitted along with the unpriced bid.<br />
Bids without EMD <strong>of</strong> tenderers (other than those exempted as stated above) shall<br />
be summarily rejected.<br />
10. Note to tenderers: Offers <strong>of</strong> Bidders failing to submit the prescribed documents in<br />
support <strong>of</strong> the above prequalification criteria shall be rejected.<br />
Pg. 5 <strong>of</strong> 5
1<br />
TENDER INVITATION
Sealed tenders are invited from Indian Bidders for ”replacement <strong>of</strong> Convection Section<br />
and Stack for Heaters 11-F-01 and 12-F-01”, as per the enclosed tender documents in<br />
TWO BID SYSTEM. The details <strong>of</strong> the tender are as follows.<br />
1. Tender document number : 7000109-HD-46002/DBS<br />
2<br />
2. Description <strong>of</strong> the work : Residual Engineering, preparation <strong>of</strong><br />
fabrication <strong>drawings</strong>, procurement <strong>of</strong> materials,<br />
fabrication at shop / site and supply, dismantling <strong>of</strong><br />
existing Stack, convection Section and associated<br />
structurals etc, and erection <strong>of</strong> new Convection<br />
Section, new Stack, associated structurals etc. for<br />
the above two heaters as per the <strong>drawings</strong> and<br />
specifications enclosed.<br />
3. Completion Period :<br />
a) Fabrication and supply : 5 months from the date <strong>of</strong> Fax <strong>of</strong> Intent.<br />
b) Dismantling and erection : 20 days from the date <strong>of</strong> advice, which shall be<br />
intimated 25 days in advance. This activity is to be<br />
completed in shut down period.<br />
4. Site Visit :<br />
a) Agencies, on downloading the bid documents, shall<br />
study the same, understand the scope <strong>of</strong> work and<br />
make a site visit along with their technical<br />
representatives and obtain clarifications, if any, on<br />
the scope in its entirety. During the site visit the<br />
agency shall visit CDU-II unit to have a first hand<br />
understanding <strong>of</strong> site conditions and obtain<br />
clarifications, if any, regarding the scope <strong>of</strong> work &<br />
other terms and conditions <strong>of</strong> the bid. Tenderers<br />
shall contact HPCL and visit site with prior<br />
appointment. The bid submitted by the tenderers<br />
without visiting site will not be considered.(For more<br />
details please refer clause no.3 <strong>of</strong> “ Special<br />
Technical conditions” <strong>of</strong> the Tender document)<br />
b) Subsequent to the site visit and discussions,<br />
agencies shall collect a certification letter from<br />
Chief. Manager / Sr.Manager – Maintenance T& I ,<br />
stating that they have completed the site visit.<br />
c) Details <strong>of</strong> Contact Person :<br />
M.Soma Sunder, Chief Manager- Maintenance<br />
(T&I) Telifax : 0891-2762297, email<br />
:soma@hpcl.co.in<br />
Yogesh Dayal, Sr.Manager – Maintenance (T&I),<br />
Tel :0891-2894219, email :dayaly@hpcl.co.in
5.0 . TENDER FEES :<br />
6.0 SPECIAL NOTE :<br />
3<br />
Agency shall submit the Tender Fees <strong>of</strong> Rs.1,000/-<br />
(Rupees One Thousand only) in the form <strong>of</strong> a<br />
Demand Draft/Bankers cheque issued by a<br />
Scheduled Bank in favour <strong>of</strong> <strong>Hindustan</strong> <strong>Petroleum</strong><br />
<strong>Corporation</strong> <strong>Limited</strong>, payable at Visakhapatnam.<br />
In order to qualify for bidding, the interested agencies shall submit the above mentioned<br />
Tender Fees and Site Certification Letter issued by Chief /Sr. Manager - Maintenance<br />
(T&I) along with agency’s covering letter in a sealed envelope and the same shall be<br />
dropped in the tender box kept at the <strong>of</strong>fice <strong>of</strong> DGM-Materials (Refinery) on or before<br />
25-April-2008 at 11 a.m.<br />
The above envelope should be superscribed as follows :<br />
________<br />
“Public Tender for Replacement <strong>of</strong> Convection section and Stack for Heaters 11-F-01 &<br />
12-F-01” for HPCL, Visakh Refinery.<br />
Tender No. : 7000109-HD-46002/DBS<br />
LAST DATE FOR QUALIFYING FOR BIDDING : 25-April-2008 at 11 a.m.<br />
The complete mailing address is as given below :<br />
DGM – MATERIALS (REFINERY)<br />
New Administration Building, 1 st Floor<br />
HINDUSTAN PETROLEUM CORPORATION LIMITED<br />
Visakh Refinery<br />
Malkapuram<br />
Visakhapatnam – 530 011<br />
Andhra Pradesh<br />
INDIA.<br />
Tel. : +91-0891-2577759 /2577486(Direct)<br />
+91-0891-2894302/2894304<br />
Fax : +91-0891-2577139 (Direct)<br />
E-Mail : ramanan@hpcl.co.in<br />
E-Mail : (alternate) : kpiiype@hpcl.co.in / dbsekhar@hpcl.co.in<br />
Important Note :<br />
Agencies who have not submitted the above mentioned site visit certification<br />
along with the tender fees on or before 25-April-2008 at 11 a.m. shall not be<br />
permitted to participate in bidding process.
7.0. PROCEDURE TO BE FOLLOWED FOR SUBMISSION OF OFFER :<br />
4<br />
7.1. PRE-BID MEETING /PRESENTATION :<br />
The agencies who have responded and qualified for bidding shall make the<br />
presentation and attend for the Pre-bid meeting as per the dates indicated by HPCL.<br />
As a part <strong>of</strong> the above, the agency is required to give a presentation regarding the<br />
method <strong>of</strong> execution for completing all the jobs within time schedule. The meeting is to<br />
clarify the scope <strong>of</strong> job and enable clear the doubts, if any, by the agencies<br />
subsequent to the field visit and review <strong>of</strong> tender enquiry.<br />
The meeting shall be represented by a competent technical person to clarify and<br />
discuss the job scope in its entirety. All the discussion shall be minuted and reviewed.<br />
The above activity (Presentation/Meeting) has to be completed on or before<br />
28-April-2008 tentatively .<br />
7.2. CLARIFICATIONS :<br />
After site visit, presentation and meeting with the bidders, if any clarifications to be still<br />
addressed, the same will be informed to the agencies before 30-April-2008 to enable<br />
them to submit their <strong>of</strong>fer.<br />
7.3. SUBMISSION OF OFFER :<br />
After considering the clarifications provided by HPCL, if any, the agency shall submit their<br />
<strong>of</strong>fer on or before 09-May-2008 at 11 a.m. The <strong>of</strong>fer (unpriced bid) should also contain the<br />
record notes <strong>of</strong> the joint meeting.<br />
AGENCY SHALL SUBMIT THEIR OFFER IN TWO BID SYSTEM IN THREE PARTS<br />
CONTAINING THREE SEPARATE SEALED ENVELOPES AS FOLLOWS :<br />
7.3.1. ENVELOPE-I (EMD) :<br />
This Envelope-I should contain EMD (Earnest Money deposit) i.e. Rs.20,00,000/- (Rupees<br />
Twenty Lakhs only).<br />
Earnest money deposit <strong>of</strong> Rs. 20.0 lakhs in the form <strong>of</strong> a crossed DD or a non-revocable<br />
B.G in favour <strong>of</strong> HPCL from any scheduled bank (Other than cooperative bank) payable at<br />
Visakhapatnam in favour <strong>of</strong> HPCL Visakhapatnam in the Pr<strong>of</strong>orma enclosed. The B.G<br />
shall be valid for 8 (eight) months from the due date <strong>of</strong> submission <strong>of</strong> bid as per B.G<br />
Pr<strong>of</strong>orma. Public sector enterprises and Vendors registered with National Small Scale<br />
Industries <strong>Corporation</strong> (NSIC) are exempted from payment <strong>of</strong> EMD.<br />
The Envelope should be superscribed as follows :<br />
------------------------------------------------------------------------------------------------------------------------<br />
ENVELOPE-I (EMD)<br />
TENDER NO. : 7000109-HD-46002/DBS<br />
TENDER DUE DATE : 09-May-2008 at 11 a.m.
5<br />
“Public Tender for Replacement <strong>of</strong> Covection section and Stack for Heaters 11-F-01 & 12-<br />
F-01” for HPCL, Visakh Refinery ----------------------------------------------------------------------------<br />
--------------------------------<br />
7.3.2. ENVEOPE-II (Unpriced Bid) :<br />
Please ensure to furnish the following, in your un-priced bid:<br />
a) EMD<br />
b) Original tender Part-I & Part- II signed and stamped on all pages including<br />
<strong>drawings</strong> as a token <strong>of</strong> acceptance + 1 copy (Part-II with out prices)<br />
c) Price bid Part-II with the schedule <strong>of</strong> lumpsum price (Pr<strong>of</strong>orma V) and price<br />
break up schedule (Pr<strong>of</strong>orma VI) should be enclosed with the technical and<br />
un-priced commercial bid leaving the price column blank. No where the<br />
price should be indicated. Bids indicating prices in the Technical and unprice<br />
bid will be rejected<br />
d) Integrity Pact form (Annexure-16 & Annexure-17) duly signed along with<br />
unpriced bid.<br />
e) Power <strong>of</strong> Attorney as per Pr<strong>of</strong>orma – I enclosed.<br />
f) Submission <strong>of</strong> confirmations, documents, certificates etc., as per Tender<br />
documents.<br />
g) Conformity to Tender requirements Pr<strong>of</strong>orma - II enclosed,<br />
h) Detailed execution Methodology for residual Engineering, Preparation <strong>of</strong><br />
detailed fabrication <strong>drawings</strong>, procurement <strong>of</strong> materials, fabrication,<br />
transportation, dismantling, erection etc.<br />
i) Preliminary Transportation scheme for Convection Section.<br />
j) Preliminary Dismantling and erection scheme.<br />
k) Typical Quality assurance plan.<br />
l) Details <strong>of</strong> similar works executed as per Pr<strong>of</strong>orma- III and details <strong>of</strong> orders<br />
on hand and their present status as per Pr<strong>of</strong>orma -IV.<br />
m) List <strong>of</strong> tools and tackles proposed to be deployed to site for fabrication,<br />
dismantling and erection.<br />
n) Detailed Net work schedule in the form <strong>of</strong> a bar chart indicating various<br />
activities viz., residual engineering, preparation <strong>of</strong> fabrication drawing,<br />
procurement <strong>of</strong> materials, fabrication <strong>of</strong> Convection Section, Refractory<br />
lining, stacks, dismantling, erection etc.
6<br />
o) A <strong>list</strong> <strong>of</strong> key persons and supervisory personnel who will be deployed for this job indicating<br />
their experience in similar works.<br />
p) Duly filled in HPCL Terms & Conditions attachment to General Terms and Conditions <strong>of</strong><br />
Works Contract.<br />
q) Schedule <strong>of</strong> lumpsum price Pr<strong>of</strong>orma and breakup <strong>of</strong> lumpsum price Pr<strong>of</strong>orma without<br />
price.<br />
r) Any other documents as mentioned elsewhere in the Tender document.<br />
The envelope should be super scribed as follows :<br />
-----------------------------------------------------------------------------------------------------------------------------------<br />
ENVELOPE-II (Unpriced Bid)<br />
TENDER NO. : 7000109-HD-46002/DBS<br />
TENDER DUE DATE : 09-May -2008 at 11 a.m.<br />
“Public Tender for Replacement <strong>of</strong> Covection section and Stack for Heaters 11-F-01 & 12-F-01” for<br />
HPCL, Visakh Refinery.<br />
7.3.3. ENVELOPE-III (Priced Bid) :<br />
a) This should contain only Part-II containing schedule <strong>of</strong> lumpsum price (Pr<strong>of</strong>orma V) and<br />
price break up schedule (Pr<strong>of</strong>orma VI) duly filled the price along with only covering letter<br />
(Same covering letter as enclosed to technical and unpriced bid). No other conditions<br />
should be written in Part-II.<br />
b) The above quoted lumpsum price (Pr<strong>of</strong>orma V) shall be firm till completion <strong>of</strong> work and<br />
shall be inclusive <strong>of</strong> all taxes & duties (like Sales tax, non cenvatable Service Tax, WCT,<br />
Entry tax, non cenvatable Excise duty, non cenvatable CVD, Education Cess, Octroi and<br />
an other taxes, duties & levies) and excluding Cenvatable CVD, Cenvatable excise duty,<br />
Cenvatable service tax and input tax credit under AP VAT.<br />
c) The Tenderer should quote separately " Amount <strong>of</strong> Cenvatable service tax", “Cenvatable<br />
amount towards Excise duty/CVD" & " Amount for which Input tax credit shall be available<br />
to HPCL" as per the Pr<strong>of</strong>orma's V.a, V.b & V.c and the same shall be reimbursed to the<br />
contractor on production <strong>of</strong> all related documents.<br />
Please note that the Priced Bid should not contain any conditions or deviations failing<br />
which agency’s <strong>of</strong>fer shall be summarily rejected.<br />
The Envelope should be superscribed as follows :<br />
------------------------------------------------------------------------------------------------------------------------<br />
ENVELOPE-III (Priced Bid) :<br />
TENDER NO. : 7000109-HD-46002/DBS<br />
TENDER DUE DATE : 09-May -2008 at 11 a.m.<br />
“Public Tender for Replacement <strong>of</strong> Convection section and Stack for Heaters 11-F-01 & 12-F-01”<br />
for HPCL, Visakh Refinery.<br />
------------------------------------------------------------------------------------------------------------------------<br />
All the above three sealed envelopes together put in another big envelope (Main envelope)<br />
and this sealed main envelope shall be dropped in the tender box kept at the
7<br />
<strong>of</strong>fice <strong>of</strong> DGM-Materials (Refinery) on or before the tender due date 09-May-2008 at 11<br />
a.m.<br />
HPCL shall not be responsible for delay in receipt <strong>of</strong> the bids due to postal or any<br />
other reason whatsoever.<br />
Bids which are not received in two bid system and not received before the due date<br />
and time as mentioned above shall be liable for rejection.<br />
Bidders failure to return the Integrity pact (Annexure-16 & Annexure-17) along with<br />
the un-priced bid , duly signed, shall lead to outright rejection <strong>of</strong> such bid.<br />
The Main Envelope should be superscribed as follows :<br />
------------------------------------------------------------------------------------------------------------------------<br />
“Public Tender for Replacement <strong>of</strong> Covection section and Stack for Heaters 11-F-01 & 12-<br />
F-01” for HPCL, Visakh Refinery.<br />
Submitted in 3 parts i.e. Envelope-I (EMD), Envelope-II (Unpriced bid), Envelope-III<br />
(Priced Bid).<br />
TENDER NO. : 7000109-HD-46002/DBS<br />
TENDER DUE DATE : 09-May -2008 at 11 a.m.<br />
------------------------------------------------------------------------------------------------------------------------<br />
The <strong>of</strong>fer shall be submitted at the following address :<br />
DGM – MATERIALS (REFINERY)<br />
New Administration Building, 1 st Floor<br />
HINDUSTAN PETROLEUM CORPORATION LIMITED<br />
Visakh Refinery<br />
Malkapuram<br />
Visakhapatnam – 530 011<br />
Andhra Pradesh<br />
INDIA.<br />
Tel. : +91-0891-2577759 /2577486(Direct)<br />
+91-0891-2894302/2894304<br />
Fax : +91-0891-2577139 (Direct)<br />
E-Mail : ramanan@hpcl.co.in<br />
E-Mail : (alternate) : kpiiype@hpcl.co.in / dbsekhar@hpcl.co.in<br />
8.0. PROCEDURE OF OPENING OF OFFERS :<br />
8.1. The Envelope-I which contains EMD will be opened first, on the due date for<br />
submission <strong>of</strong> <strong>of</strong>fers, i.e. on 09-May-2008 at 11 a.m., in the presence <strong>of</strong> the<br />
participating bidders or their authorised representatives.<br />
8.2. After the EMD/exemption details are established and found to be adequate, the<br />
envelope-II (Unpriced bid) <strong>of</strong> the bidders will be opened, on the due date for
8<br />
submission <strong>of</strong> <strong>of</strong>fers, i.e. on 09-May-2008 at 11 a.m., in the presence <strong>of</strong> the<br />
participating bidders or their authorised representatives.<br />
8.3 The Priced bids <strong>of</strong> the technically & commercially acceptable bidders, will be opened<br />
subsequently, in the presence <strong>of</strong> qualified bidders or their authorised representatives.<br />
Priced Bids opening Date and time will be intimated to the technically &<br />
commercially acceptable bidders, subsequently.<br />
8.4. NOTES :<br />
8.4.1. HPCL reserves the right to reject any or all bids without assigning any reason,<br />
whatsoever there<strong>of</strong>.<br />
8.4.2. The prevailing Government <strong>of</strong> India guidelines for units registered under NSIC<br />
regarding exemption <strong>of</strong> Tender Fees, EMD & Security Deposit and Price<br />
Preference will be applicable. However relevant supporting documents to be<br />
furnished for claiming the same.<br />
8.4.3. The prevailing Government <strong>of</strong> India guidelines for Central Public Sector<br />
Undertakings regarding exemption <strong>of</strong> EMD & Purchase preferences shall be<br />
applicable.<br />
8.4.4. HPCL takes no responsibility for delay <strong>of</strong> non receipt <strong>of</strong> bids sent by post or by any<br />
other means. Offers received after the due date and time will be rejected. Telex /<br />
Fax / E-mail <strong>of</strong>fers are not acceptable.<br />
8.4.5. If the bidder is de<strong>list</strong>ed / holiday <strong>list</strong>ed as <strong>of</strong> the closing date <strong>of</strong> the tender (last date<br />
for submission <strong>of</strong> <strong>of</strong>fer), neither their bid nor their experience shall be considered<br />
for evaluation.<br />
8.4.6 Offers submitted without the EMD (Earnest Money Deposit) <strong>of</strong> Rs.20,00,000/-<br />
(Rupees Twenty Lakhs) , shall be rejected and the subject tenderer will not be<br />
allowed to witness the tender opening.<br />
8.4.7 The EMDs <strong>of</strong> the unsuccessful bidders would be released upon placement <strong>of</strong> the<br />
Purchase order on the successful bidder. The EMD <strong>of</strong> the successful bidder would<br />
be released on submission <strong>of</strong> Security Deposit.<br />
8.4.8 Offers <strong>of</strong> Bidders not meeting the delivery clause shall be rejected.<br />
8.4.9 Offers <strong>of</strong> bidders taking any deviation from tender conditions shall be liable for<br />
rejection.<br />
9. Offer Validity : Six months from the date <strong>of</strong> opening <strong>of</strong> the bid.<br />
10. Contract Validity : 24 months from the date <strong>of</strong> Fax <strong>of</strong> Intent.<br />
.
9<br />
INSTRUCTIONS TO TENDERERS
1. Introduction<br />
2. Location <strong>of</strong> site<br />
3. Tender documents<br />
4. Responsibility<br />
10<br />
CONTENTS<br />
5. Preparation <strong>of</strong> Tender<br />
6. Power <strong>of</strong> Attorney<br />
7. Conformity to Tender documents<br />
8. Documents required to be submitted indicating Tenderers<br />
experience.<br />
9. Amendments to tender documents<br />
10. Due date <strong>of</strong> submission <strong>of</strong> tender<br />
11. Signing <strong>of</strong> Tender<br />
12. Validity <strong>of</strong> Tender
1.0 INTRODUCTION:<br />
11<br />
1.1 <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> Ltd., (HPCL) propose to award contract for<br />
replacement <strong>of</strong> Convection Section and stack and other associated works for<br />
heater No.11-F-01 and 12-F-01 at it’s Visakh Refinery in kind on lumpsum turn<br />
key contract basis.<br />
1.2. HPCL have appointed M/s. COSMOS ENGINEERING PROJECT SERVICES<br />
PVT. LTD. (CEPS) VISAKHAPATANM as PROJECT MANAGEMENT<br />
CONSULTANTS for this job.<br />
1.3. The scope <strong>of</strong> the work to be executed for which bids are hereby invited is as per<br />
enclosed documents including <strong>drawings</strong>. The total / complete responsibility for<br />
the said scope <strong>of</strong> work rests with the Contractor.<br />
2.0 LOCATION OF SITE<br />
M/s. HINDUSTAN PETROLEUM CORPORATION LIMIED, VISAKH<br />
REFEINERY, is situated in Malkapuram area <strong>of</strong> Visakhapatnam city,<br />
Visakhapatnam Dist. (Andhra Pradesh). The Refinery is approximately 15 Kms<br />
from Visakhapatnam Railway Station and 14 Kms from Visakhapatnam airport.<br />
3.0 TENDER DOCUMENTS:<br />
3.1 Tender document:<br />
The Tenderer shall submit the tender documents along with the <strong>drawings</strong> with<br />
signature and stamped on each page and on all <strong>drawings</strong> in token <strong>of</strong> their<br />
acceptance. Transfer <strong>of</strong> tender documents issued to one intending Tenderer to<br />
another is not permitted<br />
4.0 RESPONSIBILITY:<br />
Although, all the necessary details have been covered and compiled in the<br />
tender documents, it is the responsibility <strong>of</strong> the tenderer to make sure that the<br />
information provided is adequate for tendering and also for further execution.<br />
Tenderer should note that no extension <strong>of</strong> due date will be granted on any<br />
reason what so ever.<br />
In case Tenderer needs any further information, Tenderer may seek clarification<br />
by sending fax message to<br />
Sri N. Ranga Raju<br />
Sr. Manager (Minor Projects)<br />
Fax No. 0891 – 2577535,<br />
Telephone No. 0891 – 2894874<br />
HPCL, Visakhapatnam.
5.0 PREPARATION OF TENDER:<br />
5.1 Cost <strong>of</strong> Tendering.<br />
12<br />
All costs / expenditure incurred in working on the tender preparation and<br />
submission etc., till the finalization <strong>of</strong> the contract is to tenderers account.<br />
5.2 Familiarisation <strong>of</strong> site:<br />
Tenderer shall fully get familiarized with the conditions at site by visiting the<br />
site. It is the Tenderers responsibility to study the site, equipment surroundings,<br />
approach roads etc and collect all the information required for tendering and<br />
execution. No claims will be entertained for ignorance <strong>of</strong> the conditions /<br />
information.<br />
6.0 POWER OF ATTORNEY:<br />
6.1 Tenderer shall submit power <strong>of</strong> attorney in favour <strong>of</strong> the<br />
person who signs the tender and subsequent submissions on behalf <strong>of</strong> the<br />
Tenderer as per Pr<strong>of</strong>orma -I. All the tender documents, including <strong>drawings</strong>,<br />
specifications and other details submitted by the Tenderer, shall be signed and<br />
stamped on each page.<br />
6.2 The cancellation <strong>of</strong> any such document viz., Power <strong>of</strong> Attorney, Partnership<br />
deed etc., should be informed in writing to HPCL well in time, failing which<br />
HPCL shall have no responsibility for any action taken by HPCL on the strength<br />
<strong>of</strong> the said documents.<br />
7.0 CONFORMITY TO TENDER DOCUMENTS.<br />
All the Tenderers are advised that while preparing their Tender and quoting<br />
their price, all the conditions both Technical and Commercial, the requirement<br />
<strong>of</strong> all the specifications/documents / <strong>drawings</strong> are to be taken into<br />
consideration. Tenderer shall furnish a confirmation letter as per Pr<strong>of</strong>orma II<br />
that their <strong>of</strong>fer is fully in conformity with the tender requirements.<br />
8.0 DOCUMENTS REQUIRED TO BE SUBMITTED ALONG WITH THE<br />
TENDER INDICATING TENDERERS EXPERIENCE:<br />
8.1 Details <strong>of</strong> similar works executed in the last seven years by the tenderer as per<br />
Pr<strong>of</strong>orma - III.<br />
8.2 Details <strong>of</strong> orders on hand and their present status as per Pr<strong>of</strong>orma - IV.<br />
9.0 AMENDMENTS TO TENDER DOCUMENTS:
13<br />
9.1 HPCL reserves the right to issue any amendments to the Tender<br />
documents. The Tenderers shall comply with the requirements <strong>of</strong><br />
amendments also while submitting the <strong>of</strong>fer. The tenderer shall sign and<br />
stamp on all pages and submit the same along with the Tender.<br />
9.2 All such amendments shall be mailed to the tenderers. HPCL shall bear no<br />
responsibility or liability arising out <strong>of</strong> non-receipt <strong>of</strong> the same in time or<br />
otherwise.<br />
10.0 DUE DATE OF SUBMISSION OF TENDER;<br />
10.1 All the Tenderers shall ensure that their tender is put into Tender Section in<br />
the <strong>of</strong>fice <strong>of</strong> Deputy General Manager (Materials) well before the time<br />
stipulated for the Tender submission date. Further, bids received after the<br />
due date and time are liable for rejection.<br />
11.0 SIGNING OF TENDER:<br />
11.1 Tender must be signed by a competent person authorized to sign the tender.<br />
The name <strong>of</strong> the person signing the tender shall be typed or stamped below<br />
the signature. Power <strong>of</strong> attorney authorizing the signatory shall be enclosed<br />
to the tender.<br />
12.0 Validity <strong>of</strong> tender.<br />
12.1 The Tenderer shall keep the validity <strong>of</strong> this <strong>of</strong>fer for six months from the date<br />
<strong>of</strong> opening <strong>of</strong> BID.<br />
*****************
14<br />
TERMS AND CONDITIONS<br />
OF CONTRACT
15<br />
CONTENTS<br />
1. Signing <strong>of</strong> contract.<br />
2. Correspondence procedure.<br />
3. Co-ordination with other agencies<br />
4. Tenderers responsibility <strong>of</strong> free issue materials<br />
issued by HPCL.<br />
5. Time schedule<br />
6. Payment terms.<br />
7. Schedule <strong>of</strong> Lumpsum price<br />
8. Liquidated damages<br />
9. Security deposit<br />
10. Retention money<br />
11. Taxes, duties and octroi<br />
12. Defect liability period<br />
13. General
1.0 SIGNING OF THE CONTRACT:<br />
16<br />
Upon receipt <strong>of</strong> the intimation from HPCL that the contract is ready for signing,<br />
the contractor has to visit HPCL and sign the contract.<br />
2.0 CORRESPONDENCE PROCEDURE<br />
2.1 Project Manger shall communicate with HPCL and with Cosmos Engineering<br />
Project Services Pvt. Ltd. (CEPS) through HPCL at the following address.<br />
HPCL : Sr. Manager (Minor projects)<br />
(Owner) Attn: Sri N. Ranga Raju<br />
<strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong><br />
Visakh Refinery<br />
P.O. Box No. : 15<br />
Visakhapatnam – 530 011<br />
Fax No. 0891 – 2577535<br />
Tel. No. 0891 – 2894874<br />
Email : rangarajun@hpcl.co.in<br />
CEPS : Cosmos Engineering Project Services Pvt. Ltd.<br />
(Consultant)<br />
2.2 Contractor shall indicate the <strong>of</strong>ficial address <strong>of</strong> the Project manager with<br />
telephone, fax numbers, E- mail address, his residential phone numbers etc.<br />
All communication shall be by Fax/E-mail/Courier. For speedy transmission <strong>of</strong><br />
documents, all documents shall be forwarded through a reputed courier<br />
service.<br />
2.3 At site contractor shall establish a fully equipped site <strong>of</strong>fice with Fax,<br />
telephone etc., Contractor also shall provide <strong>of</strong>fice accommodation for<br />
consultants engineers who shall be stationed at site for supervision and<br />
inspection.
17<br />
2.4 SUBMISSION OF DOCUMENTS<br />
Number <strong>of</strong> copies <strong>of</strong> correspondence and documentation shall be as follows:<br />
a. Correspondence 2 ( Original to HPCL and<br />
copy to CEPS)<br />
b. Drawings for approval 4 (to HPCL)<br />
c. Detailed project schedule 2 (Original to HPCL + copy<br />
to CEPS)<br />
d. Progress Reports 2 (Original to HPCL + copy<br />
Fortnightly to CEPS)<br />
e. Un priced purchase order <strong>of</strong> materials<br />
and bought out items 2 (1 to HPCL + 1 to<br />
CEPS)<br />
f. Final approved <strong>drawings</strong> 4 Copies <strong>of</strong> Blue prints to<br />
HPCL<br />
1 set <strong>of</strong> originals on tracing<br />
paper/ cloth<br />
2 sets <strong>of</strong> CDs to HPCL<br />
g. As built <strong>drawings</strong> 2 Copies <strong>of</strong> Blue prints<br />
To HPCL<br />
1 set <strong>of</strong> originals on tracing<br />
paper / cloth<br />
2 sets <strong>of</strong> CDs to HPCL<br />
h. Final Quality documents / T. C’s etc., 4 sets to HPCL<br />
3.0 CO -ORDINATION WITH OTHER AGENCIES:<br />
During the execution <strong>of</strong> the job at site, contractor shall co-ordinate with other<br />
agencies those are working in that area and carry out the work in such a manner<br />
as to complete the works without hampering other works <strong>of</strong> other agencies. In<br />
this regard, contractor shall strictly follow the instruction <strong>of</strong> the Engineer-incharge<br />
for proper co-ordination.<br />
4.0 TENDERER’S RESPONSIBILITY OF FREE ISSUE MATERIALS ISSUED BY HPCL<br />
4.1 The tenderer shall submit indemnity bond for the free issue materials as per<br />
the requirements <strong>of</strong> HPCL. Tenderer shall ensure safe custody <strong>of</strong> materials.<br />
4.2 All free issue materials shall be collected from HPCL Stores and transported<br />
to site fabrication yard.
18<br />
4.3 On completion <strong>of</strong> work, contractor shall submit material reconciliation<br />
statement for all free issue materials issued by HPCL in the prescribed format<br />
and shall be certified by ENGINEER-IN-CHARGE. Any surplus materials shall<br />
be returned back to HPCL stores. In case contractor uses excess materials for<br />
any reason than the required material and also if the contractor could not<br />
return the balance material as per the approved material reconciliation<br />
statement by the ENGINEER-IN-CHARGE, HPCL will recover the cost <strong>of</strong><br />
materials as per their standard practice.<br />
4.4 Free issue materials will be supplied by HPCL progressively.<br />
5.0 TIME SCHEDULE:<br />
5.1 Contractor should note that this is a fast track project and hence time is the<br />
essence for the contract. The completion period for the entire job in five<br />
months for supply at HPCL site and 20 days from the date <strong>of</strong> advice for<br />
dismantling and erection during shut own period.<br />
5.2 Residual engineering, detailed fabrication <strong>drawings</strong>, approval <strong>of</strong> <strong>drawings</strong> from<br />
IBR/CEPS/HPCL, procurement <strong>of</strong> all materials (except HPCL free issue<br />
material), fabrication (at shop and site) and supply including transportation to<br />
site within 5 months from the date <strong>of</strong> Fax <strong>of</strong> Intent.<br />
5.3 Execution <strong>of</strong> site work viz., dismantling <strong>of</strong> stacks, Convection sections etc., and<br />
erection <strong>of</strong> stacks convection section, soot blowers, erection <strong>of</strong> bracings,<br />
platforms, ladders, gratings etc. to be completed during the shut down period<br />
<strong>of</strong> 20 days. The contractor shall be intimated 25 days in advance for taking up<br />
<strong>of</strong> the above job.<br />
5.4 Till such time the erection activities are taken up, it is the responsibility <strong>of</strong> the<br />
contractor for the safe custody <strong>of</strong> the completed convection section and stacks,<br />
other fabricated structural item etc., at the fabrication yard. The necessary<br />
watch and ward arrangements etc., are to be provided by the contractor. The<br />
contractor is solely responsible for any loss, damage etc., for all these<br />
materials till they are erected and handed over.<br />
5.5 Contractor should confirm the above time schedule and submit a detailed<br />
schedule <strong>of</strong> various activities.<br />
6.0 PAYMENT TERMS:<br />
- 10% interest bearing advance after acceptance <strong>of</strong> LOI and on establishment <strong>of</strong> site<br />
<strong>of</strong>fice at the fabrication yard at HPCL premises against submission <strong>of</strong> B.G as per<br />
HPCL format for equivalent for amount from a scheduled Bank (Other than Cooperative<br />
Banks) valid for the contractor period plus 3 months claim period there<br />
after. This advance shall be recovered from the running bills on prorate basis.<br />
Interest shall be charge at SBI’s PLR rate + 0.5%.<br />
- 10% <strong>of</strong> against preliminary approval <strong>of</strong> the following <strong>drawings</strong> for both the Heaters<br />
against submission <strong>of</strong> B.G as per HPCL format for equivalent amount from a
19<br />
scheduled Bank ( Other than Co-operative Bank’s ) valid for the contractual period<br />
plus 3 months claim period there after .<br />
a) Combined G. A. <strong>drawings</strong> <strong>of</strong> convection section and stack.<br />
b) G. A. drawing <strong>of</strong> convection section.<br />
c) Detailed fabrication <strong>drawings</strong> for coil arrangement.<br />
d) Detailed fabrication <strong>drawings</strong> <strong>of</strong> Header boxes.<br />
e) Convection details <strong>of</strong> end tube sheets.<br />
f) Casing plate <strong>drawings</strong>.<br />
g) Refractory <strong>drawings</strong> including anchor details, sealing plate etc for convection<br />
section.<br />
h) Steel work for convection section and platform connected elevation.<br />
i) General arrangement drawing <strong>of</strong> stack indicating two despatchable units.<br />
j) Refractory <strong>drawings</strong> including anchor details for stack.<br />
k) Stack and duct connection details.<br />
l) Off take duct <strong>drawings</strong>.<br />
- 10% against receipt <strong>of</strong> shell plates for stacks, end tube sheets, casing plates,<br />
main columns, beams, electrodes for coil welding for convection section dully<br />
certified by HPCL/ Consultant nominated by HPCL at suppliers works / HPCL<br />
Fabrication yard against submission <strong>of</strong> B.G as per HPCL format for equivalent<br />
amount from a Scheduled Bank (Other than Co-operative Bank’s) valid for the<br />
balance contractual period plus 3 months claim period.<br />
- 15% against receipt <strong>of</strong> the stacks in two pieces each <strong>of</strong> 11-F-01 and 12-F-01 at<br />
HPCL site complete in all respects including welding <strong>of</strong> dampers and refractory<br />
applications and dryout and certified by HPCL/ consultant nominated by HPCL.<br />
- 30% against completion <strong>of</strong> convection sections in all respects including refractory<br />
applications and hydraulic testing at fabrication yard dully certified by HPCL/<br />
consultant nominated by HPCL.<br />
- 10% interest bearing mobilization advance for mobilizing their Demag 2000CC<br />
crane against submission <strong>of</strong> B.G as per HPCL format for equivalent amount from a<br />
scheduled Bank (Other than Co-operative Banks) valid for the balance contractual
20<br />
period plus 3 months claim period there after. This advance shall be recovered from<br />
the running bills on prorate basis. Interest shall be charged at SBI’s PLR rate<br />
+0.5%<br />
- 25% against mechanical completion <strong>of</strong> dismantling and erection activities <strong>of</strong> stack<br />
and convections sections including insitu joints cross over pipes welding and<br />
completion in all respects and on certification by HPCL/ consultant nominated by<br />
HPCL.<br />
- 10% against completion <strong>of</strong> balance works including complete documentation and<br />
on issue <strong>of</strong> completion certificate by HPCL/ consultant nominated by HPCL.<br />
- Transportation charges shall be paid after completion <strong>of</strong> all the transportation<br />
activities including dismantled items as specified in the tender documents.<br />
- Public sector enterprises and Central / State Govt. departments are exempted from<br />
furnishing B.G against advance payment.<br />
Payments shall be released with in 7 days from the date <strong>of</strong> invoice and certification<br />
<strong>of</strong> invoice by HPCL/ consultant nominated by HPCL.<br />
All payments will be made in "e-payment", Vendor to submit necessary e-payment<br />
mandate.<br />
7.0 SCHEDULE OF LUMPSUM PRICE.<br />
7.1 All prices shall be quoted in Indian Rupees only.<br />
7.2 The lump sum price quoted shall be for the complete scope <strong>of</strong> work.<br />
7.3 Prices shall be quoted strictly in accordance with the price schedule<br />
Pr<strong>of</strong>orma - V and VI<br />
7.4 Price break up quoted as per Pr<strong>of</strong>orma – VI.<br />
7.5 Prices shall be firm and fixed for the completion <strong>of</strong> the total scope <strong>of</strong> work<br />
as per the contract. No escalation is permitted on the quoted rates through<br />
out the completion period on account <strong>of</strong> any variation in the price <strong>of</strong> material,<br />
cost <strong>of</strong> labour or any other reason.<br />
7.6 Tenderer shall consider all the terms and conditions, technical commercial,<br />
scope <strong>of</strong> work, site conditions, time schedule for the entire scope <strong>of</strong> work<br />
and quote accordingly.<br />
7.7 The lump sum price quoted by the tenderer shall include any other item and<br />
any other work not specifically mentioned in the tender document but<br />
necessary for completion <strong>of</strong> the job No extra claims what so ever will be<br />
entertained.<br />
7.8 Prices shall be quoted both in figures and words.
21<br />
8.0 LIQUIDATED DAMAGES.<br />
i. In case <strong>of</strong> any delay in completion <strong>of</strong> fabrication and supply <strong>of</strong> convection sections,<br />
stack sections and other associated items beyond the contractual delivery <strong>of</strong> 5<br />
months, the owner shall be entitled to be paid liquidated damages by the<br />
contractor. The liquidated damages shall be initially at the rate <strong>of</strong> 1% (one percent)<br />
<strong>of</strong> the total supply value for every week <strong>of</strong> delay subject to a maximum <strong>of</strong> 5% <strong>of</strong> the<br />
total supply value. The liquidated damages shall be recovered by the owner out <strong>of</strong><br />
the amounts payable to the contractor or from any Bank Guarantees or deposits<br />
furnished by the contractor or the Retention money retained from the Bills <strong>of</strong> the<br />
contractor, either under this contract or any other contract.<br />
ii. In case <strong>of</strong> any delay in completion <strong>of</strong> erection <strong>of</strong> convection sections, stack sections<br />
and associated items during shut down period beyond the contractual delivery <strong>of</strong> 20<br />
days, the owner shall be entitled to be paid liquidated damages by the contractor.<br />
The liquidated damages shall be at the rate <strong>of</strong> 1% (one percent) <strong>of</strong> the total erection<br />
value for every day <strong>of</strong> the delay subject to a maximum <strong>of</strong> 5% <strong>of</strong> the total erection<br />
value. The liquidated damages shall be recovered by the owner out <strong>of</strong> the amounts<br />
payable to the contractor or from any Bank Guarantees or deposits furnished by the<br />
contractor or the Retention money retained from the Bills <strong>of</strong> the contractor, either<br />
under this contract or any other contract.<br />
iii. The contractor shall be entitled to give an acceptable unconditional Bank<br />
Guarantee in lieu <strong>of</strong> such a deduction if contractor desires any decision on a<br />
request for time extension.<br />
iv. This final calculation <strong>of</strong> LD shall be only on the value <strong>of</strong> the unexecuted portion /<br />
quantity <strong>of</strong> work as on the CDD.<br />
v. Contractor agrees with the owner, that the above represents a genuine preestimate<br />
<strong>of</strong> the damages, which the owner will suffer on account <strong>of</strong> delay in the<br />
performance <strong>of</strong> the work by Contractor. The contractor further agrees that the LD<br />
amount is over and above any right which owner has to risk purchase under clause<br />
12.4 <strong>of</strong> G.T.C enclosed and any right to get the defects in the work rectified at the<br />
cost <strong>of</strong> the contractor.<br />
The above clause is applicable instead <strong>of</strong> clause no: “10” <strong>of</strong> the G.T.C.<br />
9.0 SECURITY DEPOSIT<br />
The Tenderer with whom the contract is decided to be entered in to and intimation is so<br />
given will have to make a security deposit <strong>of</strong> one percent (1%) <strong>of</strong> the total contract<br />
value in the form <strong>of</strong> account payee crossed demand draft drawn in favour <strong>of</strong> HPCL<br />
payable at Visakhapatnam, with in 15 days from the date <strong>of</strong> intimation <strong>of</strong> acceptance <strong>of</strong><br />
the tender, failing which, HPCL reserves the right to cancel the contract and forfeit the<br />
EMD.<br />
1% <strong>of</strong> PO/contract value as security deposit will be acceptable in the form <strong>of</strong> Demand<br />
draft upto Rs.50,000/- and in the form <strong>of</strong> demand draft/ Bank guarantee beyond<br />
Rs.50,000/-<br />
Composite PBG for 10% <strong>of</strong> PO value towards security deposit and performance bank<br />
guarantee shall be accepted: which shall be valid upto a period <strong>of</strong> 3 months beyond the<br />
expiry <strong>of</strong> Defect liability period.<br />
Demand draft should be drawn on Scheduled Banks, other than Co-operative Banks.<br />
10.0 RETENTION MONEY<br />
10% <strong>of</strong> the total value <strong>of</strong> the running account and final bill will be deducted and retained<br />
by HPCL as retention money on account <strong>of</strong> any damage / defect liability
22<br />
that may arise for the period covered under the defect liability period clause <strong>of</strong> the<br />
contract free <strong>of</strong> interest. Any damage or defect that may arise or lie undiscovered<br />
at the time <strong>of</strong> issue <strong>of</strong> completion certificate connected in any way with the<br />
equipment or materials supplied by contractor or in workmanship shall be rectified<br />
or replaced by the contractor at his own expense failing which HPCL shall be<br />
entitled to rectify the said damage / defect from the retention money. Any excess <strong>of</strong><br />
expenditure incurred by HPCL on account <strong>of</strong> damage or defect shall be payable by<br />
the contractor. The decision <strong>of</strong> HPCL in this behalf shall not be liable to be<br />
questioned but shall be final and binding on the contractor.<br />
Thus, deduction towards retention money is applicable only in case <strong>of</strong> job/ works<br />
contracts (civil, mechanical, electrical, maintenance etc.) where any damage or<br />
defect may arise in future (ie. With in 12 months from the date <strong>of</strong> completion <strong>of</strong> job)<br />
or lie undiscovered at the time <strong>of</strong> issue <strong>of</strong> completion certificate.<br />
11.0 STATUTORY LEVIES<br />
11.1 The contractor accepts full and exclusive liability for the payment <strong>of</strong> any and all<br />
taxes, duties, octroi, rates, cess, levies and statutory payments payable under<br />
all or any <strong>of</strong> the statutes etc.<br />
Variations <strong>of</strong> taxes and duties arising out <strong>of</strong> the amendments to the Central /<br />
State enactments, in respect <strong>of</strong> sale <strong>of</strong> goods / Services covered under this bid<br />
shall be to HPCL’s account, so long as:<br />
. They relate to the period after the opening <strong>of</strong> the price bid, but before the<br />
contracted completion period (excluding permitted extensions due to delay<br />
on account <strong>of</strong> the contractors, if any) or the actual completion period,<br />
whichever is earlier. and:<br />
. The Vendor furnishes documentary evidence <strong>of</strong> incurrence <strong>of</strong> such variations,<br />
in addition to the invoices/ documents for claiming Cenvat / Input Tax credit,<br />
wherever applicable.<br />
All the contributions and taxes for unemployment compensation, insurance and<br />
old age pensions or annuities now or hereafter imposed by Central or State<br />
Governmental authorities which are imposed with respect to or covered by the<br />
wages, salaries or other compensations paid to the persons employed by the<br />
Contractor and the contractor shall be responsible for the compliance with all<br />
obligations and restrictions imposed by the Labour Law or any affecting<br />
employer employee relationship and the contractor further agrees to comply and<br />
to secure the compliance <strong>of</strong> all sub contractors with all applicable Central, State,<br />
Municipal and local laws, and regulations and requirement <strong>of</strong> the central/ state<br />
or Local Governmental agency or authority.<br />
Contractor further agrees to defend, indemnify and hold harmless from any<br />
liability or penalty which may be imposed by central, state or Local authorities<br />
by reason <strong>of</strong> any violence by contractor or sub contractor <strong>of</strong> such laws,<br />
regulations or requirements and also from all claims, suits or proceedings that<br />
may be brought against the owner arising under, growing out <strong>of</strong>, or by reasons<br />
<strong>of</strong> the work provided for by this contract by third parties, or by Central, state<br />
Government authority or any administrative sub-division there<strong>of</strong>. The contractor<br />
further agrees that in case any such demand is raised against the owner has no
23<br />
way but to pay and pays / makes payment <strong>of</strong> the same, the owner shall have<br />
the right to deduct the same from the amounts due and payable to the<br />
contractor. The Contractor shall not raise any demand or dispute in respect <strong>of</strong><br />
the same but have recourse to recover / receive from the concerned authorities<br />
on the basis <strong>of</strong> the Certificate <strong>of</strong> the owner issued in the behalf.<br />
11.2 The rates quoted should be inclusive <strong>of</strong> all rates, cess, taxes and sales tax on<br />
works contracts wherever applicable. However, wherever the sales tax on works<br />
contract is applicable and is to be deducted at source, the same will be<br />
deducted from the bills <strong>of</strong> the contractor and paid to the concerned authorities.<br />
The pro<strong>of</strong> <strong>of</strong> such payments <strong>of</strong> sales tax on works contract will be furnished to<br />
the contractor.<br />
11.3 Income tax will be deducted at source as per rules at prevailing rates, unless<br />
certificate, if any, for deduction at lesser rate or nil deduction is submitted by the<br />
contractor from appropriate authority.<br />
12.0 DEFECT LIABILITY PERIOD<br />
12.1 The contractor shall guarantee the work executed for a period <strong>of</strong> 12 months<br />
from the date <strong>of</strong> commissioning <strong>of</strong> the heaters or 18 months from the date <strong>of</strong><br />
supply whichever is earlier. Any damage or defect that may arise or lie<br />
undiscovered at the time <strong>of</strong> completion <strong>of</strong> the job shall be rectified or replaced<br />
by the contactor at his own cost. The decision <strong>of</strong> the Engineer –in-charge /<br />
site –in-charge/ HPCL shall be the final in deciding whether the defect has to<br />
be rectified or replaced.<br />
12.2 Equipment or spare parts replaced under warranty / guarantees shall have<br />
further warranty for a mutually agreed period from the date <strong>of</strong> acceptance.<br />
12.3 HPCL shall intimate the defects noticed in writing by a registered A.D. letter<br />
or otherwise and the contractor with in 15 days <strong>of</strong> receipt <strong>of</strong> the intimation<br />
shall start the rectification work and complete with in the time specified by the<br />
HPCL failing which the HPCL will get the defects rectified by themselves or by<br />
any other contractor and the expenses incurred in getting the same done shall<br />
be paid by the contractor under the provision <strong>of</strong> the contract.<br />
13.0 GENERAL<br />
Thus, Defect liability is applicable only in case <strong>of</strong> job/works contract (civil,<br />
mechanical, electrical, maintenance etc) Where any damage <strong>of</strong> defect may<br />
arise in future (ie. With in 12 months from the date <strong>of</strong> completion <strong>of</strong> job) or lie<br />
undiscovered at the time <strong>of</strong> completion <strong>of</strong> job.<br />
13.1 Terms and Conditions <strong>of</strong> Contract (TCC) shall be read in conjunction with the<br />
General Terms & Conditions <strong>of</strong> Works Contract (GCC), Schedule <strong>of</strong> Rates,<br />
Specifications <strong>drawings</strong> and any other document forming part <strong>of</strong> this Contract<br />
wherever the context so requires.
24<br />
13.2 Notwithstanding the sub-division <strong>of</strong> the document into separate sections /<br />
volumes every part <strong>of</strong> each shall be deemed to be supplementary <strong>of</strong> every<br />
other part and shall be read with and into the Contract so far as it may be<br />
practicable to do so.<br />
13.3 Where any portion <strong>of</strong> the GCC is repugnant to or at variance with any<br />
provisions <strong>of</strong> the TCC, then unless a different intention appears, the<br />
provisions(s) <strong>of</strong> the TCC shall be deemed to override the provision(s) <strong>of</strong> GCC<br />
only to the extent that such repugnancies or variations in the TCC are not<br />
possible <strong>of</strong> being reconciled with the provisions <strong>of</strong> GCC.<br />
13.4 Wherever it is stated in this Bidding Document that a supply is to be made or<br />
a work is to be carried out, it shall be understood that the same shall be<br />
made/ carried out by the CONTRACTOR at his own cost, unless a different<br />
intention is specifically and expressly stated herein or otherwise explicit from<br />
the context. Contract Price shall be deemed to have included such cost.<br />
13.5 The materials, design and workmanship shall satisfy the applicable relevant<br />
Indian Standards, the job specifications contained herein and codes referred.<br />
Where the job specifications stipulate requirements in addition to those<br />
contained in the standard codes and specifications, these additional<br />
requirements shall also be satisfied. In the absence <strong>of</strong> any Standard/<br />
Specifications/ Codes <strong>of</strong> practice for detailed specifications covering any part<br />
<strong>of</strong> the work covered in this bidding document, the instructions/directions <strong>of</strong><br />
HPCL / CEPS will be binding upon the CONTRACTOR.<br />
13.6 In case <strong>of</strong> contradiction between relevant Indian standards, GCC, TCC,<br />
Specifications, Drawings and Schedule <strong>of</strong> Rates, the following shall prevail in<br />
order <strong>of</strong> precedence:<br />
i. Detailed Letter <strong>of</strong> Acceptance along with Statement <strong>of</strong> Agreed Variations,<br />
if any, and its enclosures such as Schedule <strong>of</strong> Rates, Labour Rates, etc.<br />
ii. Telex <strong>of</strong> Intent (TOI)/ Fax <strong>of</strong> Intent (FOI) Letter <strong>of</strong> Intent<br />
iii. Terms and Conditions <strong>of</strong> Contract<br />
iv. General Terms and Conditions <strong>of</strong> Works Contract<br />
v. Job Specifications<br />
vi. Drawings<br />
vii. Standard Specifications<br />
viii. Indian Standards
25<br />
POWER OF ATTORNEY<br />
To<br />
D.G.M (Materials)<br />
M/s <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> Ltd.,<br />
Visakh Refinery<br />
Post Box No. 15<br />
Visakhapatnam - 530 011.<br />
Andhra Pradesh.<br />
Dear Sir,<br />
Sub: HPCL Tender no.<br />
Pr<strong>of</strong>orma - 1<br />
We ………………………………………………………………………….…do hereby<br />
confirm that Mr.………………………………………………(Name/names, position held)<br />
is/are authorized to represent our Company to tender, negotiate and sign the agreement<br />
with your Company for the above works.<br />
Yours sincerely,<br />
Name & Designation<br />
with Company seal:<br />
Note : The above letter should be submitted on a printed letter head <strong>of</strong> the Company.<br />
The above letter should be signed by a competent person having the powers to<br />
issue this Power <strong>of</strong> Attorney
26<br />
CONFORMITY TO TENDER REQUIREMENTS<br />
Pr<strong>of</strong>orma – II<br />
We here by confirm that our tender fully conforms to the<br />
complete technical and commercial requirements <strong>of</strong> the document<br />
without any deviation.<br />
Signature <strong>of</strong> the Tenderer<br />
Note:<br />
The above letter should be submitted on a printed letterhead <strong>of</strong> the company.
SI.<br />
No<br />
Name <strong>of</strong> the<br />
Customer and<br />
Address<br />
Scope <strong>of</strong><br />
work with<br />
brief<br />
description<br />
27<br />
Work experience<br />
Value <strong>of</strong><br />
contract<br />
(Rs. In<br />
lakhs)<br />
Time<br />
schedule as<br />
per contract<br />
and zero date<br />
Pr<strong>of</strong>orma – III<br />
Signature <strong>of</strong> the Tenderer<br />
Actual date <strong>of</strong><br />
completion
SI.<br />
No.<br />
Name <strong>of</strong> the<br />
Customer<br />
and address<br />
28<br />
DETAILS OF ORDERS ON HAND AND PRESENT STATUS<br />
Scope <strong>of</strong> work with<br />
brief description<br />
Value <strong>of</strong><br />
contract<br />
(Rs. In<br />
lakhs)<br />
Time<br />
schedule<br />
as per<br />
contract<br />
and zero<br />
date<br />
Signature <strong>of</strong> the Tenderer<br />
Pr<strong>of</strong>orma – IV<br />
Brief status
29<br />
SPECIAL TECHNICAL CONDITIONS
1 INTRODUCTION<br />
30<br />
CONTENTS<br />
2 DETAILS OF CONVECTION SECTIONS AND STACKS<br />
3 SITE VISIT<br />
4 SCOPE OF WORK<br />
5 HEAVY LIFTS ERECTION<br />
6 CRANE REQUIREMENTS<br />
7 CONSTRUCTION MACHINERY<br />
8 SHUT DOWN JOB PLANNING<br />
9 RESPONSIBILITIES OF CONTRACTOR<br />
10 FINAL TESTING<br />
11 PAINTING<br />
12 COMMISIONING ASSISTANCE<br />
13 TEMPORARY WORKS<br />
14 PROTECTION OF EXISTING FACILITIES<br />
15 SITE MOBILIZATION<br />
16 SITE FACILITIES<br />
17 SITE ORGANISATION
31<br />
18 QUALITY ASSURANCE SYSTEM<br />
19 INSPECTION AND TESTS<br />
20 FINAL INSPECTION<br />
21 APPROVAL OF SUB VENDORS<br />
22 PROJECT MANAGEMENT & PROJECT EXECUTION<br />
23 DRAWINGS & DOCUMENTS<br />
24 AS BUILT DRAWINGS<br />
25 FINAL DOCUMENTS<br />
26 STATUTORY APPROVALS<br />
27 STATUTORY RULES AND REGULATION<br />
28 SITE CLEANING<br />
29 SECURITY<br />
30 SAFTEY<br />
31 LIST OF DRAWINGS<br />
32 LIST OF FREE ISSUE MATERIALS ISSUED BY HPCL<br />
33 LIST OF TECHNICAL SPECIFICATION<br />
34 EXCLUSIONS
1.0 INTRODUCTION:<br />
32<br />
Crude heater (11-F-01) and vacuum heater (12-F-01) are presently in operation in<br />
Crude Distillation Unit - II. These heaters mainly consist <strong>of</strong> Radiant Section,<br />
Convection section, Steel stack and other associated structurals as shown in the<br />
<strong>drawings</strong> enclosed.<br />
These heaters are originally designed by M/s. EIL for VREP-II project.<br />
HPCL now proposes as per this Tender to replace the existing convection section<br />
and stack, complete in all respects with associated ducting, structural items for both<br />
the Heaters.<br />
2.0 DETAILS OF CONVECTION SECTIONS / STACKS:<br />
2.1 The Convection sections comprise <strong>of</strong><br />
• Supporting steel work<br />
• Casing plates<br />
• End tube sheets<br />
• Intermediate cast steel tube sheets with support brackets<br />
• Header boxes<br />
• Coil work along with all fittings, flanges etc.(Pressure parts)<br />
• Refractory work.<br />
• All auxiliary connections Associated items connected with Convection<br />
Sections and stacks<br />
• All instrument connections<br />
• Bracings.<br />
• Platform with hand railing at different elevations.<br />
• Access ladders/Stairs<br />
• G. I. Gratings<br />
2.2 Refractory lined Stacks along with associated platforms and damper along with<br />
associated instruments, linkages etc. For vacuum heater 12-F-01 <strong>of</strong>f take ducts<br />
connecting to convection section and stack. Connecting duct pieces from stack<br />
for connecting to existing cold flue gas duct and hot flue gas duct including bolts,<br />
nuts and gaskets. For 11-F-01, connecting duct pieces from stack for connecting<br />
to existing cold flue gas duct and hot flue gas duct including bolts, nuts and<br />
gaskets.<br />
2.3 Any other items not <strong>list</strong>ed above but required for completion <strong>of</strong> job as per <strong>drawings</strong><br />
/ specifications / good engineering practices.
2.4 CONVECTION SECTIONS:<br />
33<br />
The New Convection Sections shall be fabricated and supplied in single module<br />
duly hydro tested and refractory lined. The contractor has to fabricate the<br />
convection sections in HPCL premises. The Convection Sections shall be safely<br />
transported by suitable Trailers from the Site Fabrication yard to Heater Erection<br />
Site for further erection activities. Special care shall be taken to prevent damage<br />
<strong>of</strong> refractory, coil shifting etc., during transportation/ handling and erection.<br />
2.5 STACKS:<br />
New stacks shall be fabricated with complete refractory lining including heat dry<br />
out in two transportable pieces at contractor’s workshop including assembly and<br />
welding <strong>of</strong> damper assembly ( FIM by HPCL). This being a fast track project,<br />
Stack is to be fabricated in any fabrication shops at Visakhapatnam. The<br />
fabrication shop is to be approved by HPCL / CEPS. These pieces are to be<br />
carefully transported to HPCL and erect the same in single / two pieces and<br />
complete the balance work insitu. Special care shall be taken to prevent damage<br />
<strong>of</strong> refractory during transportation / handling and erection. After the erection <strong>of</strong> the<br />
stacks, the ducts are to be connected, balance damper work is to be carried out<br />
and all the necessary instruments and mechanical linkages, instruments supplied<br />
with the dampers are to be installed and ensure the satisfactory functioning <strong>of</strong><br />
dampers.<br />
3.0 SITE VISIT:<br />
It is mandatory for all the prospective tenderers to make a visit to the Site to<br />
familiarize themselves with the following before submitting the tender and also for<br />
smooth execution<br />
a. Site facilities.<br />
b. Approach roads/routes.<br />
c. Space for site work<br />
d. Location <strong>of</strong> the heaters and its surrounding equipment / structures<br />
e. Cranes, Movement constraints / restrictions.<br />
f. To assess and understand the quantum <strong>of</strong> work and find out any missing<br />
details<br />
g. To assess the handling and transportation facilities required within the plant<br />
for movement <strong>of</strong> Convection Sections and Stack etc.<br />
h. To understand and identify precisely the extent <strong>of</strong> cutting and dismantling<br />
etc., <strong>of</strong> the associated items <strong>of</strong> work viz., bracings, platforms, supports<br />
piping connections at different elevations, cross over joints, connecting<br />
ducts etc., for freeing the existing Convection Sections and stacks<br />
i. To understand and plan the various activities and its sequences with backed<br />
up resources to meet the site works and time schedule.
34<br />
j. To decide the philosophy and methodology <strong>of</strong> Heavy lifts viz., Convection<br />
Sections and Stacks with use <strong>of</strong> Demag CC 2000 Crane and prepare<br />
preliminary erection scheme.<br />
k. The requirements <strong>of</strong> barricading etc., during dismantling and erection work.<br />
l. To understand all other related activities that are essential for the total site<br />
work completion during shut down<br />
4.0 SCOPE OF WORK;<br />
The Contractor shall have overall responsibility for execution <strong>of</strong> the job <strong>of</strong><br />
Replacement <strong>of</strong> Convection Sections along with Stacks with all the associated<br />
jobs, as per <strong>drawings</strong>, specifications, codes and as per site requirements. The<br />
Contractor’s scope <strong>of</strong> work shall include but not limited to the following. Any work<br />
not specifically mentioned but otherwise necessary to meet the site requirements<br />
and statutory requirements and also for satisfactory job completion in all respects<br />
shall be carried out by the contractor within his quoted price. The job is to be<br />
executed on single point responsibility basis as a lumpsum turnkey contract as per<br />
tender requirements.<br />
4.1 Procurement and supply <strong>of</strong> materials in contractor’s scope:<br />
Procurement <strong>of</strong> all materials (except HPCL free issue material) and consumables<br />
required for the completion <strong>of</strong> work in all respects shall be entirely the<br />
responsibility <strong>of</strong> the contractor and the quoted price shall include for all such<br />
materials etc. The BOM indicated in the drawing is only indicative. Contractor has<br />
to work out actual requirement and procure the same.<br />
4.1.1. Steel Work (Non-pressure parts)<br />
a) Steel plates and structural materials (IS2062) for Stack, ducts, Convection<br />
Sections support structures, casing plates, header boxes etc.,<br />
b) Convection Section End tube sheets (SA515/516 Gr.70)<br />
c) Structural steel materials (IS 2062) for bracings, platforms, hand railing,<br />
stairs / ladders etc.<br />
d) Hot dip galvanized gratings along with G.I support clamps<br />
e) All bolts and nuts, washers, gaskets etc including stack fixing bolts nuts etc<br />
as required.<br />
f) Auxiliary Connections attached to Convection Section steel work viz.,<br />
sleeves, vents, drains etc.<br />
g) Auxiliary connection for Instruments, piping, fitting, flanges, bolts, nuts,<br />
snuffing steam etc.<br />
h) Observation doors/ Inspection doors<br />
i) Intermediate tube sheet guide angles and connected bolts,nuts, washers etc<br />
j) Stainless steel materials:
35<br />
• SS sleeves (SS TP 316L) in End Tube Sheets.<br />
• SS Sleeves (SSTP 316L) for various sleeves, Shelf plates, Shield plates,<br />
retainer plates, and such items attached to Heater steel work etc.<br />
• SS Anchors Lugs (SSTP316 L) <strong>of</strong> different shapes for refractory application<br />
• Gaskets to SS spiral wound with CS centering ring with 200% spares<br />
• Studs / Bolts / Nuts Etc SA 193 Gr B7 / SA 194 Gr 2H with 10% spares<br />
• All other auxiliary connections Viz Vents, Drains, instrumentation<br />
connections etc as per drawing.<br />
• The necessary lifting frames / beams, trunions etc are to be designed for<br />
safe lifting and erection <strong>of</strong> convection sections and stacks and the design<br />
calculations are to be submitted for CEPS/HPCL approval. It is the<br />
responsibility <strong>of</strong> the tenderer to arrange all these items.<br />
• All balance materials those are required for completion <strong>of</strong> the job are in the<br />
contractor’s scope <strong>of</strong> supply.<br />
4.1.1.1 Bridge pieces to spec A387 Gr.9 required for the center joints <strong>of</strong> coil tubes <strong>of</strong><br />
12-F-01 are in contractor’s scope <strong>of</strong> supply.<br />
4.1.2 REFRACTORY / INSULATING MATERIALS<br />
a. All refractory materials viz., Insulation castable, Potassium silicate mortar,<br />
packing materials i.e., ceramic fibre blankets, Ceramic fibre paper, Asbestos<br />
rope, Bituminous paint etc as per Drawings /Specifications. For details <strong>of</strong><br />
Refractory work refer drawing no 11-06-43-F-102, 103, 104 & 12-06-43-F-<br />
102, 103, 104 enclosed.<br />
b. All S.S. materials (SA 240 TP 316L), retainer plate. Shelf plates, support<br />
plates. SS Anchors, V-Lug, chain links etc.<br />
4.1.3 MISC. ITEMS:<br />
a. Primer, intermediate and finish paints for structurals and Heater Convection<br />
Sections, Stacks etc. as per <strong>drawings</strong> and painting specifications.<br />
b. Sealing cloth for opening around tube sleeves suitable for high temperature<br />
application, Asbestos tape gaskets for doors<br />
c. Ceramic Fibre for packing in openings.<br />
d. Insulation wool materials where required
36<br />
e. Any other item not specifically <strong>list</strong>ed, but are required to complete the job<br />
shall also be supplied by the Contractor within their quoted price<br />
4.1.4 INSPECTION OF MATERIALS<br />
All Indigenous / Imported materials shall be inspected by Third party<br />
Inspection Agency i.e., M/s Lloyds./BVIS / CEIL/ IBR. IBR items shall be got<br />
duly inspected by IBR authorities. For items under IBR which are imported,<br />
where the above IIIrd party inspection is not available; any other competent<br />
inspection agency as approved by IBR shall be employed.<br />
Contractor shall include IIIrd party Inspection charges in the quoted price.<br />
All inspection and tests shall be made as required by the <strong>drawings</strong>/<br />
specifications. All costs towards testing shall be within the quoted rates.<br />
4.1.5 CHANGE OF MATERIALS:<br />
Contractor shall note that wherever the material specification given in the<br />
<strong>drawings</strong> for some items is in variance with materials specification <strong>list</strong>ed<br />
above, to the extent specifications as given above will be followed.<br />
However, contractor shall obtain written clarification from HPCL / CEPS<br />
before proceeding further.<br />
4.1.6 COIL WORK FOR PRESSURE PARTS<br />
4.1.6.1 The convection section coil for 11-F-01 consists <strong>of</strong> the following main<br />
materials<br />
a. Studded tube to SA 335P5/SA106 Gr B<br />
b. Plain tubes to SA 335 P5 /SA106 Gr B<br />
c. Pipe fittings to SA 234WP5 / A234WPB/A 182F5<br />
d. Forged flanges to SA 182F5/A105<br />
4.1.6.2 The convection section coil for 12-F-01 consists <strong>of</strong> the following main<br />
material:<br />
a. Studded tube to SA 335P9<br />
b. Plain tubes to SA 335 P9<br />
c. Pipe fittings to SA 234WP9 and SA 182F9<br />
d. Forged flanges to SA 182F9<br />
4.1.7 HPCL will supply the following material only as free issue materials<br />
Plain tubes to SA 335P5 and SA 335P9 / A106 Gr B<br />
Studded tubes to SA 335P5, A 335P9 AND A106 Gr B
37<br />
180 0 SR bends, 90 0 Elbows to SA 234WP5, SA 234WP9 and<br />
SA234WPB<br />
Reduced weldolets and reduced elbowlets to SA128 F5 and SA182 F9<br />
Forged Flanges to SA182 F5 and SA 182F9<br />
Intermediate cast tube sheets (Cast steel 50Cr50Ni to A-560)<br />
Supporting brackets with bolts & nuts<br />
Stack dampers for 11-F-01 and 12-F-01<br />
4.1.8 For 12-F-01 Convection coil studded tubes and plain tubes to Spec<br />
SA335P9 will be supplied in two pieces. The Tenderer has to include the<br />
welding <strong>of</strong> center joint fully conforming to the requirements in his scope.<br />
Material for the bridge pieces to spec SA387 Gr 9 is in his scope<br />
4.1.9. The <strong>list</strong> <strong>of</strong> free issue materials supplied by HPCL is attached to this special<br />
technical conditions and these are to be collected from HPCL stores. All the<br />
rest <strong>of</strong> the materials that are required for completion <strong>of</strong> total scope <strong>of</strong> work is<br />
in tenderers scope.<br />
4.2 RESIDUAL ENGINEERING / PREPARATION OF FABRICATION<br />
DRAWINGS:<br />
4.2.1 Residual Engineering:<br />
Based on the refractory details provided in the <strong>drawings</strong>, the Contractor<br />
shall design / develop the detailed <strong>drawings</strong> for the Refractory lining work<br />
including Anchors /Shelf plates / Retainer plates etc., for the refractory<br />
application work.<br />
4.2.2 HPCL will issue the old Convection Section and stack <strong>drawings</strong> to the extent<br />
available with them and these are enclosed to the Tender. Purpose <strong>of</strong> these<br />
<strong>drawings</strong> is to enable the contractor to understand scope and extent <strong>of</strong><br />
work and make <strong>of</strong>fer in line with the requirements <strong>of</strong> HPCL and execution <strong>of</strong><br />
Job further. Based on HPCL <strong>drawings</strong> contractor has to prepare the<br />
fabrication <strong>drawings</strong>. If any details / <strong>drawings</strong> are not available, contractor<br />
has to visit site and collect the details and develop the <strong>drawings</strong>.<br />
4.2.3 Preparation <strong>of</strong> <strong>drawings</strong><br />
Contractor shall prepare detailed fabrication <strong>drawings</strong> <strong>of</strong> convection<br />
sections, Stacks and associated structures heater wise and submit the<br />
<strong>drawings</strong> for the approval <strong>of</strong> HPCL / CEPS. In addition to the above, super<br />
heated steam coil drawing <strong>of</strong> 11-F-01 is to be submitted to IBR and obtain<br />
their approval. Brief scope <strong>of</strong> <strong>drawings</strong> to be prepared by the tenderer are<br />
indicated below. However, any additional drawing needed during contract<br />
stage are to be prepared as necessary.
38<br />
4.2.3.1 Detailed fabrication <strong>drawings</strong> <strong>of</strong> Convection coils for hydrocarbon and<br />
super heated steam with details <strong>of</strong> all the fittings and auxiliary connections<br />
etc (Coil work pressure parts).<br />
1. Combined General assembly drawing <strong>of</strong> convection section and stack<br />
indicating Elevation, plan, end view etc for individual heaters<br />
2. General arrangement <strong>of</strong> convection section indicating elevation, plan and<br />
end view etc.<br />
3. General arrangement drawing <strong>of</strong> stack<br />
4. Detailed fabrication <strong>drawings</strong> for Hydrocarbon and Super heated steam<br />
coil work as necessary.<br />
5. Detailed fabrication <strong>drawings</strong> for Convection Section steel work<br />
6. Detailed fabrication <strong>drawings</strong> for casing plates<br />
7. Detailed fabrication <strong>drawings</strong> for End Tube Sheets.<br />
8. Detailed fabrication <strong>drawings</strong> for Header boxes.<br />
9. Detailed fabrication <strong>drawings</strong> for bracings.<br />
10. Detailed fabrication <strong>drawings</strong> <strong>of</strong> stack and associated structurals<br />
11. Detailed fabrication <strong>drawings</strong> for ducts<br />
12. Detailed fabrication <strong>drawings</strong> for platforms with hand railing at different<br />
elevations.<br />
13. Detailed fabrication <strong>drawings</strong> for access ladders / stairs<br />
14. Detailed fabrication <strong>drawings</strong> <strong>of</strong> G.I. Gratings with supporting clamps.<br />
15. Any other <strong>drawings</strong> as necessary to meet the tender requirements<br />
4.2.3.2 Detailed <strong>drawings</strong> for Refractory work including fixing details <strong>of</strong> Anchors,<br />
Refractory supporting system etc.<br />
4.2.3.3 Any other <strong>drawings</strong> required for job completion as directed by Engineerin-Charge<br />
4.3 FABRICATION:<br />
4.3.1 Fabrication <strong>of</strong> convection sections and stacks:<br />
a. Fabrication <strong>of</strong> Convection Section Steel frame structures, built up<br />
sections, casing plates, End Tube sheets, header boxes<br />
b. Fabrication and welding <strong>of</strong> SS sleeves in End tube sheets.
39<br />
c. Fabrication <strong>of</strong> all Auxiliary connection attached to Convection Section Steel<br />
work viz., different sleeves, vent, drain, flanges etc.<br />
d. Fabrication <strong>of</strong> auxiliary connection for instruments, snuffing steam etc.,<br />
attached to casing.<br />
e. Fabrication <strong>of</strong> observation Doors/Inspection Doors.<br />
f. Fabrication, Assembly, welding and testing <strong>of</strong> Coil work (Pressure parts)<br />
Cast intermediate tube sheets, support brackets are to be assembled, aligned,<br />
and bolted in the convection section. The coils shall be pre-fabricated in<br />
hockey sticks and to be erected in the convection section tube sheets. Fit up,<br />
alignment and welding <strong>of</strong> in situ welds shall be completed. The methodology <strong>of</strong><br />
erection and alignment <strong>of</strong> coils shall be got vetted by the contractor from CEPS<br />
/ HPCL prior to start <strong>of</strong> work. The coils shall be fabricated with the pipes (plain<br />
and studded pipes) S.R. Bends, Elbows, and other fittings viz., weldolets,<br />
sockets, couplings, flanges, plugs, instrument connection etc. Where special<br />
bends are required coil pipe to be suitably bent as per approved procedure.<br />
PWHT and NDT shall be carried out as per <strong>drawings</strong> / specifications<br />
g. Cross over coil pipes for connecting to Radiant section shall be provided extra<br />
length for field fit up<br />
h. Fixing, welding <strong>of</strong> SS anchor and other tie back materials Viz. Retainer plates,<br />
shield plates etc.<br />
i. Application <strong>of</strong> refractory work<br />
4.3.2 The Convection Coils shall be hydraulically tested at the site / fabrication yard.<br />
Contractor shall provide blind flanges, fasteners, gaskets etc. for testing.<br />
4.3.3 Stacks shall be fabricated in two pieces at contractor’s workshop duly refractory<br />
lined including heat dry out and completed in all respects. The site welding and<br />
refractory work is to be carried out insitu after erection.<br />
4.3.3.1 The stack dampers shall be delivered as FIM at HPCL stores as assembled unit.<br />
The stack dampers shall be supplied with suitable bevelled ends to carry out full<br />
strength butt weld in horizontal position. 100 mm on each side <strong>of</strong> the damper<br />
with out refractory lining (but with anchors welded) shall be refractory line after<br />
welding to the stack. The tenderer shall complete the job as per the instructions<br />
<strong>of</strong> Engineer –In- Charge.<br />
4.3.4 TRANSPORTATION:<br />
The Convection Sections shall be transported in suitable trailers from the<br />
fabrication yard to Heater erection site. Stacks shall be transported from<br />
contractor workshop to erection site in suitable trailers. Contractor shall arrange<br />
necessary trailers, Cranes, and handling equipments etc., for loading, unloading<br />
the Convection Sections and stacks. Every care shall be taken to ensure that<br />
refractory lining is not damaged nor coils shifting takes place during the<br />
transportation. If any temporary measurement required for shifting to be carried<br />
out by Vendor after prior approval <strong>of</strong> scheme and the temporary arrangement to<br />
be removed and made as original after the job completion. All the balance<br />
structural items etc., are also to be transported to the site.<br />
4.3.4.1 Transportation route to be identified and finalized in coordination with HPCL.<br />
4.3.4.2 Transit insurance, storage cum erection insurance is also in the scope <strong>of</strong> tenderer.
40<br />
4.3.5 FABRICATION OF PLATFORMS / BRACINGS/ G.I.GRATINGS:<br />
4.3.5.1 Fabrication <strong>of</strong> bracings, built up sections, platforms, handrails, stairways and<br />
ladders from rolled steel section, plates, flats, pipes etc, as per <strong>drawings</strong> and<br />
specifications. The fabricated structures shall be given primer, intermediate<br />
and finish paints including surface preparation as per painting specifications.<br />
4.3.5.2 The Contractor shall make a detailed study at site the extent <strong>of</strong> Bracings,<br />
platforms at different elevations (connected with Convection Section, Stack),<br />
and are required to be cut out / dismantle to free the Convection Section /<br />
stack dismantling. The contractor shall newly fabricate these Plat forms,<br />
hand railings and Bracings etc.<br />
4.3.5.3 The connected Ladders/Stairs at different elevations shall be fabricated. All<br />
the platforms shall be fabricated to the maximum size modules with hand<br />
railings etc. and transported to site, keeping in view the constraints at site for<br />
erection.<br />
4.3.5.4 GRATINGS<br />
Procurement, fabrication and erection <strong>of</strong> hot dip galvanized gratings along<br />
with GI support clamps as per EIL standards no:7-68-0581 Rev.2 (Type II)<br />
4.4 DISMANTLING AND ERECTION:<br />
4.4.1 Dismantling works:<br />
4.4.1.1. Dismantling <strong>of</strong> existing stacks in single / two pieces. The existing stack<br />
shall be dismantled and placed on the ground. If required the same is to be<br />
cut in to 3 or 4 pieces and the same are to be transported to HPCL storage<br />
area and un-loaded as directed by HPCL engineer-in-charge. In the event<br />
<strong>of</strong> delay <strong>of</strong> new stack dampers, the clause on 4.3.3.1 to be followed.<br />
4.4.1.2 Dismantling <strong>of</strong> the existing Convection Section .The existing Convection<br />
Section shall be dismantled and placed on ground. If required the same is<br />
to be cut in to 3 or 4 pieces as directed by the Engineer-in-charge. The<br />
Existing Convection Section shall be transported to HPCL storage area and<br />
unloaded as directed by Engineer-in-charge. Chipping <strong>of</strong> refractories inside<br />
heaters to expose the metal for facilitating the cutting operation to be<br />
carried out. Good engineering practices to be followed for scaffolding,<br />
welding, dismantling and lowering <strong>of</strong> equipments / piping / stacks.<br />
4.4.1.3 Dismantling <strong>of</strong> Associated Platforms / Bracings / Piping work / ducting:<br />
Dismantling <strong>of</strong> structural platforms, staircase and ladders etc. connected to<br />
equipments is a part <strong>of</strong> scope and to be segregated items wise as per the<br />
directions <strong>of</strong> the job engineer.<br />
4.4.1.4 Dismantling includes cutting <strong>of</strong> the steel work/ removal <strong>of</strong> bolts/ nuts/cut out<br />
<strong>of</strong> welds, cut out <strong>of</strong> portion <strong>of</strong> refractory at joints, as may be necessary.<br />
Every care shall be taken to limit the dismantling up to the exact point and<br />
/or lines as directed by the Engineer-in- charge and any damage caused to
41<br />
the existing structure shall be rectified and restored to the original position<br />
at the contractor’s costs.<br />
4.4.1.5 Dismantling <strong>of</strong> equipments and other Misc. items:<br />
a. The soot blowers along with control panels shall be disconnected<br />
properly and removed and stored carefully for re-use.<br />
b. The damper assembly and painter trolley and control panels shall be<br />
disconnected and removed,<br />
c. Cutting and removal <strong>of</strong> gratings in plat form.<br />
d. Cut out coil weld joints between radiant and convection section cross<br />
over / jump over connection. All care shall b taken to mark and cut<br />
accurately these joints, since these joints are to be re-welded after<br />
erection <strong>of</strong> new Convection Section.<br />
e. Removal <strong>of</strong> insulation on pipes as required including cladding to<br />
necessitate dismantling<br />
f. Dismantling the flanged pipe joints / auxiliary connections etc.<br />
g. The contractor shall provide suitable temporary supports for connected<br />
piping, ducting, platforms etc and in the vicinity as directed by the<br />
Engineer-in-charge.<br />
h. Any other items /structures/equipments/piping which are obstructing the<br />
dismantling <strong>of</strong> convection section/ stack shall also be dismantled.<br />
i. After dismantling, parts to be cut in pieces <strong>of</strong> length less than 6 mtrs and<br />
height less than 2 mtrs, so that the same can be shifted in trailers to<br />
scrap yard locations. Transportation and stacking neatly in scrap yard is<br />
also included.<br />
4.4.1.6 The contractor shall prepare and submit dismantling and erection scheme,<br />
detail schedules / plan / bar chart for the job to be submitted immediately<br />
after P.O placement for CEPS / HPCL approval. This approval shall not<br />
absolve the responsibility <strong>of</strong> contractor. Dismantling <strong>of</strong> all items should be<br />
item wise as per the directions <strong>of</strong> Engineer – In – charge.<br />
4.4.1.7 Dismantling <strong>of</strong> Electrical connections:<br />
The electrical connections shall be removed by contractor. Contracror<br />
shall identify the electrical connections required to be removed in<br />
coordination with HPCL / CEPS. Contractor shall take all care not to<br />
damage these electrical items during dismantling works and also suitable<br />
protection as directed by Engineer in charge as they are to be re used.<br />
4.4.1.8 HPCL will arrange to dismantle control instruments or their components<br />
that interfere with the work <strong>of</strong> agency and reinstall on completion <strong>of</strong> work.<br />
Agency shall inform HPCL about any such item interfering with their work.<br />
In case <strong>of</strong> any damage to any equipment in the vicinity is caused by the
42<br />
agency, the cost <strong>of</strong> repairs / replacement <strong>of</strong> the same will be to agency’s<br />
account. In this regard, HPCL’s decision shall be final.<br />
4.4.1.9 All the serviceable materials shall be sorted out and handed over to<br />
HPCL Store as directed by Engineer-in-Charge. Scrap and other<br />
unutilized materials shall be handed over to HPCL stores/ scrap yard as<br />
directed by Engineer-In-charge.<br />
4.4.1.10 Items to be segregated separately ie. Metallic and non-metallic. The<br />
following metallic items to be segregated separated like in the separate<br />
heads:<br />
a. Mec. Valves (except small bore Valve) & control valves.<br />
b. Pipe and pipe fittings (CS, AS in group and SS and other in different)<br />
c. Structurals<br />
d. Electrical items<br />
e. Instrumentation items<br />
(Copper tubes to be separated and weighed and stores separately in<br />
warehouse)<br />
f. Cables- all electrical / instrumentation etc.<br />
g. Sheets Al cladded<br />
4.4.1.11 Transportation to be arranged for weighing the scrap with HPCL weighing<br />
machine and shifting <strong>of</strong> scrap material to scrap area for scrap,<br />
equipments, piping, structurals, cables etc. and to other designated<br />
location for debris, wastes, concrete, refractory, insulation, coke, earth,<br />
non scrap things as per the directions <strong>of</strong> the job engineer.<br />
4.5 ERECTION WORKS:<br />
The contractor shall be responsible for the dismantling and erection <strong>of</strong> the<br />
equipments in proper sequence. After placing the equipments on the structures,<br />
the equipments shall be leveled, aligned and bolted/welded. The equipment shall<br />
be set to level and square so that pipe connection can be made without strain.<br />
a. Erection <strong>of</strong> newly fabricated Convection Section over the top <strong>of</strong> Radiant Ro<strong>of</strong><br />
Section, alignment, bolting/welding.<br />
b. Erection <strong>of</strong> stack in single piece / two pieces at the top <strong>of</strong> Convection section,<br />
alignment, bolting / welding, Refractory lining etc.<br />
c. Erection <strong>of</strong> bracings, plat forms at different elevations with hand railings,<br />
stairways, ladders etc., alignment, bolting/welding.<br />
d. Erection <strong>of</strong> G.I Gratings on the platform including fixing G.I support clamps as<br />
per <strong>drawings</strong>
43<br />
e. Erection and functional testing <strong>of</strong> soot blowers & control panels (disconnected<br />
old soot blowers and control panels) as per specifications / requirements<br />
f. For new Damper assembly (FIM by HPCL) the vendor shall install winch<br />
pulleys, pneumatic pipes, position indicators etc, and other associated<br />
Electrical and Instrumentation work and its functional testing as per the<br />
requirements for completing the total damper system as per the instructions <strong>of</strong><br />
Engineer-in-charge.<br />
g. Incase new stack dampers are not installed the tenderer has to install old<br />
dampers by cutting the same from the old stacks, completing the refractory<br />
work and installing the same by welding and completing the balance work as<br />
per the instructions <strong>of</strong> Engineer-in-charge.<br />
h. Erection <strong>of</strong> Painter Trolley with rails, winch etc., and functional testing.<br />
i. Erection and welding <strong>of</strong> skin point thermo couples on the tube surface<br />
including heat treatment as necessary<br />
j. After erection <strong>of</strong> the Convection Sections and stacks the refractory lining<br />
dismantled if any at the connecting areas shall be made good by re-refractory<br />
lining as per specifications<br />
k. Application <strong>of</strong> insulation on pipe sections with cladding (which are removed)<br />
as per specifications<br />
l. Cutting extra lengths, edge preparation and assembly <strong>of</strong> cross over coil joints,<br />
between Radiant and Convection section including welding, NDT and PWHT<br />
as per specifications<br />
m. Assembly <strong>of</strong> all piping / nozzle connections upto Convection Section, battery<br />
limits, fixing gaskets and bolting, including internal and out let pipe joints <strong>of</strong><br />
Convection Section.<br />
n. Seal welds between stacks, Convection/radiant section shall be carried out<br />
and ensure air tightness <strong>of</strong> heater<br />
o. Erection <strong>of</strong> other items dismantled and are to be reused are to be re-erected.<br />
p. Fabrication and Erection <strong>of</strong> any other items not <strong>list</strong>ed above but required to<br />
successfully complete the job and make the Convection Sections and stacks<br />
to it’s original requirement is Contractor’s responsibility.<br />
q. Vendor to co-ordinate for all the mechanical errection jobs with Chief Manager<br />
/ Senior Manager T&I Maintenance.<br />
5.0 HEAVY LIFTS ERECTION<br />
5.1 The two stacks and two Convection Section modules are the Heavy lifts<br />
envisaged. The contractor shall study the actual site layout <strong>of</strong> the Heater<br />
surrounding equipments and structures, overhead lines, existing pipe lines,<br />
drains, approach roads restrictions, the availability space. Based on these details<br />
contractor shall prepare and submit the Erection scheme.
44<br />
5.2 The Contractor shall submit a detailed write up <strong>of</strong> the proposed Dismantling and<br />
Erection scheme.<br />
Approach to the Heater area.<br />
Arrangement showing placement <strong>of</strong> Demag Crane, positioning <strong>of</strong> the<br />
Convection Section/ stack on ground etc.<br />
Cranage requirements for Main crane and trailing crane and their<br />
positioning etc.<br />
Erection methodology and sequence <strong>of</strong> erection.<br />
5.3 For the Demag CC2000 Cranes and other cranes the following shall also be in<br />
the contractor’s scope<br />
a. Complete requirements for crane approach and movement viz. providing<br />
25mm sand layer on floor, sleepers matting etc., for 300t cranes, 75t crane<br />
etc., for movement <strong>of</strong> the crane in erection area/crane movement<br />
areas/assembly areas.<br />
b. For movement <strong>of</strong> crane inside the CDU-II Unit from the approach road the<br />
drains etc., shall be suitably filled up with gunny bags and sleepers to protect<br />
the drains from damages.<br />
c. Preparing approaches and working area .for the movement and operation <strong>of</strong><br />
the cranes, leveling the areas for assembly and erection shall be<br />
Contractor’s responsibility.<br />
d. Any damage to the Drains/Flooring in the Plant on account <strong>of</strong> Crane<br />
movement etc., shall be rectified and restored to its original position as<br />
directed by the Engineer-in-charge.<br />
e. In case approach road is to be temporarily blocked during heavy lifts<br />
erection, the same shall be done with approval <strong>of</strong> engineering charge.<br />
f. Debooming and Extension <strong>of</strong> booms if required shall be arranged by the<br />
Contractor.<br />
5.4 The lifting frame / beams, trunions etc are to be properly designed and<br />
necessary design calculation are to be submitted for approval <strong>of</strong> HPCL /<br />
CEPS. It is the responsibility <strong>of</strong> tenderer to arrange all these items for safe<br />
lifting and erection.<br />
6.0 CRANE REQUIREMENTS:<br />
6.1 HPCL will provide 1 No. 2000CC Demag Crane for heavy lifts. Contractor<br />
shall include one more 2000CC Demag crane in their scope and deploy to<br />
the site to work simultaneously for 11-F-01 & 12-F-01 and to complete job in<br />
schedule time <strong>of</strong> 20 days. This additional crane should be made available at<br />
HPCL site seven days in advance before the date <strong>of</strong> shut down. Contractor<br />
shall arrange suitable cranes for unloading, loading, assembly and<br />
dismantling and handling their 2000CC Demag crane.<br />
6.2 HPCL shall hand over one Demag 2000CC crane at one point. It is the<br />
responsibility <strong>of</strong> the contractor to dismantle the crane, transport and<br />
reassemble at the required erection site. After completion <strong>of</strong> the erection<br />
work contractor has to dismantle, transport and assemble the crane as per
45<br />
the instructions <strong>of</strong> Engineer-in-charge. The necessary cranes for dismantling,<br />
loading on trailor, unloading, reassemble etc., shall be included in contractors<br />
scope. The necessary trailors also are included in the contractors scope.<br />
6.3 Demag Crane requirement to be planned and advance notice to be given to<br />
HPCL for Demag crane as many other jobs <strong>of</strong> projects (FCCU 2) and<br />
Maintenance <strong>of</strong> other units CDU 1, PRU, MEROX, DHDS etc will be carried<br />
out during that period simultaneously.<br />
6.4 Contractor shall ensure deployment <strong>of</strong> suitable trailing cranes for the erection<br />
<strong>of</strong> these heavy lifts simultaneously for 11-F-01 and 12-F-01.<br />
6.5 Contractor shall deploy 2nos. 75Tonnes cranes (or above capacity) suitable<br />
for handling, loading and unloading <strong>of</strong> the convection sections and stacks.<br />
6.6 Contractor shall also provide all other cranes required for handling,<br />
fabrication, dismantling and erection <strong>of</strong> all other jobs.<br />
6.7 All cranes shall be tyre mounted except Demag 2000cc crane.<br />
6.8 The contractors scope shall include the necessary operators, supporting<br />
technicians, tools and tackles, accessories including diesel etc complete for<br />
all the cranes in their scope.<br />
7.0 CONSTRUCTION MACHINERY:<br />
7.1 The Contractor shall without prejudice to his overall responsibility to execute<br />
and complete the jobs as per specification and time schedule, progressively<br />
deploy adequate equipments and tools and tackles and augment the same<br />
as decided by the Engineer-in- charge depending on the exigencies <strong>of</strong> the<br />
work so as to suit the time schedule. The contractor shall submit <strong>list</strong> <strong>of</strong><br />
construction equipments, tools and tackles they propose to deploy for the<br />
subject works along with deployment schedule.<br />
7.2 All lifting tools and tackles, slings, crane, hydra, trailors etc., shall have load<br />
carrying certificates and the same shall be submitted. Certificates should be<br />
currently live and copies to be submitted to HPCL.<br />
7.3 All the erection machinery and lifting tackles used by the Contractor at site<br />
shall be duly tested and have valid certificates by a Govt. approved Agency<br />
and they should be in sound condition for safe usage on the job. Copies <strong>of</strong><br />
the same shall be submitted to HPCL<br />
7.4 Lifting lugs: Suitable lifting lugs/other details shall be suitably designed and<br />
provided by the Contractor for handling and erection <strong>of</strong> the heavy lifts.<br />
7.5 Spreader Beams/Lifting beams as necessary shall be suitably designed /<br />
provided by the Contractor for safe lifting <strong>of</strong> the Convection Sections and<br />
Stacks.<br />
7.6 Adequate strengthening <strong>of</strong> Convection Sections and stacks with temporary<br />
bracings etc., to prevent damage during transportation/handling/erection<br />
shall be taken care by the Contractor.<br />
7.7 The erection methods adopted shall ensure no damage to the Convection<br />
Sections /stacks during handling/erection.<br />
7.8 Load testing <strong>of</strong> heavy lift cranes i.e. both Demag cranes and trailing cranes<br />
shall be suitably load tested by the Contractor including arrangements <strong>of</strong><br />
required loads. The load testing scheme to be got approved by CEPS /<br />
HPCL. However, this will not absolve the responsibility <strong>of</strong> contractor.
46<br />
7.9 Agency should arrange grinding, Gas cutting sets, welding, concrete<br />
cutter, manual tools, generators and compressors along with skilled<br />
manpower required for the job.<br />
8.0 SHUT DOWN JOB PLANNING:<br />
The site erection works (dismantling and Erection) are to be carried out during<br />
the Refinery Plant Shut down. During the shut down Contractor shall engage<br />
his work force on round the clock basis as needed to complete all the jobs<br />
strictly within shut down period. The Contractor shall make detailed planning <strong>of</strong><br />
each and every activity and prepare Bar chart clearly showing the activities and<br />
time required for the same and ensuring completion as per shut down time<br />
period. For this purpose contractor shall also identify and mobilize the total<br />
resources required viz., Cranes, Equipments, Machinery, tools and tackles as<br />
well total number <strong>of</strong> manpower to be deployed at site during execution. The<br />
contractor shall also deploy required Quality Control Engineers and<br />
Supervisory staff in each shift basis.<br />
Contractor shall have full-fledged planning and Monitoring group, which shall<br />
plan and monitor the jobs. The job status will be reviewed every day and<br />
contractor shall take proper remedial actions as directed by the Engineer-in-<br />
Charge.<br />
9.0 RESPONSIBILITIES OF CONTRACTOR:<br />
9.1 The procurement and supply in sequence at the appropriate time <strong>of</strong> all materials<br />
and consumable shall be entirely the contractor’s responsibility.<br />
9.2 Contractor shall provide all Machinery tools and tackles etc., and keep them in<br />
good working condition throughout the job progress.<br />
9.3 All the required manpower, Engineers, supervisors, engineering safety<br />
supervisors shall be deployed by the contractor including qualified workers viz.<br />
welders, fitters, riggers etc.<br />
9.4 All consumables viz., gases, welding electrodes, tig wires, grinding sheets, DP<br />
materials, paints, safety gadgets, NDT etc. shall be arranged by the Contractor.<br />
9.5 Resources mobilization chart <strong>of</strong> the Contractor for the machinery, tools and<br />
tackles as well as Manpower shall be submitted along with their <strong>of</strong>fer.<br />
9.6 Required scaffoldings and MS gratings at all heights to be done for all areas,<br />
wherever cutting / welding / inspection etc is required as per standard safety<br />
procedures. This is in addition to the unit barricade. Agency shall provide<br />
scaffolding wherever it is required. Scaffolding to be erected with 1 ½ “ steel<br />
tubular pipe with suitable and safe clamping arrangement only to be used.<br />
Distance between adjacent vertical members shall not be more than six feet<br />
and distance between adjacent horizontal members shall not be more than<br />
three feet. Proper MS gratings to be laid on horizontal pipe and the gratings<br />
must be tied to the horizontal members by GI wire <strong>of</strong> minimum 10 gauge. The<br />
scope <strong>of</strong> job includes supply <strong>of</strong> scaffolding / staging pipes in standard sizes,<br />
clamps, planks / gratings etc. erection / staging as required including the supply<br />
<strong>of</strong> personnel protective items and removal after completion.
47<br />
9.7 Barricading: Contractor shall arrange barricading with steel tubes and G.I.<br />
sheets at heater erection area at different levels where required to get hot work<br />
permit for site welding works. The extent <strong>of</strong> barricading will be as decided by<br />
the Engineer-in-charge<br />
9.8 All welders employed shall be duly qualified, tested and approved by the CEPS<br />
/ HPCL / IBR and only qualified welders shall be engaged in the welding jobs.<br />
Contractor shall procure required material for the welding procedure<br />
qualification and welder’s qualification at his cost.<br />
9.9 The agency shall arrange for sufficient lighting at work spots (24 volts) on their<br />
own, Only at one electrical point will be given by HPCL.<br />
9.10 All jigs and fixtures and temporary supporting during fabrication, handling and<br />
erection shall be done by the contractor<br />
9.11 Contractor shall provide the required temporary plat forms, ladders, lighting,<br />
labour etc., for inspection and other testing by CEPS/HPCL.<br />
9.12 It shall be entirely the Contractor’s responsibility to provide , operate and<br />
maintain all necessary construction equipment, steel scaffolding and safety<br />
gadget, cranes and other lifting tackles, tools and appliances to perform the<br />
work in a work like and efficient manner and complete all the jobs as per time<br />
schedule.<br />
9.13 Preparing approaches and working area for the movement and operation <strong>of</strong> the<br />
Cranes, levelling the areas for assembly and erection works shall be<br />
Contractor’s responsibility<br />
9.14 It shall be the responsibility <strong>of</strong> the Contractor to obtain the approval for any<br />
revision and / or modifications proposed by the Contractor from CEPS/HPCL<br />
before implementation. All such revision/modifications, if approved shall be<br />
carried out without any extra cost.<br />
9.15 All expenses towards mobilization at site and demobilization including bringing<br />
the equipment, work-force, materials, dismantling the equipment, cleaning the<br />
site etc. shall be deemed to be included in the price and no separate payment<br />
will be entertained at any cost.<br />
9.16 Weather protection: Contractor shall make necessary arrangements for weather<br />
protection such as G.I. sheets/ Asbestos cloth etc, during fabrication and<br />
erection activities for protection from Rain etc.,<br />
9.17 Any other items but not limited to above and are required to complete the job<br />
successfully as per committed schedules is the responsibility <strong>of</strong> the contractor<br />
9.18 Agency shall coordinate / cooperate with other agencies, work parallel and in a<br />
conducive environment during the course <strong>of</strong> work execution towards<br />
expeditious completion <strong>of</strong> jobs.<br />
9.19 Agency shall strictly comply with electrical compliance requirement for its<br />
equipment and human safety and power panels should be as per electrical
48<br />
department requirement and after completion check<strong>list</strong> only power will be<br />
charged.<br />
9.20 Agency should maintain the record <strong>of</strong> the activities carried out and the same<br />
should be made available at site, which will form the basis for payment <strong>of</strong> bills.<br />
9.21 Agency shall mobilize necessary material like 125KVA Diesel sets for use <strong>of</strong><br />
welding machines, diamond saw machine, illumination etc. for emergency<br />
requirement.<br />
10.0 FINAL TESTING:<br />
After erection <strong>of</strong> Convection Sections in position the cross over connection coil<br />
joints between convection section coil and Radiant section shall be welded, radio<br />
graphed and PWHT. Thereafter, the entire coil system viz., Radiant and<br />
convection coil assembly system shall be hydraulically tested in position by the<br />
Contractor. All bolts, Nuts, Gaskets and Blind Flanges required for Hydraulic<br />
testing <strong>of</strong> the coils shall be arranged by the contractor. Gasket for testing shall be<br />
as specified. Final hydraulic testing should have clearance <strong>of</strong> HPCL Inspection<br />
Engineer.<br />
11.0 PAINTING:<br />
Contractor shall procure all primers, and finish paints as per specification and<br />
also carryout the painting application including surface preparation, colour<br />
coding, lettering etc., as per specifications, standards and suitable for corrosive<br />
industrial environment.<br />
12.0 COMMISSIONING ASSISTANCE:<br />
Contractor shall provide field assistance viz., required number <strong>of</strong> Skilled<br />
Personnel and supervision to HPCL during Heater drying out and precommissioning<br />
and commissioning activities within his quoted price. The details<br />
are has given below.<br />
For startup – Total minimum 04 gangs (2 per heater) for min, 10 shifts (5 days)<br />
Gang consisting <strong>of</strong> one fitter and one helper. The above manpower is for<br />
commissioning operation assistance only. For dry out required man power to be<br />
provided by contractor.<br />
13.0 TEMPORARY WORKS:<br />
All temporary and enabling works connected with the work shall be<br />
Responsibility <strong>of</strong> the Contractor and price quoted shall be inclusive <strong>of</strong> cost <strong>of</strong> all<br />
such works, which shall be removed by the Contractor at his cost, immediately<br />
after completion <strong>of</strong> the work.<br />
14.0 PROTECTION OF EXISTING FACILITIES:<br />
14.1 Contractor shall take all precautions to ensure that no damage is caused to<br />
the existing pipe lines / structure / equipments during fabrication / erection.<br />
Contractor shall have to adopt such methods as will be suitable for working<br />
in these areas without damaging the existing facilities.<br />
14.2. Contractor shall be deemed to have taken cognizance <strong>of</strong> all such constraints<br />
etc., while working in this area and contractor shall not be entitled to claim<br />
any extra charges on all such accounts and or any other accounts.<br />
15.0 SITE MOBILIZATION:<br />
All the site mobilization activities shall be planed and arranged fully to ensure the<br />
site fabrication works etc. are completed with in the time schedule.
16.0 SITE FACILITIES:<br />
49<br />
16.1 HPCL will provide area inside refinery premises for construction <strong>of</strong><br />
contractors Site Office and Site Fabrication Yard. Contractor to intimate the<br />
requirement <strong>of</strong> area. However contactor has to utilize the area provided by<br />
HPCL and complete the job.<br />
16.2 Contractor shall arrange construction <strong>of</strong> temporary site <strong>of</strong>fice at his own cost.<br />
16.3 Water and power will be provided free <strong>of</strong> charge at 100 meters by HPCL for<br />
site <strong>of</strong>fice only. Contractor shall arrange to provide necessary connections<br />
and distribution as per his requirements for site <strong>of</strong>fice only.<br />
16.4 Site Fabrication Yard: The entire fabrication <strong>of</strong> convection sections shall be<br />
done in this yard. Facilities for fabrication purpose shall be arranged by the<br />
contractor at his own cost. All the temporary facilities shall be removed by<br />
the contractor on completion <strong>of</strong> works and area handed over to HPCL as per<br />
the requirements <strong>of</strong> Engineer-in-charge.<br />
16.5 At the Heater erection site the contractor may arrange mobile site shed.<br />
16.6 Water and power.<br />
16.6.1 Only one electrical / drinking water point for lighting purpose / drinking will be<br />
given by HPCL. The agency shall arrange for distribution at work spot on<br />
their own.<br />
16.6.2 HPCL will not supply any power for fabrication, dismantling and erection<br />
works. Contractor shall deploy suitable capacity D.G. Set and maintain the<br />
same to provide power requirements for all his activities. Also it is necessary<br />
for the contractor to make available D.G. Welding Sets for site work. No<br />
extra payments will be made to the contractor on this account and his<br />
quoted price shall include the above.<br />
17.0 SITE ORGANISATION:<br />
The Contractor should place a qualified and experienced Engineer having<br />
experience in fabrication and erection <strong>of</strong> heater jobs as their Site-in-Charge at<br />
HPCL site, responsible for all the site activities under this contract. The<br />
contractor shall also deploy adequate experienced supervisors and skilled work<br />
force including tested welders, riggers and submit the details <strong>of</strong> Site Organisation<br />
proposed by him. Experience and qualification credentials shall be submitted.<br />
However, the manpower shall be adequately augmented as decided by the<br />
Engineer- in-Charge depending on the exigencies <strong>of</strong> work. In addition, the<br />
contractor shall deploy Quality control engineers, safety Engineer and planning<br />
Engineer exclusively to take care <strong>of</strong> all the site activities.<br />
18.0 QUALITY ASSURANCE SYSTEM:<br />
18.1 Contractor shall provide overall Quality Management and procedures required<br />
to be adhered during execution <strong>of</strong> works. Contractor shall prepare Quality<br />
Assurance System plans/procedure for various disciplines <strong>of</strong> work, which<br />
should include quality control in respect <strong>of</strong> procurement, supply, fabrication,<br />
erection and testing etc. The Q. A. Plans / procedures shall be discussed with<br />
CEPS/HPCL and got vetted.
50<br />
18.2 CEPS/HPCL shall reserve the right to inspect/witness any or all stages <strong>of</strong> work<br />
at work shop, at site fabrication yard / erection site as deemed necessary for<br />
quality assurance.<br />
18.3 Agency shall have quality control engineers / supervisors for ensuring good<br />
workmanship and job quality at every stage. They shall act as coordinators<br />
with HPCL / CEPS inspection.<br />
19.0 INSPECTION AND TESTING:<br />
19.1 The Inspection authority is CEPS/HPCL/IBR. The entire job will be subjected<br />
to inspection by CEPS/HPCL/IBR. Contractor Inspection Engineers shall<br />
inspect the job and co-ordinate and obtain necessary stage-wise approvals<br />
from CEPS/HPCL/IBR. Quantity dismantled weighted and kept at dumping<br />
yard to be certified on daily basis.<br />
19.2 The Contractor shall provide all facilities and testing equipment to HPCL/CEPS<br />
to carryout inspection.<br />
19.3 The contractor shall carryout various tests as specified in the drawing /<br />
specifications.<br />
19.4 All Welders to be engaged shall be tested at site and approved by<br />
CEPS/HPCL/IBR.<br />
19.5 All consumables such as, Welding Electrodes, Painting materials, NDT testing<br />
material shall be used after taking Inspector’s approval only. Test certificates<br />
for these items shall be submitted.<br />
19.6 All results <strong>of</strong> Inspection and Tests will be recorded in the Inspection reports<br />
and submitted in the approved Pr<strong>of</strong>orma to the Engineer-in-charge. Test<br />
reports shall also form part <strong>of</strong> the completion documents.<br />
20.0 FINAL INSPECTION:<br />
After completion <strong>of</strong> tests as per Drawings/specifications, the whole work shall be<br />
subject to final inspection to ensure that the job has been completed as per<br />
requirement.<br />
If any defects are noticed, the Contractor shall attend to the same at his own cost<br />
as and when those are brought to his notice by HPCL / CEPS.<br />
21.0 APPROVAL OF SUB- VENDORS<br />
21.1 The materials required to be supplied by the Contractor shall be procured only<br />
from CEPS/HPCL approved Sub-Vendors.<br />
22.0 PROJECT MANAGEMENT & PROJECT EXECUTION<br />
22.1 After receipt <strong>of</strong> Fax <strong>of</strong> intent, the contractor shall nominate a “Project Manager”<br />
who will be the overall in charge <strong>of</strong> the job and responsible for the successful<br />
completion <strong>of</strong> the contract meeting all the contractual requirements. The<br />
contractor shall nominate an experienced person having experience in similar<br />
projects, with the required knowledge in understanding the complete<br />
requirements <strong>of</strong> the job, plan the activities, co- ordinate with all the agencies in
51<br />
the contractors organization and all the sub suppliers and also various<br />
departments <strong>of</strong> HPCL for successful and timely completion <strong>of</strong> the job.<br />
CEPS/HPCL will correspond with the Project Manager only.<br />
22.2 The Project Manager shall prepare a detailed schedule covering all the activities<br />
to achieve the contractual delivery schedule.<br />
- Residual engineering wherever required<br />
- Preparation <strong>of</strong> detailed fabrication <strong>drawings</strong><br />
- Quality assurance plan and NDT plan.<br />
- Placement <strong>of</strong> orders for all materials (Except HPCL free issue materials)<br />
- Delivery <strong>of</strong> the above materials to shop / site.<br />
- Fabrication <strong>of</strong> casing plates, structural work, coil work etc. as per sequence<br />
- N.D.T<br />
- Refractory application including welding <strong>of</strong> tie bars etc.,<br />
- Assembly and hydraulic testing <strong>of</strong> convection sections<br />
- Dismantling <strong>of</strong> existing stack and existing Convection Section.<br />
- Transportation <strong>of</strong> new convection sections and stack from fabrication yard /<br />
workshop to erection site.<br />
- Shifting <strong>of</strong> Demag CC2000 crane to erection site and its assembly<br />
- Erection <strong>of</strong> new convection sections and stacks and structures etc.,<br />
- Completion <strong>of</strong> all balance works in all respects as per the instructions <strong>of</strong><br />
engineer-in-charge.<br />
- Submission <strong>of</strong> as built <strong>drawings</strong> and other documents etc.,<br />
22.3 The Project Manager shall monitor the progress on daily basis and submit<br />
progress report on the progress <strong>of</strong> the job, percentage completion etc. The<br />
Project Manger shall take all the necessary steps, and prepare contingency plan<br />
to avoid any slippages. In Case <strong>of</strong> any slippages, the Project Manger shall take<br />
all necessary corrective steps to bring back the progress to the original planned<br />
schedule.<br />
22.4 The Project Manager also has to prepare and submit the manpower<br />
deployment in detail and the <strong>list</strong> <strong>of</strong> tools and tackles that are going to be<br />
deployed to site for fabrication, dismantling and erection.<br />
22. 5 The Project Manager along with his team shall attend progress review meeting<br />
conducted at HPCL <strong>of</strong>fice. During the review meeting HPCL/CEPS may advise<br />
the Project Manager for augmentation <strong>of</strong> manpower and more resource<br />
deployment. The Project Manager shall abide by the advice <strong>of</strong> HPCL/CEPS to<br />
achieve the committed delivery schedule.<br />
22.6 As this is a fast track project, delivery is the essence <strong>of</strong> the contract. For<br />
achieving the delivery commitments, the tenderer should have a full fledged<br />
<strong>of</strong>fice at Visakhapatnam with project Manager supported by Engineering and<br />
planning pr<strong>of</strong>essionals for taking on the spot decisions with out referring to head<br />
<strong>of</strong>fice. The project Manager should monitor the project from Visakhapatnam
52<br />
<strong>of</strong>fice, right from ordering <strong>of</strong> materials, drawing approvals, receipt <strong>of</strong> materials,<br />
site organization etc.<br />
The Project Manager should have all the powers for taking on the spot<br />
decisions, and local purchases, emergency purchases, augmenting the<br />
manpower etc. The <strong>of</strong>fice should have all the latest facilities Viz. Telephone, fax<br />
and computer with inter net connection etc.<br />
23.0 DRAWINGS AND DOCUMENTS:<br />
23.1 HPCL will issue available <strong>drawings</strong> <strong>of</strong> the existing Convection Section and<br />
stacks. However, Contractor shall prepare the detailed fabrication <strong>drawings</strong> for<br />
Convection Sections, stacks, structurals, coils, intermediate tube sheets,<br />
refractory works, bracings, plat forms and gratings etc., and submit for<br />
review/approval <strong>of</strong> CEPS/HPCL before start <strong>of</strong> work.<br />
23.2 The review /approval <strong>of</strong> documents and <strong>drawings</strong> by HPCL/CEPS shall not be<br />
construed by Contractor as limiting any <strong>of</strong> his responsibility to meet the<br />
requirements <strong>of</strong> specifications, <strong>drawings</strong> etc. and liabilities for mistakes and<br />
deviations. The Contractor shall duly incorporate the comments <strong>of</strong> HPCL/CEPS<br />
as required and resubmit the final <strong>drawings</strong>.<br />
23.3 Construction shall be as per Drawings/specifications as approved by Engineerin-charge<br />
during course <strong>of</strong> execution <strong>of</strong> work. It is, however, clearly agreed by<br />
the Contractor that review and approval <strong>of</strong> the <strong>drawings</strong> by the CEPS/HPCL<br />
does not absolve <strong>of</strong> his responsibilities to carryout the work as per<br />
specifications.<br />
23.4 As these items are replacement for the existing items viz. convection sections,<br />
stack etc., the contractor has to physically verify the actual dimensions where<br />
ever discrepancies are noticed with respect to drgs. and also where ever these<br />
are to be matched with existing convection section viz. Ducts, pipe connections<br />
etc.<br />
23.5 Four sets <strong>of</strong> approved <strong>drawings</strong> shall be submitted by the Contractor.<br />
24.0 AS BUILT DRAWINGS:<br />
Upon completion <strong>of</strong> work, the contractor shall complete all <strong>drawings</strong> to “As<br />
Built “status and submit in blue prints, polyester prints and CD.<br />
25.0 FINAL DOCUMENTS:<br />
The Contractor as part <strong>of</strong> completion documents shall submit the following.<br />
a. Materials Test Certificates, Q.A Plans/Procedures.<br />
b. Welding procedure Qualification reports.<br />
c. Welder Qualification Report<br />
d. Radiographic reports along with radiographs (only in original)<br />
e. PWHT Records.<br />
f. Hydro Test Records.<br />
g. Batch certificates <strong>of</strong> electrodes wires etc.
53<br />
h. As Built <strong>drawings</strong> in blue prints, polyester prints, CDs etc.<br />
i. Any other document as required by Engineer-In-charge.<br />
j. No Demand certificate from Engineer-in-Charge.<br />
k. No Demand Certificate from CISF <strong>of</strong> surrendering gate passes etc.<br />
26.0 STATUTORY APPROVALS:<br />
26.1 All statutory approvals from local bodies viz., IBR etc. is in contractor’s scope.<br />
26.2 For IBR scope <strong>of</strong> work the contractor shall prepare the <strong>drawings</strong> and<br />
documents along with design calculations and obtain necessary approvals <strong>of</strong><br />
IBR etc.<br />
26.3 All materials procured for IBR jobs shall be duly inspected approved by the<br />
IBR Inspector and stamped. All the IBR Inspection documents shall be<br />
submitted.<br />
26.4 The Contractor shall also arrange necessary Inspection <strong>of</strong> the IBR authorities<br />
and also co-ordinate and liaison with IBR inspector.<br />
26.5 The Contractor shall arrange for ground inspection <strong>of</strong> materials welders<br />
testing, stage wise fabrication inspection and hydraulic testing by IBR<br />
Inspector.<br />
26.6 The inspection and acceptance <strong>of</strong> the works by the authorities shall however,<br />
not absolve the Contractor from any <strong>of</strong> his responsibilities under this contract.<br />
27.0 STATUTORY RULES AND REGULATIONS:<br />
27.1 Contractor shall strictly adhere to the following provisions laid down in the<br />
Factories Act 1948 and The Contract Labour Act 1970 while carrying out the<br />
jobs inside the Refinery Premises.<br />
1. Labour licence for the personnel working.<br />
2. Safety <strong>of</strong> personnel<br />
3. Minimum wages as per Legislation.<br />
4. Coverage <strong>of</strong> Employees under PF and ESI as per Law<br />
5. Payment <strong>of</strong> wages for the leave period as specified under the Acts.<br />
6. Maintenance <strong>of</strong> workbooks, Registers indicating the work force deployed<br />
daily.<br />
27.2 The Contractor shall obtain necessary Labour License from the licensing<br />
authority under the Contract Labour Regulations & Abolition Act 1970) and<br />
produce a copy <strong>of</strong> license to CEPS /HPCL prior to starting <strong>of</strong> work.<br />
27.3 The Contractor shall enforce the provision ESI Act with regard to all his<br />
employees engaged in this contract work.<br />
27.4 Factory Inspector’s requirements are to be met by the contractor fully.
54<br />
27.5 The contractor shall follow strictly all the rules and regulations <strong>of</strong> HPCL at<br />
their refinery premises and other statutory rules.<br />
28.0 SITE CLEANING:<br />
During fabrication, dismantling and erection at HPCL, area shall be cleaned<br />
regularly. Good house keeping at working site forms part <strong>of</strong> agency’s scope.<br />
House keeping to be taken up on daily basis. The scrap / debris includes insulation<br />
waste generated loose drums and it’s contents removed waste shall be removed<br />
by the agency and dumped at the specified locations as per the directions <strong>of</strong><br />
Engineer-in-charge. Agency also should obtain clearance certificate from HPCL<br />
Engineer-in-charge from operations and same to be enclosed to final bill.<br />
29.0 SECURITY:<br />
The Refinery being a protected area, entry into the Refinery area shall be<br />
restricted and governed by issue <strong>of</strong> photo gate passes by HPCL security. The<br />
Contractor shall arrange and obtain in advance all necessary entry permits/gate<br />
passes for his staff and labour and materials, and are liable to vigorous check<br />
by the Security Staff.<br />
30.0 SAFETY:<br />
30.1 The Contractor and his staff and labour shall be bound by all the Security, fire<br />
and safety regulations in the Refinery.<br />
30.2 Contractor shall strictly adhere to all safety rules and regulation <strong>of</strong> HPCL during<br />
the execution <strong>of</strong> works in the Refinery. Minimum <strong>of</strong> two safety supervisors to be<br />
deployed and their credentials shall be submitted. They should have diploma<br />
from recognized institute with 5 years experience as safety supervisor or 10<br />
years experience as safety supervisor. It may be noted that penalty shall be<br />
levied on the Agency for violation <strong>of</strong> safety for each incident. Penalty amount<br />
will be decided by HPCL and shall be binding on the agency. The safety<br />
Engineer shall constantly co-ordinate with HPCL’s Safety and operations<br />
departments for smooth and safe conduct <strong>of</strong> job. Safety supervisor shall be<br />
accompany his companies workmen daily (all 24 hrs) till the work men leave<br />
the refinery after completion <strong>of</strong> the assigned work.<br />
30.3 Agency shall provide required personnel protective gadgets (like safety shoes,<br />
helmets, belts, fall protective nets etc.) to their work force for carrying out the<br />
job safely. Also agency shall provide adequate no <strong>of</strong> fire hoses, DCP cylinders<br />
etc. at the work site during job execution.<br />
30.4 Hot permits:<br />
30.4.1 Agency shall start work only after taking permit from HPCL, subject to<br />
availability <strong>of</strong> safety and works supervisor <strong>of</strong> the agency at site agency<br />
shall be responsible for safety <strong>of</strong> the installation and people working with<br />
him and the other connected equipments. Other vehicles except Demag<br />
crane 300MT like cranes, hydra, tractor trailers, dumpers, all lifting<br />
accessories should have valid load test certificates and flame arrestors for<br />
vehicles.<br />
30.4.2 Contractor shall strictly comply with all the safety requirements <strong>of</strong> hot work<br />
permit during permit time. If the contractor fails to comply, HPCL shall<br />
exercise their right to stop the hot work and all the cost and time effect<br />
there<strong>of</strong> shall be to contractors account.
55<br />
Any default and violation <strong>of</strong> the security, fire and safety regulations <strong>of</strong><br />
HPCL by the contractor and his staff and labour shall constitute an<br />
infringement <strong>of</strong> relevant clauses <strong>of</strong> the contract and also liable for penalties<br />
and consequences as per the said rules. The opinion <strong>of</strong> the Engineer-In-<br />
Charge is final and binding in this regard.<br />
30.4.3 Any default and violation <strong>of</strong> the security, fire and safety regulations <strong>of</strong><br />
HPCL by the contractor and his staff and labour shall constitute and<br />
infringement <strong>of</strong> relevant clauses <strong>of</strong> the contract and also liable for<br />
penalties and consequences as per the said rules. The opinion <strong>of</strong> the<br />
engineer-in-charge is final and binding in this regard.<br />
30.4.4 Important Safety Regulations:<br />
Full body safety harness is compulsory for working at height over 10 f<br />
feet, shall have complete fall protection in the form <strong>of</strong> Full body safety harness. Full<br />
body safety belt conforming to IS:3521 made <strong>of</strong> nylon with 4” width shoulder strap<br />
with double folded stitches, O-ring buckles made <strong>of</strong> stainless steel and 2.5 meter<br />
long two polyamide ropes with self closing hook <strong>of</strong> stainless steel attached to it for<br />
anchoring with scaffold pipe <strong>of</strong> dia 50mm. This safety belt should be examined by<br />
a competent person at least once in six months and a record <strong>of</strong> certificate to be<br />
maintained.<br />
Only Recommended Vendors for safety harness system:<br />
i) M/s. P.N. Safetech Pvt. Ltd. Visakhapatnam.<br />
ii) M/s. Unicare Emergency Equipment Pvt. Ltd. Mumbai.<br />
iii) M/s. Suri Industrial Engineering Co. Hyderabad.<br />
iv) M/s. Shubham Safety Solutions. Visakhapatnam.<br />
v) M/s. National Engineering <strong>Corporation</strong>. Visakhapatnam<br />
b) Others : Double life time line safety belt, Safety nets for working at<br />
heights, Welding and grinding helmets, Insulated tools for excavation<br />
jobs, daily checking recork <strong>of</strong> ELCB’s on all electrical circuits<br />
including welding, lighting, grinding tools etc are to be compulsory<br />
used wherever required.<br />
30.4.5 Scaffolding:<br />
Scaffolding at all heights to be done for all areas, wherever cutting is<br />
required as per standard safety procedures MWPM/SAFETY/1. Refer<br />
page nos. 388 & 389.<br />
30.05 Dress code:<br />
Dress code for contractor’s employees is as given below:<br />
30.05.01 All contractor employee’s to wear boiler suit in the following manner.<br />
Boiler suits will have contractor’s amblem on the back side.<br />
Supervisor :- Boiler suit in orange colour.<br />
Safety Supervisor :- Boiler suit in blue colour along with safety<br />
jerkin in fluorescent colour.<br />
Worker :- Boiler suit in blue colour.<br />
30.05.02 All contractor employees shall wear badge containing the details <strong>of</strong><br />
employee ( Name, Age, Contractor’s Name, Details <strong>of</strong> the job, Job<br />
engineers name and Company).
56<br />
30.05.03 A colour cloth badge having contractor’s name shall be tied to<br />
the contractor’s employee’s shoulder.<br />
30.06 Reporting plan<br />
30.06.01 First Reporting Plan<br />
DAY Activity to be done<br />
Reporting Day minus 35 days 1. Notice to HPCL confirming the<br />
Reporting date.<br />
2. Receipt <strong>of</strong> Medical Certificates<br />
by HPCL from the Agency as<br />
per page no. 256, clause no.<br />
3.14 <strong>of</strong> Tender.<br />
Reporting Day minus 28 days 1. HPCL response on acceptance<br />
or other requirement <strong>of</strong> the<br />
personnel.<br />
2. Despatch <strong>of</strong> Gate Pass<br />
Formats by HPCL for<br />
Personnel and Vehicle.<br />
Reporting Day minus 21 days 1. Receipt <strong>of</strong> Pass Application<br />
with required Photographs by<br />
HPCL.<br />
Reporting Day minus 14 days 1. Submission <strong>of</strong> PPE and Dress<br />
for inspection by HPCL.<br />
Reporting Day To report with the Personnel,<br />
Vehicle and other requirements.<br />
30.06.02 Contractor shall submit <strong>list</strong> <strong>of</strong> employees entering into the company<br />
shift wise daily.<br />
30.06.03 All the employees <strong>of</strong> the contractor shall be present at the designated<br />
location equipped with PPE equipment before they attend the job in<br />
working location.<br />
30.06.04 The <strong>list</strong> <strong>of</strong> employees expected to be releaved from the work site<br />
after completion <strong>of</strong> the work to be inspected by HPCL <strong>of</strong>ficials. They<br />
shall not be permitted the refinery premises without HPCL personnel<br />
inspection.<br />
31. List <strong>of</strong> <strong>drawings</strong>: The <strong>list</strong> <strong>of</strong> <strong>drawings</strong> that will be provided to the successful<br />
bidder is enclosed. However for the purpose <strong>of</strong> tendering <strong>drawings</strong><br />
against sl. nos. 2,4, 5, 6, 11, 19, 21, 28, 47, 48 and 49 for 11-F-01<br />
and <strong>drawings</strong> against sl. nos 2, 4, 5, 6, 7, 8, 10, 11, 19, 32, 33, and<br />
34 against 12-F-01 are to be down loaded from the web site. For<br />
successful bidder copies <strong>of</strong> the balance <strong>drawings</strong> will be made<br />
available after award <strong>of</strong> the contract.<br />
32. List <strong>of</strong> free issue materials issued by HPCL is attached.<br />
List <strong>of</strong> technical specification as attached.<br />
34. Check <strong>list</strong> for safety inspection <strong>of</strong> work site:<br />
Contractor should ensure the accident prevention in site. Inspection <strong>of</strong><br />
site is to be carried out periodically as per the check <strong>list</strong> attached.<br />
35.EXCLUSIONS:<br />
Civil works.
LIST OF FREE ISSUE MATERIALS<br />
ISSUED BY HPCL
1. List <strong>of</strong> Studded tubes<br />
SL<br />
NO<br />
DESCRIPTION OF ITEM<br />
1 OD 6.625x0.28"A.W, studded tubes<br />
dduly edge prepared with cs studs<br />
11/2"diax1.25"high,<br />
24 spp and 63p/m<br />
Total length=9532mm<br />
Studded length= 9232mm<br />
Plain length X=150mm<br />
Plain length Y=150mm<br />
2 OD 6.625x0.28"A.W , studded tubes duly<br />
edge prepared with cs studs<br />
0.5"diax1.25"high,12 spp and 63p/m<br />
Total length=9532mm<br />
Studded length= 9232mm<br />
Plain length X=150mm<br />
Plain length Y=150mm<br />
3 OD 6.625x0.28"A.W , studded tubes duly<br />
edge prepared with cs studs<br />
0.5"diax1.25"high, 6 spp and 63 p/m<br />
Total length=9532<br />
Studded length= 9232<br />
Plain length X=150mm<br />
Plain length Y=150mm<br />
Design pres.: 14 kg/cm²G<br />
Design temp: 350°C<br />
4 OD 4.5"x 0.237" A.W, studded tubes<br />
duly edge prepared with<br />
c s studs 1/2"diax1"high,16 spp and<br />
63p/m<br />
Total length=8462mm<br />
Studded length=8262mm<br />
Plain length X=50mm<br />
Plain length Y=150mm<br />
5 OD 4.5"x 0.237" A.W , studded tubes<br />
duly edge prepared with<br />
c s studs 1/2"diax1"high,16 spp and<br />
63p/m<br />
Total length=7862mm<br />
Studded length=7662mm<br />
Plain length X=50mm<br />
Plain length Y=150mm<br />
6 OD 4.5"x 0.237" A.W , studded tubes<br />
duly edge prepared with<br />
c s studs 1/2"diax1"high,16 spp and<br />
63p/m<br />
Total length=8462mm<br />
Studded length=8262mm<br />
Plain length X=50mm<br />
Plain length Y=150mm<br />
MATERIAL<br />
SPEC.<br />
SA 335 P5<br />
SA 335 P5<br />
SA 106 Gr.B<br />
SA 335 P9<br />
SA 335 P9<br />
SA 335 P9<br />
QTY<br />
NOS<br />
40<br />
16<br />
8<br />
8<br />
REMARKS<br />
11-F-01<br />
11-F-01<br />
11-F-01<br />
12-F-01<br />
8 12-F-01<br />
8 12-F-01
SL<br />
NO<br />
7<br />
DESCRIPTION OF ITEM<br />
OD 4.5"x 0.237" A.W , studded tubes<br />
duly edge prepared with<br />
c s studs 1/2"diax1"high,16 spp and<br />
63p/m<br />
Total length=7862mm<br />
Studded length=7662mm<br />
Plain length X=50mm<br />
Plain length Y=150mm<br />
Note: All tubes shall be supplied in normalized and tempered condition.<br />
2. List <strong>of</strong> Bare Tubes<br />
SL NO DESCRIPTION OF ITEM<br />
MATERIAL SPECIFI-<br />
CATION<br />
QTY NOS REMARKS<br />
1 Bare tubes OD 6.625"x0.28" A.W<br />
x9532mm long duly edge prepared SA 335 P5 16 11-F-01<br />
2 Bare tubes OD 6.625"x0.28" A.W<br />
x6000mm long (with straight cut edge) SA 335 P5 10 11-F-01<br />
3 Bare tubes OD 6.625"x0.28" A.W<br />
x6000mm long (with straight cut edge)<br />
Design pres.: 14 kg/cm²G<br />
Design temp: 350°C<br />
4 Bare tubes OD 4.5"x 0.237" A.W x7862<br />
long duly edge prepared<br />
5 Bare tubes OD 4.5"x 0.237" A.W<br />
x8462mm long duly edge prepared<br />
MATERIAL<br />
SPEC.<br />
QTY<br />
NOS<br />
REMARKS<br />
SA 335 P9 8 12-F-01<br />
SA 106 GR.B 1 11-F-01<br />
SA 335 P9 8 12-F-01<br />
SA 335 P9 8 12-F-01<br />
6 Bare pipes OD 4.5"x 0.237" A.W x<br />
6000mm long (with straight cut edge) SA 335 P9 7 12-F-01
3. List <strong>of</strong> Pipe Fittings<br />
SL NO<br />
DESCRIPTION OF ITEM<br />
1 180º S.R bend<br />
OD 6.625”x0.28” A.W<br />
2 180º S.R bend<br />
OD 6.625”x0.28” A.W<br />
3 90º S.R bend<br />
OD 6.625”x0.28” A.W<br />
4 Reducing weldolet to suit 2”N.Bxsch 80<br />
branch and OD 6.625”x0.28” A.W run<br />
pipe<br />
5 Reducing weldolet to suit 2”N.Bxsch 40<br />
branch and OD 6.625”x0.28” A.W run<br />
pipe<br />
6 Reducing elbolet to suit<br />
1 ½”N B pipe on 6”N Bx0.28” thk<br />
SR 180º bend<br />
7 Reducing elbolet to suit 2”N.B pipe on<br />
6”N Bx0.28” thk<br />
SR 180º bend<br />
8 S.R 180º ret. Bend(203c/c)<br />
OD 4.5”x0.237” A.W.<br />
9 SR 90º elbow (102C/F)<br />
OD 4.5”x 0.237” A.W.<br />
10 Reducing weldolet 4"N.Bx2"N.B to suit<br />
4.5" OD x0.237" A.W run pipe and<br />
2.375" OD x0.218" A.W branch pipe<br />
11 Reducing elbolet 4"NBx2"NB<br />
to suit 4.5" ODx 0.237" A.W 90º S.R<br />
bend and 2.375" ODx 0.218" A.W<br />
branch pipe<br />
12 Reducing elbolet 4"N.Bx 1 ½ "N.B to<br />
suit 4.5" OD x0.237" A.W 90º S.R<br />
bend and 2.375" ODx 0.218" A.W<br />
branch pipe<br />
MATERIAL<br />
SPECIFICATION<br />
QTY<br />
NOS<br />
REMARKS<br />
SA234WP5 80 11-F-01<br />
SA234WPB 10 11-F-01<br />
SA234WP5 35 11-F-01<br />
SA 182 F5 6 11-F-01<br />
SA105 3 11-F-01<br />
SA 182 F5 5 11-F-01<br />
SA 182 F5 5 11-F-01<br />
SA234WP9 20 12-F-01<br />
SA 234WP9 30 12-F-01<br />
SA 182 F9 10 12-F-01<br />
SA 182 F9 8 12-F-01<br />
SA 182 F9 4 12-F-01
4. List <strong>of</strong> Forged Flanges<br />
SL<br />
NO<br />
DESCRIPTION OF ITEM<br />
1 Raised face weld neck<br />
Flange 6"N.B, ANSI 300<br />
(bored to ID154.05mm)<br />
2 Raised face weld neck<br />
Flange 6"N.B, ANSI 300<br />
(Bored to ID154.05mm)<br />
3 Raised face weld neck<br />
Flange 2"N.B,ANSI 300 (bored<br />
to ID49.22mm)<br />
4 Raised face weld neck<br />
Flange 2"N.B,ANSI 300 (bored<br />
to ID52.48 mm)<br />
MATERIAL<br />
SPEC.<br />
QTY<br />
NOS<br />
REMARKS<br />
SA 182 F5 6 11-F-01<br />
SA 105 3 11-F-01<br />
SA 182 F5 10 11-F-01<br />
SA105<br />
3<br />
11-F-01<br />
5 Raised face blind<br />
Flange 2"N.B,ANSI 300 SA 182 F5 6 11-F-01<br />
6 Raised face blind<br />
Flange 2"N.B,ANSI 300 SA 105 2 11-F-01<br />
7 Raised face weld neck<br />
Flange 2"NB,ANSI 300, bored<br />
to ID49.22mm<br />
8 Raised face weld neck<br />
Flange 1 1/2"N.B,ANSI 300, bored to<br />
ID38.14mm.<br />
9 Raised face weld neck<br />
Flange 4"N.B,ANSI 300, bored to<br />
ID102.26mm.<br />
10 Raised face blind<br />
Flange 2"N.B,ANSI 300<br />
SA 182 F9 14 12-F-01<br />
SA 182 F9 4 12-F-01<br />
SA 182 F9 4 12-F-01<br />
SA 182 F9 8 12-F-01
5. List <strong>of</strong> Intermediate Tube Sheets & Support Brackets<br />
SL NO<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
7<br />
8<br />
DESCRIPTION OF<br />
ITEM<br />
Top Tube sheets<br />
Drg no. 1667-17-00-00-D-112 Rev 0<br />
(VR-11-F-01-00009)<br />
Bottom Tube sheets<br />
Drg no. 1667-17-00-00-D-112 Rev 0<br />
(VR-11-F-01-00009)<br />
Tube sheet support brackets<br />
(Heavy pattern)<br />
7-17-0101 Rev 3<br />
(EIL Standard drg.)<br />
Bolts, Nuts & washers for<br />
intermediate tube sheet support<br />
bracket (Heavy)<br />
7-17-0406 Rev 1<br />
(EIL Standard drg.)<br />
Top Tube sheets<br />
Drg no. 1667-17-12-00-00-D-203 Rev 1<br />
(VR-12-F-01-0004)<br />
Bottom Tube sheets<br />
Drg no. 1667-17-12-00-00-D-203Rev 1<br />
(VR-12-F-01-0004)<br />
Tube sheet support brackets<br />
(Heavy pattern)<br />
7-17-0101 Rev 3<br />
(EIL Standard drg.)<br />
Bolts, Nuts & washers for<br />
intermediate tube sheet support<br />
bracket (Heavy)<br />
7-17-0406 Rev 1<br />
(EIL Standard drg.)<br />
6. Stack dampers<br />
MATERIAL SPECIFI-<br />
CATION<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
SS 18/8<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
50Cr-48.5Ni-<br />
1.5Nb<br />
(INS 657)<br />
QTY NOS<br />
2<br />
1<br />
6<br />
32 Sets<br />
3<br />
3<br />
12<br />
SS 18/8 56 Sets<br />
REMARKS<br />
11-F-01<br />
11-F-01<br />
11-F-01<br />
11-F-01<br />
12-F-01<br />
12-F-01<br />
12-F-01<br />
12-F-01
LIST OF<br />
TECHNICAL SPECIFICATIONS<br />
0 14.08.07 ISSUED FOR TENDER G.N.R R.S.N G.C.S<br />
No DATE REVISION PREPARED BY REVIEWED BY APPROVED<br />
BY<br />
COSMOS<br />
ENGINEERING<br />
LIST OF<br />
TECHNICAL Specification no REV<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
SPECIFICATIONS<br />
Page 1 <strong>of</strong> 3 0
Sl.no Title<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
LIST OF TECHNICAL SPECIFICATIONS<br />
01 Standard specification for steel work <strong>of</strong> Fire<br />
heaters and APH systems<br />
02 Standard specification <strong>of</strong> coil work for<br />
fired heaters<br />
03<br />
Standard specification for studded Tubes <strong>of</strong><br />
fired heaters<br />
04 Technical notes for pipes<br />
05 Standard specification <strong>of</strong> tube support casting<br />
for fired heaters<br />
06 Technical specification for flanges, spectacle<br />
blinds and drip rings<br />
07<br />
08<br />
Standard specification for Refractory<br />
Materials, sampling, Inspection and criteria for<br />
acceptance<br />
Standard specification for ceramic fibre<br />
blankets<br />
09 Standard specification for manual<br />
application <strong>of</strong> Insulating concrete<br />
10<br />
Standard specification for insulating<br />
castables<br />
LIST OF<br />
TECHNICAL<br />
SPECIFICATIONS<br />
Spec. no.<br />
6-17-0002 Rev 2<br />
6-17-0003 Rev 2<br />
6-17-0004 Rev 3<br />
6-44-0051 Rev 3<br />
6-17-0007 Rev 2<br />
6-44-0053 Rev 3<br />
6-79-01 Rev 0<br />
6-79-0005 Rev 1<br />
6-79-07 Rev 1<br />
6-79-0008 Rev 1<br />
11 Technical notes for gaskets 6-44-0056 Rev 2<br />
Specification no REV<br />
Page 2 <strong>of</strong> 3 0
Sl.no Title Spec.no.<br />
12 Technical specification for quality control<br />
requirements<br />
13 Technical notes for butt welded, socket<br />
welded, screwed fittings<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
LIST OF<br />
TECHNICAL<br />
SPECIFICATIONS<br />
CEPS-TS-01 Rev 0<br />
6-44-0054 Rev 3<br />
14 Intermediate weld for studded tubes 7-17-0608 Rev 2<br />
15 Technical specification for painting CEPS-TS-13 Rev 0<br />
16 Technical specification for Quality plan for<br />
refractory lining<br />
17<br />
Convection section intermediate tube<br />
sheet support bracket with 102x102 bearing<br />
surface (heavy pattern)<br />
18 Detail <strong>of</strong> insulation at tube supports for<br />
concrete walls<br />
19 Bolts and shear plate for intermediate tube<br />
sheet Support bracket (Heavy)<br />
20 Chain link reinforcement for insulating<br />
concrete lining (Maximum thickness-50)<br />
CEPS-TS-12 Rev 0<br />
7-17-0101 Rev 3<br />
7-17-0306 Rev 2<br />
7-17-0406 Rev 1<br />
7-17-0202 Rev 2<br />
21 Tube sealing detail 7-17-0322 Rev 2<br />
22 Steel stack field splice details 7-17-0428 Rev 1<br />
23 Shipping spiders for prefabricated stacks<br />
(for stack diameters up to 3050)<br />
7-17-0439 Rev 1<br />
24 Welding specification charts for piping classes 6-77-0005 Rev 3<br />
Specification no REV<br />
Page 3 <strong>of</strong> 3 0
139
1.0 SCOPE<br />
140
144
145
146
147
148
149
150
151
152
153
154
155
156
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL SPECIFICATION<br />
FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
0 12.05.03 ISSUED FOR TENDER G.N.R R.S.N. G.C.S.<br />
No DATE REVISION PREPARED BY REVIEWED BY APPROVED BY<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 1 <strong>of</strong> 6<br />
0
01. SCOPE<br />
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
CONTENTS<br />
02. QUALITY ASSURANCE REQUIREMNTS<br />
03. QUALITY CONTROL REQUIREMNTS<br />
04. DOCUMENTS<br />
05. DEPLOYMENT OF RIGHT WORKERS<br />
06. QUALITY REQUIRES A TEAM EFFORT<br />
07. MATERIAL CONTROL<br />
08. ALIGNMENT OF PART<br />
09. WELDING<br />
10. NON DESTRUCTIVE TESTING<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 2 <strong>of</strong> 6<br />
0
1.0 SCOPE:<br />
This specification covers the Quality Control requirements that are to be met during<br />
execution <strong>of</strong> the contract. This covers the quality assurance requirement, quality<br />
control requirements, documentation etc.<br />
2.0 Quality Assurance requirements:<br />
2.1 The Tenderer should completely study the tender documents, specification and<br />
<strong>drawings</strong> and should understand the scope <strong>of</strong> work and technical requirements<br />
including quality requirements.<br />
2.2 Quality Assurance Plan:<br />
The objective <strong>of</strong> Quality Assurance Plan is –<br />
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
To understand the operating conditions.<br />
To understand the code requirements.<br />
To understand the specification requirements<br />
To understand the complete job requirements<br />
To understand total contract scope <strong>of</strong> work<br />
To convert all the above requirements into a plan based on which stage-wise<br />
inspection can be carried out to ensure the desired quality.<br />
Further this will also enable contractor to meet the job requirements without<br />
any variations.<br />
2.3 The Quality Assurance Plan shall invariably contain the following:<br />
Design data<br />
Code <strong>of</strong> Construction<br />
Inspection Agency<br />
Reference documents<br />
Materials <strong>of</strong> construction<br />
Stages <strong>of</strong> inspection<br />
Material identification<br />
Inspection during fabrications<br />
Inspection during assembly and fit up<br />
Welding procedures and qualifications<br />
Dimensional check<br />
NDE requirements<br />
PWH requirements<br />
Pressure test requirements<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 3 <strong>of</strong> 6<br />
0
Cleaning requirements<br />
Painting requirements<br />
Packing requirements<br />
3.0 QUALITY CONTROL REQUIREMENTS:<br />
3.1 The Contractor shall submit the total <strong>list</strong> <strong>of</strong> <strong>drawings</strong> required for approval /<br />
information within one week from the date <strong>of</strong> Fax <strong>of</strong> Intent. The <strong>list</strong> also should<br />
contain the schedule <strong>of</strong> submission <strong>of</strong> each drawing. The schedule <strong>of</strong> submission<br />
shall be worked out to suit the overall schedule <strong>of</strong> completion <strong>of</strong> the job.<br />
3.2 The Contractor shall submit the total <strong>list</strong> <strong>of</strong> all materials except bolts, nuts and<br />
gaskets, and the schedule for procurement <strong>of</strong> the same item-wise indicating the<br />
delivery and the Supplier. All critical materials shall be procured from the aproved<br />
Vendors <strong>list</strong> as specified in Attachment to the Tender Document.<br />
3.3 Conformity to specification/drawing requirement and deviations.<br />
3.3.1 The Contractor shall fully comply to the job requirements.<br />
3.4 APPROVAL OF SUB-VENDORS:<br />
The contractor shall procure all materials in his scope only from CEPS/HPCL<br />
approved sub-vendors. The contractor shall submit his proposed sub-vendors <strong>list</strong><br />
well In advance and obtain the written approval from CEPS/HPCL.<br />
The contractor should select only the reputed and reliable suppliers. The<br />
approval <strong>of</strong> CEPS/HPCL shall not relieve the responsibility <strong>of</strong> contractor in<br />
procurement <strong>of</strong> right quality material to meet job requirements<br />
3.5 MEASURING AND TESTING INSTRUMENTS:<br />
The Contractor shall use only calibrated instruments for measuring and testing.<br />
The contractor shall maintain all the calibration records for the instruments used.<br />
All these records should be made available to the Inspector.<br />
3.6 QUALITY RECORDS:<br />
The contractor shall maintain all the quality records and shall submit the same to<br />
the Inspection Engineer stationed at site as and when called for.<br />
3.7 IDENTIFICATION OF ITEMS:<br />
The Contractor shall identify all the parts/items with a part number as per the<br />
<strong>drawings</strong> during all stages <strong>of</strong> production. This will facilitate contractor to use the<br />
right part at the right place during assembly.<br />
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 4 <strong>of</strong> 6<br />
0
4.0 DOCUMENTS:<br />
4.1 Contractor shall strictly ensure that the documents used during various<br />
stages <strong>of</strong> execution <strong>of</strong> the contract are latest revisions.<br />
4.2 Contractor shall ensure that their Inspector carryout the inspection as per<br />
the latest quality assurance plans approved by CEPS/HPCL and latest<br />
<strong>drawings</strong>. All inspection/test results shall be recorded/ documented in such a<br />
way that the results can be co-related.<br />
5.0 DEPLOYMENT OF RIGHT WORKERS:<br />
The Contractor shall deploy only qualified and experienced workers and Inspectors<br />
so that the job can be completed meeting all the requirements. In case<br />
CEPS/HPCL observes any deficiency, the contractor shall replace the workers/<br />
Inspectors with the required experience. CEPS/HPCL decision is final.<br />
6.0 QUALITY REQUIRES A TEAM EFFORT:<br />
During the past 40 years the role <strong>of</strong> Quality Control has changed significantly<br />
throughout the world. The myth that a good Quality Control Organization can on<br />
its own assure that only a quality product is shipped is completely false. It needs a<br />
team effort. This effort must include all Departments from Sales to Shipping. Every<br />
one has to contribute for the quality <strong>of</strong> the job but not just worker and inspector on<br />
the shop floor. The Contractor must infuse the above theme to all their personnel<br />
so that a team effort will bring a quality product.<br />
7.0 MATERIAL CONTROL:<br />
7.1 All codes stipulate that raw materials used are fully tested and supplied meeting the<br />
material specification and further verified with Mill Test Certificate.<br />
7.2 Material used for pressure parts shall be identified with the stamping on the material<br />
and correlated with test certificate. The material not fully identified with code<br />
approved specification shall not be used for pressure parts. However, CEPS/HPCL<br />
may agree for retesting the material for chemical and mechanical properties for<br />
comparing these values with the code specification and take a final decision.<br />
8.0 ALIGNMENT OF PARTS:<br />
The soundness <strong>of</strong> weld joint is very much dependent on good joint fit up i.e., root<br />
gap, overlaps, bevel alignment etc. The design and shape <strong>of</strong> welding joint edges<br />
shall be such that complete fusion <strong>of</strong> the edges and weld penetration is achieved.<br />
Prior establishment <strong>of</strong> welding procedure qualification will confirm the satisfactory<br />
joint design.<br />
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 5 <strong>of</strong> 6<br />
0
9.0 WELDING:<br />
9.1 As the convection coils are fabricated by welding process, utmost care and<br />
quality checks are required at various stages <strong>of</strong> welding. Codes do not stipulate<br />
any welding method or procedure. But, it is required to be confirmed the welding<br />
is sound and the methods adopted are qualified as per code stipulations.<br />
Welding Procedure Specification (WPS) and Procedure Qualification Record<br />
(PQR) are to be established and approved by CEPS based on which actual<br />
welding shall be performed on the job.<br />
9.2 Once procedures are qualified, the welders should show their ability to make<br />
sound weld in position. This is to be demonstrated by welding a test pipe and<br />
carrying out radiography <strong>of</strong> the weld. Besides weld procedures and welder, the<br />
quality <strong>of</strong> welding depends on the following factors. As such Inspector has to<br />
check these aspects:<br />
COSMOS ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
a) The way the procedure is handled.<br />
b) Usage <strong>of</strong> correct consumables<br />
c) Pre-heating<br />
d) Post weld heat treatment etc.<br />
The Inspector shall check the following aspects:<br />
a) All butt welds shall have complete fusion and shall be free from defects<br />
like porosity, under cuts and overlaps or valleys etc.<br />
b) The weld reinforcement shall be within permissible limits <strong>of</strong> code.<br />
c) Fillet welds shall be free from under-cuts and overlaps.<br />
d) The throat <strong>of</strong> the leg <strong>of</strong> the weld shall be <strong>of</strong> required size<br />
10.0 NON-DESTRUCTIVE TESTING<br />
10.1 Various non-destructive examination techniques are employed during various<br />
stages <strong>of</strong> fabrication <strong>of</strong> Convection Sections. This NDE methods will provide<br />
to check the various manufacturing defects <strong>of</strong> castings, forgings, pipes, pipe<br />
fittings etc., and also to inspect weld defects at various stages <strong>of</strong> fabrication.<br />
10.2 The procedure for NDT examination shall be as per the prescribed procedure<br />
(as per Q.A. System) and to be conducted by Contractors qualified technical<br />
personnel who should evaluate the results and maintain the records as per<br />
code and submit the same to CEPS/HPCL.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY CONTROL<br />
REQUIREMENTS<br />
Specification no REV<br />
CEPS-TS-01<br />
Page 6 <strong>of</strong> 6<br />
0
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL SPECIFICATION<br />
FOR<br />
PAINTING<br />
0 12.05.03 ISSUED FOR TENDER G.N.R R.S.N G.C.S<br />
No DATE REVISION PREPARED BY REVIEWED BY APPROVED BY<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
PAINTING<br />
Specification no REV<br />
CEPS-TS- 13<br />
Sheet 1 <strong>of</strong> 4<br />
0
1. SCOPE<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
CONTENTS<br />
2. CODES AND STANDARDS<br />
3. SURFACE PREPARATION<br />
4. COATING PROCEDURE<br />
5. DRYING OF COATED SURFACE<br />
6. DETAILS OF PAINTING COATS<br />
7. ACCEPTABLE PAINTS MANUFACTURERS<br />
8. TEST CERTIFICATES<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
PAINTING<br />
Specification no REV<br />
CEPS-TS- 13<br />
Sheet 2 <strong>of</strong> 4<br />
0
1.0 SCOPE<br />
The scope <strong>of</strong> this specification covers surface preparation, selection and application <strong>of</strong><br />
paints on external surface <strong>of</strong> convection section & structurals<br />
2.0 CODES AND STANDARDS<br />
The following codes shall be followed:<br />
IS: 5 – colour coding<br />
IS: 101 – Method <strong>of</strong> testing for ready mixed paints and enamels<br />
3.0 SURFACE PREPARATION<br />
All external surfaces <strong>of</strong> convection section & structural shall be blast cleaned to SA 2 ½<br />
Swedish standards SIS-05-5900 or SSPC-SP-10 (US standard)<br />
4.0 COATING PROCEDURE<br />
4.1 Surface shall not be coated in rain, wind or in environment injurious air borne<br />
elements etc<br />
4.2 Blast cleaned surface shall be coated with one complete application <strong>of</strong> primer with in<br />
four hrs.<br />
4.3 Each coat shall be in proper state <strong>of</strong> cure or dryness before the next coat<br />
5.0 DRYING OF THE COATED SURFACE<br />
No coat shall be applied until the preceding coat has dried.<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
PAINTING<br />
Specification no REV<br />
CEPS-TS- 13<br />
Sheet 3 <strong>of</strong> 4<br />
0
6.0 DETAILS OF PAINTING COATS<br />
SL<br />
NO<br />
DESCRIPTION PRIMER COAT FINISH COAT<br />
01 Convection 1x60 microns DFT 2x20 microns DFT<br />
section<br />
inorganic zinc silicate modified aluminum<br />
(External) primer<br />
silicon paint<br />
02 Stack<br />
a. Internal<br />
b. External<br />
c.Aviation colour<br />
bands (top 6<br />
meters)<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
2x100 microns DFT with<br />
Protectomatsic paint <strong>of</strong> M/s<br />
Berger or equivalent<br />
1x65 microns DFT<br />
inorganic zinc silicate<br />
primer applied by the<br />
method <strong>of</strong> air less spray<br />
1x65 microns DFT<br />
inorganic zinc silicate<br />
primer applied by the<br />
method <strong>of</strong> air less spray<br />
1x50 microns epoxy zinc<br />
phosphate primer<br />
05 Structures 1x50 microns DFT Zinc rich<br />
apoxy primer<br />
2x100 microns DFT epoxy<br />
high build paint<br />
7.0 ACCEPTABLE PAINT MANUFACTURERS<br />
1. Asian paints<br />
2. Berger paints<br />
3. Jenson & Nicholson<br />
4. Coromandal Paints & Chemicals Ltd.<br />
5. Goodlas NEROLAC<br />
6. Shalimar paints Ltd<br />
7. Sigma Coatings<br />
8. Any other Paints manufacturers as approved by HPCL<br />
8.0 TEST CERTIFICATES<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
PAINTING<br />
2x30 microns DFT per<br />
coat ferrotol stack black<br />
paint<br />
2 x 20 micron DFT<br />
ALKYD finish paints<br />
( high gloss enamel)<br />
1x40 microns DFT<br />
acrylic polyurethane<br />
finish paint<br />
Specification no REV<br />
CEPS-TS- 13<br />
Sheet 4 <strong>of</strong> 4<br />
COLOUR<br />
CODE<br />
Aluminium<br />
Protectomatsic<br />
3 bands <strong>of</strong> 1.2<br />
meter wide red<br />
and 2 bands <strong>of</strong><br />
1.2 meter wide<br />
white<br />
Grey for<br />
structurals,<br />
light gray for<br />
hand rails<br />
ladders<br />
All paints including primers shall be accompanied with standard test certificates from<br />
the manufacturers / dealers duly signed by paint manufacturer’s representative.<br />
0
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
157<br />
TECHNICAL SPECIFICATION<br />
FOR<br />
QUALITY PLAN<br />
FOR<br />
REFRACTORY LINING<br />
0 22.08.07 ISSUED FOR TENDER G.N.R R.S.N G.C.S<br />
No DATE REVISION PREPARED BY REVIEWED BY APPROVED BY<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY PLAN FOR<br />
REFRACTORY LINING<br />
Specification no REV<br />
CEPS-TS-12<br />
Sheet 1 <strong>of</strong> 4<br />
0
1. SCOPE<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
158<br />
CONTENTS<br />
2. VERIFICATION OF REFRACTORY AND ANCHOR MATERIALS<br />
3. SURFACE PREPARATION<br />
4. SPACING, WELDING AND INSPECTION OF ANCHORS<br />
5. APPLICATION OF REFRACTORIES<br />
6. TOLERENCES<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY PLAN FOR<br />
REFRACTORY LINING<br />
Specification no REV<br />
CEPS-TS-12<br />
Sheet 1 <strong>of</strong> 4<br />
0
1.0 SCOPE This specification covers<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
159<br />
a. The verification <strong>of</strong> refractory an anchor material at fabrication yard<br />
b. Surface preparation<br />
c. Spacing welding and inspection <strong>of</strong> anchors and studs<br />
d. Various checks to be made during application <strong>of</strong> refractory brick and<br />
castables.<br />
2.0 VERIFICATION OF REFRACTORY AND ANCHOR MATERIALS AT FABRICATION YARD<br />
- Inspection / test certificates <strong>of</strong> all refractory and anchor materials shall be verified and<br />
co-relate with the actual material received at fabrication yard<br />
- In case <strong>of</strong> non-availability <strong>of</strong> Inspection certificates waiver from the client / consultant<br />
is to be verified<br />
- Refractory material with specified shelf life is to be ascertained for remaining life.<br />
3.0 SURFACE PRPARATION<br />
- Mechanical cleaning <strong>of</strong> surfaces is carried out as specified I the procedure<br />
- Casing plates are to be checked for un-evenness and undulation, rigidity and<br />
soundness joints and openings in the casing plates shall be rectified prior to start <strong>of</strong><br />
lining]<br />
4.0 SPACING, WELDING AND INSPECTION OF ANCHORS / STUDS<br />
- Anchor spacing is to be checked as per approved <strong>drawings</strong> / documents<br />
- Types <strong>of</strong> welding electrodes and specified welding procedures is to be checked<br />
- Welding quality <strong>of</strong> anchors / studs to be checked by hammer test / bent test<br />
5.0 APPLICATION OF REFRACTORIES<br />
- Refractory bricks, insulation firebricks and insulation blocks<br />
- Physical verification <strong>of</strong> bricks and blocks – vertical and horizontal joints <strong>of</strong> brick lining<br />
shall be staggered. If any gaps exist, the same shall be filled with suitable material.<br />
- In the lining area, it is to be ensured that no gaps shall exist. If any gaps exists, the<br />
same shall be filled with suitable material.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY PLAN FOR<br />
REFRACTORY LINING<br />
Specification no REV<br />
CEPS-TS-12<br />
Sheet 1 <strong>of</strong> 4<br />
0
160<br />
- Verticality and horizontality <strong>of</strong> lining surface shall be maintained<br />
- Bricks used for lining shall not be wet<br />
- Additional loads shall not be put over the lining before setting / hardening <strong>of</strong> mortar<br />
- Electrical drilling machine shall be use for making holes in bricks<br />
5.2 REFRACTORY CASTABLES<br />
6. TOLERANCE<br />
- Soundness <strong>of</strong> lining is to be ensured<br />
- Lining thickness is to be checked<br />
- Dimension <strong>of</strong> expansion joints are to be checked and cleaned before filling with<br />
packing material<br />
- Water used for mixing shall be <strong>of</strong> drinking quality<br />
- Shuttering shall be designated such that there shall be no leakage <strong>of</strong> water or<br />
castable<br />
- It is to be ensured that the castable mix is with in a temperature range <strong>of</strong> 15 to<br />
25 0 C<br />
- The time schedule for air drying water curing and heat drying shall be obtained<br />
from the supplier<br />
6.1 Castable insulation thickness ±5 mm<br />
6.2 Block insulation thickness / brick shall be as per the respective technical<br />
specification.<br />
6.3 Expansion gaps +3.0, -0.0 mm<br />
6.4 Max size <strong>of</strong> crack 3 mm wide X 38 mm deep<br />
If crack is more than the above, the same shall be repaired as per the standard<br />
procedure.<br />
COSMOS<br />
ENGINEERING<br />
PROJECT SERVICES<br />
PVT. LTD.<br />
TECHNICAL<br />
SPECIFICATION FOR<br />
QUALITY PLAN FOR<br />
REFRACTORY LINING<br />
Specification no REV<br />
CEPS-TS-12<br />
Sheet 1 <strong>of</strong> 4<br />
0
(SPECIMEN)<br />
GENERAL TERMS & CONDITIONS OF WORKS CONTRACT<br />
1 PRELIMINARY<br />
ANNEXURE - 7<br />
1.1 This is a Contract for execution <strong>of</strong> __________________ work at<br />
_______________________. (please fill up the blanks)<br />
1.2 The tenderer for the abovementioned item <strong>of</strong> work is<br />
____________________________. (please give the name and address <strong>of</strong> the<br />
tenderer)<br />
1.3 The terms and conditions mentioned hereunder are the terms and conditions<br />
<strong>of</strong> the Contract for the execution <strong>of</strong> the work mentioned under item 1.1<br />
above.<br />
1.4 It is the clear understanding between <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong><br />
<strong>Limited</strong> and the tenderer ______________________________________ that<br />
(name and address <strong>of</strong> the tenderer) in case the tender <strong>of</strong><br />
______________________________________________________________ is<br />
(name and address <strong>of</strong> the tenderer) accepted by <strong>Hindustan</strong><br />
<strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong> and an intimation to that effect is so issued and<br />
also a Purchase Order is placed with<br />
________________________________________________________<br />
(name and address <strong>of</strong> the tenderer) this document will be termed as a Contract<br />
between the parties and terms and conditions hereunder would govern the<br />
parties interest.<br />
1.5 Interpretation <strong>of</strong> Contract Documents: All documents forming part <strong>of</strong> the<br />
Contract are to be taken mutually explanatory. Should there be any<br />
discrepancy, inconsistency, error or omission in the contract, the decision <strong>of</strong> the<br />
Owner/Engineer-in-Charge/Site-in-Charge shall be the final and the contractor<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.14 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
shall abide by the decision. The decision shall not be arbitrable. Works shown<br />
upon the <strong>drawings</strong> but not mentioned in the specification or described in the<br />
specifications without being shown on the <strong>drawings</strong> shall nevertheless be deemed to be<br />
included in the same manner as if they are shown in the <strong>drawings</strong> and described in<br />
the specifications.<br />
1.6 Special conditions <strong>of</strong> Contract : The special conditions <strong>of</strong> contract, if any<br />
provided and whenever and wherever referred to shall be read in conjunction with<br />
General Terms and Conditions <strong>of</strong> contract, specifications, <strong>drawings</strong>, and any<br />
other documents forming part <strong>of</strong> this contract wherever the context so requires.<br />
Notwithstanding the subdivision <strong>of</strong> the documents into separate sections, parts<br />
volumes, every section, part or volume shall be deemed to be supplementary or<br />
complementary to each other and shall be read in whole. In case <strong>of</strong> any<br />
misunderstanding arising the same shall be referred to decision <strong>of</strong> the Owner/<br />
Engineer-in-Charge/Site-in-Charge and their decision shall be final and binding<br />
and the decision shall not be arbitrable.<br />
It is the clear understanding that wherever it is mentioned that the Contractor shall<br />
do/perform a work and/or provide facilities for the performance <strong>of</strong> the work, the<br />
doing or the performance or the providing <strong>of</strong> the facilities is at the cost and expenses <strong>of</strong><br />
the work not liable to be paid or reimbursed by the Owner.<br />
2. DEFINITIONS<br />
In this contract unless otherwise specifically provided or defined and unless a contrary<br />
intention appears from the contract the following words and expressions are used in<br />
the following meanings;<br />
2.1 The term "Agreement" wherever appearing in this document shall be read as<br />
"Contract".<br />
2.2 The "Authority" for the purpose <strong>of</strong> this Contract shall be the Chairman and<br />
Managing Director or any other person so appointed or authorised.<br />
2.3 The "Chairman and Managing Director" shall mean the Chairman and Managing<br />
Director <strong>of</strong> HINDUSTAN PETROLEUM CORPORATION LIMITED or any<br />
person so appointed, nominated or designated and holding the <strong>of</strong>fice <strong>of</strong><br />
Chairman & Managing Director.<br />
2.4 The "Change Order" means an order given in writing by the Engineer-in-Charge or by<br />
Owner to effect additions to or deletion from or alterations into the Work.<br />
2.5 The "Construction Equipment" means all appliances and equipment <strong>of</strong> whatsoever<br />
nature for the use in or for the execution, completion, operation or maintenance <strong>of</strong> the<br />
work except those intended to form part <strong>of</strong> the Permanent Work.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.15 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
2.6 The "Contract" between the Owner and the Contractor shall mean and include all<br />
documents like enquiry, tender submitted by the contractor and the purchase order<br />
issued by the owner and other documents connected with the issue <strong>of</strong> the purchase<br />
order and orders, instruction, <strong>drawings</strong>, change orders, directions issued by the<br />
Owner/Engineer-in-Charge/Site-in-Charge for the execution, completion and<br />
commissioning <strong>of</strong> the works and the period <strong>of</strong> contract mentioned in the Contract<br />
including such periods <strong>of</strong> time extensions as may be granted by the owner at the<br />
request <strong>of</strong> the contractor and such period <strong>of</strong> time for which the work is continued by<br />
the contractor for purposes <strong>of</strong> completion <strong>of</strong> the work.<br />
2.7 "The Contractor" means the person or the persons, firm or Company whose tender has<br />
been accepted by the Owner and includes the Contractor's legal heirs,<br />
representative, successor(s) and permitted assignees.<br />
2.8 The "Drawings" shall include maps, plans and tracings or prints there<strong>of</strong> with any<br />
modifications approved in writing by the Engineer-in-Charge and such other<br />
<strong>drawings</strong> as may, from time to time, be furnished or approved in writing by the<br />
Engineer-in-Charge.<br />
2.9 The "Engineer-in-Charge or Site-in-Charge" shall mean the person appointed or<br />
designated as such by the Owner and shall include those who are expressly authorised<br />
by the owner to act for and on its behalf.<br />
2.10 "The Owner" means the HINDUSTAN PETROLEUM CORPORATION<br />
LIMITED incorporated in India having its Registered <strong>of</strong>fice at PETROLEUM<br />
HOUSE, 17, JAMSHEDJI TATA ROAD, BOMBAY - 400020 and<br />
Marketing <strong>of</strong>fice at ____________________________________________ or<br />
their successors or assignees.<br />
2.11 The "Permanent Work" means and includes works which form a part <strong>of</strong> the work<br />
to be handed over to the Owner by the Contractor on completion <strong>of</strong> the contract.<br />
2.12 The "Project Manager" shall mean the Project Manager <strong>of</strong> HINDUSTAN<br />
PETROLEUM CORPORATION LIMITED, or any person so appointed,<br />
nominated or designated.<br />
2.13 The "Site" means the land on which the work is to be executed or carried out and<br />
such other place(s) for purpose <strong>of</strong> performing the Contract.<br />
2.14 The "Specifications" shall mean the various technical and other specifications<br />
attached and referred to in the tender documents. It shall also include the latest<br />
editions, including all addenda/corrigenda or relevant Indian Standard Specifications<br />
and Bureau Of Indian Standards.<br />
2.15 The "Sub-Contractor" means any person or firm or Company (other than the<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.16 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
Contractor) to whom any part <strong>of</strong> the work has been entrusted by the Contractor with the<br />
prior written consent <strong>of</strong> the Owner/Engineer-in-Charge/Site-in- Charge and<br />
their legal heirs, representatives, successors and permitted assignees <strong>of</strong> such<br />
person, firm or Company.<br />
2.16 The "Temporary Work" means and includes all such works which are a part <strong>of</strong> the<br />
contract for execution <strong>of</strong> the permanent work but does not form part <strong>of</strong> the permanent<br />
work confirming to practices, procedures applicable rules and regulations relevant in<br />
that behalf.<br />
2.17 The "Tender" means the document submitted by a person or authority for carrying out<br />
the work and the Tenderer means a person or authority who submits the tender<br />
<strong>of</strong>fering to carry out the work as per the terms and conditions.<br />
2.18 The "Work" shall mean the works to be executed in accordance with the Contract<br />
or part there<strong>of</strong> as the case may be and shall include extra, additional, altered or<br />
substituted works as maybe required for the purposes <strong>of</strong> completion <strong>of</strong> the work<br />
contemplated under the Contract.<br />
3. SUBMISSION OF TENDER<br />
3.1 Before submitting the Tender, the Tenderer shall at their own cost and expenses visit<br />
the site, examine and satisfy as to the nature <strong>of</strong> the existing roads, means <strong>of</strong><br />
communications, the character <strong>of</strong> the soil, state <strong>of</strong> land and <strong>of</strong> the excavations, the<br />
correct dimensions <strong>of</strong> the work facilities for procuring various construction and<br />
other material and their availability, and shall obtain information on all matters<br />
and conditions as they may feel necessary for the execution <strong>of</strong> the works as intended<br />
by the Owners and shall also satisfy <strong>of</strong> the availability <strong>of</strong> suitable water for<br />
construction <strong>of</strong> civil works and for drinking purpose and power required for fabrication<br />
work etc. Tenderer, whose tender may be accepted and with whom the Contract is<br />
entered into shall not be eligible and be able to make any claim on any <strong>of</strong> the said<br />
counts in what so ever manner for what so ever reasons at any point <strong>of</strong> time and such<br />
a claim shall not be raised as a dispute and shall not be arbitrable.<br />
® A pre-bid meeting may be held as per the schedule mentioned in the tender.<br />
3.2 The Tenderer shall be deemed to have satisfied fully before tendering as to the<br />
correctness and sufficiency <strong>of</strong> his tender for the works and <strong>of</strong> the rates and prices quoted<br />
in the schedule <strong>of</strong> quantities which rates and prices shall except as otherwise provided<br />
cover all his obligations under the contract.<br />
3.3 It must be clearly understood that the whole <strong>of</strong> the conditions and specifications are<br />
intended to be strictly enforced and that no work will be considered as extra work<br />
and allowed and paid for unless they are clearly outside the scope, spirit, meaning <strong>of</strong><br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.17 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
the Contract and intent <strong>of</strong> the Owner and have been so ordered in writing by<br />
Owner and/or Engineer-in-Charge/Site-in-Charge, whose decision shall be final and<br />
binding.<br />
3.4 Before filling the Tender the Contractor will check and satisfy all <strong>drawings</strong> and<br />
materials to be procured and the schedule <strong>of</strong> quantities by obtaining clarification from<br />
the Owner on all the items as may be desired by the Tenderer. No claim for any<br />
alleged loss or compensation will be entertained on this account, after submission <strong>of</strong><br />
Tender by the Tenderer/Contractor and such a claim shall not be arbitrable.<br />
®3.5 Unless specifically provided for in the tender documents or any Special Conditions,<br />
no escalation in the Tender rates or prices quoted will be permitted throughout<br />
the period <strong>of</strong> contract or the period <strong>of</strong> actual completion <strong>of</strong> the job whichever is<br />
later on account <strong>of</strong> any variation in prices <strong>of</strong> materials or cost <strong>of</strong> labour or due<br />
to any other reasons. Claims on account <strong>of</strong> escalation shall not be arbitrable.<br />
3.6 The quantities indicated in the Tender are approximate. The approved schedule <strong>of</strong> rates<br />
<strong>of</strong> the contract will be applicable for variations upto plus or minus 25% <strong>of</strong> the contract<br />
value. No revision <strong>of</strong> schedule <strong>of</strong> rates will be permitted for such variations in the<br />
contract value, including variations <strong>of</strong> individual quantities, addition <strong>of</strong> new items,<br />
alterations, additions/deletions or substitutions <strong>of</strong> items, as mentioned above.<br />
Quantities etc. mentioned and accepted in the joint measurement sheets shall alone<br />
be final and binding on the parties.<br />
3.7 Owner reserve their right to award the contract to any tenderer and their decision in<br />
this regard shall be final. They also reserve their right to reject any or all tenders<br />
received. No disputes could be raised by any tenderer(s) whose tender has been<br />
rejected.<br />
3.8 The Rates quoted by the Tenderer shall include Costs and expenses on all counts viz.<br />
cost <strong>of</strong> materials, transportation <strong>of</strong> machine(s), tools, equipments, labour,<br />
power, Administration charges, price escalations, pr<strong>of</strong>its, etc. etc. except to the<br />
extent <strong>of</strong> the cost <strong>of</strong> material(s), if any, agreed to be supplied by Owner and<br />
mentioned specifically in that regard in condition <strong>of</strong> Contract, in which case, the cost<br />
<strong>of</strong> such material if taken for preparation <strong>of</strong> the Contractor's Bill(s) shall be deducted<br />
before making payment <strong>of</strong> the Bill(s) <strong>of</strong> the Contractor. The description given in the<br />
schedule <strong>of</strong> quantities shall unless otherwise stated be held to include wastage<br />
on materials, carriage and cartage, carrying in and return <strong>of</strong> empties, hoisting,<br />
setting, fitting and fixing in position and all other expenses necessary in and for the<br />
full and complete execution and completion <strong>of</strong> works and in accordance with good<br />
practice and recognised principles in that regard.<br />
3.9 Employees <strong>of</strong> the State and Central Govt. and employees <strong>of</strong> the Public Sector<br />
Undertakings, including retired employees are covered under their respective service<br />
conditions/rules in regard to their submitting the tender. All such persons should<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.18 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
ensure compliance to the respective/applicable conditions, rules etc. etc. Any<br />
person not complying with those rules etc. but submitting the tender in violation <strong>of</strong><br />
such rules, after being so noticed shall be liable for the forfeiture <strong>of</strong> the Earnest<br />
Money Deposit made with the tender, termination <strong>of</strong> Contract and sufferance on<br />
account <strong>of</strong> forfeiture <strong>of</strong> Security Deposit and sufferance <strong>of</strong> damages arising as a<br />
result <strong>of</strong> termination <strong>of</strong> Contract.<br />
®3.10 In consideration for having a chance to be considered for entering into a contract<br />
with the Owner, the Tenderer agrees that the Tender submitted by him shall<br />
remain valid for the period prescribed in the tender conditions, from the date <strong>of</strong><br />
opening <strong>of</strong> the tender. The Tenderer shall not be entitled during the said<br />
validity period, to revoke or cancel the tender without the consent in writing<br />
from the Owner.<br />
In case the tenderer revokes or cancels the tender or varies any <strong>of</strong> terms <strong>of</strong> the tender<br />
without the Consent <strong>of</strong> the Owner, in writing, the Tenderer forfeits the right to the<br />
refund <strong>of</strong> the Earnest Money paid along with the tender.<br />
®3.11 The prices quoted by the Tenderer shall be firm during the validity period <strong>of</strong> the<br />
bid and Tenderer agrees to keep the bid alive and valid during the said period.<br />
The Tenderers shall particularly take note <strong>of</strong> this factor before submitting their<br />
tender(s).<br />
3.12 The works shall be carried out strictly as per approved specifications. Deviations, if<br />
any, shall have to be authorised by the Engineer-in-Charge/Site-in-Charge in<br />
writing prior to implementing deviations. The price benefit, if any, arising out <strong>of</strong><br />
the accepted deviation shall be passed on to the Owner. The decision <strong>of</strong><br />
Engineer-in-Charge shall be final in this matter.<br />
3.13 The contractor shall make all arrangements at his own cost to transport the required<br />
materials outside and inside the working places and leaving the premises in a neat<br />
and tidy condition after completion <strong>of</strong> the job to the satisfaction <strong>of</strong> Owner. All<br />
materials except those agreed to be supplied by the Owner shall be supplied by the<br />
contractor at his own cost and the rates quoted by the Contractor should be<br />
inclusive <strong>of</strong> all royalties, rents, taxes, duties, octroi, statutory levies, if any, etc. etc.<br />
3.14 The Contractor shall not carry on any work other than the work under this Contract<br />
within the Owners premises without prior permission in writing from the<br />
Engineer-in-Charge/Site-in-charge.<br />
3.15 The Contractor shall be bound to follow and ensure compliance to all the safety<br />
and security regulations and other statutory rules applicable to the area. In the<br />
event <strong>of</strong> any damage or loss or sufference caused due to non-observance <strong>of</strong> such<br />
rules and regulations, the contractor shall be solely responsible for the same and<br />
shall keep the Owner indemnified against all such losses and claims arising from<br />
the same.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.19 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
3.16 At any time after acceptance <strong>of</strong> tender, the Owner reserves the right to add,<br />
amend or delete any work item, the bill <strong>of</strong> quantities at a later date or reduce the<br />
scope <strong>of</strong> work in the overall interest <strong>of</strong> the work by prior discussion and intimation<br />
to the Contractor. The decision <strong>of</strong> Owner, with reasons recorded therefor, shall be<br />
final and binding on both the Owner and the Contractor. The Contractor shall not<br />
have right to claim compensation or damage etc. in that regard. The Owner<br />
reserves the right to split the work under this contract between two or more<br />
contractors without assigning any reasons.<br />
3.17 Contractor shall not be entitled to sublet, sub contract or assign, the work<br />
under this Contract without the prior consent <strong>of</strong> the Owner obtained in writing.<br />
3.18 All signatures in tender document shall be dated as well as all the pages <strong>of</strong> all<br />
sections <strong>of</strong> the tender documents shall be initialled at the lower position and<br />
signed, wherever required in the tender papers by the Tenderer or by a person<br />
holding Power <strong>of</strong> Attorney authorising him to sign on behalf <strong>of</strong> the tenderer<br />
before submission <strong>of</strong> tender.<br />
3.19 The tender should be quoted in English, both in figures as well as in words. The rates<br />
and amounts tendered by the Tenderer in the Schedule <strong>of</strong> rates for each item and in<br />
such a way that insertion is not possible. The total tendered amount should also be<br />
indicated both in figures and words with the signature <strong>of</strong> tenderer.<br />
® If some discrepancies are found between the rates given in words and figures <strong>of</strong><br />
the amount shown in the tender, the following procedure shall be applied :<br />
(a) When there is a difference between the rates in figures and words, the rate<br />
which corresponds to the amount worked out by the tenderer shall be taken<br />
as correct.<br />
(b) When the rate quoted by the tenderer in figures and words tallies but the<br />
amount is incorrect, the rate quoted by the tenderer shall be taken as<br />
correct.<br />
(c) When it is not possible to ascertain the correct rate in the manner<br />
prescribed above the rate as quoted in words shall be adopted.<br />
3.20 All corrections and alterations in the entries <strong>of</strong> tender paper will be signed in full<br />
by the tenderer with date. No erasures or over writings are permissible.<br />
3.21 Transfer <strong>of</strong> tender document by one intending tenderer to the another one is not<br />
permissible. The tenderer on whose name the tender has been sent only can quote.<br />
3.22 The Tender submitted by a tenderer if found to be incomplete in any or all<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.20 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
manner is liable to be rejected. The decision <strong>of</strong> the Owner in this regard is final<br />
and binding. In case <strong>of</strong> any error/discrepancy in the amount written in words and<br />
figures, the lower amount between the two shall prevail.<br />
4. DEPOSITS<br />
a) EARNEST MONEY DEPOSIT (EMD)<br />
The tenderer will be required to pay a sum as specified in the covering letter,<br />
as earnest money deposit alongwith the tender either thru a crossed demand<br />
draft or a non-revokable Bank Guarantee in favour <strong>of</strong> <strong>Hindustan</strong> <strong>Petroleum</strong><br />
<strong>Corporation</strong> <strong>Limited</strong>, from any Scheduled Bank (other than a Co-Operative<br />
Bank) payable at Mumbai in favour <strong>of</strong> <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong><br />
<strong>Limited</strong>, Mumbai in the pr<strong>of</strong>orma enclosed. The earnest money deposit will be<br />
refunded after finalisation <strong>of</strong> the contract.<br />
Note: Public sector enterprises and small scale units registered with National<br />
Small Scale Industries are exempted from payment <strong>of</strong> Earnest Money<br />
Deposit. Small scale units registered with National Small Scale Industries<br />
should enclose a photocopy <strong>of</strong> their registration certificate with their quotation<br />
to make their quotation eligible for consideration. The Registration Certificate<br />
should remain valid during the period <strong>of</strong> the contract that may be entered<br />
into with such successful bidder. Such tenderers should ensure validity <strong>of</strong> the<br />
Registration Certificate for the purpose.<br />
® b) SECURITY DEPOSIT:<br />
The tenderer, with whom the contract is decided to be entered into and<br />
intimation is so given will have to make a security deposit <strong>of</strong> one percent<br />
(1%) <strong>of</strong> the total contract value in the form <strong>of</strong> account payee crossed<br />
demand draft drawn in favour <strong>of</strong> the Owner, within 15 days from the date <strong>of</strong><br />
intimation <strong>of</strong> acceptance <strong>of</strong> their tender, failing which the Owner reserves the<br />
right to cancel the Contract and forfeit the EMD.<br />
1% <strong>of</strong> PO/Contract value as Security deposit will be acceptable in the form<br />
<strong>of</strong> Demand draft upto Rs. 50,000/- and in the form <strong>of</strong> Demand draft / Bank<br />
guarantee beyond Rs. 50,000/-.<br />
Composite PBG for 10% <strong>of</strong> PO value towards Security Deposit and<br />
Performance bank guarantee shall be accepted; which shall be valid upto a<br />
period <strong>of</strong> 3 months beyond the expiry <strong>of</strong> Defect liability period.<br />
Demand Draft should be drawn on Scheduled Banks, other than<br />
co-operative bank.<br />
5. EXECUTION OF WORK<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.21 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
All the works shall be executed in strict conformity with the provisions <strong>of</strong> the contract<br />
documents and with such explanatory details, <strong>drawings</strong>, specifications and instructions<br />
as may be furnished from time to time to the Contractor by the Engineer-in-Charge/<br />
Site-in-Charge, whether mentioned in the Contract or not. The Contractor shall be<br />
responsible for ensuring that works throughout are executed in the most proper and<br />
workman- like manner with the quality <strong>of</strong> material and workmanship in strict<br />
accordance with the specifications and to the entire satisfaction <strong>of</strong> the Engineer-in-<br />
Charge/Site-in-Charge.<br />
The completion <strong>of</strong> work may entail working in monsoon also. The contractor must<br />
maintain the necessary work force as may be required during monsoon and plan to<br />
execute the job in such a way the entire project is completed within the contracted<br />
time schedule. No extra charges shall be payable for such work during monsoon.<br />
It shall be the responsibility <strong>of</strong> the contractor to keep the construction work site free<br />
from water during and <strong>of</strong>f the monsoon period at his own cost and expenses.<br />
For working on Sundays/Holidays, the contractor shall obtain the necessary<br />
permission from Engineer Incharge/Site Incharge in advance. The contractor<br />
shall be permitted to work beyond the normal hours with prior approval <strong>of</strong><br />
Engineer-In-Charge/Site-In-Charge and the contractors quoted rate is inclusive <strong>of</strong> all<br />
such extended hours <strong>of</strong> working and no extra amount shall be payable by the owner on<br />
this account.<br />
5.a. SETTING OUT OF WORKS AND SITE INSTRUCTIONS<br />
5.a.1. The Engineer-in-Charge/Site-in-Charge shall furnish the Contractor with only the four<br />
corners <strong>of</strong> the work site and a level bench mark and the Contractor shall set out the<br />
works and shall provide an efficient staff for the purpose and shall be solely<br />
responsible for the accuracy <strong>of</strong> such setting out.<br />
5.a.2. The Contractor shall provide, fix and be responsible for the maintenance <strong>of</strong> all<br />
necessary stakes, templates, level marks, pr<strong>of</strong>iles and other similar things and<br />
shall take all necessary precautions to prevent their removal or disturbance and shall<br />
be responsible for consequences <strong>of</strong> such removal or disturbance should the same<br />
take place and for their efficient and timely reinstatement. The Contractor shall<br />
also be responsible for the maintenance <strong>of</strong> all existing survey marks, either existing<br />
or supplied and fixed by the Contractor. The work shall be set out to the<br />
satisfaction <strong>of</strong> the Engineer-in-Charge/Site-in-Charge. The approval there<strong>of</strong> or<br />
joining in setting out the work shall not relieve the Contractor <strong>of</strong> his responsibility.<br />
5.a.3. Before beginning the works, the Contractor shall, at his own cost, provide all<br />
necessary reference and level posts, pegs, bamboos, flags ranging rods, strings and<br />
other materials for proper layout <strong>of</strong> the work in accordance with the scheme,<br />
for bearing marks acceptable to the Engineer-in-Charge/Site-in-Charge. The<br />
Centre longitudinal or face lines and cross lines shall be marked by means <strong>of</strong> small<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.22 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
masonary pillars. Each pillar shall have distinct marks at the centre to enable<br />
theodolite to be set over it. No work shall be started until all these points are<br />
checked and approved by the Engineer-in-Charge/Site-in-Charge in writing. But<br />
such approval shall not relieve the contractor <strong>of</strong> any <strong>of</strong> his responsibilities. The<br />
Contractor shall also provide all labour, materials and other facilities, as necessary, for<br />
the proper checking <strong>of</strong> layout and inspection <strong>of</strong> the points during construction.<br />
5.a.4. Pillars bearing geodetic marks located at the sites <strong>of</strong> units <strong>of</strong> works under construction<br />
should be protected and fenced by the Contractor.<br />
5.a.5. On completion <strong>of</strong> works, the contractor shall submit the geodetic documents according<br />
to which the work was carried out.<br />
5.a.6. The Engineer-in-Charge/Site-in-Charge shall communicate or confirm his instructions<br />
to the contractor in respect <strong>of</strong> the executions <strong>of</strong> work in a "work site order book"<br />
maintained in the <strong>of</strong>fice having duplicate sheet and the authorised representative <strong>of</strong><br />
the contractor shall confirm receipt <strong>of</strong> such instructions by signing the relevant<br />
entries in the book.<br />
5.a.7. All instructions issued by the Engineer-in-Charge/Site-in-Charge shall be in writing.<br />
The Contractor shall be liable to carry out the instructions without fail.<br />
5.a.8. If the Contractor after receipt <strong>of</strong> written instruction from the Engineer-in-Charge/<br />
Site-in-Charge requiring compliance within seven days fails to comply with such<br />
<strong>drawings</strong> or 'instructions' or both as the Engineer-in-Charge/Site-in-Charge may issue,<br />
owner may employ and pay other persons to execute any such work whatsoever that<br />
may be necessary to give effect to such <strong>drawings</strong> or `instructions' and all cost and<br />
expenses incurred in connection therewith as certified by the Engineer-in-Charge/<br />
Site-in-Charge shall be borne by the contractor or may be deducted from amounts due<br />
or that may become due to the contractor under the contract or may be recovered<br />
as a debt.<br />
5.a.9. The Contractor shall be entirely and exclusively responsible for the horizontal and<br />
vertical alignment, the levels and correctness <strong>of</strong> every part <strong>of</strong> the work and shall<br />
rectify effectually any errors or imperfections therein. Such rectifications shall<br />
be carried out by the Contractor, at his own cost.<br />
5.a.10. In case any doubts arise in the mind <strong>of</strong> the Contractor in regard to any expressions,<br />
interpretations, statements, calculations <strong>of</strong> quantities, supply <strong>of</strong> material rates,<br />
etc. etc., the contractor shall refer the same to the Site-in-Charge/<br />
Engineer-in-Charge for his clarification, instructions, guidance or clearing <strong>of</strong> doubts.<br />
The decision <strong>of</strong> the Engineer-in-Charge/Site-in-Charge shall be final and the contractor<br />
shall be bound by such a decision.<br />
5.a.11. "The Contractor shall take adequate precautions, to ensure that his operations do not<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.23 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
create nuisance or misuse <strong>of</strong> the work space that shall cause unnecessary<br />
disturbance or inconvenience to others at the work site".<br />
5.a.12. "All fossils, coins articles <strong>of</strong> value <strong>of</strong> antiquity and structure or other remains <strong>of</strong><br />
geological or archaeological discovered on the site <strong>of</strong> works shall be declared to be<br />
the property <strong>of</strong> the Owner and Contractor shall take reasonable precautions to<br />
prevent his workmen or any other persons from removing or damaging any such<br />
articles or thing and shall immediately inform the Owner/<br />
Engineer-in-Charge/Site-in-Charge."<br />
5.a.13. "Contractor will be entirely and exclusively responsible to provide and<br />
maintain at his expenses all lights, guards, fencing, etc. when and where even<br />
necessary or/as required by the Engineer-in-Charge/Site-in-Charge for the<br />
protection <strong>of</strong> works or safety and convenience to all the members employed at the site<br />
or general public."<br />
5.b. COMMENCEMENT OF WORK<br />
The contractor shall after paying the requisite security deposit, commence work<br />
within 15 days from the date <strong>of</strong> receipt <strong>of</strong> the intimation <strong>of</strong> intent from the Owner<br />
informing that the contract is being awarded. The date <strong>of</strong> intimation shall be the<br />
date/day for counting the starting day/date and the ending day/date will be<br />
accordingly calculated. Penalty, if any, for the delay in execution shall be calculated<br />
accordingly.<br />
Contractor should prepare detailed fortnightly construction programme for<br />
approval by the Engineer-in-Charge within one month <strong>of</strong> receipt <strong>of</strong> Letter Of Intent.<br />
The work shall be executed strictly as per such time schedule. The period <strong>of</strong><br />
Contract includes the time required for testing, rectifications, if any, re-testing and<br />
completion <strong>of</strong> work in all respects to the entire satisfaction <strong>of</strong> the Engineer-in-Charge.<br />
A Letter <strong>of</strong> Intent is an acceptance <strong>of</strong> <strong>of</strong>fer by the Owner and it need not be accepted<br />
by the contractor. But the contractor should acknowledge a receipt <strong>of</strong> the purchase<br />
order within 15 days <strong>of</strong> mailing <strong>of</strong> Purchase Order and any delay in acknowledging the<br />
receipt will be a breach <strong>of</strong> contract and compensation for the loss caused by such breach<br />
will be recovered by the Owner by forfeiting earnest money deposit/bid bond.<br />
5.c. SUBLETTING OF WORK<br />
5.c.1. No part <strong>of</strong> the contract nor any share or interest there<strong>of</strong> shall in any manner or<br />
degree be transferred, assigned or sublet, by the Contractor, directly or indirectly<br />
to any firm or corporation whatsoever, without the prior consent in writing <strong>of</strong> the<br />
Owner.<br />
5.c.2. At the commencement <strong>of</strong> every month the Contractor shall furnish to the<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.24 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
Engineer-in-charge/Site-in-Charge <strong>list</strong> <strong>of</strong> all sub-contractors or other persons or<br />
firms engaged by the Contractor.<br />
5.c.3 The contract agreement will specify major items <strong>of</strong> supply or services for which the<br />
Contractor proposes to engage sub-Contractor/sub-Vendor. The contractor may from<br />
time to time propose any addition or deletion from any such <strong>list</strong> and will submit the<br />
proposals in this regard to the Engineer-in-charge/Designated <strong>of</strong>ficer-in-charge for<br />
approval well in advance so as not to impede the progress <strong>of</strong> work. Such approval <strong>of</strong><br />
the Engineer-in-charge/Designated <strong>of</strong>ficer-in-charge will not relieve the contractor<br />
from any <strong>of</strong> his obligations, duties and responsibilities under the contract.<br />
5.c.4. Notwithstanding any sub-letting with such approval as resaid and notwithstanding<br />
that the Engineer-in-Charge shall have received copies <strong>of</strong> any sub-contract, the<br />
Contractor shall be and shall remain solely to be responsible for the quality and proper<br />
and expeditious execution <strong>of</strong> the works and the performance <strong>of</strong> all the conditions <strong>of</strong><br />
the contract in all respects as if such subletting or sub-contracting had not taken<br />
place and as if such work had been done directly by the Contractor.<br />
5.c.5 Prior approval in writing <strong>of</strong> the Owner shall be obtained before any change is made in<br />
the constitution <strong>of</strong> the contractor/Contracting agency otherwise contract shall be<br />
deemed to have been allotted in contravention <strong>of</strong> clause entitled “sub-letting <strong>of</strong><br />
works” and the same action may be taken and the same consequence shall ensue as<br />
provided in the clause <strong>of</strong> “sub- letting <strong>of</strong> works”.<br />
5.d EXTENSION OF TIME<br />
® 1) If the Contractor anticipates that he will not be able to complete the work<br />
within the contractual delivery/ completion date (CDD), then the Contractor<br />
shall make a request for grant <strong>of</strong> time extension clearly specifying the<br />
reasons for which he seeks extension <strong>of</strong> time and demonstrating as to how<br />
these reasons were beyond the control <strong>of</strong> the contractor or attributable to<br />
the Owner. This request should be made well before the expiry <strong>of</strong> the<br />
Contractual Delivery/ Completion Date (CDD).<br />
2) If such a request for extension is received with a Bank Guarantee for the full<br />
Liquidated Damages amount calculated on the Total Contract Value, the<br />
concerned General Manager <strong>of</strong> the Owner shall grant a Provisional<br />
extension <strong>of</strong> time, pending a decision on the request.<br />
3) The concerned General Manager <strong>of</strong> the Owner shall expeditiously decide<br />
upon the request for time extension and in any case not later than 6 months<br />
from the CDD or date <strong>of</strong> receipt <strong>of</strong> the request, whichever is later.<br />
4) Grant <strong>of</strong> any extension <strong>of</strong> time shall be by means <strong>of</strong> issuance <strong>of</strong> a<br />
Change Order.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.25 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
5) In order to avoid any cash crunch to the Contractor, a Bank Guarantee<br />
could be accepted against LD, as stated above. Once a decision is taken, the<br />
LD shall be recovered from any pending bills or by encashment <strong>of</strong> the BG.<br />
Any balance sum <strong>of</strong> Contractor or the BG (if LD is fully recovered from the<br />
bills) shall be promptly refunded/returned to the Contractor.<br />
5.e. SUSPENSION OF WORKS<br />
5.e.1. Subject to the provisions <strong>of</strong> this contract, the contractor shall if ordered in writing<br />
by the Engineer- in-Charge/Site-in-Charge for reasons recorded suspend the works<br />
or any part there<strong>of</strong> for such period and such time so ordered and shall not, after<br />
receiving such, proceed with the work therein ordered to uspended until he shall have<br />
received a written order to re-start. The Contractor shall be entitled to claim<br />
extension <strong>of</strong> time for that period <strong>of</strong> time the work was ordered to be suspended.<br />
Neither the Owner nor the Contractor shall be entitled to claim compensation or<br />
damages on account <strong>of</strong> such an extension <strong>of</strong> time.<br />
5.e.2. In case <strong>of</strong> suspension <strong>of</strong> entire work, ordered in writing by<br />
Engineer-in-Charge/Site-in-Charge, for a period <strong>of</strong> 30 days, the Owner shall<br />
havethe option to terminate the Contract as provided under the clause fortermination.<br />
The Contractor shall not be at liberty to remove from the site <strong>of</strong> the works any<br />
plant or materials belonging to him and the Employer shall have lien upon all such<br />
plant and materials.<br />
5.e.3. The contract shall, in case <strong>of</strong> suspension have the right to raise a dispute and have<br />
the same arbitrated but however, shall not have the right to have the work stopped<br />
from further progress and completion either by the owner or through other contractor<br />
appointed by the owner.<br />
5.f. OWNER MAY DO PART OF WORK<br />
Not withstanding anything contained elsewhere in this contract, the owner upon<br />
failure <strong>of</strong> the Contractor to comply with any instructions given in accordance with<br />
the provisions <strong>of</strong> this contract, may instead <strong>of</strong> Contract and undertaking charge<br />
<strong>of</strong> entire work, place additional labour force, tools, equipment and materials on<br />
such parts <strong>of</strong> the work, as the Owner may decide or engage another Contractor to<br />
carryout the balance <strong>of</strong> work. In such cases, the Owner shall have the right to deduct<br />
from the amounts payable to the Contractor the difference in cost <strong>of</strong> such work and<br />
materials with ten percent overhead added to cover all departmental charges.<br />
Should the total amount there<strong>of</strong> exceed the amount due to the contractor, the<br />
Contractor shall pay the difference to the Owner within 15 days <strong>of</strong> making demand for<br />
payment failing which the Contractor shall be liable to pay interest at 24% p.a. on<br />
such amounts till the date <strong>of</strong> payment.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.26 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
5.g. INSPECTION OF WORKS<br />
5.g.1. The Engineer-in-Charge/Site-in-Charge and Officers from Central or State<br />
Government will have full power and authority to inspect the works at any time<br />
wherever in progress, either on the site or at the Contractor's premises/workshops<br />
<strong>of</strong> any person, firm or corporation where work in connection with the contract may<br />
be in hand or where the materials are being or are to be supplied, and the<br />
Contractor shall afford or procure for the Engineer-in-Charge/Site-in-Charge<br />
every facility and assistance to carryout such inspection. The Contractor shall, at all<br />
times during the usual working hours and at all other times at which reasonable<br />
notice <strong>of</strong> the intention <strong>of</strong> the Engineer-in-Charge/Site-in-Charge or his representative<br />
to visit the works shall have been given to the Contractor, either himself be<br />
present to receive orders and instructions, or have a responsible agent, duly<br />
accredited in writing, present for the purpose. Orders given to the Contractor's agent<br />
shall be considered to have the same force as if they had been given to the<br />
Contractor himself. The Contractor shall give not less than seven days notice in<br />
writing to the Engineer-in-Charge/Site-in-Charge before covering up or otherwise<br />
placing beyond reach <strong>of</strong> inspection and measurement any work in order that the<br />
same may be inspected and measured. In the event <strong>of</strong> breach <strong>of</strong> above, the same<br />
shall be uncovered at Contractor's expense for carrying out such measurement and/or<br />
inspection.<br />
5.g.2. No material shall be removed and despatched by the Contractor from the site<br />
without the prior approval in writing <strong>of</strong> the Engineer-in-charge. The contractor is to<br />
provide at all times during the progress <strong>of</strong> the work and the maintenance period proper<br />
means <strong>of</strong> access with ladders, gangways, etc. and the necessary attendance to move<br />
and adapt as directed for inspection or measurements <strong>of</strong> the works by the<br />
Engineer-in-Charge/Site-in-Charge.<br />
5.h. SAMPLES<br />
5.h.1. The contractor shall furnish to the Engineer-in-charge/Site-in-Charge for approval<br />
when requested or required adequate samples <strong>of</strong> all materials and finishes to be used<br />
in the work.<br />
5.h.2. Samples shall be furnished by the Contractor sufficiently in advance and before<br />
commencenent <strong>of</strong> the work so as the Owner can carry out tests and<br />
examinations there<strong>of</strong> and approve or reject the samples for use in the works. All<br />
material samples furnished and finally used/applied in actual work shall fully be <strong>of</strong><br />
the same quality <strong>of</strong> the approved samples.<br />
5.i. TESTS FOR QUALITY OF WORK<br />
5.i.1. All workmanship shall be <strong>of</strong> the respective kinds described in the contract<br />
documents and in accordance with the instructions <strong>of</strong> the Engineer-in-Charge /<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.27 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
Site-in- Charge and shall be subjected from time to time to such tests at Contractor's<br />
cost as the Engineer-in-Charge/Site-in-Charge may direct at the place <strong>of</strong><br />
manufacture or fabrication or on the site or at all or any such places. The<br />
Contractor shall provide assistance, instruments, labour and materials as are<br />
normally required for examining, measuring and testing any workmanship as may be<br />
selected and required by the Engineer-in-Charge/Site-in-Charge.<br />
5.i.2. All the tests that will be necessary in connection with the execution <strong>of</strong> the work as<br />
decided by the Engineer-in- charge/Site-in-Charge shall be carried out at the<br />
contractors cost and expenses.<br />
5.i.3. If any tests are required to be carried out in connection with the work or<br />
materials or workmanship to be supplied by the owner, such tests shall be carried out<br />
by the Contractor as per instructions <strong>of</strong> Engineer-in-Charge/Site-in-Charge and<br />
expenses for such tests, if any, incurred by the contractor shall be reimbursed by<br />
the Owner. The contractor should file his claim with the owner within 15<br />
(fifteen) days <strong>of</strong> inspection/test and any claim made beyond that period shall<br />
lapse and be not payable.<br />
5.j. ALTERATIONS AND ADDITIONS TO SPECIFICATIONS, DESIGNS<br />
AND WORKS<br />
5.j.1. The Engineer-in-Charge/Site-in-Charge shall have powers to make any alterations,<br />
additions and/or substitutions to the schedule <strong>of</strong> quantities, the original specifications,<br />
<strong>drawings</strong>, designs and instructions that may become necessary or advisable or<br />
during the progress <strong>of</strong> the work and the Contractor shall be bound to carryout such<br />
altered/extra/new items <strong>of</strong> work in accordance with instructions which may be given<br />
to him in writing signed by the Engineer-in-Charge/Site- in-Charge. Such alterations,<br />
omissions, additions or substitutions shall not invalidate the contract. The altered,<br />
additional or substituted work which the Contractor may be directed to carryon in the<br />
manner as part <strong>of</strong> the work shall be carried out by the Contractor on the same<br />
conditions in all respects on which he has agreed to do the work. The time for<br />
completion <strong>of</strong> such altered added and/or substituted work may be extended for that<br />
part <strong>of</strong> the particular job. The rates for such additional altered or substituted<br />
work under this Clause shall, be worked out in accordance with the following<br />
provisions:<br />
5.j.2. If the rates for the additional, altered or substituted work are specified in the contract<br />
for similar class <strong>of</strong> work, the Contractor is bound to carryout the additional,<br />
altered or substituted work at the same rates as are specified in the contract.<br />
5.j.3. If the rates for the additional, altered or substituted work are not specifically provided<br />
in the contract for the work, the rates will be derived from the rates for similar class<br />
<strong>of</strong> work as are specified in the contract for the work. In the opinion <strong>of</strong> the<br />
Engineer-in- Charge/Site-in-Charge as to whether or not the rates can be<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.28 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
easonably so derived from the items in this contract, will be final and binding on the<br />
Contractor.<br />
5.j.4. If the rates for the altered, additional or substituted work cannot be determined in the<br />
manner specified above, then the Contractor shall, within seven days <strong>of</strong> the date <strong>of</strong><br />
receipt <strong>of</strong> order to carry out the work, inform the Engineer-in-Charge/<br />
Site-in-Charge <strong>of</strong> the rate at which he intends to charge for such class <strong>of</strong> work,<br />
supported by analysis <strong>of</strong> the rate or rates claimed and the Engineer-In-Charge/<br />
Site-in-Charge shall determine the rates on the basis <strong>of</strong> the prevailing market rates<br />
for both material and labour plus 10% to cover overhead and pr<strong>of</strong>it <strong>of</strong> labour rates and<br />
pay the Contractor accordingly. The opinion <strong>of</strong> the Engineer-in-<br />
Charge/Site-in-Charge as to current market rates <strong>of</strong> materials and the quantum <strong>of</strong><br />
labour involved per unit <strong>of</strong> measurement will be final and binding on the<br />
contractor.<br />
5.j.5. The quantities indicated in the Tender are approximate. The approved schedule <strong>of</strong><br />
rates <strong>of</strong> the contract will be applicable for variations <strong>of</strong> upto +25% <strong>of</strong> the estimated<br />
contract value. No revision <strong>of</strong> schedule <strong>of</strong> rates will be permitted for such variations<br />
in the contract value, even for variations <strong>of</strong> individual quantities, addition <strong>of</strong> new<br />
items, alterations, additions/deletions or substitutions <strong>of</strong> items, as mentioned above.<br />
5.j.6. In case <strong>of</strong> any item <strong>of</strong> work for which there is no specification supplied by the<br />
Owner and is mentioned in the tender documents, such work shall be carried out in<br />
accordance with Indian Standard Specifications and if the Indian Standard<br />
Specifications do not cover the same, the work should be carried out as per standard<br />
Engineering Practice subject to the approval <strong>of</strong> the Engineer-in-Charge/ Site-in-Charge.<br />
5.k. PROVISIONAL ACCEPTANCE<br />
Acceptance <strong>of</strong> sections <strong>of</strong> the works for purposes <strong>of</strong> equipment erection, piping,<br />
electrical work and similar usages by the Owner and payment for such work or parts<br />
<strong>of</strong> work shall not constitute a waiver <strong>of</strong> any portion <strong>of</strong> this contract and shall not be<br />
construed so as to prevent the Engineer from requiring replacement <strong>of</strong> defective<br />
work that may become apparent after the said acceptance and also shall not absolve<br />
the Contractor <strong>of</strong> the obligations under this contract. It is made clear that such an<br />
acceptance does not indicate or denote or establish to the fact <strong>of</strong> execution <strong>of</strong> that<br />
work or the Contract until the work is completed in full in accordance with the<br />
provisions <strong>of</strong> this Contract.<br />
5.l. COMPLETION OF WORK AND COMPLETION CERTIFICATE<br />
As soon as the work is completed in all respects, the contractor shall give notice <strong>of</strong><br />
such completion to the site in charge or the Owner and within thirty days <strong>of</strong> receipt<br />
<strong>of</strong> such notice the site in charge shall inspect the work and shall furnish the<br />
contractor with a certificate <strong>of</strong> completion indicating:<br />
a) defects, if any, to be rectified by the contractor<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.29 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
) items, if any, for which payment shall be made in reduced rates<br />
c) the date <strong>of</strong> completion.<br />
5.m. USE OF MATERIALS AND RETURN OF SURPLUS MATERIALS<br />
5.m.1. Notwithstanding anything contained to the contrary in any or all <strong>of</strong> the clauses <strong>of</strong> this<br />
contract, where any materials for the execution <strong>of</strong> the contract are procured with<br />
the assistance <strong>of</strong> Government either by issue from Government stocks or purchase<br />
made under orders or permits or licences issued by Government, the contractor shall<br />
use the said materials economically and solely for the purpose <strong>of</strong> the contract and<br />
shall not dispose them <strong>of</strong> without the permission <strong>of</strong> the Owner.<br />
5.m.2. All surplus(serviceable) or unserviceable materials that may be left over after the<br />
completion <strong>of</strong> the contract or at its termination for any reason whatsoever, the<br />
Contractor shall deliver the said product to the Owner without any demur. The price<br />
to be paid to the Contractor, if not already paid either in full or in part, however,<br />
shall not exceed the amount mentioned in the Schedule <strong>of</strong> Rates for such material<br />
and in cases where such rates are not so mentioned, shall not exceed the CPWD<br />
scheduled rates. In the event <strong>of</strong> breach <strong>of</strong> the aforesaid condition the contractor<br />
shall become liable for contravention <strong>of</strong> the terms <strong>of</strong> the Contract.<br />
5.m.3. The surplus (serviceable) and unserviceable products shall be determined by joint<br />
measurement. In case where joint measurement has failed to take place, the Owner<br />
may measure the same and determine the quantity.<br />
5.m.4. It is made clear that the Owner shall not be liable to take stock and keep possession<br />
and pay for the surplus and unserviceable stocks and the Owner may direct the<br />
Contractor to take back such material brought by the Contractor and becoming<br />
surplus and which the Owner may decide to keep and not to pay for the same.<br />
5.n. DEFECT LIABILITY PERIOD<br />
The contractor shall guarantee the work executed for a period <strong>of</strong> 12 months from the<br />
date <strong>of</strong> completion <strong>of</strong> the job. Any damage or defect that may arise or lie<br />
undiscovered at the time <strong>of</strong> completion <strong>of</strong> the job shall be rectified or replaced by the<br />
contractor at his own cost. The decision <strong>of</strong> the Engineer<br />
In-charge/Site-Incharge/Owner shall be the final in deciding whether the defect has<br />
to be rectified or replaced.<br />
Equipment or spare parts replaced under warranty/guarantees shall have further<br />
warranty for a mutually agreed period from the date <strong>of</strong> acceptance.<br />
The owner shall intimate the defects noticed in writing by a Registered A.D. letter or<br />
otherwise and the contractor within 15 days <strong>of</strong> receipt <strong>of</strong> the intimation shall start<br />
the rectification work and complete within the time specified by the owner failing<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.30 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
which the owner will get the defects rectified by themselves or by any other<br />
contractor and the expenses incurred in getting the same done shall be paid by the<br />
Contractor under the provision <strong>of</strong> the Contract.<br />
Thus, defect liability is applicable only in case <strong>of</strong> job/works contract (civil,<br />
mechanical, electrical, maintenance etc. ) where any damage <strong>of</strong> defect may arise in<br />
future (i.e. within 12 months from the date <strong>of</strong> completion <strong>of</strong> job) or lie<br />
undiscovered at the time <strong>of</strong> completion <strong>of</strong> job.<br />
In other words, in case <strong>of</strong> service contracts (like car hire etc.) where there is no<br />
question <strong>of</strong> damage or defect arising in future, the defect liability clause is not<br />
applicable.<br />
5.o. DAMAGE TO PROPERTY<br />
5.o.1. Contractor shall be responsible for making good to the satisfaction <strong>of</strong> the Owner any<br />
loss <strong>of</strong> and any damage to all structures and properties belonging to the Owner or being<br />
executed or procured by the Owner or <strong>of</strong> other agencies within the premises <strong>of</strong> the<br />
work <strong>of</strong> the Owner, if such loss or damage is due to fault and/or the negligence or<br />
willful acts or omission <strong>of</strong> the Contractor, his employees, agents, representatives<br />
or sub-contractors.<br />
5.o.2. The Contractors shall indemnify and keep the Owner harmless <strong>of</strong> all claims for<br />
damage to Owner's property arising under or by reason <strong>of</strong> this contract.<br />
6. DUTIES AND RESPONSIBILITIES OF CONTRACTOR<br />
6.a. EMPLOYMENT LIABILITY TOWARDS WORKERS EMPLOYED BY THE<br />
CONTRACTOR<br />
6.a.1 The Contractor shall be solely and exclusively responsible for engaging or<br />
employing persons for the execution <strong>of</strong> work. All persons engaged by the<br />
contractor shall be on Contractor's payroll and paid by Contractor. All disputes or<br />
differences between the Contractor and his/their employees shall be settled by<br />
Contractor.<br />
6.a.2. Owner has absolutely no liability whatsoever concerning the employees <strong>of</strong> the<br />
Contractor. The Contractor shall indemnify Owner against any loss or damage or<br />
liability arising out <strong>of</strong> or in the course <strong>of</strong> his/their employing persons or relation<br />
with his/their employees. The Contractor shall make regular and full payment <strong>of</strong><br />
wages and on any complaint by any employee <strong>of</strong> the Contractor or his sub<br />
contractor regarding non-payment <strong>of</strong> wages, salaries or other dues, Owner reserves<br />
the right to make payments directly to such employees or sub- contractor <strong>of</strong> the<br />
Contractor and recover the amount in full from the bills <strong>of</strong> the Contractor and<br />
the contractor shall not claim any compensation or reimbursement there<strong>of</strong>.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.31 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
The Contractor shall comply with the Minimum Wages Act applicable to the area<br />
<strong>of</strong> work site with regard to payment <strong>of</strong> wages to his employees and also to<br />
employees <strong>of</strong> his sub contractor.<br />
6.a.3. The Contractor shall advise in writing or in such appropriate way to all <strong>of</strong> his<br />
employees and employees <strong>of</strong> sub-contractors and any other person engaged by him<br />
that their appointment/employment is not by the Owner but by the Contractor and<br />
that their present appointment is only in connection with the construction contract<br />
with Owner and that therefore, such an employment/appointment would not<br />
enable or make them eligible for any employment/appointment with the Owner<br />
either temporarily or/and permanent basis.<br />
6.b. NOTICE TO LOCAL BODIES<br />
The contractor shall comply with and give all notices required under any<br />
Government authority, instruction, rule or order made under any act <strong>of</strong> parliament,<br />
state laws or any regulations or by-laws <strong>of</strong> any local authority relating to the<br />
works.<br />
6.c. FIRST AID AND INDUSTRIAL INJURIES<br />
6.c.1 Contractor shall maintain first aid facility for his employees and those <strong>of</strong> his<br />
sub-contractors.<br />
6.c.2. Contractor shall make arrangements for ambulance service and for the treatment<br />
<strong>of</strong> all types <strong>of</strong> injuries. Names and telephone numbers <strong>of</strong> those providing such<br />
services shall be furnished to Owner prior to start <strong>of</strong> construction and their name<br />
board shall be prominently displayed in Contractor's field <strong>of</strong>fice.<br />
6.c.3. All industrial injuries shall be reported promptly to owner and a copy <strong>of</strong> contractor's<br />
report covering each personal injury requiring the attention <strong>of</strong> a physician shall be<br />
furnished to the Owner.<br />
6.d. SAFETY CODE<br />
6.d.1. The Contractor shall at his own expenses arrange for the Safety provisions as may<br />
be necessary for the execution <strong>of</strong> the work or as required by the<br />
Engineer-in-Charge in respect <strong>of</strong> all labours directly or indirectly employed for<br />
performance <strong>of</strong> the works and shall provide all facilities in connections<br />
therewith. In case the contractor fails to make arrangements and provide<br />
necessary facilities as aforesaid, the Owner shall be entitled to do so and recover the<br />
cost there<strong>of</strong> from the Contractor.<br />
6.d.2. From the commencement to the completion <strong>of</strong> the works, the contractor shall take<br />
full responsibility for the care there<strong>of</strong> and <strong>of</strong> all the temporary works (defined as<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.32 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
meaning all temporary works <strong>of</strong> every kind required in or for the execution,<br />
completion or maintenance <strong>of</strong> the works). In case damage, loss or injury shall<br />
happen to the works or to any part there<strong>of</strong> or to temporary works or to any cause<br />
whatsoever repair at his (Contractor's) own cost and make good the same so that at<br />
the time <strong>of</strong> completion, the works shall be in good order and condition and in<br />
conformity in every respect with the requirement <strong>of</strong> the contract and<br />
Engineer-in-Charge's instructions.<br />
6.d.3. In respect <strong>of</strong> all labour, directly or indirectly employed in the work for the<br />
performance <strong>of</strong> the Contractor's part <strong>of</strong> this agreement, the contractor shall at his<br />
own expense arrange for all the safety provisions as per relevant Safety Codes <strong>of</strong><br />
C.P.W.D Bureau <strong>of</strong> Indian Standards, the Electricity Act/I.E. Rules. The Mines<br />
Act and such other Acts as applicable.<br />
6.d.4. The Contractor shall observe and abide by all fire and safety regulations <strong>of</strong> the<br />
Owner. Before starting construction work, the Contractor shall consult with<br />
Owner's Safety Engineer or Engineer-in-Charge/Site-in-Charge and must make good<br />
to the satisfaction <strong>of</strong> the Owner any loss or damage due to fire to any portion <strong>of</strong> the<br />
work done or to be done under this agreement or to any <strong>of</strong> the Owner's existing<br />
property.<br />
6.d.5. The Contractor will be fully responsible for complying with all relevant provisions <strong>of</strong><br />
the Contract Labour Act and shall pay rates <strong>of</strong> Wages and observe hours <strong>of</strong><br />
work/conditions <strong>of</strong> employment according to the rules in force from time to time.<br />
6.d.6. The Contractor will be fully responsible for complying with the provision including<br />
documentation and submission <strong>of</strong> reports on the above to the concerned<br />
authorities and shall indemnify the <strong>Corporation</strong> from any such lapse for which the<br />
Government will be taking action against them.<br />
6.d.7. Owner shall on a report having been made by an inspecting Office as defined in<br />
the Contract Labour Regulations have the power to deduct from the money due to<br />
the Contractor any sum required or estimated to be required for making good the<br />
loss suffered by a worker(s) by reasons <strong>of</strong> non-fulfillment <strong>of</strong> conditions <strong>of</strong> contract<br />
for the benefit <strong>of</strong> workers no-payment <strong>of</strong> wages or <strong>of</strong> deductions made from his or<br />
their wages which are not justified by the terms <strong>of</strong> contract or non observance <strong>of</strong> the<br />
said contractor's labour Regulation.<br />
6.e. INSURANCE AND LABOUR<br />
Contractor shall at his own expense obtain and maintain an insurance policy with a<br />
Nationalised Insurance Company to the satisfaction <strong>of</strong> the Owner as provided<br />
hereunder.<br />
6.e.1. EMPLOYEES STATE INSURANCE ACT<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.33 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
i. The Contractor agrees to and does hereby accept full and exclusive liability for<br />
the compliance with all obligations imposed by Employees State Insurance Act,<br />
1948, and the Contractor further agrees to defend indemnify and hold Owner<br />
harmless from any liability or penalty which may be imposed by the Central, State<br />
or local authority by reason <strong>of</strong> any asserted violation by Contractor, or<br />
sub-contractor <strong>of</strong> the Employees' State Insurance Act, 1948 and also from all<br />
claims, suits or proceedings that may be brought against the Owner arising<br />
under, growing out <strong>of</strong> or by reason <strong>of</strong> the work provided for by this contract<br />
whether brought by employees <strong>of</strong> the Contractor, by third parties or by Central<br />
or State Government authority or any political sub-division there<strong>of</strong>.<br />
ii. The Contractor agrees to file with the Employees State Insurance <strong>Corporation</strong>, the<br />
Declaration forms and all forms which may be required in respect <strong>of</strong> the<br />
Contractor's or sub-contractor's employee whose aggregate emuneration is<br />
within the specified limit and who are employed in the work provided or those<br />
covered by ESI Act under any amendment to the Act from time to time.<br />
The Contractor shall deduct and secure the agreement <strong>of</strong> the sub-contractor to<br />
deduct the employee's contribution as per the first schedule <strong>of</strong> the Employee's<br />
State Insurance Act from wages and affix the employee's contribution cards at<br />
wages payment intervals. The Contractor shall remit and secure the agreement<br />
<strong>of</strong> the sub contractor to remit to the State Bank <strong>of</strong> India, Employee's State<br />
Insurance <strong>Corporation</strong> Account, the Employee's contribution as required by the<br />
Act.<br />
iii. The Contractor agrees to maintain all records as required under the Act in<br />
respect <strong>of</strong> employees and payments and the Contractor shall secure the<br />
agreement <strong>of</strong> the sub contractor to maintain such records. Any expenses<br />
incurred for the contributions, making contribution or maintaining records shall<br />
be to the Contractor's or sub-contractor's account.<br />
iv. The Owner shall retain such sum as may be necessary from the total contract<br />
value until the Contractor shall furnish satisfactory pro<strong>of</strong> that all contributions<br />
as required by the Employees State Insurance Act, 1948, have been paid.<br />
v. WORKMAN'S COMPENSATION AND EMPLOYEE'S LIABILITY<br />
INSURANCE<br />
Provide Insurance for all the Contractor's employees engaged in the performance<br />
<strong>of</strong> this contract. If any <strong>of</strong> the work is sublet, the Contractor shall ensure that the<br />
sub contractor provides workmen's compensation and Employer's Liability<br />
Insurance for the latter's employees who are not covered under the Contractor's<br />
insurance.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.34 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
vi. AUTOMOBILE LIABILITY INSURANCE<br />
Contractor shall take out an Insurance to cover all risks to Owner for each <strong>of</strong> his<br />
vehicles plying on works <strong>of</strong> this contract and these insurances shall be valid for<br />
the total contract period. No extra payment will be made for this insurance.<br />
Owner shall not be liable for any damage or loss not made good by the Insurance<br />
Company, should such damage or loss result from unauthorised use <strong>of</strong> the<br />
vehicle. The provisions <strong>of</strong> the Motor Vehicle Act would apply.<br />
vii. FIRE INSURANCE<br />
Contractor shall within two weeks after award <strong>of</strong> contract insure the Works,<br />
Plant and Equipment and keep them insured until the final completion <strong>of</strong> the<br />
Contract against loss or damage by accident, fire or any other cause with an<br />
insurance company to be approved by the Employer/Consultant in the joint names<br />
<strong>of</strong> the Employer and the Contractor (name <strong>of</strong> the former being placed first in<br />
the Policy). Such Policy shall cover the property <strong>of</strong> the Employer only.<br />
6.e.2. ANY OTHER INSURANCE REQUIRED UNDER LAW OR REGULATION OR<br />
BY OWNER<br />
i. Contractor shall also provide and maintain any and all other insurance which<br />
may be required under any law or regulations from time to time. He shall also<br />
carry and maintain any other insurance which may be required by the Owner.<br />
ii. The aforesaid insurance policy/policies shall provide that they shall not be<br />
cancelled till the Engineer-in-Charge has agreed to their cancellation.<br />
iii. The Contractor shall satisfy to the Engineer-in-Charge/Site-in-Charge from<br />
time to time that he has taken out all insurance policies referred to above and<br />
has paid the necessary premium for keeping the policies alive till the expiry <strong>of</strong><br />
the defects liability period.<br />
iv. The contractor shall ensure that similar insurance policies are taken out by<br />
his sub-contractor (if any) and shall be responsible for any claims or losses to<br />
the Owner resulting from their failure to obtain adequate insurance<br />
protections in connection there<strong>of</strong>. The contractor shall produce or cause to be<br />
proceed by his sub-contractor (if any) as the case may be, the relevant policy<br />
or policies and premium receipts as and when required by the<br />
Engineer-in-Charge/Site-in-Charge.<br />
6.e.3. LABOUR AND LABOUR LAWS<br />
i. The contractor shall at his own cost employ persons during the period <strong>of</strong><br />
contract and the persons so appointed shall not be construed under any<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.35 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
circumstances to be in the employment <strong>of</strong> the Owner.<br />
ii. All payments shall be made by the contractor to the labour employed by him<br />
in accordance with the various rules and regulations stated above. The<br />
contractor shall keep the Owner indemnified from any claims whatsoever<br />
inclusive <strong>of</strong> damages/costs or otherwise arising from injuries or alleged<br />
injuries to or death <strong>of</strong> a person employed by the contractor or damages or<br />
alleged damages to the property.<br />
iii. No labour below the age <strong>of</strong> eighteen years shall be employed on the work.<br />
The Contractor shall not pay less than what is provided under the provisions <strong>of</strong><br />
the contract labour (Regulations and Abolition) Act, 1970 and the rules made<br />
thereunder and as may be amended from time to time. He shall pay the<br />
required deposit under the Act appropriate to the number <strong>of</strong> workman to be<br />
employed by him or through sub contractor and get himself registered under<br />
the Act. He shall produce the required Certificates to the Owner before<br />
commencement <strong>of</strong> the work. The Owner recognises only the Contractor and<br />
not his sub contractor under the provisions <strong>of</strong> the Act. The Contractor will<br />
have to submit daily a <strong>list</strong> <strong>of</strong> his workforce. He will also keep the wage<br />
register at the work site or/and produce the same to the Owner, whenever<br />
desired. A deposit may be taken by the Owner from the Contractor to be<br />
refunded only after the Owner is satisfied that all workmen employed by<br />
the Contractor have been fully paid for the period <strong>of</strong> work in Owner's premises<br />
at rates equal to or better than wages provided for under the Minimum Wages<br />
Act. The contractor shall be responsible and liable for any complaints that<br />
may arise in this regard and the consequences thereto.<br />
iv. The Contractor will comply with the provisions <strong>of</strong> the Employee's Provident<br />
Fund Act and the Family Pension Act as may be applicable and as amended<br />
from time to time.<br />
v. The Contractor will comply with the provisions <strong>of</strong> the payment <strong>of</strong> Gratuity Act,<br />
1972, as may be applicable and as amended from time to time.<br />
vi. IMPLEMENTATION OF APPRENTICES ACT, 1961<br />
The Contractor shall comply with the provisions <strong>of</strong> the Apprentices Act, 1961<br />
and the Rules and Orders issued thereunder from time to time. If he fails to<br />
do so, his failure will be a breach <strong>of</strong> the contract and the Engineer-in-Charge<br />
may, at his discretion, cancel the contract. The Contractor shall also be liable<br />
for any pecuniary liability arising on account <strong>of</strong> any violation by him <strong>of</strong> the<br />
provision <strong>of</strong> the Act.<br />
vii. MODEL RULES FOR LABOUR WELFARE<br />
The Contractor shall at his own expenses comply with or cause be complied<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.36 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
with Model rules for Labour Welfare as appended to those conditions or rules<br />
framed by the Government from time to time for the protection <strong>of</strong> health<br />
and for making sanitary arrangements for worker employed directly or<br />
indirectly on the works. In case the contractor fails to make arrangements as<br />
aforesaid the Engineer-in-Charge/Site-in-Charge shall be entitled to do so<br />
and recover the cost there<strong>of</strong> from the contractor.<br />
6.f. DOCUMENTS CONCERNING WORKS<br />
6.f.1. All documents including <strong>drawings</strong>, blue prints, tracings, reproducible models,<br />
plans, specifications and copies, there<strong>of</strong> furnished by the Owner as well as all<br />
<strong>drawings</strong>, tracings, reproducibles, plans, specifications design calculations etc.<br />
prepared by the contractor for the purpose <strong>of</strong> execution <strong>of</strong> works covered in or<br />
connected with this contract shall be the property <strong>of</strong> the Owner and shall not be used<br />
by the contractor for any other work but are to be delivered to the Owner at the<br />
completion or otherwise <strong>of</strong> the contract.<br />
6.f.2. The Contractor shall keep and maintain secrecy <strong>of</strong> the documents, <strong>drawings</strong> etc.<br />
issued to him for the execution <strong>of</strong> this contract and restrict access to such<br />
documents, <strong>drawings</strong> etc. and further the Contractor shall execute a SECRECY<br />
agreement from each or any person employed by the Contractor having access to<br />
such documents, <strong>drawings</strong> etc. The Contractor shall not issue <strong>drawings</strong> and<br />
documents to any other agency or individual without the written approval by<br />
the Engineer-in-Charge/Site-in- Charge.<br />
6.f.3. Contractor will not give any information or document etc. concerning details <strong>of</strong> the<br />
work to the press or a news disseminating agency without prior written approval<br />
from Engineer-in-charge/Site-in-Charge. Contractor shall not take any pictures on<br />
site without written approval <strong>of</strong> Engineer-in-Charge/Site-in-Charge.<br />
7. PAYMENT OF CONTRACTOR'S BILLS<br />
7.1. Payments will be made against Running Accounts bills certified by the Owner's<br />
Engineer-in-Charge/Site-in-Charge within 15 days from the date <strong>of</strong> receipt <strong>of</strong> the<br />
certified bill.<br />
7.2. Running Account Bills and the final bill shall be submitted by the Contractor<br />
together with the duly signed measurements sheet(s) to the Engineer-in-Charge/<br />
Site-in-Charge <strong>of</strong> the Owner in quadruplicate for certification.<br />
The Bills shall also be accompanied by quantity calculations in support <strong>of</strong> the<br />
quantities contained in the bill along with cement consumption statement,<br />
actual/theoretical, wherever applicable duly certified by the Engineer-in-Charge/<br />
Site-in-Charge <strong>of</strong> the Owner.<br />
7.3. All running account payments shall be regarded as on account payment(s) to be<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.37 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
finally adjusted against the final bill payment. Payment <strong>of</strong> Running Account Bill(s)<br />
shall not determine or affect in any way the rights <strong>of</strong> the Owner under this Contract<br />
to make the final adjustments <strong>of</strong> the quantities <strong>of</strong> material, measurements <strong>of</strong> work<br />
and adjustments <strong>of</strong> amounts etc.etc. in the final bill.<br />
7.4. The final bill shall be submitted by the Contractor within one month <strong>of</strong> the date <strong>of</strong><br />
completion <strong>of</strong> the work fully and completely in all respects. If the Contractor fails to<br />
submit the final bill accordingly Engineer-in-Charge/Site-in-Charge may make the<br />
measurement and determine the total amount payable for the work carried out by the<br />
Contractor and such a certification shall be final and binding on the Contractor.<br />
The Owner/Engineer- in-Charge/Site-in-Charge may take the assistance <strong>of</strong> an<br />
outside party for taking the measurement, the expenses <strong>of</strong> which shall be payable<br />
by the Contractor.<br />
7.5. Payment <strong>of</strong> final bill shall be made within 15 days from the date <strong>of</strong> receipt <strong>of</strong> the<br />
certified bill.<br />
7.a. MEASUREMENT OF WORKS<br />
7.a.1. All measurements shall be in metric system. All the works will be jointly measured<br />
by the representative <strong>of</strong> the Engineer-in-Charge/Site-in-Charge and the Contractor<br />
or their authorised agent progressively. Such measurement will be recorded in the<br />
Measurement Book/Measurement Sheet by the Contractor or his authorised<br />
representative and signed in token <strong>of</strong> acceptance by the Owner or their<br />
authorised representative.<br />
7.a.2. For the purpose <strong>of</strong> taking joint measurement, the Contractor/representative shall be<br />
bound to be present whenever required by the Engineer-in-Charge/Site-in-Charge.<br />
If, however, they are absent for any reasons whatsoever, the measurement will be<br />
taken by the Engineer-in-Charge/Site-in-Charge or his representative and the same<br />
would be deemed to be correct and binding on the Contractor.<br />
7.a.3. In case <strong>of</strong> any dispute as to the mode <strong>of</strong> measurement for any item <strong>of</strong> work, the<br />
latest Indian Standard Specifications shall be followed. In case <strong>of</strong> any further<br />
dispute on the same the same shall be as per the certification <strong>of</strong> an outside<br />
qualified Engineer/ Consultant. Such a measurement shall be final and binding on<br />
the Owner and the Contractor.<br />
7.b. BILLING OF WORKS EXECUTED<br />
The Contractor will submit a bill in approved pr<strong>of</strong>orma in quadruplicate to the<br />
Engineer-in-Charge/Site-in-Charge <strong>of</strong> the work giving abstract and detailed<br />
measurement for the various items executed during a month, before the expiry <strong>of</strong><br />
the first week <strong>of</strong> the succeeding month. The Engineer-in-Charge/Site-in-Charge<br />
shall take or cause to be taken the requisite measurements for the purpose <strong>of</strong> having<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.38 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
the bill verified and/or checked before forwarding the same to the disbursement<br />
<strong>of</strong>fice <strong>of</strong> the Owner for further action in terms <strong>of</strong> the Contract and payment thereafter.<br />
The Engineer-in-Charge/Site-in-Charge shall verify the bills within 7 days <strong>of</strong><br />
submission <strong>of</strong> the Bill by the Contractor.<br />
7.c. RETENTION MONEY<br />
10% <strong>of</strong> the total value <strong>of</strong> the Running Account and Final Bill will be deducted and<br />
retained by the Owner as retention money on account <strong>of</strong> any damage/defect<br />
liability that may arise for the period covered under the defect liability period clause<br />
<strong>of</strong> the Contract free <strong>of</strong> interest. Any damage or defect that may arise or lie undiscovered<br />
at the time <strong>of</strong> issue <strong>of</strong> completion certificate connected in any way with the<br />
equipment or materials supplied by contractor or in workmanship shall be rectified<br />
or replaced by the contractor at his own expense failing which the Owner shall be<br />
entitled to rectify the said damage/defect from the retention money. Any excess <strong>of</strong><br />
expenditure incurred by the Owner on account <strong>of</strong> damage or defect shall be payable by<br />
the Contractor. The decision <strong>of</strong> the Owner in this behalf shall not be liable to be<br />
questioned but shall be final and binding on the Contractor.<br />
Thus, deduction towards retention money is applicable only in case <strong>of</strong> job/works<br />
contracts (civil, mechanical, electrical, maintenance etc.) where any damage or<br />
defect may arise in future (i.e. within 12 months from the date <strong>of</strong> completion <strong>of</strong> job) or<br />
lie undiscovered at the time <strong>of</strong> issue <strong>of</strong> completion certificate.<br />
®7.d. STATUTORY LEVIES<br />
7.d.1 The Contractor accepts full and exclusive liability for the payment <strong>of</strong> any and all<br />
taxes, duties, octroi, rates, cess, levies and statutory payments payable under all or<br />
any <strong>of</strong> the statutes etc.<br />
® Variations <strong>of</strong> taxes and duties arising out <strong>of</strong> the amendments to the Central / State<br />
enactments, in respect <strong>of</strong> sale <strong>of</strong> goods / services covered under this bid shall be to<br />
HPCL’s account, so long as :<br />
• They relate to the period after the opening <strong>of</strong> the price bid, but before the<br />
contracted completion period ( excluding permitted extensions due to delay<br />
on account <strong>of</strong> the contractors, if any) or the actual completion period,<br />
whichever is earlier; and<br />
• The vendor furnishes documentary evidence <strong>of</strong> incurrence <strong>of</strong> such<br />
variations, in addition to the invoices/documents for claiming Cenvat /Input<br />
Tax credit, wherever applicable.<br />
All contributions and taxes for unemployment compensation, insurance and old age<br />
pensions or annuities now or hereafter imposed by Central or State Governmental<br />
authorities which are imposed with respect to or covered by the wages, salaries or<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.39 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
other compensations paid to the persons employed by the Contractor and the Contractor<br />
shall be responsible for the compliance with all obligations and restrictions imposed<br />
by the Labour Law or any other law affecting employer-employee relationship and<br />
the Contractor further agrees to comply and to secure the compliance <strong>of</strong> all<br />
sub-contractors with all applicable Central, State, Municipal and local laws, and<br />
regulations and requirements <strong>of</strong> any Central, State or Local Government agency or<br />
authority.<br />
Contractor further agrees to defend, indemnify and hold harmless from any liability<br />
or penalty which may be imposed by the Central, State or Local authorities by reason<br />
<strong>of</strong> any violation by Contractor or sub-contractor <strong>of</strong> such laws, regulations or<br />
requirements and also from all claims, suits or proceedings that may be brought<br />
against the Owner arising under, growing out <strong>of</strong>, or by reasons <strong>of</strong> the work provided<br />
for by this contract by third parties, or by Central or State Government authority<br />
or any administrative sub-division there<strong>of</strong>. The Contractor further agrees that in case<br />
any such demand is raised against the Owner, and Owner has no way but to pay and<br />
pays/makes payment <strong>of</strong> the same, the Owner shall have the right to deduct the same<br />
from the amounts due and payable to the Contractor. The Contractor shall not<br />
raise any demand or dispute in respect <strong>of</strong> the same but may have recourse to<br />
recover/receive from the concerned authorities on the basis <strong>of</strong> the Certificate <strong>of</strong> the<br />
Owner issued in that behalf.<br />
7.d.2. The rates quoted should be inclusive <strong>of</strong> all rates, cess, taxes and sales tax on works<br />
contracts wherever applicable. However, wherever the sales tax on works contract is<br />
applicable and is to be deducted at source, the same will be deducted from the bills<br />
<strong>of</strong> the Contractor and paid to the concerned authorities. The pro<strong>of</strong> <strong>of</strong> such payments<br />
<strong>of</strong> sales tax on works contract will be furnished to the contractor.<br />
7.d.3. Income tax will be deducted at source as per rules at prevailing rates, unless<br />
certificate, if any, for deduction at lesser rate or nil deduction is submitted by the<br />
Contractor from appropriate authority.<br />
7.e. MATERIALS TO BE SUPPLIED BY CONTRACTOR<br />
7.e.1. The Contractor shall procure and provide the whole <strong>of</strong> the materials required for<br />
construction including tools, tackles, construction plant and equipment for the<br />
completion and maintenance <strong>of</strong> the works except the materials viz. steel and cement<br />
which may be agreed to be supplied as provided elsewhere in the contract. The<br />
contractor shall make arrangement for procuring such materials and for the transport<br />
there<strong>of</strong> at their own cost and expenses.<br />
7.e.2. The Owner may give necessary recommendation to the respective authority if so<br />
desired by the Contractor but assumes no responsibility <strong>of</strong> any nature. The<br />
Contractor shall procure materials <strong>of</strong> ISI stamp/certification and supplied by<br />
reputed suppliers borne on DGS&D <strong>list</strong>.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.40 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
7.e.3. All materials procured should meet the specifications given in the tender document.<br />
The Engineer-in-charge may, at his discretion, ask for samples and test certificates<br />
for any batch <strong>of</strong> any materials procured. Before procuring, the Contractor should<br />
get the approval <strong>of</strong> Engineer-in-Charge/Site-in-Charge for any materials to be<br />
used for the works.<br />
7.e.4. Manufacturer's certificate shall be submitted for all materials supplied by the<br />
Contractor. If, however, in the opinion <strong>of</strong> the Engineer-in-Charge/Site-in-Charge<br />
any tests are required to be conducted on the material supplied by the Contractor,<br />
these will be arranged by the Contractor promptly at his own cost.<br />
7.f. MATERIALS TO BE SUPPLIED BY THE OWNER<br />
7.f.1. Steel and Cement maybe supplied by the Owner to the contractor against payment by<br />
Contractor from either godown or from the site or within work premises itself and<br />
the contractor shall arrange for all transport to actual work site at no extra cost.<br />
7.f.2. The contractor shall bear all the costs including loading and unloading, carting<br />
from issue points to work spot storage, unloading, custody and handling and<br />
stacking the same and return the surplus steel and cement to the Owner's storage<br />
point after completion <strong>of</strong> job.<br />
7.f.3. The contractor will be fully accountable for the steel and cement received from the<br />
Owner and contractor will give acknowledgement/receipt for quantity <strong>of</strong> steel and<br />
cement received by him each time he uplifts cement from Owner's custody.<br />
7.f.4. For all computation purposes, the theoretical cement consumption shall be<br />
considered as per CPWD standards.<br />
7.f.5. Steel and Cement as received from the manufacturer/stockists will be<br />
issued to the contractor. Theoretical weight <strong>of</strong> cement in a bag will be considered<br />
as 50 Kg. Bags weighing upto 4% less shall be accepted by the contractor and<br />
considered as 50 Kg. per bag. Any shortage in the weight <strong>of</strong> any cement bag by<br />
more than 4% will be to the Owner's account only when pointed out by the<br />
Contractor and verified by Engineer-in-Charge/Site in Charge at the time <strong>of</strong><br />
Contract or taking delivery.<br />
7.f.6. The contractor will be required to maintain a stock register for receipt, issuance and<br />
consumption <strong>of</strong> steel and cement at site. Cement will be stored in a warehouse<br />
at site. Requirement <strong>of</strong> cement on any day will be taken out <strong>of</strong> the warehouse.<br />
Cement issued shall be regulated on the basis <strong>of</strong> FIRST RECEIPT to go as FIRST<br />
ISSUE.<br />
7.f.7. Empty cement bag shall be the property <strong>of</strong> the Contractor. Contractor shall be<br />
penalised for any excess/under consumption <strong>of</strong> cement. The penal rate will be<br />
twice the rate <strong>of</strong> issue <strong>of</strong> cement for this work.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.41 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
7.f.8. All the running bills as well as the final bills will be accompanied by cement<br />
consumption statements giving the detailed working <strong>of</strong> the cement used, cement<br />
received and stock-on-hand.<br />
7.f.9. The Contractor will be fully responsible for safe custody <strong>of</strong> cement once it is<br />
received by him and during transport. Owner will not entertain any claims <strong>of</strong> the<br />
contractor for theft, loss or damage to cement while in their custody.<br />
7.f.10. The contractor shall not remove from the site any cement bags at any time.<br />
7.f.11. The Contractor shall advise Engineer-in-charge/Site-in-charge in writing atleast 21<br />
days before exhausting the Cement stocks already held by Contractor to ensure that<br />
such delays do not lead to interruptions in the progress <strong>of</strong> work.<br />
7.f.12. Cement shall not be supplied by the Owner for manufacturing <strong>of</strong> mosaic tiles,<br />
precast cement jali and any other bought out items which consume cement and for<br />
temporary works.<br />
7.f.13. Cement in bags and in good usable condition left over after the completion <strong>of</strong> work<br />
shall be returned by the contractor to the Owner. The Owner shall make payment to<br />
the Contractor at the supply rate for such stocks <strong>of</strong> cement they accept and receive.<br />
Any refused stock <strong>of</strong> cement shall be removed by the Contractor from the site at his<br />
cost and expenses within 15 days <strong>of</strong> completion <strong>of</strong> the work.<br />
8. PAYMENT OF CLAIMS AND DAMAGES<br />
8.1. Should the Owner have to pay money in respect <strong>of</strong> claims or demands as aforesaid<br />
the amount so paid and the costs incurred by the Owner shall be charged to and<br />
paid by the Contractor and the Contractor shall not be entitled to dispute or question<br />
the right <strong>of</strong> the Owner to make such payments notwithstanding the same may have<br />
been without his consent or authority or in law or otherwise to the contrary.<br />
8.2. In every case in which by virtue <strong>of</strong> the provisions <strong>of</strong> Workmen's Compensation<br />
Act, 1923, or other Acts, the Owner is obliged to pay Compensation to a<br />
Workman employed by the Contractor in execution <strong>of</strong> the works, the Owner will<br />
recover from the Contractor the amount <strong>of</strong> compensation so paid and without<br />
prejudice to the rights <strong>of</strong> Owner under the said Act. Owner shall be at liberty to<br />
recover such amount or any part there<strong>of</strong> by deducting it from the security deposit or<br />
from any sum due to the Contractor whether under this contract or otherwise. The<br />
Owner shall not be bound to contest any claim made under Section 12 sub section (1)<br />
<strong>of</strong> the said Act, except on the written request <strong>of</strong> the Contractor and upon his giving<br />
to the Owner full security for all costs for which the owner might become liable<br />
in consequence <strong>of</strong> contesting such claim.<br />
8.a. ACTION AND COMPENSATION IN CASE OF BAD WORK<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.42 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
If it shall appear to the Engineer-in-Charge/Site-in-Charge that any work has been<br />
executed with bad, imperfect or unskilled workmanship, or with materials, or that<br />
any materials or articles provided by the Contractor for execution <strong>of</strong> the work are<br />
not <strong>of</strong> standards specified/inferior quality to that contracted for, or otherwise not in<br />
accordance with the contract, the CONTRACTOR shall on demand in writing from<br />
the Engineer-in-Charge/Site-in-Charge or his authorised representative specifying<br />
the work, materials or articles complained <strong>of</strong>, notwithstanding that the same may<br />
have been inadvertently passed, certified and paid for, forthwith rectify or remove<br />
and reconstruct the work so specified and at his own charge and cost and expenses<br />
and in the event <strong>of</strong> failure to do so within a period <strong>of</strong> 15 days <strong>of</strong> such intimation/<br />
information/knowledge, the Contractor shall be liable to pay compensation equivalent<br />
to the cost <strong>of</strong> reconstruction by the Owner. On expiry <strong>of</strong> 15 days period mentioned<br />
above, the Owner may by themselves or otherwise rectify or remove and re-execute<br />
the work or remove and replace with others, the materials or articles complained<br />
<strong>of</strong> as the case may be at the risk and expenses in all respects <strong>of</strong> the Contractor. The<br />
decision <strong>of</strong> the Engineer-in- Charge/ Site-in-Charge as to any question arising under<br />
this clause shall be final and conclusive and shall not be raised as a dispute or shall<br />
be arbitrable.<br />
8.b. INSPECTION AND AUDIT OF CONTRACT AND WORKS<br />
This project is subject to inspection by various Government agencies <strong>of</strong><br />
Government <strong>of</strong> India. The contractor shall extend full cooperation to all the<br />
Government and other agencies in the inspection <strong>of</strong> the works, audit <strong>of</strong> the Contract<br />
and the documents <strong>of</strong> Contract Bills, measurements sheets etc. etc. and<br />
examination <strong>of</strong> the records <strong>of</strong> works and make enquiries interrogation as they may<br />
deem fit, proper and necessary. Upon inspection etc. by such agencies if it is<br />
pointed out that the contract work has not been carried out according to the<br />
prescribed terms and conditions as laid down in the tender documents and if any<br />
recoveries are recommended, the same shall be recovered from the contractors<br />
running bills/final bill/from ordered/suggested Security Deposit/retention money.<br />
The Contractor shall not rise any dispute on any such account and the same shall not<br />
be arbitrable.<br />
9. CONTRACTOR TO INDEMNIFY THE OWNER<br />
The Contractor shall indemnify the Owner and every member, <strong>of</strong>ficer and<br />
employee <strong>of</strong> the Owner, also the Engineer-in-Charge/Site-in-Charge and his staff<br />
against all the actions, proceedings, claims, demands, costs, expenses, whatsoever<br />
arising out <strong>of</strong> or in connection with the works and all actions, proceedings, claims,<br />
demands, costs, expenses which may be made against the Owner for or in respect <strong>of</strong><br />
or arising out <strong>of</strong> any failure by the Contractor in the performance <strong>of</strong> his<br />
obligations under the contract. The Contractor shall be liable for or in respect <strong>of</strong> or<br />
in consequence <strong>of</strong> any accident or injury to any workmen or other person in the<br />
employment <strong>of</strong> the Contractor or his sub contractor and Contractor shall indemnify<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.43 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
and keep indemnified the Owner against all such damages, proceedings, costs,<br />
charges and expenses whatsoever in respect there<strong>of</strong> or in relation thereto.<br />
10. LIQUIDATED DAMAGES<br />
® i) In case <strong>of</strong> any delay in completion <strong>of</strong> the work beyond the CDD, the<br />
Owner shall be entitled to be paid Liquidated Damages by the Contractor.<br />
The liquidated damages shall be initially at the rate <strong>of</strong> 0.5% (half percent) <strong>of</strong><br />
the total contract value for every week <strong>of</strong> the delay subject to a maximum<br />
<strong>of</strong> 5% <strong>of</strong> the total contract value. The liquidated damages shall be<br />
recovered by the Owner out <strong>of</strong> the amounts payable to the Contractor<br />
or from any Bank Guarantees or Deposits furnished by the Contractor or<br />
the Retention Money retained from the Bills <strong>of</strong> the Contractor, either<br />
under this contract or any other contract.<br />
ii) The Contractor shall be entitled to give an acceptable unconditional Bank<br />
Guarantee in lieu <strong>of</strong> such a deduction if Contractor desires any decision on a<br />
request for time extension.<br />
iii) Once a final decision is taken on the request <strong>of</strong> the Contractor or otherwise,<br />
the LD shall be applicable only on the basic cost <strong>of</strong> the contract and on each<br />
full completed week(s) <strong>of</strong> delay (and for part <strong>of</strong> the week, a pro-rata LD<br />
amount shall be applicable).<br />
iv) This final calculation <strong>of</strong> LD shall be only on the value <strong>of</strong> the unexecuted<br />
portion/quantity <strong>of</strong> work as on the CDD.<br />
v) Contractor agrees with the Owner, that the above represents a genuine<br />
pre-estimate <strong>of</strong> the damages which the Owner will suffer on account <strong>of</strong> delay<br />
in the performance <strong>of</strong> the work by Contractor. The Contractor further<br />
agrees that the LD amount is over and above any right which owner has to<br />
risk purchase under Clause 12.4 and any right to get the defects in the work<br />
rectified at the cost <strong>of</strong> the contractor.<br />
11. DEFECTS AFTER TAKING OVER OR TERMINATION OF WORK<br />
CONTRACT BY OWNER<br />
The Contractor shall remain responsible and liable to make good all losses or damages<br />
that may occur/appear to the work carried out under this Contract within a period <strong>of</strong><br />
12 months from date <strong>of</strong> issue <strong>of</strong> the Completion Certificate and/or the date <strong>of</strong><br />
Owner taking over the work, which ever is earlier. The Contractor shall issue a Bank<br />
Guarantee to the Owner in the sum <strong>of</strong> 10% <strong>of</strong> the work entrusted in the Contract, from<br />
any nationalised Bank acceptable to the Owner and if however, the Contractor<br />
fails to furnish such a Bank Guarantee the Owner shall have right to retain the Security<br />
Deposit and Retention Money to cover the 10% <strong>of</strong> the Guarantee amount under this<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.44 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
clause and to return/refund the same after the expiry <strong>of</strong> the period <strong>of</strong> 12 months without<br />
any interest thereon.<br />
12. TERMINATION OF CONTRACT<br />
12.1 The owner may terminate the contract at any stage <strong>of</strong> the construction for reasons to<br />
be recorded in the letter <strong>of</strong> termination.<br />
12.2 The Owner inter alia may terminate the Contract for any or all <strong>of</strong> the following reasons<br />
that the contractor<br />
a) has abandoned the work/Contract.<br />
b) has failed to commence the works, or has without any lawful excuse under<br />
these conditions suspended the work for 15 consecutive days.<br />
c) has failed to remove materials from the site or to pull down and replace the<br />
work within 15 days after receiving from the Engineer written notice that<br />
the said materials or work were condemned and/or rejected by the Engineer<br />
under specified conditions.<br />
d) has neglected or failed to observe and perform all or any <strong>of</strong> the terms acts,<br />
matters or things under this Contract to be observed and performed by<br />
the Contractor.<br />
e) has to the detriment <strong>of</strong> good workmanship or in defiance <strong>of</strong> the Engineer's<br />
instructions to the contrary sub-let any part <strong>of</strong> the Contract.<br />
f) has acted in any manner to the detrimental interest, reputation, dignity, name<br />
or prestige <strong>of</strong> the Owner.<br />
g) has stopped attending to work without any prior notice and prior permission for<br />
a period <strong>of</strong> 15 days.<br />
h) has become untraceable.<br />
i) has without authority acted in violation <strong>of</strong> the terms and conditions <strong>of</strong> this<br />
contract and has committed breach <strong>of</strong> terms <strong>of</strong> the contract in best judgement<br />
<strong>of</strong> the owner.<br />
j) has been declared insolvent/bankrupt.<br />
k) in the event <strong>of</strong> sudden death <strong>of</strong> the Contractor.<br />
12.3 The owner on termination <strong>of</strong> such contract shall have the right to appropriate the<br />
Security Deposit, Retention Money and invoke the Bank Guarantee furnished by the<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.45 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
contractor and to appropriate the same towards the amounts due and payable by the<br />
contractor as per the conditions <strong>of</strong> Contract and return to the contractor excess<br />
money, if any, left over.<br />
® 12.4 In case <strong>of</strong> Termination <strong>of</strong> the contract, Owner shall have the right to carry out the<br />
unexecuted portion <strong>of</strong> the work either by themselves or through any other<br />
contractor(s) at the risk and cost <strong>of</strong> the Contractor. In view <strong>of</strong> paucity <strong>of</strong> time,<br />
Owner shall have the right to place such unexecuted portion <strong>of</strong> the work on any<br />
nominated contractor(s). However, the overall liability <strong>of</strong> the Contractor shall be<br />
restricted to 100 % <strong>of</strong> the total contract value.<br />
12.5 The contractor within or at the time fixed by the Owner shall depute his authorised<br />
representative for taking joint final measurements <strong>of</strong> the works executed thus far and<br />
submit the final bill for the work as per joint final measurement within 15 days <strong>of</strong> the<br />
date <strong>of</strong> joint final measurement. If the contractor fails to depute their<br />
representative for joint measurement, the owner shall take the measurement with<br />
their Engineer-in-Charge/Site-in-Charge or any other outside representatives.<br />
Such a measurement shall not be questioned by the Contractor and no dispute can<br />
be raised by the Contractor for purpose <strong>of</strong> Arbitration.<br />
12.6 The Owner may enter upon and take possession <strong>of</strong> the works and all plant, tools,<br />
scaffoldings, sheds, machinery, power operated tools and steel, cement and other<br />
materials <strong>of</strong> the Contract at the site or around the site and use or employ the same for<br />
completion <strong>of</strong> the work or employ any other contractor or other person or persons to<br />
complete the works. The Contractor shall not in any way object or interrupt or do<br />
any act, matter or thing to prevent or hinder such actions, other Contractor or<br />
other persons employed for completing and finishing or using the materials and<br />
plant for the works. When the works shall be completed or as soon thereafter the<br />
Engineer shall give a notice in writing to the Contractor to remove surplus<br />
materials and plant, if any, and belonging to the Contractor except as provided<br />
elsewhere in the Contract and should the Contractor fail to do so within a period <strong>of</strong><br />
15 days after receipt there<strong>of</strong> the Owner may sell the same by public auction and shall<br />
give credit to the contractor for the amount realised. The Owner shall thereafter<br />
ascertain and certify in writing under his hand what (if anything) shall be due or<br />
payable to or by the Owner for the value <strong>of</strong> the plant and materials so taken<br />
possession and the expense or loss which the Owner shall have been put to in<br />
procuring the works, to be so completed, and the amount if any, owing to the<br />
Contractor and the amount which shall be so certified shall thereupon be paid by the<br />
Owner to the Contractor or by the Contractor to the Owner, as the case may, and the<br />
Certificate <strong>of</strong> the Owner shall be final and conclusive between the parties.<br />
12.7 When the contract is terminated by the Owner for all or any <strong>of</strong> the reasons mentioned<br />
above the Contractor shall not have any right to claim compensation on account <strong>of</strong><br />
such termination.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.46 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
13. FORCE MAJEURE<br />
13.1. Any delay in or failure <strong>of</strong> the performance <strong>of</strong> either part hereto shall not constitute<br />
default hereunder or give rise to any claims for damage, if any, to the extent such<br />
delays or failure <strong>of</strong> performance is caused by occurrences such as Acts <strong>of</strong> God or<br />
an enemy, expropriation or confiscation <strong>of</strong> facilities by Government authorities,<br />
acts <strong>of</strong> war, rebellion, sabotage or fires, floods, explosions, riots, or strikes.<br />
The Contractor shall keep records <strong>of</strong> the circumstances referred to above and bring<br />
these to the notice <strong>of</strong> the Engineer-in-Charge/Site-in-Charge in writing<br />
immediately on such occurrences. The amount <strong>of</strong> time, if any, lost on any <strong>of</strong> these<br />
counts shall not be counted for the Contract period. One decision <strong>of</strong> the Owner<br />
arrived at after consultation with the Contractor, shall be final and binding. Such<br />
a determined period <strong>of</strong> time be extended by the Owner to enable the Contractor to<br />
complete the job within such extended period <strong>of</strong> time.<br />
13.2. If Contractor is prevented or delayed from the performing any <strong>of</strong> its obligations<br />
under this Agreement by Force Majeure, then Contractor shall notify Owner he<br />
circumstances constituting the Force Majeure and the obligations performance <strong>of</strong><br />
which is thereby delayed or prevented, within seven days <strong>of</strong> the occurrence <strong>of</strong> the<br />
events.<br />
14. ARBITRATION<br />
14.1 All disputes and differences <strong>of</strong> whatsoever nature, whether existing or which shall at any<br />
time arise between the parties hereto touching or concerning the agreement, meaning,<br />
operation or effect there<strong>of</strong> or to the rights and liabilities <strong>of</strong> the parties or arising out <strong>of</strong> or<br />
in relation thereto whether during or after completion <strong>of</strong> the contract or whether before<br />
after determination, foreclosure, termination or breach <strong>of</strong> the agreement (other than those<br />
in respect <strong>of</strong> which the decision <strong>of</strong> any person is, by the contract, expressed to be final<br />
and binding) shall, after written notice by either party to the agreement to the other <strong>of</strong><br />
them and to the Appointing Authority hereinafter mentioned, be referred for adjudication<br />
to the Sole Arbitrator to be appointed as hereinafter provided.<br />
®14.2 The appointing authority shall either himself act as the Sole Arbitrator or nominate<br />
some <strong>of</strong>ficer/retired <strong>of</strong>ficer <strong>of</strong> <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong> (referred to<br />
as owner or HPCL) or any other Government Company, or any retired <strong>of</strong>ficer <strong>of</strong> the<br />
Central Government not below the rank <strong>of</strong> a Director, to act as the Sole Arbitrator to<br />
adjudicate the disputes and differences between the parties. The contractor/vendor<br />
shall not be entitled to raise any objection to the appointment <strong>of</strong> such person as the<br />
Sole Arbitrator on the ground that the said person is/was an <strong>of</strong>ficer and/or shareholder<br />
<strong>of</strong> the owner, another Govt. Company or the Central Government or that he/she has to<br />
deal or had dealt with the matter to which the contract relates or that in the course <strong>of</strong><br />
his/her duties, he/she has/had expressed views on all or any <strong>of</strong> the matters in dispute or<br />
difference.<br />
14.3 In the event <strong>of</strong> the Arbitrator to whom the matter is referred to, does not accept the<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.47 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
appointment, or is unable or unwilling to act or resigns or vacates his <strong>of</strong>fice for any<br />
reasons whatsoever, the Appointing Authority aforesaid, shall nominate another<br />
person as aforesaid, to act as the Sole Arbitrator.<br />
14.4 Such another person nominated as the Sole Arbitrator shall be entitled to proceed with<br />
the arbitration from the stage at which it was left by his predecessor. It is expressly<br />
agreed between the parties that no person other than the Appointing Authority or a<br />
person nominated by the Appointing Authority as aforesaid, shall act as an Arbitrator.<br />
The failure on the part <strong>of</strong> the Appointing Authority to make an appointment on time<br />
shall only give rise to a right to a Contractor to get such an appointment made and not<br />
to have any other person appointed as the Sole Arbitrator.<br />
14.5 The Award <strong>of</strong> the Sole Arbitrator shall be final and binding on the parties to the<br />
Agreement.<br />
14.6 The work under the Contract shall, however, continue during the Arbitration proceedings<br />
and no payment due or payable to the concerned party shall be withheld (except to the<br />
extent disputed) on account <strong>of</strong> initiation, commencement or pendency <strong>of</strong> such<br />
proceedings.<br />
14.7 The Arbitrator may give a composite or separate Award(s) in respect <strong>of</strong> each dispute or<br />
difference referred to him and may also make interim award(s) if necessary.<br />
14.8 The fees <strong>of</strong> the Arbitrator and expenses <strong>of</strong> arbitration, if any, shall be borne equally by<br />
the parties unless the Sole Arbitrator otherwise directs in his award with reasons. The<br />
Award <strong>of</strong> the Sole Arbitrator shall be final and binding on both the parties.<br />
14.9 Subject to the aforesaid, the provisions <strong>of</strong> the Arbitration and Conciliation Act, 1996 or<br />
any statutory modification or re-enactment there<strong>of</strong> and the rules made thereunder, shall<br />
apply to the Arbitration proceedings under this Clause.<br />
14.10 The Contract shall be governed by and constructed according to the laws in force in<br />
India. The parties hereby submit to the exclusive jurisdiction <strong>of</strong> the Courts situated at<br />
at Visakhapatnam for all purposes. The Arbitration shall be held at Visakhapatnam and<br />
conducted in English language.<br />
14.11 The Appointing Authority is the Functional Director <strong>of</strong> <strong>Hindustan</strong> <strong>Petroleum</strong><br />
<strong>Corporation</strong> <strong>Limited</strong>.<br />
(Note:- * = While printing the GTCs, each Purchasing Authorities at various location,<br />
may mention the correct place before printing the GTC and not leave Clause 14.10 blank<br />
or as stated above. Bracketed portion is to be removed.<br />
15. GENERAL<br />
15.1. Materials required for the works whether brought by the or supplied by the Owner shall<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.48 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
e stored by the contractor only at places approved by<br />
Engineer-in-Charge/Site-in-Charge. Storage and safe custody <strong>of</strong> the material shall be the<br />
responsibility <strong>of</strong> the Contractor.<br />
15.2. Owner and/or Engineer-in-Charge/Site-in-Charge connected with the contract, shall<br />
be entitled at any time to inspect and examine any materials intended to be used in or<br />
on the works, either on the site or at factory or workshop or at other place(s)<br />
manufactured or at any places where these are laying or from which these are being<br />
obtained and the contractor shall give facilities as may be required for such inspection<br />
and examination.<br />
15.3. In case <strong>of</strong> any class <strong>of</strong> work for which there is no such specification supplied by the owner<br />
as is mentioned in the tender documents, such work shall be carried out in accordance<br />
with Indian Standard Specifications and if the Indian Standard Specifications do not<br />
cover the same the work should be carried out as per standard Engineering practice<br />
subject to the approval <strong>of</strong> the Engineer-in-Charge/Site-in-Charge.<br />
15.4. Should the work be suspended by reason <strong>of</strong> rain, strike, lockouts or other cause the<br />
contractor shall take all precautions necessary for the protection <strong>of</strong> the work<br />
and at his own expense shall make good any damages arising from any <strong>of</strong> these causes.<br />
15.5 The contractor shall cover up and protect from injury from any cause all new work also<br />
for supplying all temporary doors, protection to windows and any other requisite<br />
protection for the whole <strong>of</strong> the works executed whether by himself or special<br />
tradesmen or sub- contractors and any damage caused must be made good by the<br />
contractors at his own expense.<br />
15.6 If the contractor has quoted the items under the deemed exports, then it will be the<br />
responsibility <strong>of</strong> the contractor to get all the benefits under deemed exports from the<br />
Government. The Owner’s responsibility shall only be limited to the issuance <strong>of</strong><br />
required certificates. The quotation will be unconditional and phrases like “subject to<br />
availability <strong>of</strong> deemed exports benefit” etc. will not find place in it.<br />
®16. Integrity Pact :<br />
Integrity Pact (refer Annexure-17) is a Pact between HPCL (as a purchaser)<br />
on one hand and the prospective bidder/contractor (vendor) on the other hand<br />
stating that the two parties shall make certain commitments to each other in regard<br />
to ensuring transparency and fair dealings in the purchansing activities <strong>of</strong> the <strong>Corporation</strong>.<br />
_____________________________________________________________________________<br />
Annexure 7 (General Terms & Conditions <strong>of</strong> Works Contract) Systems & Procedures<br />
Purchase Manual VI.49 HPCL, Mumbai<br />
® REVISION : PUR-019/07.08.2007
(SPECIMEN)<br />
BANK GUARANTEE FOR ADVANCES<br />
(on non-judicial stamp paper <strong>of</strong> appropriate value)<br />
To,<br />
<strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> Ltd.,<br />
(Address as applicable)<br />
ANNEXURE -9<br />
In CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION<br />
LIMITED, a Government <strong>of</strong> India Company registered under the Companies Act 1956,<br />
having its registered <strong>of</strong>fice at 17, Jamshedji Tata Road, Bombay - 400 020 (hereinafter called<br />
"the <strong>Corporation</strong>" which expression shall include its successors in business and assigns)<br />
having placed an order on Messrs ___________________ a partnership firm/sole proprietor<br />
business/ a company registered under the Companies Act, 1956 having its <strong>of</strong>fice at<br />
_______________________ (hereinafter called "the Supplier" which expression shall<br />
include its successors and assigns) vide Order No. ____________ dated _________<br />
(hereinafter called "the Order" which expression shall include any amendments/alterations<br />
thereto as issued by "the <strong>Corporation</strong>") for the supply <strong>of</strong> goods/to the execution <strong>of</strong> Service<br />
for "the <strong>Corporation</strong>" and having agreed to pay the supplier as and by way <strong>of</strong> advance upto<br />
a sum <strong>of</strong> Rs. _________ (Rupees ____________________________________<br />
only ) being _____ % <strong>of</strong> the value <strong>of</strong> the order in terms <strong>of</strong> "the Order" on production <strong>of</strong><br />
an acceptable Bank Guarantee for an amount <strong>of</strong> Rs. ____________ (Rupees<br />
__________________________________ only)<br />
1. We, ____________________ Bank having <strong>of</strong>fice at _________________<br />
(hereafter referred to as "the Bank") do at the request and on behalf <strong>of</strong> "the Supplier's"<br />
hereby agree to pay "the <strong>Corporation</strong>" without any demur on first demand an amount<br />
not exceeding Rs. _________ (Rs. ______________________ only) against any<br />
loss or damage, costs, charges and expenses caused to or suffered or would be caused<br />
to or suffered by "the <strong>Corporation</strong>" by reason <strong>of</strong><br />
any breach on the part <strong>of</strong> "the Supplier" <strong>of</strong> any <strong>of</strong> the terms and conditions <strong>of</strong> the said<br />
order.<br />
_____________________________________________________________________________<br />
Annexure 9 ( Bank Guarantee for Advances) Systems & Procedures<br />
Purchase Manual VI.55 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
2. We, _______________ Bank further agree that "the <strong>Corporation</strong>" shall be sole judge<br />
whether the said "Supplier" has committed breach <strong>of</strong> any <strong>of</strong> the terms and conditions <strong>of</strong><br />
"the Order" and the extent <strong>of</strong> loss, damage, cost charges and expenses suffered or<br />
incurred or would be suffered or incurred by "the <strong>Corporation</strong>" on account there<strong>of</strong> and<br />
we waive in favour <strong>of</strong> "the <strong>Corporation</strong>" all the rights and defences to which we as<br />
guarantors and/or "the Supplier" may be entitled to.<br />
3. We, ___________________ Bank further agree that the amount demanded by "the<br />
<strong>Corporation</strong>" as such shall be final and binding on "the Bank" as to "the Bank's" liability<br />
to pay and amount demanded and "the Bank" undertake to pay "the <strong>Corporation</strong>" the<br />
amount so demanded on first demand and without any demur notwithstanding any dispute<br />
raised by "the Supplier" or any suit or other legal proceedings including arbitration<br />
pending before any court tribunal or arbitrator relating thereto, our liability under this<br />
guarantee being absolute and unconditional. (We __________________ Bank further<br />
agree that the guarantee herein contained shall remain in full force and continue to<br />
have full effect so long as the said amount remains unadjusted, provided, however,<br />
the value <strong>of</strong> the guarantee shall progressively reduce upon any adjustments being made<br />
by "the <strong>Corporation</strong>" against the said advance and "the <strong>Corporation</strong>" rights shall extend<br />
only to the value <strong>of</strong> the unadjusted amount.<br />
4. We, __________________ Bank further agree with "the <strong>Corporation</strong>" that "the<br />
<strong>Corporation</strong>" shall have the fullest liberty without our consent and without affecting in<br />
any manner our obligations hereunder to vary any <strong>of</strong> the terms and conditions <strong>of</strong> the<br />
said "order"/or to extend time <strong>of</strong> performance by "the Supplier" from time to time or<br />
to postpone for any time or from time to time any <strong>of</strong> the powers exercisable by "the<br />
<strong>Corporation</strong>" against "the Supplier" and to forbear to enforce any <strong>of</strong> the terms and<br />
conditions relating to "the Order" and we shall not be relieved from our liability by<br />
reason <strong>of</strong> any such variation or extension being granted to "the Supplier" or for any<br />
forbearance, act or omission on "the Supplier" or by any such matter or things<br />
whatsoever which under the law relating to suretics would be for this provisions have the<br />
effect <strong>of</strong> relieving us.<br />
5. Not withstanding anything contained herein above :<br />
i) Our liability under this guarantee shall not exceed Rs..........<br />
ii) This Bank Guarantee shall be valid upto and including .......; and<br />
iii) We are liable to pay the guarantee amount or any part there<strong>of</strong> under this Bank<br />
Guarantee only and only if you serve upon us a written claim or demand on or # before<br />
the expiry <strong>of</strong> 30 days from the date <strong>of</strong> expiry <strong>of</strong> this guarantee<br />
6. We, ________________ Bank further undertake not to revoke this guarantee during its<br />
currency except with the previous consent <strong>of</strong> "the <strong>Corporation</strong>" in writing.<br />
_____________________________________________________________________________<br />
Annexure 9 ( Bank Guarantee for Advances) Systems & Procedures<br />
Purchase Manual VI.56 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
7. We, ____________________ Bank lastly agree that "the Bank" liability under this<br />
guarantee shall not be affected by any change in the constitution <strong>of</strong> "the Supplier".<br />
8. We, _________________ Bank has power to issue this guarantee in favour <strong>of</strong> "the<br />
<strong>Corporation</strong>" in terms <strong>of</strong> the documents and/or the agreement/contract or MOU<br />
entered into between"the supplier" and "the Bank" in this regard.<br />
IN WITNESS WHEREOF the Bank has executed this document on this ________________<br />
day <strong>of</strong> ___________________<br />
____________________________<br />
(FOR _________ BANK)<br />
(by its constituted attorney)<br />
(signature <strong>of</strong> a person authorized<br />
to sign on behalf <strong>of</strong> "the Bank")<br />
_____________________________________________________________________________<br />
Annexure 9 ( Bank Guarantee for Advances) Systems & Procedures<br />
Purchase Manual VI.57 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
(SPECIMEN)<br />
ANNEXURE - 11<br />
COMPOSITE BANK GUARANTEE FOR MOBILISATION ADVANCE, SECURITY<br />
DEPOSIT/RETENTION MONEY/PERFORMANCE GUARANTEE<br />
(On Non-Judicial stamp paper <strong>of</strong> appropriate value)<br />
TO : <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong><br />
(Address as applicable)<br />
IN CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION<br />
LIMITED, a Government <strong>of</strong> India Company registered under the<br />
Companies Act, 1956, having its registered <strong>of</strong>fice at 17,<br />
Jamshedji Tata Road, Bombay-20 (hereinafter called "The<br />
<strong>Corporation</strong>" (which expression shall include its successor in<br />
business and assigns) having placed an order on<br />
Messers ............................ a partnership firm/sole<br />
proprietor business/a company registered under the Companies Act,<br />
1956 having its <strong>of</strong>fice at .............. (hereinafter called "the<br />
supplier" (which expression shall include executors,<br />
administrators and assigns) vide order No.......................<br />
dated.............. (hereinafter called "the order" which<br />
expression shall include any amendments/alterations to "the<br />
order" issued by "the <strong>Corporation</strong>") for the supply <strong>of</strong> goods<br />
to/execution <strong>of</strong> services for "the <strong>Corporation</strong>" and "the<br />
<strong>Corporation</strong>" having agreed :<br />
a) not to insist upon immediate payment <strong>of</strong> Security deposit for<br />
the fulfilment and performance <strong>of</strong> the said order<br />
b) to pay "the supplier" as and by way <strong>of</strong> advance upto a sum <strong>of</strong><br />
Rupees__________ (Rupees _____________________________ only)<br />
being ____% <strong>of</strong> the value <strong>of</strong> "the order";<br />
c) that "the supplier" shall furnish a security for the<br />
performance <strong>of</strong> "the supplier's" obligations and/or discharge<br />
<strong>of</strong> "the supplier's" liability in connection with the said<br />
"order"; and "the <strong>Corporation</strong>" having agreed with "the<br />
supplier" to accept a composite Bank Guarantee for the<br />
mobilisation advance, security deposit, retention money and<br />
_____________________________________________________________________________<br />
Annexure 11 (Composite Bank Gaurantee for Mobil. Systems & Procedures<br />
Purchase Manual Advance,Security Dep. Etc.) VI.61 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
performance guarantee.<br />
_____________________________________________________________________________<br />
Annexure 11 (Composite Bank Gaurantee for Mobil. Systems & Procedures<br />
Purchase Manual Advance,Security Dep. Etc.) VI.62 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
We, .................................................... Bank<br />
having <strong>of</strong>fice at ............................................<br />
(hereinafter referred to as "the Bank" which expression shall<br />
includes its successors and assigns) at the request and on behalf<br />
<strong>of</strong> "the supplier" hereby agree to pay to "the <strong>Corporation</strong>"without<br />
any demur on first demand an amount not exceeding Rs...........<br />
(Rupees.............................only) against any loss or<br />
damage, costs, charges and expenses caused to or suffered by "the<br />
<strong>Corporation</strong>" by reason <strong>of</strong> non performance and fulfilment or for<br />
any breach on the part <strong>of</strong> "the supplier" <strong>of</strong> any <strong>of</strong> the terms and<br />
conditions <strong>of</strong> the said "order".<br />
2. We, ............................. Bank further agree that<br />
"the <strong>Corporation</strong>" shall be sole judge whether the said<br />
"Supplier" has failed to perform or fulfill the said "order"<br />
in terms there<strong>of</strong> or committed breach <strong>of</strong> any terms and<br />
conditions <strong>of</strong> "the order" and the extent <strong>of</strong> loss, damage,<br />
cost, charges and expenses suffered or incurred or would be<br />
suffered or incurred by "the <strong>Corporation</strong>" on account there<strong>of</strong><br />
and we waive in the favour <strong>of</strong> "the <strong>Corporation</strong>" all the<br />
rights and defences to which we as guarantors and/or "the<br />
Supplier" may be entitled to.<br />
3. We, ................................. Bank further agree<br />
that the amount demanded by "the <strong>Corporation</strong>" as such shall<br />
be final and binding on "the Bank" as to "the Bank" 's<br />
liability to pay and the amount demanded and "the Bank"<br />
undertake to pay "the <strong>Corporation</strong>" the amount so demanded on<br />
first demand and without any demur notwithstanding any<br />
dispute raised by "the Supplier" or any suit or other legal<br />
proceedings including arbitration pending before any court,<br />
tribunal or arbitrator relating thereto, our liability under<br />
this guarantee being absolute and unconditional.<br />
4. We, .................................. Bank further agree<br />
with "the <strong>Corporation</strong>" that "the <strong>Corporation</strong>" shall have the<br />
fullest liberty without our consent and without affecting in<br />
any manner our obligations hereunder to vary any <strong>of</strong> the terms<br />
and conditions <strong>of</strong> the said "order"/or to extend time <strong>of</strong><br />
performance by "the Supplier" from time to time or to<br />
_____________________________________________________________________________<br />
Annexure 11 (Composite Bank Gaurantee for Mobil. Systems & Procedures<br />
Purchase Manual Advance,Security Dep. Etc.) VI.63 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
postpone for any time to time any <strong>of</strong> the powers exercisable<br />
by "the <strong>Corporation</strong>" against "the Supplier" and to forbear to<br />
enforce any <strong>of</strong> the terms and conditions relating to "the<br />
order" and we shall not be relieved from our liability by<br />
reason <strong>of</strong> any such variation or extension being granted to<br />
"the Supplier" or for any forbearance, act or ommission on<br />
the part <strong>of</strong> "the <strong>Corporation</strong>" or any indulgence by "the<br />
<strong>Corporation</strong>" to "the Supplier" or by any such matter or<br />
things whatsoever which under the law relating to sureties<br />
would but for this provision have the effect <strong>of</strong> relieving us.<br />
5. However, it has been agreed between "the Supplier" and "the<br />
<strong>Corporation</strong>" that there shall be only one Composite Bank<br />
Guarantee for both the advance and security deposit<br />
performance guarantee/Retention Money @ <strong>of</strong> ____% valid till<br />
the end <strong>of</strong> the defects liability period as per the terms <strong>of</strong><br />
the P.O. No. _______________ dated ______________ and that in<br />
proportion with the recovery <strong>of</strong> advance @ ______% per bill<br />
the same amount/value automatically stands credited to the<br />
defects liability account/security deposit or retention money<br />
as the case may be and will continue to be credited/treated<br />
till the entire advance <strong>of</strong> Rs._______________________ is<br />
fully recovered from the running bills and from the date <strong>of</strong><br />
full recovery <strong>of</strong> the advance <strong>of</strong> Rs.__________________ this<br />
guarantee automatically, shall stand valid towards the ____%<br />
retention money/defects liability, fully valid in all<br />
respects unto a further period <strong>of</strong> six months, as per the<br />
Purchase Order <strong>of</strong> "the <strong>Corporation</strong>".<br />
6. Not withstanding anything contained herein above :<br />
i) Our liability under this guarantee shall not exceed<br />
Rs..........<br />
ii) This Bank Guarantee shall be valid upto and<br />
including .......; and<br />
iii) We are liable to pay the guarantee amount or any part<br />
there<strong>of</strong> under this Bank Guarantee only and only if you serve<br />
upon us a written claim or demand on or # before the expiry <strong>of</strong><br />
30 days from the date <strong>of</strong> expiry <strong>of</strong> this guarantee.<br />
_____________________________________________________________________________<br />
Annexure 11 (Composite Bank Gaurantee for Mobil. Systems & Procedures<br />
Purchase Manual Advance,Security Dep. Etc.) VI.64 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
7. We, ........................................ Bank further<br />
undertake not to revoke this guarantee during its currency<br />
except with the previous consent <strong>of</strong> "the <strong>Corporation</strong>" in<br />
writing.<br />
8. We, ......................................... Bank lastly<br />
agree that "the Bank"'s liability under this guarantee shall<br />
not be affected by any change in the constitution <strong>of</strong> "the<br />
Supplier".<br />
9. "The Bank" has power to issue this guarantee in favour <strong>of</strong><br />
"the <strong>Corporation</strong>" in terms <strong>of</strong> the documents and/or the<br />
Agreement/Contract or MOU entered into between "the Supplier"<br />
and "the Bank" in this regard.<br />
IN WITNESS WHEREOF the Bank has executed this document on this<br />
............................. day <strong>of</strong> ...........................<br />
For ........................ Bank<br />
(by its constituted attorney)<br />
(Signature <strong>of</strong> a person authorised<br />
to sign on behalf <strong>of</strong> "the Bank")*<br />
_____________________________________________________________________________<br />
Annexure 11 (Composite Bank Gaurantee for Mobil. Systems & Procedures<br />
Purchase Manual Advance,Security Dep. Etc.) VI.65 HPCL, Mumbai<br />
# REVISION (Effective 01/05/2001)
(SPECIMEN)<br />
ANNEXURE - 13<br />
BANK GUARANTEE IN LIEU OF EARNEST MONEY<br />
(On Non-Judicial stamp paper <strong>of</strong> appropriate value)<br />
TO : <strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong><br />
(Address as applicable)<br />
IN CONSIDERATION OF MESSRS. HINDUSTAN PETROLEUM CORPORATION<br />
LIMITED a Government <strong>of</strong> India Company registered under the<br />
Companies Act, 1956, having its registered <strong>of</strong>fice at 17,<br />
Jamshedji Tata Road, Bombay-20 (hereinafter called "The<br />
<strong>Corporation</strong>" which expression shall include its successor in<br />
business and assigns) issued a tender on<br />
Messrs. ................................................ a<br />
partnership firm/sole proprietor business/a company registered<br />
under the Companies Act, 1956 having its <strong>of</strong>fice at<br />
(hereinafter called "the Tenderer" which expression shall include<br />
its executors, administrators and assigns) against Tender<br />
no............ dated .................... (hereinafter called<br />
"the tender" which expression shall include any amendments/<br />
alterations to "the tender" issued by "the <strong>Corporation</strong>") for the<br />
supply <strong>of</strong> goods to/execution <strong>of</strong> services for "the <strong>Corporation</strong>"<br />
and "the <strong>Corporation</strong>" having agreed not to insist upon immediate<br />
payment <strong>of</strong> Earnest Money for the fulfilment <strong>of</strong> the said tender in<br />
terms there<strong>of</strong> on production <strong>of</strong> an acceptable Bank Guarantee for<br />
an amount <strong>of</strong> Rs....... (Rupees .................................<br />
only).<br />
We, ................................... Bank having <strong>of</strong>fice<br />
at ..................................................... Bombay<br />
(hereinafter referred to as "the Bank" which expression shall<br />
include its successors and assigns) at the request and on behalf<br />
<strong>of</strong> "the Tenderer" hereby agree to pay to the <strong>Corporation</strong> without<br />
any demur on first demand an amount not exceeding Rs...........<br />
(Rupees ...................................... only) against any<br />
loss or damage, costs, charges and expenses caused to or suffered<br />
by "the <strong>Corporation</strong>" by reason <strong>of</strong> non performance and fulfilment<br />
or for any breach on the part <strong>of</strong> "the Tenderer" <strong>of</strong> any <strong>of</strong> the<br />
terms and conditions <strong>of</strong> the said "tender".<br />
________________________________________________________________________________<br />
Annexure 13 ( Bank Guarantee in lieu <strong>of</strong> Earnest Money) Systems & Procedures<br />
Purchase Manual VI.69 HPCL, Mumbai
2. We, ........................................ Bank further<br />
agree that "the <strong>Corporation</strong>" shall be sole Judge whether the<br />
said "Tenderer" has failed to perform or fulfill the said<br />
"tender" in terms there<strong>of</strong> or committed breach <strong>of</strong> any <strong>of</strong> the<br />
terms and conditions <strong>of</strong> "the order" and the extent <strong>of</strong> loss,<br />
damage, cost, charges and expenses suffered or incurred or<br />
would be suffered or incurred by "the <strong>Corporation</strong>" on account<br />
there<strong>of</strong> and we waive in favour <strong>of</strong> "the <strong>Corporation</strong>" all the<br />
rights and defences to which we as guarantors and/or "the<br />
Tenderer" may be entitled to.<br />
3. We, ................................. Bank further agree that<br />
the amount demanded by "the <strong>Corporation</strong>" as such shall be<br />
final and binding on "the Bank" as to "the Bank" 's liability<br />
to pay and the amount demanded and "the Bank" to undertake to<br />
pay "the <strong>Corporation</strong>" the amount so demanded on first demand<br />
and without any demur notwithstanding any dispute raised by<br />
"the Tenderer" or any suit or other legal proceedings<br />
including arbitration pending before any court, tribunal or<br />
arbitrator relating thereto, our liability under this<br />
guarantee being absolute and unconditional.<br />
4. We, ....................................... Bank further<br />
agree with "the <strong>Corporation</strong>" that "the <strong>Corporation</strong>" shall<br />
have the fullest liberty without our consent and without<br />
affecting in any manner our obligations hereunder to vary<br />
any <strong>of</strong> the terms and conditions <strong>of</strong> the said "tender"/or to<br />
extend time <strong>of</strong> performance by "the Tenderer" from time to<br />
time or to postpone for any time to time any <strong>of</strong> the powers<br />
exercisable by "the <strong>Corporation</strong>" against "the Tenderer" and<br />
to forbear to enforce any <strong>of</strong> the terms and conditions<br />
relating to "the tender" and we shall not be relieved from<br />
our liability by reason <strong>of</strong> any such variation or extension<br />
being granted to "the Tenderer" or for any forbearance, act<br />
or ommission on the part <strong>of</strong> "the <strong>Corporation</strong>" or any<br />
indulgence by "the <strong>Corporation</strong>" to "the tenderer" or by any<br />
such matter or things whatsoever which under the law relating<br />
to sureties would but for this provision have the effect <strong>of</strong><br />
relieving us.<br />
________________________________________________________________________________<br />
Annexure 13 ( Bank Guarantee in lieu <strong>of</strong> Earnest Money) Systems & Procedures<br />
Purchase Manual VI.70 HPCL, Mumbai
5. NOTWITHSTANDING anything hereinbefore contained, our<br />
liability under this Guarantee is restricted to Rs. .........<br />
(Rupees....................................... only). Our<br />
liability under this guarantee shall remain in force until<br />
expiration <strong>of</strong> six months from the due date <strong>of</strong> opening <strong>of</strong> the<br />
said "tender". Unless a demand or claim under this guarantee<br />
is made on us in writing within said period, that is, on or<br />
before .................................... all rights <strong>of</strong><br />
"the <strong>Corporation</strong>" under the said guarantee shall be forfeited<br />
and we shall be relieved and discharged from all liabilities<br />
thereunder.<br />
6. We, ........................................ Bank further<br />
undertake not to revoke this guarantee during its currency<br />
except with the previous consent <strong>of</strong> "the <strong>Corporation</strong>" in<br />
Writing.<br />
7. We, ......................................... Bank lastly<br />
agree that "the Bank" 's liability under this guarantee shall<br />
not be affected by any change in the constitution <strong>of</strong> "the<br />
Tenderer".<br />
8. "The Bank" has power to issue this guarantee in favour <strong>of</strong><br />
"the <strong>Corporation</strong>" in terms <strong>of</strong> the documents and/or the<br />
Agreement/Contract or MOU entered into between "the Tenderer"<br />
and "the Bank" in this regard.<br />
IN WITNESS WHEREOF the Bank has executed this document on<br />
this .......................... day <strong>of</strong> ........................<br />
For ........................ Bank<br />
(by its constituted attorney)<br />
(Signature <strong>of</strong> a person authorised<br />
to sign on behalf <strong>of</strong> "the Bank")<br />
________________________________________________________________________________<br />
Annexure 13 ( Bank Guarantee in lieu <strong>of</strong> Earnest Money) Systems & Procedures<br />
Purchase Manual VI.71 HPCL, Mumbai
ATTACHMENT FOR TENDER ENQUIRY NO<br />
H.P.C.L. COMMERCIAL TERMS AND CONDITIONS<br />
ATTACHMENT<br />
To be duly filled, signed and submitted alongwith your unpriced / priced <strong>of</strong>fer failing<br />
which your <strong>of</strong>fer is liable for rejection.<br />
SL<br />
No<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
DESCRIPTION<br />
Two bid system: Priced and unpriced bids to be<br />
submitted separately<br />
<strong>Corporation</strong> to supply: As per tender<br />
Agency to supply: All material, labour, tools and<br />
tackles and supervision necessary to complete the job<br />
/ As per tender<br />
Job commencement: From the date <strong>of</strong> FOI / as per<br />
tender<br />
Period <strong>of</strong> job completion: As per tender<br />
Liquidated damages: As per tender<br />
7 Earnest Money Deposit: As per tender<br />
8 Security deposit: As per tender<br />
PARTY’S<br />
CONFIRMATION<br />
[ / X]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]
SL<br />
No<br />
DESCRIPTION PARTY’S<br />
CONFIRMATION<br />
[ / X]<br />
9 Retention money: 10% <strong>of</strong> the total value <strong>of</strong> the running<br />
account and final bill be deducted and retained by the<br />
owner as retention money on account <strong>of</strong> any damages/<br />
defects liability that may arise for the period covered under<br />
the defect liability period (one year from the date <strong>of</strong> job<br />
completion) clause <strong>of</strong> the contract free <strong>of</strong> interest (as per<br />
General conditions <strong>of</strong> contract)..<br />
10 Payment terms: As per tender<br />
11<br />
All the provisions <strong>of</strong> the General Conditions <strong>of</strong> Contract<br />
(GCC) are accepted without any deviations.<br />
12 Confirm that all the document required for availing cenvat<br />
benefit for excise duty, service tax and incident <strong>of</strong> input tax<br />
(VAT) will be provided<br />
13<br />
Validity: The rates quoted are valid for 6 months from the<br />
date <strong>of</strong> opening <strong>of</strong> price bid<br />
14 Confirmation that if your submit bid, qualifies and does not<br />
get the contract because <strong>of</strong> you being not the lowest you<br />
will be prohibited from working as a subcontractor for the<br />
contractor who is executing the contract,<br />
15<br />
16<br />
Confirm that you have not been banned or de-<strong>list</strong>ed by any<br />
Government or quasi Government agencies or PSU’s<br />
Contract validity: 24 months from the date <strong>of</strong> F.O.I<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
[ ]<br />
SIGNATURE OF THE CONTRACTOR
LIST OF DRAWINGS DOC No. CEPS-DL-11-F-01<br />
CRUDE HEATER (11-F-01) Rev 0<br />
Sheet 1 <strong>of</strong> 3<br />
SL NO. DRAWING NO TITLE OF THE DRAWING<br />
1 VR-11-F-01-0001 Scantling drawing<br />
2 VR-11-F-01-0002 General arrangement, elevation + plan<br />
3 VR-11-F-01-0003 General arrangement (plans)<br />
4 VR-11-F-01-0004 Coil arrangement (for hydro carbon)<br />
5 VR-11-F-01-0004A Steam super heater Coil<br />
6 VR-11-F-01-0006 Steel work for convection section<br />
7 VR-11-F-01-0007 Platform details<br />
8 VR-11-F-01-0008 Stack & duct connection details<br />
9 VR-11-F-01-0009 Intermediate tube sheets<br />
10 VR-11-F-01-0024 Convection section details <strong>of</strong> bracings<br />
11 VR-11-F-01-0025 Convection section details <strong>of</strong> steel work<br />
12 VR-11-F-01-0026 Convection section details <strong>of</strong> steel work<br />
13 VR-11-F-01-0027 Convection section details <strong>of</strong> steel work<br />
14<br />
VR-11-F-01-0028 Convection section details <strong>of</strong> steel work<br />
15 VR-11-F-01-0029 Convection section details <strong>of</strong> steel work = moment con.<br />
16 VR-11-F-01-0030 Crude convection details <strong>of</strong> casing<br />
17 VR-11-F-01-0031 Crude convection detail <strong>of</strong> casing<br />
18 VR-11-F-01-0032 Crude convection
LIST OF DRAWINGS DOC No. CEPS-DL-11-F-01<br />
CRUDE HEATER (11-F-01) Rev 0<br />
Sheet 2 <strong>of</strong> 3<br />
SL NO. DRAWING NO TITLE OF THE DRAWING<br />
19 VR-11-F-01-0033 Convection details <strong>of</strong> tube sheets<br />
20 VR-11-F-01-0034 Convection details <strong>of</strong> tube sheets<br />
21 VR-11-F-01-0035 Convection details <strong>of</strong> header boxes<br />
22 VR-11-F-01-0036 Convection detail <strong>of</strong> header boxes<br />
23 VR-11-F-01-0037 Convection detail <strong>of</strong> header boxes<br />
24 VR-11-F-01-0038 Convection detail <strong>of</strong> header boxes<br />
25 VR-11-F-01-0039 Convection details <strong>of</strong> header boxes<br />
26 VR-11-F-01-0040 Convection detail <strong>of</strong> header boxes<br />
27 VR-11-F-01-0041 Convection detail <strong>of</strong> header boxes<br />
28 VR-11-F-01-0042 Stack details <strong>of</strong> base<br />
29 VR-11-F-01-0043 Details <strong>of</strong> 12 thk shell & duct openings & access door<br />
30 VR-11-F-01-0044 Stack details <strong>of</strong> 12 thk shell & duct openings & access door<br />
31 VR-11-F-01-0045 Stack details <strong>of</strong> 10 thk shell & 8 thk shell & tube pull out rail<br />
32 VR-11-F-01-0046 Stack details <strong>of</strong> 6 thk shell & painters trolley rail<br />
33 VR-11-F-01-0051 Details <strong>of</strong> platform steel work at EL + 33900<br />
34 VR-11-F-01-0052 Details <strong>of</strong> platform steel work at EL +23257<br />
35 VR-11-F-01-0061 Details <strong>of</strong> hand rail at EL+ 29412
LIST OF DRAWINGS DOC No. CEPS-DL-11-F-01<br />
CRUDE HEATER (11-F-01) Rev 0<br />
Sheet 3 <strong>of</strong> 3<br />
SL NO. DRAWING NO TITLE OF THE DRAWING<br />
36 VR-11-F-01-0062 Details <strong>of</strong> platform hand rail at EL + 25950<br />
37 VR-11-F-01-0063 Details <strong>of</strong> platform handrail at EL +25950<br />
38 VR-11-F-01-0064 Details <strong>of</strong> platform handrail at EL + 25950<br />
39 VR-11-F-01-0065 Details <strong>of</strong> platform handrail at EL + 25950<br />
40 VR-11-F-01-0066 Side bracing details at EL +25,950/EL+23,257 / EL+20857<br />
41 VR-11-F-01-0067 Side bracing details at EL +25,950/ EL+23,257 / EL+20857<br />
42 VR-11-F-01-0068 Details <strong>of</strong> ladders<br />
43 VR-11-F-01-0069 Details <strong>of</strong> ladders<br />
44 VR-11-F-01-0070 Details <strong>of</strong> ladders<br />
45 VR-11-F-01-0077 Stack ladder for platform at EL+12.500,20.000, 23.600,<br />
30.250 & EL 4000 APH<br />
46 VR-11-F-01-0088 Providing additional tubes on convection side<br />
47 11-06-43-F-102<br />
REV 0<br />
48 11-06-43-F-103<br />
REV 0<br />
49 11-06-43-F-104<br />
REV 0<br />
Convection section details REVAMP (Refractory details)<br />
Detail <strong>of</strong> ducts and stack REVAMP (Refractory details)<br />
Anchor details and bill <strong>of</strong> material REVAMP
LIST OF DRAWINGS DOC NO.CEPS-DL-12-F-01<br />
VACUUM HEATER (12-F-01) Rev 0<br />
Sheet 1 <strong>of</strong> 2<br />
SL NO. DRAWING NO TITLE OF THE DRAWING<br />
1 VR-12-F-01-0002 Vacuum heater scantling drawing<br />
2 VR-12-F-01-0003 Vacuum heater coil arrangement<br />
3 VR-12-F-01-0004 Vacuum heater intermediate tube sheet<br />
4 VR-12-F-01-0005 Vacuum heater general arrangement cross section &<br />
longitudinal section<br />
5 VR-12-F-01-0006 General arrangement (plans) sheet 1<br />
6 VR-12-F-01-0007 General arrangement (plans) sheet 2<br />
7 VR-12-F-01-0008 Steel work cross section and Details<br />
8 VR-12-F-01-0009 Steel work elevation and Details<br />
9 VR-12-F-01-0010 Steel work plans at EL+2400~ 15500 & EL+16065<br />
10 VR-12-F-01-0011 Vacuum heater stack & duct <strong>of</strong>f take Details<br />
11 VR-12-F-01-0012 Header box end tube sheet<br />
12 VR-12-F-01-0013 Platform at EL+2400, 4700,8800 & 12153<br />
13 VR-12-F-01-0014 Platform at EL+16065 & 20265 ladder stair case & bracket<br />
details<br />
14 VR-12-F-01-0019 Detail <strong>of</strong> header box on grid line<br />
15 VR-12-F-01-0020<br />
Details <strong>of</strong> header box on grid line A<br />
16 VR-12-F-01-0025 Details <strong>of</strong> header box on grid line A<br />
17<br />
VR-12-F-01-0026 Detail <strong>of</strong> header box on grid line A
LIST OF DRAWINGS DOC NO.CEPS-DL-12-F-01<br />
VACUUM HEATER (12-F-01) Rev 0<br />
Sheet 2 <strong>of</strong> 2<br />
SL NO. DRAWING NO TITLE OF THE DRAWING<br />
18 VR-12-F-01-0027 Convection Details <strong>of</strong> header boxes grid line E<br />
19 VR-12-F-01-0032 Stack Details <strong>of</strong> base & GA<br />
20<br />
VR-12-F-01-0033 Details <strong>of</strong> 12 Thk shell, access door & openings for damper<br />
support<br />
21 VR-12-F-01-0034 Stack Details <strong>of</strong> 12thk shell access door opening for damper<br />
details.<br />
22 VR-12-F-01-0035 Details <strong>of</strong> <strong>of</strong>f take duct & opening for duct<br />
23 VR-12-F-01-0036 Detail <strong>of</strong> shell plate<br />
24 VR-12-F-01-0037 Detail <strong>of</strong> 10 thk conical shell<br />
25 VR-12-F-01-0038 Stack Details <strong>of</strong> 10 thk conical shell<br />
26 VR-12-F-01-0039 Stack Details <strong>of</strong> shell plates<br />
27 VR-12-F-01-0044 Details <strong>of</strong> platform at EL+12155<br />
28 VR-12-F-01-0045 Details <strong>of</strong> platform at EL+12155<br />
29 VR-12-F-01-0046 Details <strong>of</strong> platform steel work at EL+20065<br />
30 VR-12-F-01-0048 Ladder Details<br />
31 VR-12-F-01-0049 Ladder Details for EL+12155 to EL+16065<br />
32 12-06-43-F-102<br />
REV 0<br />
33 12-06-43-F-103<br />
REV 0<br />
34 12-06-43-F-104<br />
REV 0<br />
Convection section detail Vacuum heater REVAMP<br />
Detail <strong>of</strong> duct and stack Vacuum heater REVAMP<br />
Details and bill <strong>of</strong> materials Vacuum heater REVAMP
PART-II<br />
PRICED BID
INDEX<br />
PART-II – PRICED BID<br />
SL NO. DESCRIPTION PAGE No.<br />
1. SCHEDULE OF LUMPSUM PRICE 1-7<br />
2. PRICE BREAK UP OF LUMPSUM PRICE 8-9
SCHEDULE OF LUMPSUM PRICE
Pr<strong>of</strong>orma-V<br />
SCHEDULE OF LUMPSUM PRICE<br />
Sl<br />
No<br />
DESCRIPTION<br />
1.0 Lumpsum price for execution <strong>of</strong> complete scope <strong>of</strong><br />
work on turnkey basis fully conforming to HPCL<br />
tender documents.<br />
- Residual design, preparation <strong>of</strong> detailed<br />
fabrication <strong>drawings</strong>, obtaining approvals <strong>of</strong><br />
-<br />
documents mentioned else where in the tender<br />
document.<br />
Procurement <strong>of</strong> all required ,materials (except free<br />
issue materials from HPCL) fabrication,<br />
Inspection, testing and supply convection<br />
-<br />
sections, stacks and all other items<br />
Dismantling <strong>of</strong> existing Stack and convection<br />
sections <strong>of</strong> both heaters (11-F-01 and 12-F-01)<br />
and associated items.<br />
- Erection <strong>of</strong> new convection sections and stacks for<br />
both heaters and associated items.<br />
- Transportation <strong>of</strong> all items viz. stacks, Convection<br />
sections, Structural items etc. to HPCL erection<br />
site, transportation <strong>of</strong> dismantle stacks, convection<br />
sections and other items to HPCL’s designated<br />
area as per the instructions <strong>of</strong> the Engineer-incharge<br />
- Deploying one Demag 2000CC crane as detailed<br />
in clause no.6.1 and 6.8 <strong>of</strong> special technical<br />
conditions and other cranes as per Tender.<br />
- All other jobs required for completion <strong>of</strong> the job.<br />
Note:<br />
TOTAL LUMPSUM PRICE (IN RS.)<br />
(in figures) (in words)<br />
The above quoted lumpsum price shall be firm till completion <strong>of</strong> work and shall be<br />
inclusive <strong>of</strong> all taxes & duties (like Sales tax, non cenvatable service Tax, WCT,<br />
Entry tax, non cenvatable Excise duty, non cenvatable CVD, Education cess,<br />
Octroi and any other taxes, duties & levies) and excluding Cenvatable CVD,<br />
cenvatable excise duty, Cenvatable service tax and input tax under AP VAT.<br />
Bidders shall be evaluated basing on lumpsum price quoted above.<br />
Signature / Seal <strong>of</strong> Tenderer
Sales Tax<br />
Owner shall issue "C"-Form to CONTRACTOR on all inter-state sales in India <strong>of</strong> materials for<br />
permanent incorporation in the works (and only for finished items) by the contractor to enable<br />
the Contractor to avail concessional rate <strong>of</strong> Sales Tax on such sales. The consignee should<br />
be mentioned as " Consignee-<strong>Hindustan</strong> <strong>Petroleum</strong> <strong>Corporation</strong> <strong>Limited</strong> A/C Contractor.<br />
Works Contract Tax<br />
Works Contract Tax, at the prevailing rate as applicable from time to time shall be deducted<br />
from the Contractor's bills, and the quoted rates shall be deemed to include this.<br />
Taxes, Duties, Octroi, Levies e t c.<br />
The quoted prices shall be deemed to be. inclusive <strong>of</strong> all taxes, duties, levies etc., including<br />
sales tax, non, cenvatable service tax, Non cenvatable excise duty and Non cenvatable<br />
CVD, custom duty, works contract tax, entry tax, corporate tax, personal taxes seignorage<br />
fee etc., but excluding Cenyatable excise duty, Cenvatable CVD, Cenvatable service tax and<br />
VAT amount for which Input tax credit shall be available to owner under VAT act. Income tax<br />
at the prevailing rate will be deducted form Contractor s bills as per Income tax act. Agency<br />
shall furnish all the necessary documents to HPCL for availing CENVAT benefit to the extent <strong>of</strong><br />
CENVAT benefit amount indicated in the pr<strong>of</strong>orma V.a,V.b & V.c.<br />
Service Tax<br />
The Lump sum rate quoted in the schedule <strong>of</strong> prices shall be exclusive <strong>of</strong> CENVATABLE<br />
Service Tax. Bidders shall quote CENVATABLE service tax in the Pr<strong>of</strong>orma V.a <strong>of</strong> Price<br />
Schedule.<br />
CENVATABLE service tax shall be reimbursed to the Contractor at actual against submission <strong>of</strong><br />
Cenvatable documents for service tax as mentioned in the following para and to the satisfaction<br />
<strong>of</strong> the owner. In case owner is not able t o avail Cenvatable credit based on the documentation<br />
furnished by the Contractor, then such amount shall not be reimbursed.<br />
As per Cenvat Credit Rules 2004, Owner can avail credit o n payment <strong>of</strong> Service Tax to the<br />
Contractor. Contractor shall submit proper invoice (s) showing the service tax paid and payable<br />
on the taxable value. To enable owner to claim Cenvat benefit, Contractor shall furnish the<br />
following information in invoice, Bill/ challan issued by him:<br />
(i) Name and address <strong>of</strong> the Contracor<br />
(ii) Service Tax Registration no./ STC, no.<br />
(iii) SI. No. <strong>of</strong> the invoice/ challan<br />
(iv) Date <strong>of</strong> issue<br />
(v) Description and value <strong>of</strong> input service<br />
(vi) Service tax paid/ payable<br />
CENVATABLE service tax given in the price part shall be subject to the statutory variation in service . tax<br />
subsequent to submission <strong>of</strong> last price bid.
CENVAT BENEFITS<br />
(I) Cenvat benefit is being availed by HPCL. All documents <strong>of</strong> materials brought to the site <strong>of</strong> work<br />
by CONTRACTOR shall be prepared with the notation "Consignee - <strong>Hindustan</strong> <strong>Petroleum</strong><br />
<strong>Corporation</strong> <strong>Limited</strong>, Visakh Refinery A/c CONTRACTOR" to enable Owner to claim CENVAT<br />
benefits. In case, due to the consignee name being mentioned in any other way or due to any<br />
other defect in the relevant documents, HPCL is deprived <strong>of</strong> availing cenvat benefit, than such<br />
amount shall not be reimbursed to the CONTRACTOR. Contractor to ensure that all valid<br />
documents are provided to HPCL to avail cenvat benefit.<br />
(II) The CONTRACTOR shall confirm that Cenvat benefit for supply <strong>of</strong> the specified goods can be<br />
passed on to HPCL and shall be required to provide the OWNER with all documents necessary<br />
for the OWNER to claim CENVAT benefit on the countervailing duty and excise, duty paid on<br />
the materials covered by the supplies, including (but not limited to) transporter's Copy <strong>of</strong> Challan<br />
for excise duty, copy <strong>of</strong> Registration with Central Excise Authority & Invoices under Rules 57G or<br />
57T for CVD.<br />
(III) The classification <strong>of</strong> goods as per Central Excise / Customs Tariff should be correctly done to<br />
ensure that CENVAT benefit is not lost by the OWNER on account <strong>of</strong> any error on the part <strong>of</strong> the<br />
CONTRACTOR.<br />
(IV) The amount <strong>of</strong> cenvatable excise duty and cenvatable CVD shall be reimbursed to the<br />
CONTRACTOR at actual against documentary evidence on production <strong>of</strong> all related documents<br />
in accordance with provision <strong>of</strong> Bidding Document enabling the OWNER to avail Cenvat<br />
benefits and only after the materials / equipments supplied are erected / installed. In case Owner<br />
is not able to avail Cenvatable credit based on documentation furnished by the<br />
CONTRACTOR then such amount shall not be reimbursed. CONTRACTOR shall indicate<br />
the cenvatable Excise duty and Cenvatable CVD in Pr<strong>of</strong>orma V.b <strong>of</strong> Schedule <strong>of</strong> Price.<br />
Value Added tax (VAT)<br />
Bidders shall indicate the VAT amount for which input tax credit shall be available to owner<br />
under VAT act in the Pr<strong>of</strong>orma V.c <strong>of</strong> the price schedule. The input tax credit amount shall be<br />
reimbursed to the contractor on production <strong>of</strong> all related documents and owner is able to take<br />
VAT credit in accordance with provision <strong>of</strong> VAT act. Contractor shall submit proper tax invoices<br />
for local purchases as per the AP VAT act, to enable HPCL to make full input tax credit under<br />
AP VAT act. TIN No. <strong>of</strong> HPCL is 28790125395.
Sl.<br />
No.<br />
Description<br />
1 Amount <strong>of</strong> Cenvatable service tax<br />
NOTE :<br />
CENVATABLE SERVICE TAX DETAILS<br />
Amount In figures<br />
(Rs)<br />
1. Owner shall reimburse Cenvatable service tax against production <strong>of</strong> documentary evidence.<br />
2. The quoted lump sum price in Pr<strong>of</strong>orma-V, shall be excluding Cenvatable service tax.<br />
Pr<strong>of</strong>orma-V.a<br />
Amount in words<br />
(Rs)<br />
SIGNATURE / SEAL OF TENDERER
Sl.<br />
No.<br />
CENVATABLE EXCISE DUTY AND CENVATABLE CVD AMOUNT<br />
Description<br />
A CENVATABLE AMOUNT TOWARDS EXCISE DUTY in INR<br />
B CENVATABLE AMOUNT TOWARDS CVD in INR<br />
C Total (A + B)<br />
NOTE :<br />
Amount In figures<br />
(Rs)<br />
Pr<strong>of</strong>orma-V.b<br />
Amount in words<br />
(Rs)<br />
1. The quoted Lump sum price in Pr<strong>of</strong>orma-V, shall be excluding CENVATABLE EXCISE DUTY and<br />
CENVATABLE CVD. The amount <strong>of</strong> cenvatable excise duty and cenvatable CVD shall be reimbursed to the<br />
contractor on production <strong>of</strong> all related documents in accordance with bidding document and after the material /<br />
equipment supplied are fabricated / erected and installed.<br />
SIGNATURE / SEAL OF TENDERER
Sl.<br />
No.<br />
INPUT TAX CREDIT UNDER VAT ACT<br />
Description<br />
1 Total amount for which Input tax credit shall be available to owner under<br />
VAT act.<br />
NOTE :<br />
Amount In<br />
figures<br />
(Rs)<br />
Pr<strong>of</strong>orma-V.c<br />
Amount in<br />
words<br />
(Rs)<br />
1. The quoted Lumpsum price in Pr<strong>of</strong>orma-V shall be excluding VAT amount for which input tax credit shall be<br />
available to owner under VAT act.<br />
2. The input tax credit amount shall be reimbursed to the contractor on production <strong>of</strong> all related documents and<br />
owner is able to take VAT credit in accordance with provision VAT act.<br />
SIGNATURE / SEAL OF TENDERER
PRICE BREAK UP<br />
OF<br />
LUMPSUM PRICE
Sl<br />
No<br />
1.0<br />
2.0<br />
3.0<br />
4.0<br />
Pr<strong>of</strong>orma – VI<br />
PRICE BREAK UP SCHEDULE<br />
PRICE (IN Rs.)<br />
DESCRIPTION (in figures) (in words)<br />
Procurement <strong>of</strong> all materials, fabrication and<br />
supply <strong>of</strong> one stack each for 11-F-01 and<br />
12-F-01 including refractory lining, heat dry out<br />
and painting ex-contractor’s work shop in two<br />
pieces and all other structural items.<br />
Procurement <strong>of</strong> all materials (except FIM by<br />
HPCL) Fabrication and supply <strong>of</strong> one<br />
convection section each for 11-F-01 and<br />
12-F-01 including refractory lining, hydraulic<br />
testing and painting at HPCL fabrication yard.<br />
Dismantling <strong>of</strong> one stack each and one<br />
convection section each for 11-F-01 and<br />
12-F-01 and other associated items and<br />
erection <strong>of</strong> one new stack each and one new<br />
convection section each for 11-F-01 and<br />
12-F-01 and other associated items complete in<br />
all aspects. Deploying Demag 2000 CC crane<br />
and other cranes..<br />
Lumpsum transportation charges for<br />
transportation <strong>of</strong> all items viz, stacks,<br />
convection sections, structural items etc. to<br />
HPCL erection site, transportation <strong>of</strong><br />
dismantled stacks, convection sections and<br />
other items to HPCL’s designated area as per<br />
the instructions <strong>of</strong> the Engineer in-charge.<br />
NOTE :<br />
1. The break up prices at 1,2 & 4 indicated above are for calculating LD<br />
against supply as per clause no: 8.i <strong>of</strong> terms and conditions <strong>of</strong> contract <strong>of</strong><br />
tender document<br />
2. The break up prices at 3 indicated above are for calculating LD against<br />
supply as per clause no: 8.ii <strong>of</strong> terms and conditions <strong>of</strong> contract <strong>of</strong> tender<br />
document<br />
Signature <strong>of</strong> the Tenderer